BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Fetter Lane, London, EC4Y 1NL |
||
B e f o r e :
____________________
SAINSBURY'S SUPERMARKETS LIMITED |
Claimant |
|
- and - |
||
RYAN JAYBERG LIMITED |
Defendant |
____________________
Duncan McCall QC and Matthew Thorne (instructed by Beale & Co LLP) for the Defendant
Hearing date: 25th September 2020
____________________
Crown Copyright ©
"Covid-19 Protocol: This judgment was handed down by the judge remotely by circulation to the parties; representatives by email and release to Bailii. The date and time for hand-down is deemed to be Friday 11th December 2020 at 10:30am"
Mrs Justice O'Farrell:
i) an application by the Claimant ("SSL") to amend its Particulars of Claim, which is opposed by the Defendant ("RJL"); andii) an application by RJL to strike out parts of the Reply and Response to the Request for Further Information on the basis that certain new allegations by SSL have no real prospect of success and are sought to be added outside the limitation period.
Background
Proceedings
"12. … The CO2 Units operate at up to 120 bar (gauge) and are, therefore, regulated in accordance with the Pressure Systems Safety Regulations 2000.
…
16. The relevant specifications and design guides ("the Specifications") were set out within the "Refrigeration" section of SSL Standards and Projects Website ("the Standards Website"). The Specifications were revised and updated from time to time. Each of the Defendants had access to, and did access, the Standards Website at all material times from 2009 and, in particular the following specifications:
16.1. The "Refrigeration Spec – Refrigeration Equipment" ("the Refrigeration Specification") …
16.2. The "Refrigeration Spec – Refrigeration Design Guide" ("the Design Guide") …
16.3. In about 2010, following the refurbishment of the "initial stores" … the Claimant, in consultation with each of the Defendants, produced additional specifications specific to the CO2 system, namely:
16.3.1. The "Refrigeration Spec – Carbon Dioxide Refrigeration Installation Specification – Addendum" ("the CO2 Refrigeration Installation Specification") …
16.3.2. The "Refrigeration Spec – Carbon Dioxide Refrigeration Plant Specification – Addendum" ("the CO2 Plant Specification")."
"…the said Refrigeration Specification included, inter alia, the requirement that: "The plant and equipment supplier [the Defendants] must state the expected useful lifetime of any item supplied. SSL expect a minimum lifetime of 15 years for major items of plant such as compressor pack/condensers" ("the 15-Year Minimum Lifetime Requirement"). The CO2 Units constituted "major items of plant" within the meaning of the Refrigeration Specification and were therefore subject to the 15-Year Minimum Lifetime Requirement. The Refrigeration Specification stipulated where requirements were to apply to HFC only. All other requirements were required to apply to all refrigeration systems (including CO2)."
"45. … each of the Defendants was in breach of the express and/or implied terms of the relevant contract in relation to the design, selection, supply and/or installation of the CO2 Units …
46. Further or alternatively, each of the Defendants acted in breach of their contractual and/or common law duties in respect of the advice which they provided in relation to the design of the CO2 system and in relation to the CO2 Units and in relation to their design of that system and their selection, and supply of the CO2 Units.
47.1. The Defendants failed to exercise reasonable care and skill in relation to the advice provided in respect of the design of the CO2 system and/or in relation to the selection of the said CO2 Units in failing to ensure that the CO2 Units would meet the requirements of the Claimant and the Specifications. Without prejudice to the generality of the foregoing, the CO2 Units as designed, selected, supplied and installed were prone to premature corrosion.
47.2. The CO2 Units selected, supplied and installed by the Defendants do not comply with the 15-Year Minimum Lifetime Requirement, contrary to the requirements in the Specifications …
47.3. The CO2 Units designed, selected, supplied and installed by the Defendants were not of satisfactory quality, not of appropriate durability, and/or were not reasonably fit for purpose in that they suffered from premature corrosion as aforesaid.
47.4. Without prejudice to the generality of the foregoing, the CO2 Units selected supplied and installed were prone to and at risk of premature corrosion because of the failure of the Defendants …"
"1.1. … The Second Defendant was not engaged to design or advise on appropriate units and it did not do so. Rather, the Second Defendant was simply engaged to supply units nominated by the Claimant. It did so.
1.2. The alleged 15 year service life requirement, which is fundamental to the claim, is said by the Claimant to arise from a specification document.
1.2.1. That specification was not incorporated into the contracts under which the Second Defendant was engaged.
1.2.2. The specification is, in any event, inapplicable to CO2 Units including those forming the basis of the claim. Rather, it applies to older-technology HFC refrigeration units used by the Claimant.
1.2.3. In any event, the sentence referred to by the Claimant within the specification is merely to an "expectation" which would not give rise to a contractual obligation even if the specification had been incorporated into the relevant contracts.
1.3. Nor does such an obligation arise outside the express terms on the contracts on which the Claimant relies. The CO2 Units were new technology, and there was no obligation to achieve any particular service life. The Claimant is now seeking to claim for something to which it was never entitled and reflecting technology which did not exist. "
"76. … RJL had no obligation in respect of the design and/or selection of the CO2 Units, and was obliged only to supply the units specified by SSL…
77. …SSL has failed properly to particularise the advice alleged to have been given by RJL, and RJL is unable properly to respond. It is in any event denied that RJL was obliged to advise SSL as to the appropriate CO2 Units or materials…
78. Paragraph 47 and its sub-paragraphs are insufficiently particularised: SSL has failed to detail what it alleges RJL ought to have done but failed to do, or what RJL did but ought not to have done …"
"If and to the extent that SSL succeeds in its allegations in respect of design or selection of the CO2 Units, any such design or selection was completed by, at the latest, May 2010, by which point SSL had defined and/or specified the manufacturers and units to be procured. Accordingly any such claim would be statute-barred by virtue of the Limitation Act 1980."
"4. Systems which incorporate equipment operating under pressure pose particular safety risks. Sound engineering practices must therefore be followed in respect of the design and supply of systems incorporating such equipment. Common law and statutory duties of care apply to those who supply such equipment and to those who design, those who assemble and those who install systems incorporating such equipment, including the duties provided for by the Pressure Systems Safety Regulations 2000 ("PSSR 2000") and/or the Pressure Equipment Regulations 1999 ("PER 1999")…
5. As a designer, and/or as a supplier, and/or as an assembler/installer of the relevant refrigeration systems and, separately, as a supplier and/or installer of the CO2 Units, RJL owed common law and statutory duties to provide sufficient written information to the Claimant concerning the design, construction, examination, operation and maintenance, including as to the fatigue life, creep life and corrosion allowances, of those systems and their components, including the CO2 Units. The Claimant will rely on the requirements imposed on RJL pursuant to the PER 1999 and the corresponding guidance and/or pursuant to, inter alia, the PSSR 2000 and the corresponding guidance in this regard …"
"5(d) RJL was required to design and/or select and/or supply and/or install the refrigeration equipment and/or systems in accordance with applicable 'Laws', including product safety laws. The relevant laws included, inter alia, the PER 1999 and/or PSSR 2000. RJL expressly admits the application of the PSSR 2000 at paragraph 19 of its Defence. The obligations contained therein necessarily meant that RJL's obligations under the 2011 RJ Framework Agreement extended to ensuring compliance with the relevant regulatory requirements imposed by the PER 1999 and/or PSSR 2000; those regulatory requirements required RJL to provide information and/or advice to SSL at all material times in relation, amongst other things, to the minimum service life of the CO2 Units…"
The application
i) Red amendments – not opposed;ii) Purple amendments – allegations in respect of the PER 1999 and PSSR 2000 (collectively, "the Pressure Regulations"), which are opposed on the grounds that they have no real prospect of success and seek to introduce a new claim that does not arise out of the same, or substantially the same, facts and matters already pleaded, outside the limitation period;
iii) Blue amendments – opposed on the grounds that they have no reasonable prospects of success or are inadequately particularised and they raise new claims outside the limitation period;
iv) Green amendments – deletions of allegations against Space, which are opposed on the grounds that they are relevant to the remaining allegations against RJL.
The applicable tests
i) When deciding whether to grant permission to amend, the court must exercise its discretion having regard to the overriding objective.ii) Applications always involve the court striking a balance between injustice to the applicant if the amendment is refused, and injustice to the opposing party and other litigants in general, if the amendment is permitted.
iii) Although the court will have regard to the desirability of determining the real dispute between the parties, it must also deal with the case justly and at proportionate cost, which includes (amongst other things) saving expense, ensuring that the case is dealt with expeditiously and fairly, and allocating to it no more than a fair share of the court's limited resources.
iv) An application to amend will be refused if it is clear that the proposed amendment has no real prospect of success. The court must consider whether the claimant has a "realistic" as opposed to a "fanciful" prospect of success: Swain v Hillman [2001] 1 All ER 91. A "realistic" claim is one that carries some degree of conviction. This means a claim that is more than merely arguable: ED & F Man Liquid Products v Patel [2003] EWCA Civ 472. In reaching its conclusion the court must not conduct a "mini-trial": Swain v Hillman.
"(1) This rule applies where –"
(a) a party applies to amend his statement of case in one of the ways mentioned in this rule; and
(b) a period of limitation has expired under –
(i) the Limitation Act 1980 …;
(2) The court may allow an amendment whose effect will be to add or substitute a new claim, but only if the new claim arises out of the same facts or substantially the same facts as a claim in respect of which the party applying for permission has already claimed a remedy in the proceedings…"
"[19] A cause of action is, as Diplock LJ famously observed in Letang v Cooper [1965] 1 QB 232 at 242/3, "a factual situation the existence of which entitles one person to obtain from the court a remedy against another person". Longmore LJ in Berezovsky v Abramovich [2011]1 WLR 2290 at 2309 expressed the concept in essentially the same way: "A cause of action is that combination of facts which gives rise to a legal right."
[20] In the quest for what constitutes a "new" cause of action, i.e. a cause of action different from that already asserted, it is the essential factual allegations upon which the original and the proposed new or different claims are reliant which must be compared. Thus "the pleading of unnecessary allegations or the addition of further instances or better particulars do not amount to a distinct cause of action" – see Paragon Finance v Thakerar [1999] 1 All ER 400 at 405 per Millett LJ. "So in identifying a new cause of action the bare minimum of essential facts abstracted from the original pleading is to be compared with the minimum as it would be constituted under the amended pleading " - see per Robert Walker LJ in Smith v Henniker-Major [2003] Ch 182 at 210.
[21] The court is therefore concerned with the comparison of "the essential factual elements in a cause of action already pleaded with the essential factual elements in the cause of action as proposed" – see per David Richards J in HMRC v Begum [2010] EWHC 1799 (Ch) at paragraph 32. "A change in the essential features of the factual basis (rather than, say, giving further particulars of existing allegations) will introduce a new cause of action" – ibid, paragraph 30.
[22] … I would not therefore dissent from the following distillation of the principles by Jackson J, as he then was, in Secretary of State for Transport v Pell Frischmann [2006] EWHC 2909 (TCC) at paragraph 38:-
"(i) If the claimant asserts a duty which was not previously pleaded and alleges a breach of such duty, this usually amounts to a new claim.
(ii) If the claimant alleges a different breach of some previously pleaded duty, it will be a question of fact and degree whether that constitutes a new claim.
(iii) In the case of a construction project, if the claimant alleges breach of a previously pleaded duty causing damage to a different element of the building, that will generally amount to a new claim."
I would simply add my own gloss to the effect that if the new breach does not arise out of the same or substantially the same facts as those already in issue on a claim previously made in the original action, it is likely to be a new cause of action."
"[35] It is clear from the structure of CPR Pt 17.4(2) that the court only has a discretion to allow an amendment ("may allow …") to introduce a new claim (i.e. cause of action) into an existing claim where a limitation period defence will be circumvented by operation of the "relation back" rule when a prior condition has been satisfied, namely that the new claim arises out of the same or substantially the same facts as the already existing claim. Although it is sometimes said that this is substantially a matter of impression (see Welsh Development Agency v Redpath Dorman Long Ltd [1994] 1 W.L.R. 1409, at 1418 per Glidewell LJ), it was emphasised by Millett LJ in Paragon Finance Plc v DB Thakerar & Co [1999] 1 All ER 400, CA, at 418, that while in borderline cases this may be so, "In others it must be a question of analysis" (and see Ballinger v Mercer Ltd at [36], set out below). It is clear from Pt 17.4(2) itself that the condition must be satisfied before permission to amend can be granted in a case to which it applies. In some cases, that may involve an evaluative judgment by the court in which it is possible to say that there is more than one answer which could rationally be given on the point, and in relation to which it could not be said of any of those answers on appeal that it is "wrong" such that an appeal should be allowed (CPR Part 52.21(3)(a)). In other cases, the issue may be more clear-cut and admit of a single answer which is right, so that if a different answer is given by a judge it can readily be seen on appeal to be wrong. In both sorts of case it is, strictly, a matter of analysis whether the judge has made the proper or an acceptable evaluation on the question whether the condition has been satisfied.
[36] This is a substantive question of law, and an important one. Parliament has decided that valuable limitation defences which it has introduced for the benefit of defendants should only be circumvented by operation of the "relation back" rule where the precondition has been satisfied. This is not a matter of discretion for a judge."
"[40] It is to be noted that in the Ballinger case Tomlinson LJ said the words "the same or substantially the same" are not synonymous with "similar": Loc. Cit. p. 3611, paragraph 37. He also quoted with approval Colman J's identification of the purpose of the test laid down in s.35(5) of the Act, i.e. that a defendant is not to be put in the position of having to,
"…investigate facts and obtain evidence of matters which are completely outside the ambit of, and unrelated to those facts which he could reasonably be assumed to have investigated for the purpose of defending the unamended claim".
Both matters clearly have their validity, but the emphasis upon whether facts are the "same" or only "similar" and what is beyond the ambit of the original claim may well need careful analysis.
[50] … Broadly similar allegations, implicitly made or understood will not do… "
"The court may strike out a statement of case if it appears to the court:
…
(a) that the statement of case discloses no reasonable grounds for bringing or defending the claim …"
The Pressure Regulations ("purple") amendments
"12A. … the CO2 Units were classified as "piping" pursuant to regulation 7(2)(c)(i)(bb) of Pressure Equipment Regulations 1999 ("PER 1999") and the Second Defendant was required, in respect of the supply and/or installation of the CO2 Units and/or the assemblies and/or systems into which they were incorporated, to comply, inter alia, with regulations 7 (as an authorised representative of the manufacturer of the CO2 Pack and/or Units), and/or 8 (as a manufacturer of the relevant CO2 system assemblies) and/or 10 (as a supplier of such equipment and/or assemblies) of the PER 1999 and/or as a matter of good industry practice should have ensured compliance with the said provisions.
12B. Further or alternatively, as the designer and/or manufacturer and/or supplier of the pressure system and/or assembly into which the CO2 Units were incorporated, the Second Defendant was required to comply with, and/or as a matter of good industry practice should have complied with, regulation 4 and/or 5 of the PSSR 2000 and the approved Code of Practice.
…
33A. As the designers and/or assemblers and/or suppliers of the relevant CO2 refrigeration systems and of the CO2 Units, the Second Defendant was under a statutory duty pursuant to the PER 1999 and/or PSSR 2000 to provide information to the Claimant in writing as to the design, construction, examination, operation and maintenance of the relevant CO2 refrigeration systems and of the CO2 Units, including as to the minimum service life of the CO2 Units, or in the words of the DTI Guidance issued in respect of the PER 1999, as to the "intended life" of the CO2 Units… At all material times, the Second Defendant was under an express contractual duty … to ensure that the refrigeration systems, including the CO2 Units, which it designed and/or supplied and/or installed complied with all relevant laws, including the PER 1999 and/or the PSSR 2000, alternatively such compliance was an implied term of the relevant contacts …
…
46A. Further or alternatively, if and insofar as the Second Defendant contends by its Defence that (i) the Refrigeration Specification and/or the 15-Year Minimum Lifetime Requirement for the CO2 Units was not incorporated into the relevant contracts and/or was not agreed by the parties and/or was not applicable to the CO2 Units and/or that (ii) there was no minimum service life stipulated by the Claimant and/or accepted by the Second Defendant in respect of the CO2 Units and/or (iii) that the service life of the CO2 Units was not (and/or could not be) reliably stated by the Second Defendant, then the Claimant will contend that the Second Defendant was in breach of its common law duties of care and/or contractual duties (including the contractual duty to ensure that the CO2 Units and related refrigeration systems conformed to all applicable legal requirements, including the PER 1999 and/or the PSSR 2000) to provide adequate and appropriate information to the Claimant in respect of the minimum service life of the CO2 Units… The Claimant will rely upon such breaches of statutory duty under the PER 1999 and/or the PSSR 2000 as may be proved as evidence of negligence on the part of the Second Defendant and/or as evidence of breach of the Second Defendant's contractual duty …
46B. Further or alternatively, if and insofar as the Second Defendant contends by its Defence that the corrosion of the CO2 Units was caused and/or contributed to (i) by any failure on the part of the Claimant to maintain or clean the CO2 Units appropriately and/or (ii) by any change to the control settings, then the Claimant will rely on the Second Defendant's breaches of its common law duties of care and/or contractual duties to provide adequate and appropriate information to the Claimant in respect of the CO2 Units and the CO2 systems into which they were incorporated, including as to the requisite cleaning and maintenance regimes and/or the control setting parameters outside which the CO2 Units should not be operated … The Claimant will rely upon such breaches of statutory duty under the PER 1999 and/or the PSSR 2000 as may be proved as evidence of negligence on the part of the Second Defendant and/or as evidence of breach of the Second Defendant's contractual duty …"
"47.1A.1 The Second Defendant was in breach of Regulations 7 and/or 8, and/or 10 and Schedule 2 of the PER 1999 (including, but not limited to, the requirement that: (i) "pressure equipment must be designed, manufactured and checked, and if applicable equipped and installed, in such a way as to ensure its safety when put into service in accordance with manufacturer's instructions, or in reasonably foreseeable conditions" as required by paragraph 1.1 of Schedule 2(ii) "the pressure equipment must be properly designed taking all relevant factors into account in order to ensure that the equipment will be safe throughout its intended life" as required by paragraph 2.1 of Schedule 2 and /or (iii) that "the pressure equipment must be designed for loadings appropriate to its intended use and other reasonably foreseeable operating conditions" including "corrosion, erosion, fatigue etc" as required by paragraph 2.2.1 of Schedule 2 and/or (iv) that, "in particular … the design must take appropriate account of all possible combinations of temperature and pressure which might arise under reasonably foreseeable operating conditions …" as provided by paragraph 2.2.3(b) of Schedule 2 and/or (v) that "adequate allowance or protection against corrosion or other chemical attack must be provided, taking due account of the intended and reasonably foreseeable use" as provided by paragraph 2.6 of Schedule 2) and/or the requirements of good industry, for the reasons set out in paragraph 47.1 above and/or 47.1A.2 below.
47.1A.2 Further, or alternatively, the Second Defendant was in breach of Regulation 4 and/or 5(1)(a) of the PSSR 2000 and the corresponding Approved Code of Practice and/or the requirements of good industry practice in failing to have any or any adequate regard to the need to ensure that the CO2 Units, once incorporated as part of the relevant systems or assemblies, would safely achieve a minimum service life of 15 years (or any stated minimum service life) and/or that appropriate instructions and information were provided to the Claimant as to maintenance and/or cleaning and/or control settings so as to ensure that, properly operated, the CO2 Units would achieve such a minimum service life (or any stated minimum service life) safely.
47.1A.3 The aforesaid breaches of statutory duty are relied upon as evidence of negligence (that is, breach of the contractual and common law duty of care) and as evidence of breach of the said contractual duties to comply with the relevant regulatory requirements and/or the requirements of good industry practice. Paragraphs 47.1 above and 47.2 to 47.5 below are relied upon. The provision of adequate protection against corrosion could have been achieved, and should have been achieved, by the types of measures, or a combination of the measures, identified in paragraph 41B above."
"Had the Second Defendant discharged its duties in this regard and informed the Claimant that the CO2 Units could not be stated to have a 15 year minimum service life and/or could not be stated to have any particular minimum service life then the Claimant would not have agreed to the system design and would not have purchased the CO2 Units…"
i) whether the proposed amendments have a realistic, as opposed to a fanciful, prospect of success;ii) whether they constitute new claims within the meaning of CPR 17.4(2) and section 35 of the Limitation Act 1980;
iii) if new claims, whether they arise out of the same, or substantially the same, facts and matters already pleaded;
iv) whether the Court should exercise discretion to allow the amendments.
Whether the purple amendments have a real prospect of success
"(a) the manufacturer or his authorised representative established within the Community; or
(b) where neither the manufacturer nor his authorised representative is established within the Community, the person who places the pressure equipment or assembly on the market or put it into service as the case may be."
He submits that RJL was not the manufacturer of the CO2 Units; they were manufactured by Lu-Ve or Eco-Luvata, companies based in Italy. RJL was not the manufacturer of the assembly; the CO2 Packs were supplied by SCM. RJL was not the authorised representative of SCM. RJL did not place the CO2 Units or Packs on the market. Therefore, SSL has no real prospect of establishing that regulations 7 or 8 applied to RJL.
i) RJL failed to provide adequate and appropriate information in respect of the minimum service life of the CO2 Units;ii) RJL failed to provide adequate and appropriate information as to the required cleaning and maintenance regimes and/or the control setting parameters outside which the CO2 Units should not be operated.
"… no person who is a responsible person shall place on the market or put into service any pressure equipment … unless the requirements of paragraph (3) have been complied with in relation to it. "
"(a) it satisfies the relevant essential requirements [Schedule 2];
(b) the appropriate conformity assessment procedure in respect of the pressure equipment has been carried out …;
(c) the CE marking has been affixed …;
(d) a declaration of conformity has been drawn up …; and
(e) it is in fact safe. "
"1.1 Pressure equipment must be designed, manufactured and checked, and if applicable equipped and installed, in such a way as to ensure its safety when put into service in accordance with the manufacturer's instructions …
2.1 The pressure equipment must be properly designed taking all relevant factors into account in order to ensure that the equipment will be safe throughout its intended life…
2.2.1 The pressure equipment must be designed for loadings appropriate to its intended use and other reasonably foreseeable operating conditions. In particular, the following factors must be taken into account … corrosion and erosion, fatigue, etc …
2.6 Where necessary, adequate allowance or protection against corrosion or other chemical attack must be provided, taking due account of the intended and reasonably foreseeable use."
"Any person who designs, manufactures, imports or supplies any pressure system or any article which is intended to be a component part of any pressure system shall ensure that paragraphs (2) to (5) are complied with."
"Any person who –
(a) designs for another any pressure system or any article which is intended to be a component part thereof; or
(b) supplies … any pressure system or any such article,
shall provide sufficient written information concerning its design, construction, examination, operation and maintenance as may reasonably foreseeably be needed to enable the provisions of these Regulations to be complied with."
Whether the purple amendments raise a new claim
i) RJL contracted to design, supply and install the CO2 Units in accordance with the specification requirements that they should be of satisfactory quality and durability, have a minimum life of 15 years and be fit for purpose.ii) RJL was in breach of contract and/or negligent in that the CO2 Units suffered premature corrosion and failed to satisfy the 15 year minimum lifetime requirement.
iii) SSL is entitled to damages assessed as the costs of replacement of the CO2 Units.
i) RJL owed a statutory duty to provide information and advice to SSL as to the design, construction, examination, operation and maintenance of the CO2 Units pursuant to the Pressure Regulations.ii) RJL was in breach of its statutory duty under the Pressure Regulations to provide adequate and appropriate information to SSL in respect of: (a) the minimum service life of the CO2 Units; and (b) the required cleaning, maintenance and operational control of the CO2 Units, such that it was in breach of contract and/or negligent.
iii) If properly advised by RJL in accordance with its statutory duties, SSL would not have purchased the CO2 Units.
iv) SSL is entitled to damages assessed as the costs of replacement of the CO2 Units.
Same, or substantially same, facts and matters
i) whether the Pressure Regulations applied to RJL;ii) whether RJL was obliged to provide information to SSL as to the intended service life of the relevant goods and, if so, whether it was in breach of such obligation;
iii) what SSL would have done if it had been informed that the CO2 Units did not have a 15 year minimum service life (or any stated minimum service life);
iv) whether RJL was obliged to provide information to SSL as to the required maintenance, cleaning or control settings for the CO2 Units and, if so, whether it was in breach of such obligation.
"the cause of the corrosion is Sainsbury's own inadequate cleaning and maintenance and/or operation using inappropriate control settings."
Therefore, these factual issues are in any event going to be litigated between the parties. In those circumstances, SSL should be able to rely upon the additional allegations which substantially arise from those facts.
i) The matters pleaded in paragraphs 12A, 12B, 29, 34.1 (save for the reference to paragraph 33A), 46B and 47.4.6 have a real prospect of success.ii) They do not raise new claims and arise out of the same facts and matters already pleaded.
iii) The proceedings are not at an advanced stage procedurally and no prejudice will be suffered by RJL if the amendments are permitted.
iv) In those circumstances, the Court exercises its discretion to allow the amendments.
v) The matters pleaded in paragraphs 33A, 36, 46A, 47.1A.1, 47.1A.2, 47.1A.3, 47.5 and 48A raise new claims and do not arise out of the same facts and matters already pleaded.
vi) It follows that the Court does not have discretion to allow the amendments.
vii) In any event, any discretion would be exercised against allowing the amendments on the ground that they do not disclose a case that has a real prospect of success.
The blue amendments
"The Claimant is under no obligation to prove the means by which protection against, or resistance to corrosion could have been achieved by the Second Defendant so as to ensure a minimum 15-year service life for the CO2 Units."
The green amendments
Strike out application
Conclusion
i) Permission is given for the "purple" amendments in paragraphs 12A, 12B, 29, 34.1 (save for the reference to paragraph 33A), 46B and 47.4.6 of the Particulars of Claim.ii) Permission is refused for the "purple" amendments in paragraphs 33A, 36, 46A, 47.1A.1, 47.1A.2, 47.1A.3, 47.5 and 48A of the Particulars of Claim.
iii) Permission is given for the "blue" amendments in paragraphs 26.1, 28, 31A, 31A.1, 31A.3 and 41B of the Particulars of Claim.
iv) Permission is refused for the "blue" amendments in paragraphs 18, 18.2, 18.3, 29, 31A.2, 47.2, 47.3, 47.4, 47.4.1 and 31.2 of the Particulars of Claim.
v) Permission is given for the "green" amendments in the Particulars of Claim.
vi) Permission is given for the "red" amendments in the Particulars of Claim.
vii) Associated matters pleaded in the Reply and the Further Information should be struck out or remain in accordance with the above rulings.
viii) All consequential or other matters, if not agreed, will be dealt with by the Court at a further hearing to be fixed by the parties.