QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
SECRETARY OF STATE FOR TRANSPORT |
Claimant |
|
v |
||
PELL FRISCHMANN CONSULTANTS LIMITED |
Defendant |
|
(No. 2) |
____________________
Official Court Reporters
Cliffords Inn, Fetter Lane, London, EC4A 1LD
Telephone: 0207 269 0370
Mr Jeremy Nicolson QC and Mr James Cross QC ( instructed by Beale & Co) appeared for the defendant
____________________
Crown Copyright ©
MR JUSTICE JACKSON:
Part 1: Introduction
Part 2: The Facts
"(1) The contractor shall design parts of the permanent works as required in accordance with the provisions of the specification and submit drawings and specifications of his design to the Engineer. The contractor may submit a design prepared on his behalf by a sub-contractor or professional designer or propose a design prepared by the manufacturer.
(2) The Engineer shall examine and check the contractor's design or proposal and inform the contractor in writing, within a reasonable period after receipt of full particulars, either:
(a) that the design or proposal has the approval of the Engineer, or
(b) in what respects in the opinion of the Engineer the design or proposal fails to meet the requirements of the specification.
In the latter event the contractor shall take such steps or make such changes to the design or proposal as may be necessary to meet the Engineer's requirements and to obtain his approval…"
Part 3: The Present Proceedings
Part 4: The Proposed Amendments
(i) Pell Frischmann owed contractual and tortious duties to the Secretary of State to perform its functions under Clause 8B of the Contract with reasonable skill and care.
(ii) The Contract specification allowed AMEC three options in respect of steel for the bearings.
(iii) AMEC sub-contracted the design and supply of the roller bearings to FIP.
(iv) Pell Frischmann approved the bearings design, which was produced by FIP and adopted by AMEC.
(v) The bearings were made of steel which was too hard and/or not in a permanent oil bath. Also, the rollers and bearings have been affected by corrosion. The steel used did not comply with the requirements of the specification.
(vi) Pell Frischmann was negligent and in breach of contract in that it failed to spot that AMEC's design for the rollers and bearings did not comply with the requirements of the specification.
(i) A great deal more detail is given about the design of the roller bearings and the narrative history of events.
(ii) The mechanism of failure, in particular the development of stress corrosion, is pleaded in greater detail.
(iii) The particulars of breach of duty pleaded in paragraph 43 of the particulars of claim are substantially expanded. In particular sub-paragraph (c) is expanded to allege that Pell Frischmann ought to have spotted flaws in the design relating to the hardness of the steel, the composition of the steel and propensity to corrosion. In relation to corrosion, the Secretary of State's case is further amplified in a new sub-paragraph (g).
"Further, PF ought to have established and/or ascertained that AMEC's design of the roller bearings meant that (i) the non working faces of stainless roller plates were attached to structural steel upper and base plates, which were sprayed with aluminium and that this allowed two dissimilar metals (namely, the aluminium and the stainless steel of the roller plates) (ii) the ends of the stainless rollers were covered by tin bronze end plates (referred by FIP in their drawings as 'guide low friction strips') and that this allowed contact, and the trapping of moisture, between two dissimilar metals (namely, the tin bronze of the end plates and the stainless steel of the rollers) and that AMEC's design thereby failed to take any or any adequate account of paragraph 6.3 of BS5400: Part 9: Section 9.2 and/or paragraph 6 of the Guidance Notes. Further, PF should have known and/or ascertained that this led to the risk of electrolytic action between the metals and any increased risk of corrosion".
"Further, in breach of the duty of care pleaded at paragraph 20 above, Pell Frischmann failed to exercise reasonable skill and care in its role as engineer under the SST/AMEC Contract and/or in the directing and supervising of the works in that:
(a) Pell Frischmann failed to check adequately or at all whether the steel and/or the bearings in fact supplied complied with SST/AMEC Contract. In particular, Pell Frischmann should have checked and ascertained (whether by consideration of material certificates and or heat treatment certificates or otherwise):
(i) The hardness of the steel in fact supplied
(ii) The composition of the steel in fact supplied
If PF had done so, it would have discovered that the bearings did not comply with the SST/AMEC Contract by virtue of their hardness and composition and should have refused to allow AMEC to use the materials on the Viaduct. The SST refers to and further relies upon paragraph 43 above and Appendices 7 and 8.
(b) PF failed to inspect the installation of the bearings adequately or at all in that it should have discovered that steel supplied and/or installed was corroding and/or exhibiting rust staining (a photograph dated 20th February 1997 of an installed roller bearing exhibiting rust staining is attached at appendix). As a result, PF should have appreciated that the steel was not non corroding and/or did not have adequate corrosion resistant properties and therefore did not comply with the AIP or BS5400: Part 9: Section 9.1, that AMEC had not used adequate corrosion protection measures and/or systems (contrary to Clause 6.2 of BS5400: Part 9: Section 9.2 and despite FIP's technical report number RC95046) and that this led to risks of corrosion on other roller bearings, that the required co-efficient of friction (in the order of 0.01) would be exceeded and of maintenance problems.
(c) PF failed to warn or advise the SST that:
(i) The steel of the rollers and roller plates was not non corroding, was not adequately corrosion resistant for use in the environment on the Viaduct and/or was not adequately protected against corrosion.
(ii) Inner skirts were to be and/or were installed only on a total of 16 roller bearings at piers A,U1, II and JJ, and that no such inner skirts were to be provided to the other bearings. The SST does not know, in advance of disclosure, whether PF or AMEC intended such skirts to provide any protection from corrosion but avers, in any event, they were only installed on a limited number of bearings".
Part 5: The Law
"(1) For the purposes of this Act, any new claim made in the course of any action shall be deemed to be a separate action and to have been commenced:
(a) in the case of a new claim made in or by way of third party proceedings, on the date on which those proceedings were commenced; and
(b) in the case of any other new claim, on the same date as the original action.
(2) In this section a new claim means any claim by way of set off or counterclaim, and any claim involving either:
(a) the addition or substitution of a new cause of action; or
(b) the addition or substitution of a new party…
(3) Except as provided by section 33 of this Act or by rules of court, neither the High Court nor any County Court shall allow a claim within sub-section (1)(b) above other than an original set off or counterclaim to be made in the course of any action after the expiry of any time limit under this Act which would affect a new action to reinforce that claim…
(4) Rules of court may provide for allowing a new claim to which sub-section (3) above applies to be made as they are mentioned, but only if the condition specified in sub-section (5) below are satisfied and subject to any further restrictions the rules may impose.
(5) The conditions referred to in sub-section (4) above are the following:
(a) In the case a claim involving a new cause of action, if the new cause of action arises out of the same facts or substantially the same facts as are already in issue on any claim previously made in the original action; and…"
"(1) This rule applies where:
(a) a party applies to amend his statement of case in one of the ways mentioned in this rule; and
(b) a period of limitation has expired under:
(i) the Limitation Act of 1980…
(2) The court may allow an amendment whose effect will be to add or substitute a new claim but only if the new claim arises out of the same facts or substantially the same facts as a claim in respect of which the party apply for permission has already claimed a remedy in the proceedings".
"A cause of action is simply a factual situation the existence of which entitles one person to obtain from the court a remedy against another person"
That definition has subsequently been adopted on many occasions.
"Where there are found in completed buildings serious defects of the type here under review the facts relating to design, execution and superintendence are inextricably entangled until such time as the court succeeds in elucidating the position through evidence. The design has inevitably to be closely examined even if the only claim relates to superintendence, and all the more so if the designs are, as is further alleged here, experimental or such as need amplification in the construction progresses. The architect is under a continuing duty to check that his design will work in practice and to correct any errors as they emerge. It savours of the ridiculous for the architect to be able to say, as it was here suggested to him that he could say: 'true, my design was faulty, but, of course, I saw to it that the contractors followed it faithfully' and be enabled on that ground to succeed in the action.
The same, or substantially the same set of facts, falls to be investigated in relation to the design claim and the superintendence claim. The plans and specifications and ancillary documents are relevant to the superintendence claim as well as to the designer claim: hence the inability of the defendant to allege prejudice with regard to the preparation of his defence if this appeal is allowed. Accordingly, the "new cause of action" falls within the ambit of RSC Ord. 20 r. 5(5), and it is one which the court has jurisdiction to permit to be pursued".
At page 879 G Edmund Davies L.J. expressed his complete agreement with Sachs L.J. on this point. At page 880 Cross L.J. said this:
"It is no objection to amendment under Ord. 20, r. (5) that some of the facts out of which the new cause of action arises are peculiar to it, and some of the facts out of which the old cause of action arises are peculiar to it. It is enough if the overlap is so great that the new cause of action can fairly be said to arise out of substantially the same facts as the old cause of action. For the reasons given by Sachs L.J. I think that this is the case here and that there was power to allow the amendment in question under Ord. 20, r. 5(5)"
"In the present case, if one remembers what a cause of action is (for instance, to refer back to the dictum in Letang), if one looks to the size of this particular building, to its complexities, to other matters of degree, to the statement of claim before the proposed re-amendment, to the attitude of the appellants' solicitors in the correspondence at the material time, to which I have referred, and avoids what I think are unnecessary subtleties, I feel bound to agree with the learned judge where he concluded, having referred to the cases on what is a cause of action, the statement in both its original and amended form related only to the air conditioning. I think that its effect was to narrow the causes of action so that they became confined to breaches of contract concerned with air conditioning and negligence resulting in damages to the air conditioning. In the light of the definitions of a cause of action already referred to, I do not think one can look only to the duty on a party, but one must also look to the nature and extent of the breach relied upon, as well as to the nature and extent of the damage complained of n deciding whether, as a matter of degree, a new cause of action is sought to be relied upon. The mere fact that one is considering what are, as it is said, after all only different defects to the same building does not necessarily mean in any way that they are constituents of one and the same cause of action.
Thus I conclude that whether there is a new cause of action in any circumstances is a mixed question of law and fact. I am satisfied that the learned judge correctly directed himself on the law on this point, and not only am I unable to say that he applied that law incorrectly to the facts of the case, I think positively that he applied that law correctly to the facts of the case.
Thus I must consider whether the contended for new cause of action arises out of the same, or substantially the same, set of facts as is provided for by Order 20 r. 5(5). Although exception was taken to the proposition in the course of the argument, I am still of the view that in the context of this particular case the position on this aspect is a fortiori the position on the first aspect, to which I have referred. Again, it must be a question of degree. The learned judge decided that there was insufficient overlap, relying upon a dictum from the judgment of Cross L.J. in Brickfield's case, to which I have already referred.
I respectfully agree with the conclusion to which the learned judge came that there was insufficient overlap. Thus the learned judge (I think correctly) held that he had no jurisdiction to allow the sought for re-amendment of the statement of claim in this case".
Both Lloyd L.J. and Caulfield J. agreed with that judgment. At page 101 Lloyd L.J. said this:
"It may seem hard on the plaintiffs in this case that they cannot amend their statement of claim to include damage to the brickwork. But in general, the proposition for which Mr. Harvey contends would work against the interests of building owners. Thus, if in the present case there had been no question of limitation, and if the plaintiffs had brought an action for damage to the air conditioning and recovered judgment at a time when the damage to the brickwork had not yet occurred, then, if Mr. Harvey's propositions were correct, it would be too late for the plaintiffs to bring an action for the brickwork, not because of any question of limitation, but because of the so-called rule in Conquer v Boot under which a plaintiff must bring forward his entire case in respect of one and the same cause of action at the same time. That rule could work obvious injustice to a plaintiff if Mr. Harvey's universal proposition were correct. In general, justice between the parties to a building contract will best be served by allowing that there may be separate causes of action in relation to the same building, depending upon the facts of the case. Where the limitation has intervened between pleading the first cause of action and applying for leave to amend to plead the second cause of action, as it may have done here, then RSC Order 20, r. 5 goes at least some way to mitigate the hardship to the building owner".
"Mr. Steel argued that the new cause of action does not arise out of the same or substantially the same facts as the pleaded claim. He submitted that the material facts upon which the new cause of action has to be founded are significantly different and go much further than the material facts that were pleaded in support of the unamended cause of action. He submitted that there was insufficient overlap between the material facts of the a cause of which alleges negligent inspection and certificate of the castings with that which alleges reliance by APPH on negligently made misstatements in both Black Clawson and Lloyds Register certificates. Mr. .Steel summed up the position by submitting that one only had to look at the facts in McNaughton and compare the unamended pleading with those factors. It was clear that to embark upon the new cause of action was to embark upon quite a different exercise from that involved in the original cause of action. He pointed out that this was emphasised by the extent and scope of the proposed amendment.
Mr. Steel referred me to the decision of Court of Appeal and the judgment of May L.J. in Steamship Mutual v Trollope & Colls (1986) 6 Con LR 11 at 24 and submitted that it was a question of degree and involved forming a broad impression as to whether or not there was a sufficient overlap in the facts giving rise to the two causes of action. He argued that, although there was an overlap, it was insufficient. I agree with Mr. Steeel's submission. I accept that it is a matter of degree. It is true that a certain amount of factual material is common to both causes of action such as the role of Lloyds Register in the inspection and certification of the steel castings being manufactured by Black Clawson for Redman Broughton for APPH. I am prepared to accept that the facts relating to the manner in which Lloyds Register carried out their inspection and certification are relevant to deciding whether the misstatements made in the certificates (if misstatements there be) were made negligently. However, I agree with Mr. Steel that the cause of action for negligent misstatement does represent a significant change in the nature of the proceedings and will involve a consideration of factual material which did not arise on the original claim. I agree that an impression of the potentially significant extent of this can be seen by comparing the unamended pleading with the guidelines in McNaughton and Caparo. In my opinion, the most obvious way in which my conclusion that there is an insufficient overlap between the facts out of which the two causes of action arise is the serious prejudice to which I am persuaded Lloyds Register would be exposed in dealing with the factual matters raised by the proposed amendment (as to which, see below). I have therefore come to the conclusion that the facts of the new cause of action are not the same or substantially the same as the pleaded case. Accordingly, in my judgment, I have not got jurisdiction to allow the amendment".
"Whether or not the new cause of action arises out of substantially the same facts as that already pleaded is substantially a matter of impression".
The Court of Appeal also considered the effect of other amendments which were being allowed upon the amendments under consideration. At page 1416 the court said this:
"He (the judge) started by deciding that the correct approach was to assume that the amendments which he had already allowed to add the plea of breach of contract had been made. In this respect we are confident that he was correct".
"In my view where an amendment pleads a duty which differs from that pleaded in the original statement of claim it will, or certainly will usually, raise a new cause of action. If there is no allegation of a different duty but different fats are alleged to constitute a breach of the duty it is more difficult to decide whether a new cause of action is pleaded. Several of the cases to which we were referred during the course of argument seem to me to come into this caregory, namely Brickfield Properties Limited v Newton [1971] 1 WLR 862; Steamship Mutual v Trollope & Colls (referred to above) and Hamlin v Edward Evans (1996) PNLR 398".
At page 372 Sir Iain Glidewell said this:
"I turn therefore to consider whether the facts pleaded in the proposed amendment are "the same…or substantially the same" as those originally pleaded in the unamended statement of claim. In Welsh Development Agency v Redpath Dorman Long Ltd [1994] 1 WLR 1409 a division of this court of which I was a member said that "whether or not the new cause of action arises out of substantially the same facts as that already pleaded is substantially a matter of impression" (at page 1418D). I do not resile from that description. Having in the present case considered the facts alleged in the unamended statement of claim and the facts sought to be added by way of amendment it is my clear impression that the second set of facts are not "the same … or substantially the same …" as those originally pleaded".
(i) If the claimant asserts a duty which was not previously pleaded and alleges a breach of such duty, this usually amounts to a new claim.
(ii) If the claimant alleges a different breach of some previously pleaded duty, it will be a question of fact and degree whether that constitutes a new claim.
(iii) In the case of a construction project, if the claimant alleges breach of a previously pleaded duty causing damage to a different element of the building, that will generally amount to a new claim.
(iv) When considering whether one claim arises out of "substantially the same facts" as a previous claim, it is necessary to examine the extent to which the facts of the first claim and the facts of the second claim overlap, and the extent to which they diverge. It will then be a matter of impression whether the test is satisfied.
(v) When carrying out the analysis required by section 35 of the 1980 Act and CPR r. 17.4, the judge must treat as part of the original claim those amendments which he has already decided to allow.
Part 6: Decision
(i) Sub-paragraph (h) alleges breach of a duty which has previously been pleaded.
(ii) The breach alleged in sub-paragraph (h) is causative of damage to the same element of the Viaduct as previously pleaded, namely the roller bearings.
(iii) The mechanism of failure flowing from sub-paragraph (h), namely corrosion, has previously been pleaded.
(iv) The Secretary of State's case on corrosion has been expanded by those amendments which (by consent) I have decided to allow. Sub-paragraph (h) is only a modest extension of those other pleaded allegations.
(v) One of the drawings relied upon by the Secretary of State in relation to paragraph 43(h) is FIP's drawing A13924. This shows the tin bronze end plates referred to in paragraph 43(h). This drawing is already pleaded in amended paragraph 30(f) of the particulars of claim (an amendment which is being made by consent).
(vi) The loss and damage flowing from this breach is the same as that already pleaded, namely the cost of removing and replacing the roller bearings.
(i) The matters which Pell Frischmann allegedly overlooked while supervising are essentially the same as the matters which, allegedly, Pell Frischmann failed to foresee when checking AMEC's design.
(ii) The defects which allegedly flowed from the breaches alleged in paragraph 44 are the same as the defects already pleaded, namely deterioration and failure of the roller bearings.
(iii) The mechanism of failure allegedly flowing from the breaches set out in paragraph 44 is the same as the mechanism of failure already pleaded.
(iv) The loss and damage flowing from the breaches alleged in paragraph 44 are precisely the same as the loss and damage already pleaded.
(v) Both paragraph 43 and paragraph 44 of the amended particulars of claim allege breaches of Pell Frischmann's checking duties. Although the checking function in paragraph 43 is performed before the checking function in paragraph 44, both checking functions are broadly similar.
(vi) The reasoning of the Court of Appeal in Brickfield Properties Limited v Newton [1971] 1 WLR 862 would suggest that the degree of factual overlap in the present case is quite sufficient. Mr. Nicholson has submitted that I ought not to follow the approach of the Court of Appeal in Brickfield. I reject that submission. The Court of Appeal was applying a provision of the RSC which has re-appeared in section 35 of the 1980 Act and in CPR r. 17.4(2). Brickfield has been followed or cited with approval on many occasions. The Court of Appeal's decision in Brickfield is binding upon me.
(End of Judgment)