BUSINESS & PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY & CONSTRUCTION COURT (QBD)
2 Redcliff Street Bristol BS1 6GR |
||
B e f o r e :
(sitting as a Judge of the High Court)
____________________
COMMUNITY R4C LTD |
Claimant |
|
- and - |
||
GLOUCESTERSHIRE COUNTY COUNCIL |
Defendant |
____________________
Sarah Hannaford QC (instructed by Eversheds Sutherland (International) LLP, Cardiff) for the Defendant
Hearing dates: 2nd to 4th March and 24th June 2020
____________________
Crown Copyright ©
Covid-19 Protocol: This judgment was handed down by the judge remotely by circulation to the parties' representatives by email and its release to BAILII at 10:15am on 17 July 2020.
HH Judge Russen QC:
i) Introduction (paragraph 2)
ii) The Witnesses (paragraph 27)
iii) CR4C's Application dated 2 June 2020 (paragraph 41)
iv) The First Issue: CR4C as an economic operator which could have pre-qualified
a) Preliminary Observations (paragraph 57)
b) The Benchmark for Pre-Qualification (paragraph 79)
c) The Interpretation of Regulation 91 (paragraph 104)
d) The Concept of an 'Economic Operator' (paragraph 144)
e) The Pleaded Case (paragraph 168)
f) CR4C as an Economic Operator (paragraph 184)
g) CR4C's Prospects of Pre-Qualifying (paragraph 207)
v) The Second Issue: Limitation
a) The Test under Regulation 92(2) (paragraph 261)
b) The Rival Contentions (paragraph 273)
c) Analysis (paragraph 278)
vi) Disposal (paragraph 347)
Introduction
"C4RC instead brings this case for non-commercial reasons in the public interest.
These include:
(a) Public (judicial) recognition that GCC breached the law, ultimately signing a revised contract unlawfully that cost it some £140-£160m more than the competitive result signed in 2013. As a public letter signed by Councillors and others in January 2019 and sent to GCC puts it, GCC consistently wrongly and publicly represented the contract cost was £500m right up until disclosure in December 2018.
(b) The issue of secrecy is particularly at issue at this stage of the case as your Lordship will have to decide (preliminary Issue I) whether, as we submit, C4RC did not and could not have known of the breach of law until GCC released material on 20 December 2018, nearly 6 years after the early 2013 contract and nearly 3 years after the February 2016 contract. The Court need only address what was known or could have been known by C4RC, but as the Judge will no doubt appreciate it is the Claimant's belief and stated position that there was deliberate concealment of important facts.
(c) It is a matter of important principle that GCC obtains the best value for money available on behalf of taxpayers and this is only possible by compliance with the procurement rules.
(d) Finally, and importantly, if ultimately a breach of procurement law is found at final trial, there will be a solid basis for the UK Government/GCC to find that the overpayment to UBB is unlawful State aid. Any overpayment to date will be recoverable from UBB (GCC may immediately have £10's of millions to spend on public services) and any future overpayment will not be payable."
"[t]he County Council's planned solution is to build a huge "mass-burn" incinerator into which everything in our black bags will be thrown with no sorting or pre-treatment, costing the taxpayer an estimated £600 million over 30 years, creating greenhouse gases and risk of widespread pollution, and destroying valuable materials forever. With regulations heading towards recycling, recovery and climate protection, this wasteful project may soon be heavily taxed and/or unusable."
i) firstly, it was made pursuant to a clear, precise and unequivocal amendment clause (in Schedule 26 of the 2013 Contract), which means that it was permissible under Regulation 72(1)(a); and
ii) secondly, it was not a "substantial" amendment (as that is defined in Regulation 72(8)) and was permissible under Regulation 72(1)(e).
i) Limitation; and
ii) Whether CR4C is an economic operator which could have pre-qualified having regard to any selection criteria that could have been imposed upon it by the Council pursuant to Regulation 58 of the Regulations.
The Witnesses
CR4C's Application dated 2 June 2020
i) the suggested justification for the lateness of Mr Burnett's statement;
ii) the apparent significance of the point sought to be addressed in that statement to the determination of the limitation issue. There would obviously be less prejudice to CR4C in not permitting it to adduce belated evidence on a marginal point than a central one; and
iii) the prejudice to the Council in admitting the statement (even as hearsay evidence) if the practical effect of doing so, at such a late stage, is that it unfairly leaves the Council in a position of being unable to address it adequately. Again, the apparent significance of the late evidence comes into the balancing exercise when viewed from the perspective of the respondent to the application. That said, I have already explained that the Council's position was that Mr Burnett's statement addressed a rather marginal point which did not compel the need for him to be cross-examined.
The First Issue: CR4C as an economic operator which could have pre-qualified
Preliminary Observations
"any person or public entity or group of such persons and entities, including any temporary association of undertakings, which offers the execution of works or a work, the supply of products or the provision of services on the market".
"Enforcement of duties through the Court
(1) A breach of the duty owed in accordance with regulation 89 or 90 is actionable by any economic operator which, in consequence, suffers, or risks suffering, loss or damage."
"Member States shall ensure that the review procedures are available, under detailed rules which member states may establish, at least to a person having or having had an interest in obtaining a particular contract and who has been or risks being harmed by an alleged infringement."
i) that Satisfactory Planning Permission for the EfWP (within the meaning of the 2013 Contract) was obtained in August 2015, UBB submitted their revised project plan on 24 June 2015 ("the RPP" which was the subject of the Ernst & Young Report mentioned below on the limitation issue) and the Council resolved to accept it at its Cabinet meeting on 11 November 2015. The Amended Contract was signed on 21 January 2016; and
ii) on the hypothetical analysis that the Council would have decided that it needed to procure a new contract, the relevant time for commencing a "new" procurement was no later than November 2015. That is because the decision to reject the RPP would have been made after 24 June 2015 (when the RPP was submitted) and, at the latest, on 11 November 2015 when the Cabinet meeting took place. In any event, the relevant date should be no later than the actual date of the 2016 Contract, namely 21 January 2016.
The Benchmark for Pre-Qualification
i) that the Cabinet Office guidance (to which Regulation 107 directs attention) required "[t]he financial assessment of potential providers to be undertaken in a manner that is proportionate, flexible and not overly risk-averse while ensuring taxpayer value and safety is protected and the relevant EU procurement law is complied with." CR4C also referred to the guidance pointing out that potential providers may have been recently formed and so unable to provide accounts and should not be purely disadvantaged on that basis, as there were a number of alternative means of providing sufficient evidence of financial and economic standing. The guidance relied upon was contained in 'Procurement Policy Note Supplier Financial Risk Issues, February 2013';
ii) that Regulation 58(9) provides that the minimum yearly turnover required of an economic operator "shall not exceed twice the estimated contract value, except in duly justified cases" and that a purposive reading of the provision and EU Guidance means that the comparison is between a bidder's (including a consortium's) annual turnover and the estimated annual value of the contract. This provision for a cap upon the minimum required turnover would also be subject to the need for proportionality imposed by Regulation 58(4); and
iii) in relation to technical resources and experience, that "it is averred that what the [Council] could ask for would have to be proportionate and linked to the requirements of the contract to be let (Regulations 18 and 58)" and "would have been sufficiently flexible to accept a range of cogent evidence of technical experience/expertise."
"The type of proportionate requirement that the [Council] may lawfully have chosen is open to conjecture, but would need to be directly linked to having sufficient access to finance [sic] to undertake the services (based on its own solution, not on the costs of an EfW plant this is far more capital intensive) and (likely) indemnity insurance to cover any risk."
" does not (really cannot) counter with an alternative "shadow PQQ" but submits that under any putative tender process GCC would have undertaken market testing first and if approached with an open mind, and as is becoming increasingly accepted (in particular in the competitive dialogue procedure), have kept the selection criteria relatively light, and incorporate aspects of deliverability (which may entail aspects of financial viability) in the later stages of the process."
and
"Certainly GCC must be able to be comfortable as to financial and economic issues (and technical issues, though its case on this is vanishingly thin) but the selection criteria should be set at levels which permit a number of alternative solutions to proceed past the first threshold test and into the more detailed elaboration of a Competitive Dialogue procedure described [in the Regulations]"
For the first-stage, turnover test:
"For consortium/group submissions where supported by an appropriate guarantee then the consolidated turnover across the entities will be assessed."
and
"GCC reserves the right to reject PQ Applications, and not assess the PQQ further (if any Applicant and, in the case of Consortia, if any Party fails to meet the Minimum Standards as identified in this PQP Section [x] and in the PQQ; otherwise, the assessment of the PQ Application continues."
For the second stage, due diligence test:
"Where the Applicant is a Consortium, each Party to an Applicant will be assessed against these criteria in order for GCC to obtain confidence in the ability of the Parties to fulfil their obligations under a Contract, on a joint and several basis, should it be successful."
"The weighted score from each section are then added together to derive a combined score for each Applicant, shareholder or consortium member within a Group SPV or Contractual JV respectively. An Applicant must achieve combined score of no less than 5 out of a possible 10 to pass the 2nd stage of the financial assessment."
"In order to establish an overall score for a Group SPV or Contractual JV the scores of each shareholder or consortia member will be averaged."
"As part of its due diligence process, GCC will ask Applicants and Parties to a Consortium, to provide a statement detailing their financial position in full from the date of their latest submitted company accounts, or relevant financial information, to the PQ Application Deadline."
and
"The accounts of any Guarantor of a Party or a single Applicant will only be assessed if:
- The Applicant, or Party to a Consortium, is relying on a Guarantor in order to prequalify;
- Further investigations are triggered as described above during the due diligence process; and
- The Applicant or Party as applicable provides satisfactory confirmation from that parent company (or other Guarantor) that it will provide a Parent Company Guarantee."
"Where necessary, contracting authorities may clarify in the procurement documents how groups of economic operators are to meet the requirements as to economic financial standing or technical ability referred to in regulation 58 provided that this is justified by objective reasons and is proportionate."
The Interpretation of Regulation 91
"A Contracting Authority could raise the "preliminary issue" of selection criteria against any Claimant in a direct award case (where by definition there was no PQQ) and the case would be entirely disposed of on the basis of an inability to prove that a (necessarily hypothetical) bid would not have met a (hypothetical) PQQ."
"Issue3: Causation of loss
205. In order for a breach of the Regulations to be actionable Regulation 46(6) provides:
"A breach of the duty owed in accordance with paragraph (1) and (2) is actionable by any economic operator which, in consequence, suffers, or risks suffering, loss or damage and those proceedings shall be brought in the High Court."
206. What then is the test to be applied in relation to this issue where a breach of the Regulations has been established? I accept Mr Patel's submission that the correct test, in the context of this case where I am not considering the detail of the loss, is whether there is a real or significant as opposed to a fanciful chance that Mears would have been selected for the ITCD stage of the Procurement had LCC given advance disclosure of the weightings in the Scoring Table. I consider that this follows from the following decisions."
[The Judge then went on to refer to Letting International v Newham [2007] EWCA Civ 1522 (Court of Appeal); [2008] LGR 908 (Silber J) and Lion Apparel Systems Limited v Firebuy Limited [2008] EuLR 191 (Morgan J).]
i) Regulation 2(1) of the Regulations defines the "Public Contracts Directive" as Directive 2014/24/EU. Regulation 2(2) provides that unless the context requires any expression used in the operative part 2 of the PCRs shall have the same meaning as in the Directive. Mr Sinclair said that this is the effect of EU law in any event under the well-established Marleasing principle of consistent interpretation (and disapplication of conflicting national rules) when a Directive is implemented. He referred to the decision of the CJEU in Uniplex (UK) Ltd v NHS Business Services Authority, Case C-406/08, [2010] PTSR 1377, [45]-[49], for the specific application of this principle as regards UK procurement Regulations and the EU Directives;
ii) Such consistent interpretation also extended to the provisions of the Remedies Directive which was also implemented by the Regulations. The right to a remedy under Regulation 91(1) if a party 'suffers or risks suffering loss or damage' is in line with the wording of Article 1(2) of the Remedies Directive. Article 1(3) of the Remedies Directive provides that "Member States shall ensure that the review procedures are available, under detailed rules which the Member States may establish, at least to any person having or having had an interest in obtaining a particular contract and who has been or risks being harmed by an alleged infringement." (my emphasis);
iii) In Pressetext Nachrichtenagentur, Case C-454/06 (19 June 2008), the national court had referred to the CJEU (by its question 6) the question as to what was involved in the concept of 'harm' in Article 1(3) of the Remedies Directive and whether it extended to the situation where a party has been deprived of the opportunity to participate in a procurement procedure because the contracting authority did not, prior to making the award, publish a contract notice. The CJEU did not address that question as it followed the proposal of Advocate General Kokott, delivered on 13 March 2008, that it should decide only the first three questions referred to it. However, AG Kokott delivered her Opinion on question 6 in terms which emphasised the need for the Directive to be practically effective (see further below). Mr Sinclair pointed out that AG Kokott had also relied on the effectiveness of the objectives of damages actions in procurement cases (namely that of providing legal protection for candidates and tenderers as well as having a disciplinary effect upon contracting authorities) in her Opinion in Uniplex at [AG55] [AG56].
"143. Article 1(3) of Directive 89/665 permits the Member States to restrict the right to bring an application in relation to a review procedure for the award of public contracts in two respects: on the one hand, through the requirement that the applicant should have an interest in the relevant public contract and, on the other, through the requirement of existing or imminent harm to the applicant. In this way public interest actions and actions brought by applicants with no prospect of success may be excluded."
144. However, that must not affect the practical effectiveness of the directive. The restrictions on the entitlement to bring an action must therefore be construed in the light of the twofold aim of the directive: on the one hand, the individual must be afforded an effective legal remedy in connection with the award of public contracts and, on the other, the requisite review of the lawfulness of the decisions by contracting authorities must be facilitated.
145. For, as is apparent from the first and second recitals in its preamble, Directive 89/665 seeks to strengthen the means available at national and Community levels in order to secure the actual application of the Community directives in the sphere of public procurement. To that end the Member States are obliged under Article 1(1) of the directive to ensure that unlawful decisions by contracting authorities can be reviewed effectively and as swiftly as possible.
[ ]
148. The possibility of harm to the person concerned must be presumed where it is not manifestly excluded that the applicant would have received the award if the legal infringement alleged had not occurred. Where, as in the present case, the public contract is awarded directly without prior contract notice, it follows from the fact that the person concerned is allegedly unlawfully precluded from participating in the award procedure that he may have lost a contract and thus suffered loss.
[ ]
149. Nor may actual proof of standing be required of the person concerned at the stage of an application for review; in the same way, he cannot be required to provide evidence that he would have received the award if the alleged infringement had not taken place. Otherwise access to the review procedure would be rendered impossible in practice or at any rate excessively difficult. In particular in cases of direct awards such as the present case, it would be barely possible for the person concerned to provide actual proof of standing, since he would have no accurate information about the requirements laid down by the contracting authority because of the lack of a prior contract notice.
[ .]
151. On the sixth question I therefore conclude that an application for review under Article 1(3) of Directive 89/665 is admissible if the applicant persuasively asserts an interest in the public contract, the existence of a legal error and the possible harm suffered or about to be suffered. If the contract was awarded without prior publication of a contract notice, it follows from the fact that the person concerned was precluded from participating in the award procedure that he may have suffered harm unless there is a manifest lack of standing on its part."
The Concept of an Economic Operator
i) The clarification in recital (14) to the Public Contracts Directive (2014/24/EU) that the notion of 'economic operators' should be "interpreted in a broad manner so as to include any persons or entities which offer the execution of works irrespective of the legal form under which they have chosen to operate".
ii) That recital, informing the interpretation of the substantive provisions of the Directive, was consistent with the express inclusion of universities within the list then set out in the recital and with the decision of the CJEU in December 2009 in Consorzio Nazionale Interuniversitario per le Scienze del Mare (CoNISMa), Case C-305/08. That decision, under the earlier Directive 2004/18/EC, confirmed that one of the primary objectives of the EC rules on public procurement was the attainment of the widest possible opening up of competition; that a person's classification as an economic operator did not depend upon establishing capability for direct performance of the contract using its own resources but that "[t]he person in question need only be able to arrange for execution of the works in question and to furnish necessary guarantees in that connection"; and that eligibility to put itself forward as a candidate was regardless of "whether it is active as a matter of course on the market or only on an occasional basis." The Court said that "any person or entity which, in the light of the conditions laid down in a contract notice, believes that it is capable of carrying out the contract, either directly or by using subcontractors is eligible to put itself forward as a candidate."
iii) Regulation 19(3) of the Regulations provides that "Groups of economic operators, including temporary associations, may participate in procurement procedures and shall not be required by contracting authorities to have a specific legal form in order to submit a tender or a request to participate."
The Pleaded Case
"The Claimant is an economic entity (as defined in Regulation 2 of the PCR 2015), the legal form being a registered Community Benefit Society. The Claimant had previously (in 2015-15) taken steps to form a consortium to win a contract for waste disposal from the Defendant (this was ultimately abandoned only once it became clear the UBB contract left no realistic scope for any other provision of services) and it would have used that consortium to bid had a procurement exercise taken place."
"As regards these issues, it is respectfully suggested that the Defendant wait until disclosure has taken place and the Claimant's witness evidence has been provided as the (hypothetical but realistic) members/composition of the consortium will be set out and made clear by way of evidence (by witnesses and contemporary documents) as will their financial standing and technical ability and how this would meet any lawful requirements."
"Our client's Part 18 request dated 21 August 2019 was made in order to identify your client's consortium bid on the basis that this had not been confirmed in your client's pleadings, despite references to a consortium having been formed previously which would have been used in this procurement exercise. Our client wanted to ensure that details of your client's consortium was within the scope of both disclosure and witness evidence so that it would have the opportunity to consider and respond in advance of the hearing in March."
CR4C as an Economic Operator
"to carry on any business for the benefit of the community by the protection and the preservation of the environment for the public benefit by:
The promotion of waste reduction, resource re-use reclamation, recycling, use of recycled products, and the use of surplus.
Advancing the education of the public about all aspects of waste generation, waste management, waste recycling and the circular economy.
The promotion of such other activities and initiatives that contribute to and stimulate the development of a local circular resource economy."
"As regards the question of economic operator, C4RC, our position, just to be clear, C4RC was offering services on the market. We do not need to, but we could, if necessary, rely on forming a consortium to do so. C4RC was offering services to Stroud District Council. Therefore, within, if you like, an English black and white letter interpretation of economic operator."
The reference to offering services to Stroud District Council was to what by the time of CR4C's 2016 Share Offer was known as the R4C Recycling Plant.
i) at the date of the 2016 Contract, 21 January 2016, CR4C had not even been registered as a Community Benefit Society; and
ii) CR4C was not by that date, and for the purposes of applying the definition of 'economic operator' in Regulation 2, carrying out or offering on the market the relevant works or services (i.e. construction, waste incineration or waste plant operation). The Council referred to CR4C's objects quoted above and to the terms of its Share Offer which was published in 2016 (and self-evidently after CR4C had been registered on 8 February 2016 with the ability to raise share capital) and referred to that initial offer being open from 29 April 2016 to 27 May 2016.
"a community-owned sustainable enterprise with a commitment to delivering long term economic, social and environmental benefits through working with local businesses and communities that will prevent, reduce, reuse and recycle material which would otherwise be thrown away and wasted thus destroying our valuable resources and doing great harm to the environment through global warming gasses and toxic emissions."
"It is also very clear that they were going to work with other parties, whether it was in a bid for a Gloucestershire City Council contract, which didn't exist" - by which he meant the contemplated consortium had not been given an opportunity to tender for the 2016 Contract "or for any other party, they would work with other parties. And as such a consortium would consist of Community R4C and Revolution R4C and other parties."
CR4C's Prospects of Pre-Qualifying
i) 2013: net current assets of £53,967 and an operating loss of £217,505;
ii) 2014: no turnover (and indicating the same for 2013 which had been in abbreviated form and not included a P&L account), net current assets of £98 and an operating loss of £95,040; and
iii) 2015: net current assets of £4,653 and (although these accounts were in abbreviated form and did not include a P&L account) an operating loss of £25,516.
"You're applying a valuation process which is not the evaluation process that a PQQ process goes through or a full tender process goes through. They look at the proposal that I put on the table to them and the proposal that I put on the table to them, or we, the consortium, put on the table to them would include aspects that prove that we have a track record of delivering the equipment, delivering it, installing it, running it. We have personnel and skill levels that meet all the requirements in terms of health and safety throughput, guarantees and all the rest. You would deliver that and you would use it, you'd do it using people with the skill set of Paul Winter, who was the CEO of Biocentre at the time, extensive experience delivering £100 million type contracts in the energy waste field. So of course, we had the experience to do this. In terms of technical experience, as the track record shows in terms of the technology in the process, it's been installed in a number of plants. KMH, who was an active technical partner of ours, were installing plants as we were talking and still do."
"But the point is that clearly a track record is not something that a company owns, it's soft intellectual property, it's something that people and processes and documentation and, you know, process diagrams and certification and data from modelling, the metrics, the model that you run all of this complicated mechanical equipment and ensure that flow rates are correct and all the rest. All of that is deep engineering modelling with experience. It's built on empirical data - you test what your outputs are and you build that into your future models. All of that is, therefore All of these plants built into Tony Manser's models, which were then transferred into ART and then later to BTL. So, these engineering models, which NBHT is based around, come from this track record."
"This is a financial model for a very different plant to what would have been proposed to the County Council. It operates at much lower margins and operates with a very low price, £20 a tonne for treating waste - the incinerator's headline price is £190 a tonne. You can understand that that makes it very demanding in terms of how you operate the plant."
i) that RR4C was a newly incorporated company which did not have direct company experience of waste plant, development construction and operation;
ii) that CR4C was also newly established as a community benefits society and had no direct experience of community fundraising under the CR4C name; and
iii) that BTL had obtained its intellectual property from ART in circumstances where ART had established a consortium to commercialise the MBHT process but the venture did not proceed because (as Mr Jarman had explained at an earlier point in his testimony) one of the consortium members Cargill Incorporation had wanted to step out of the waste market.
i) none of the projects relied upon by them had been in the last 5 years;
ii) none of them had been carried out by CR4C, RR4C or BTL; and
iii) they had not built or operated any waste disposal plants.
"I am also aware of other members of a possible consortium bid that could have been brought together for a bid in 2015/16. For example, PBS (funding and offtake, biomass boiler), Smiths (operations and CIW waste supply), Veolia (waste supply), Damar/Finning (EPC provider), KMH (mechanical design and installation)."
"Where an economic operator wants to rely on the capacities of other entities, it shall prove to the contracting authority that it will have at its disposal the resources necessary, for example by producing a commitment by those other entities to that effect."
"It is submitted that, whilst C4RC faces the inherent difficulty of any party dealing with a failure to tender (see AG Kokott in Pressetext) it is likely that a consortium consisting of all or some of the parties described by Mr Jarman and/or Mr Christensen would have bid for the GCC contract in 2015/16 (the degree of likelihood of this need not be separated from the overall question of a substantial as opposed to fanciful chance of meeting lawful selection criteria)."
The Second Issue: Limitation
The Test under Regulation 92(2)
"(2) Subject to paragraphs (3) to (5), such proceedings must be started within 30 days beginning with the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen."
The Rival Contentions
"By disclosure on 20 December 2018 of previously redacted material, including disclosure for the first time of the changes that had taken place between the First Contract and the Second Contract it became apparent that there were material changes (including to 'gate fees' or payment levels and an increase in up-front payment by the [Council]) such that the total value of the contracts were assessed by the Claimant as being in the order of a change from c. £455m (First contract/contract signed in February 2013) to c. £600m (Second Contract/contract as materially amended and signed in February (sic) 2016). In contrast, the Council had publicly consistently cited a revised value/cost of £500m."
i) that there had been a modification of the 2013 Contract which was 'substantial' within the meaning of Regulation 72(8). That provision identifies five conditions, any one or more of which will, if met, lead to the modification being considered to be substantial. They require a comparison between the 2013 Contract and the 2016 Contract. He pointed out that the terms of the 2013 Contract were only disclosed (almost entirely unredacted) in March 2017 after the Council's appeal to the First Tier Tribunal against the Information Commissioner's ruling in favour of its disclosure had failed. The 2016 Contract was not seen by CR4C (with trigger dates redacted) until 20 December 2018, after the Council had abandoned its appeal against a further ruling by the ICO and also relented on making available an unredacted version of the EY Report.
ii) once the extent of changes between the two contracts were known, whether or not the 2016 Contract had been made pursuant to a 'clear, precise and unequivocal review clause' for the purposes of Regulation 72(1)(a). One example of such a clause identified in the regulation are 'price revision clauses or options' which meet certain specified criteria); and
iii) after those first two matters had been considered, establishing that the Council was not paying UBB more for additional works or services of the kind contemplated in Regulation 72(1)(b). The regulation says a modification of contract, without undertaking a new procurement exercise, may be justified not only by reference to a regulatorily compliant review clause but also in certain prescribed circumstances militating against the case for a change of contractor despite the need for further work, services or supplies.
Analysis
(1) the 2013 Contract had been varied and the change had increased the price. However, Mr Jarman noted that the minutes referred to the authority to sign the variation being delegated to a Council office and offered his view that this signified that there had not been a material change to the contract as "you do not give delegated authority on a material change";
(2) the delay to the planning permission had resulted in increased project cost, price indexation of the capital equipment and additional financing costs. Mr Jarman observed that the net increase (after mitigation through the increased capital contribution) was not clear;
(3) the Council was having to make a further capital contribution of £17m. Mr Jarman described this as a payment to mitigate the costs of delay; and
(4) the amendment had reduced the savings by around £37m (to £153m) when compared against the landfill alternative.
i) in Mr Sinclair's opening submissions, that the £600m was a calculation based on 30 years, not 25 years. This was a correct observation upon two of the references in the offer but the Council said the point was the document noted an increase in costs rather than any change in the number of years which CR4C was using in its calculation;
ii) according to what Mr Jarman said in his witness statement, the £600m figure was just an estimate. The Council said that this explanation did not lie happily with the importance of the Share Offer to CR4C in obtaining funds for its proposed new plant. CR4C would have taken care to ensure that the price comparison between the UBB solution and its own solution was accurate and the difference in cost from the UBB contract was one of its key selling points; and
iii) according to what Mr Jarman said in cross-examination, use of the £595m figure was a mistake and it should have been pulled into line with the other references to the round £600m based upon 30 years. In addition to its other observations, the Council said that this answer was aimed simply at avoiding the obvious conclusion that CR4C had been able to reach a calculation of the increased costs (including from the information provided to the meeting of the Cabinet on 12 November 2015) for the purposes of inclusion in such a significant fund-raising document.
"It is abundantly clear that the starting point for any analysis of the process and its results, and specifically of compliance with the procurement rules, must be consideration of the original contract (first) and the nature of the changes to it (including payments made by way of 'capital contribution'), in this case therefore including the RPP and the E&Y Report and any material information (e.g. models used) to arrive at the conclusions GT has (provisionally) formed."
i) that the (redacted) figure for "Base Case with capital cont(ribution)" would have reflected "an additional Council capital contribution of £17m funded from reserves";
ii) the £86m increase in nominal all-in cost identified by Mr Mawdsley;
iii) an increase in operating costs of £23m.
i) the approximate updated Engineering and Procurement Contractor ("EPC") price (or "Updated Capex Price") which UBB had indicated in May 2015;
ii) the revised EPC price identified in a Revised Project Plan submitted by UBB on 24 June 2015;
iii) the EPC price as negotiated down by the Council between June 2015 and the date of the Report; and
iv) the increase in Capex (redacted in Table 15).
Disposal
i) CR4C is not an economic operator which could have pre-qualified having regard to any selection criteria that could have been lawfully imposed upon it by the Council pursuant to Regulation 58; and
ii) the Claim is not barred on limitation grounds under the provisions of Regulation 92(2),