ON APPEAL FROM THE HIGH COURT OF JUSTICE
TECHNOLOGY AND CONSTRUCTION COURT,
MANCHESTER DISTRICT REGISTRY
His Honour Judge Stephen Davies (sitting as a Judge of the High Court)
0MA50090
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE RIMER
and
LORD JUSTICE TOMLINSON
____________________
Co-operative Group Limited |
Respondent |
|
- and - |
||
Birse Developments Ltd - and - Stuarts Industrial Flooring Limited (in Administration) |
Appellant Third Party Appellant |
____________________
WordWave International Limited
A Merrill Communications Company
165 Fleet Street, London EC4A 2DY
Tel No: 020 7404 1400, Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
Fiona Sinclair (instructed by Clyde and Co Solicitors) for the Appellant
Mark Cannon QC and Katie Powell (instructed by Reynolds Porter Chamberlain LLP) for the Third Party Appellant
Hearing date : 26 March 2013
____________________
Crown Copyright ©
Lord Justice Tomlinson:
Introduction
The existing statement of case
". . . the Employer's Requirements which formed part of the Building Contract contained the Specification for the sub-structure which provided inter alia as follows:
. . .
2.06 CONCRETE WORK
Concrete work will comply with BS8110 and carried out to the Structural Engineer's requirements.
2.08 GROUND FLOOR SLAB
A reinforced concrete ground slab will be provided to all ground floor areas within the buildings. The slab in respect of the warehouse areas will be designed in accordance with the BCA Interim Technical Note ll, Loading Category 3, Classification: "Heavy" and will accommodate a uniformly distributed superimposed loading of 50.00 KN/m2 (1000 lbs/ft2) and pallet racking of 70 KN/leg (racking leg loading based on leg centres of 2.70m along length, 0.09m centres across width and 0.20m centres for back legs where positioned back to back).
Ground floor movement joints will be designed so that no vertical movement occurs. The ground floor slab will be constructed so that the top surface is within the tolerances as defined in Concrete Society Technical Report No 34 of FM2 Property IV and free movement areas, and ±10mm from datum. Local level variations shall not exceed ±3mm in a 3.0m straight edge in any direction.
Each warehouse floor slab shall be constructed with not more than 9 No. bays and saw cut joints within the slab shall not be made less than 9.0m apart, unless constrained by pallet layout.
Saw cut and bay joints shall be infilled with suitable filler during construction and to accessible floor areas twelve months after the date of practical completion. A floor joint design drawing shall be produced and issued to the Tenant's representative for agreement before construction commences.
On completion of each warehouse area floor slab a profileograph survey will confirm the achieved surface tolerance, prior to any fitting out works taking place.
Where appropriate, the slab will be designed and constructed in accordance with the recommendations of "The Cement and Concrete Association Technical Report No 550 and BCA Interim Technical Note II". The surface will be power floated and treated with a proprietary surface hardener and penetrating dust inhibitor in accordance with the manufacturer's instructions.
A 1,200 gauge P.I.F.A. polythene damp-proof membrane will be laid beneath the ground floor slab.
The office ground floor slab to be designed to take an imposed loading of 15kN/m2 (300 lbs/ft2) with a surface tolerance and finish appropriate to the specified floor finishes."
Paragraph 15 is also relevant to the pleaded duties:-
"The Defendant also had the following further obligations arising out of or in connection with the Building Contract:
(i) There was a term necessarily implied into the Building Contract that the Defendant would carry out and complete the Building Contract Works so that, upon completion, they would be fit for their intended purpose, namely a high quality distribution warehouse complex.
(ii) There was a term necessarily implied into the Building Contract that the Defendant would carry out and complete the Building Contract Works in a good and workmanlike manner.
(iii) There was a further term necessarily implied into the Building Contract that the Defendant would carry out and complete the Building Contract Works using materials of good quality.
(iv) Further, insofar as the Defendant was a specialist carrying out specialist design and/or construction as part of the Building Contract Works, the Defendant owed to its employer a duty of care at common law in the performance of that specialist design and/or construction work."
Paragraph 28 is headed "The Defects in the Property" and so far as relevant provides as follows:-
"28. The Property suffers from defects, which may be summarised in this way:
. . .
(iii) The slab in Warehouses 1 and 2 has failed inter alia in the following general respects:
(a) In Warehouse 1 there are cracks up to 20mm wide in the floor that run parallel to the main movement (IDC) joints. Mid-bay cracking has appeared in numerous locations, with crack widths of up to 6mm, substantially exceeding the normal width of structural cracks of 0.3mm. There are misplaced dowels at the IDC joints, preventing them opening and closing properly.
(b) In Warehouse 2 mid-bay cracking has appeared in some locations, with crack widths of up to 1mm, substantially exceeding the normal width of structural cracks of 0.3mm. The slab is below the design thickness of 150mm (less 15mm tolerance), being only 112mm thick in places.The arrises to the main construction joints have deteriorated to such an extent that the central aisle is unusable, because the IDC joints were not designed to be armoured. At certain locations, particularly in the north-west bay, there is severe cracking and displacement, with a 100mm step in the surface of the slab, attributable to defects in the underlying foundation."
It will be apparent from the foregoing that there are two deletions from the original Particulars of Claim.
Paragraph 30 deals with "Breach and Causation". It reads:-
"The defects in and damage to the Property described in paragraph 28 above have been caused by the breaches of contract and/or breaches of duty of the Defendant, as more particularly set out below."
It is in paragraph 33 that particulars are given of the breaches said to be relevant to "Failure of the Slab in Warehouses 1 and 2". That paragraph reads:-
"33. The failure of the slab in Warehouses 1 and 2, described in paragraph 28(iii) above, has resulted from poor and/or inadequate workmanship and/or design in respect of the slab and/or in respect of the preparation and/or improvement of the ground underneath the slab and/or a failure to adhere to the Employer's Requirements contained in the Main Contract. In particular:
(i) The failure to design the floor to meet the intended use as an industrial warehouse, in particular provision of non-armoured joints in conjunction with 50m bay sizes, which has resulted in damaged arrises in Warehouses 1 and 2.
(ii) The failure to construct to the design intent and in accordance with good practice, in particular the installation of locked IDC joints resulting in wide cracking and areas of the slab that are below the required thickness.
(iii) The inadequacy of the ground improvement works in the area underneath the slab in Warehouse 2, which failed to deal with the tendency of the existing sub-base material, given its physical and chemical composition, to cause movement and/or heave which would then adversely impact upon the condition of the slab.
(iv) The absence of sawn joints at not less that 9m centres within the slab, which resulted in inadequate provision for expansion and contraction of the slab which, in turn, has resulted in the cracking and other damage evident within the slab in Warehouses 1 and 2."
"36. The defects in, and damage to, the slab in Warehouses 1 and 2 have been caused by the breaches of contract of the Defendant. In particular:
(i) The slab in Warehouses 1 and 2 did not comply with sections 2.06 and 2.08 of the Specification within the Employer's Requirements in that the slab was not a reinforced concrete slab designed to BS8110 or was not designed or built in accordance with industry standards such as Concrete Society Technical Report TR34. Further, this was a breach of clauses 2.1, 2.5.1.1.1, 2.5.1.1.2, 2.5.1.1.3, 2.5.1.2, 2.5.2 of the Building Contract and also a breach of the further obligations set out in paragraph 15 above, together with a breach of clauses 4.1.1., 4.1.2 and/or 4.1.3 of the Defendant's Warranty.
(ii) The slab in Warehouses 1 and 2 did not comply with section 2.08 of the Specification with the Employer's Requirements in that the slab did not contain sawn joints at not less than 9m centres. Further, this was a breach of clauses 2.1, 2.5.1.1.1, 2.5.1.1.2, 2.5.1.1.3, 2.5.1.2, 2.5.2 of the Building Contract and also a breach of the further obligations set out in paragraph 15 above, together with a breach of clauses 4.1.1, 4.1.2 and/or 4.1.3 of the Defendant's Warranty.
(iii) The sub-base beneath Warehouses 1 and 2 did not comply with the requirements of TR34 such that, as a result, the slab was of insufficient thickness in places which has, in its turn, led to cracking in the slab; in the alternative, the slab was of insufficient thickness in any event. This was a breach of clauses 2.1, 2.5.1.1.1, 2.5.1.1.2, 2.5.1.1.3, 2.5.1.2, 2.5.2 of the Building Contract and also a breach of the further obligations set out in paragraph 15 above, together with a breach of clauses 4.1.1, 4.1.2 and/or 4.1.3 of the Defendant's Warranty.
(iv) The jointing system used in Warehouses 1 and 2 was not fit for its intended purpose and/or it was not installed correctly, in that the joint was not armoured against normal wear and tear; it was experimental in its design; and was laid with debonded dowels that were not horizontal leading to locking of the joints and cracking in the slab. This was in turn a breach of clauses 2.1, 2.5.1.1.1, 2.5.1.1.2, 2.5.1.1.3, 2.5.1.2, and/or 2.5.2 of the Building Contract; a breach of the further obligations set out in paragraph 15 above; and accordingly a breach of clauses 4.1.1, 4.1.2 and 4.1.3 of the Defendant's Warranty."
"Loss and Damage Resulting from Breach
41. As a result of the breaches of contract and/or duty of the Defendant, set out above, the Claimant has suffered loss and damage, namely to the extent that there are very substantial defects in the Property. This means that:
(i) A repair scheme addressing all of the defects, together with the material risk of future damage, will need to be designed and constructed at the Property, at very significant expense to the Claimant.
(ii) There will be engineering and other professional fees associated with the design and implementation of a repair scheme at the Property.
(iii) The Claimant has suffered lost rental in circumstances where, as a result of the defects, the Claimant has been unable to find a commercial tenant.
(iv) Further commercial and/or operational losses have been, and continue to be, incurred by the Claimant as a consequence of the defects in the Property.
42 Accordingly, the Claimant is entitled to claim, and claims in these proceedings, damages for breach of contract and/or breach of duty. The Claimant's claim for damagesiswas set out in a Schedule of Loss and Damage dated 25 November 2011 and a draft Amended Schedule of Loss is to be served on the Parties by Friday 20 July 2012, pursuant to the Court order of 19 June 2012."
"63. In addition to the general matters described above, the remedial works in the warehouses generally fall within the following categories:
(i) Remedial works to cracks in the floor slab:
(a) Replacement of sections of the cracked and/or damaged floor slab; and
(b) Repair of individual cracks not covered by replacement works.
(ii) Remedial works to IDC joints:
(a) Replacement of IDC joints; and
(b) Repair of IDC joints."
The work required is then exhaustively particularised. The cost is put at about £381,000. It is relevant to note that the work allegedly required falls far short of complete replacement of the floor slabs.
The proposed re-amendment
". . . "33A In the course of works being carried out, and testing, in connection with the remedial work, the claimant has discovered that the steel fibre content of the concrete used by the defendant for the construction of the internal slab warehouse floor is substantially less than the value that had previously been assumed. The consequence of this finding, which follows from testing, is that all of the internal slab is now understrength and liable to early failure if not replaced, particularly when this finding is considered together with the available evidence on inadequate thickness of the slab in many areas."
(It is then pleaded that "the foregoing" is a breach of specified clauses of the building contract, of implied terms and duty of care, and of specified clauses of the defendant's warranties.)
36. I do not intend to set out the following 15 subparagraphs in full. In summary, the case has (sic) advanced is that:
(i) Prior to testing during the course of the remedial works the claimant and its advisers had reasonably assumed that the slabs were designed to be 150 mm thick with a steel fibre content of 30kg/m3.
(ii) However testing revealed that the steel fibre content was significantly less than assumed, with the result that it would not meet the racking leg load requirement found in the Employers Requirements. The structural capacity of the floor is also significantly reduced by reason of the reduced steel fibre content, both by itself and/or coupled with the reduced floor thicknesses found in a number of areas on inspection during the course of the remedial works.
(iii) The conclusion, in subparagraph (n) is that "there remains a high probability that the floor could fail in service due to undetected thin areas beneath or adjacent to racking legs, irrespective of the fibre content. However, the evidence now available that the fibre content is also low and below what would be needed in a design of compliant 150 mm thickness, is also reason to condemn the floor."
To this summary by the judge I would add sub-paragraphs (m) and (n) of the proposed paragraph 33A of the Re-Amended Particulars of Claim which read as follows:-
"(m) Significantly, the floor has never seen, as far as the Claimant is aware, the intended racking leg load of 70kN, which would require five levels of racking stacked with 1.4t "euro-pallets" either side of the central frame, back to back. This type of loading was never intended to be used by Woolworths, and the racking was only rated at 50kN leg load. However, these loads could easily happen when a future tenant re-rates the racking at 70kN and stores pallets of paint or other liquids, steel components, stone/cement, or paper ream. Loads from the wheels of heavy-duty high-reach fork-lift trucks would also be much more severe than has been the case previously.
(n) There remains a high probability that the floor could fail in service due to undetected thin areas beneath or adjacent to tracking legs, irrespective of the fibre content. However, the evidence now available that the fibre content is also low and below what would be needed in a design of compliant 150mm thickness, is also reason to condemn the floor."
"37. There is no amendment to paragraph 36. However, during the course of the hearing, I suggested to Mr Hughes QC that if, as appeared clear from the content of paragraph 33A, the claimant was contending that the effect of the reduced steel fibre content, whether by itself or in conjunction with the reduced floor thicknesses, rendered the defendant in breach of specific obligations imposed by the Employers Requirements, particularly the obligation appearing in paragraph 2.08, set out in full in paragraph 13, that the slab should be designed to accommodate a pallet racking leg loading requirement of 70 KN/leg, then that would need to be pleaded in terms in paragraph 36. Although Mr Hughes submitted that it was sufficient that paragraph 36 pleaded that the slabs did not comply with paragraph 2.08 of the Employers Requirements, I have to say that I remain of the view that it would be necessary to plead this specific non-compliance expressly in order to allow that claim to be advanced in these proceedings.
38. There was no amendment to paragraphs 41 and 42, other than to refer to the draft amended schedule of loss which was to be served in accordance with the order of 19 June 2012 but which, as I have already identified, has not in fact yet been served. It is common ground nonetheless, as I have also already identified, that if permission is given the amended schedule of Loss will include a claim that it is necessary to take up and replace the existing slabs in both warehouse floors at a very substantial cost, both direct and indirect, by reason of the matter is [sic] sought to be introduced by paragraph 33A."
The law
"(i) If the claimant asserts a duty which was not previously pleaded and alleges a breach of such duty, this usually amounts to a new claim.
(ii) If the claimant alleges a different breach of some previously pleaded duty, it will be a question of fact and degree whether that constitutes a new claim.
(iii) In the case of a construction project, if the claimant alleges breach of a previously pleaded duty causing damage to a different element of the building, that will generally amount to a new claim."
I would simply add my own gloss to the effect that if the new breach does not arise out of the same or substantially the same facts as those already in issue on a claim previously made in the original action, it is likely to be a new cause of action.
A new cause of action? Discussion
". . . It is clear that this development, like those under consideration in the Steamship Mutual, WDA and Aldi cases, is a substantial and complex structure (or series of structures). My view is that since the existing claim is advancing a claim for damages for breach of contract in relation to design, workmanship and non-compliance with the Employers Requirements which is limited to 3 specified elements of that development, one being the internal warehouse concrete floor slabs, then it follows that further allegations of further defects in those slabs, even though they involve separate and distinct allegations of breach and allegations of loss, are nonetheless part of the same cause of action. . . ."
Arising out of the same or substantially the same facts?
"If I am wrong in my conclusion in relation to the new claim, I consider that the claimant cannot successfully rely in the alternative upon this argument. That is because I do accept the arguments of Ms Sinclair and Mr Cannon QC that to introduce the steel fibre content claim would involve a major investigation, both pre-trial and at trial, into facts and matters which are not on the existing statement of case on the agenda at all for trial. In particular, I accept their submissions that if the steel fibre content claim was allowed to be added, that would involve a major investigation into:
(1) The original design for the floor slabs in terms of thickness and steel fibre content. I accept Mr Cannon's submission that notwithstanding the references in the existing Particulars of Claim to isolated areas of floor thickness, there would have been no need to consider the design so far as thickness or steel fibre content on the existing pleading.
(2) The extent to which the floor slabs have been constructed using steel fibres with a content below 30kg/m3, and the consequences of that in terms of the structural adequacy of the floor slabs in the long term.
Mr Hughes QC submitted that this would inevitably have been raised at trial, because now that it is known it is a factor which the experts would undoubtedly have wished to raise in order to support or to criticise (as the case may be) the remedial works solution adopted by the claimant. However I do not accept that submission. On the current pleaded case the claim would be limited to damages for the repair costs. There would be no slab replacement claim in play. It follows that there would be no necessity to investigate the structural adequacy of the slabs. Furthermore, even if I was wrong about that, it would be perfectly possible for the claimant's expert to refer to the steel fibre content issue to support the remedial scheme on a technical basis, without it becoming in issue at trial. That is because it would be no different to other cases where a particular remedial scheme is being justified by reference to one factor or series of factors which are said to be the defendant's legal responsibility and others which are not. The court would be concerned with the latter category only as relevant to the question whether the remedial scheme was justified by reference to the matters for which the defendant was liable, which is very different to the enquiry necessary where they are also relied upon as further allegations of breach by the defendant.
(3) Whether or not the use of concrete with a steel fibre content of below 30kg/m3 rendered the defendant in breach of its obligations in relation to design, workmanship or the Employers Requirements, including an investigation into whether or not it meant that the specified rack loading requirement could not be guaranteed, and the consequences of that upon the "lettability" of the unit.
(4) The nature and extent of the proposed remedial scheme to address this particular problem, i.e. complete replacement, and its justification on cost and other grounds. The costs incurred. Whether or not the claimant could also claim what would not appear to be the wasted costs already incurred in undertaking the more limited remedial works previously identified."
Costs
Lord Justice Rimer:
Lord Justice Longmore: