[2017] UKSC 34
On appeal from: [2015] EWCA Civ 1262
JUDGMENT
Nuclear Decommissioning Authority (Appellant) v EnergySolutions EU Ltd (now called ATK Energy EU Ltd) (Respondent)
before
Lord Neuberger, President
Lady Hale, Deputy President
Lord Mance
Lord Sumption
Lord Carnwath
JUDGMENT GIVEN ON
11 April 2017
Heard on 1 and 2 March 2017
Appellant Lord Pannick QC Joseph Barrett Rupert Paines (Instructed by Burges Salmon LLP) |
|
Respondent John Howell QC Andrew Hunter QC Ewan West (Instructed by Skadden, Arps, Slate, Meagher & Flom (UK) LLP) |
LORD MANCE: (with whom Lord Neuberger, Lady Hale, Lord Sumption and Lord Carnwath agree)
Introduction
3. ATK has pursued against the NDA a claim for damages for breaches of the NDA’s obligations under the PP Directive and the 2006 Regulations in respect of the award of a contract for the decommissioning of 12 Magnox power stations, at Berkeley, Bradwell, Chapelcross, Dungeness A, Hinkley Point A, Hunterston A, Oldbury, Sizewell A, Trawsfynydd, Wylfa and two others. An agreement of compromise has been reached in respect of the claim, but the parties wish this judgment to be issued nonetheless. In short, Fraser J held, and it is for the purposes of the present appeal to be assumed, that the NDA failed to award the contract to the tenderer which submitted the most economically advantageous offer determined in accordance with the criteria which the NDA had itself specified, in breach of obligations under regulations 18(27) and 30(1) to (4) of the 2006 Regulations read against the background of the articles 29.1, 29.7 and 53 of the PP Directive. The NDA erroneously concluded that a consortium, known as CFP, had provided the most economically advantageous offer, awarding it a score of 86.48%. It awarded a consortium known as Reactor Site Solutions (“RSS”), of which ATK and another company, Bechtel, were members, a score of 85.42%. Fraser J [2016] EWHC 1988 (TCC) found (i) that CFP should have been disqualified from the competition for failing two threshold requirements, and (ii) that, in any event, RSS would have won the competition had the NDA not made “many manifest errors” (para 944) in its assessment of the tenders, but for which the NDA would have awarded RSS a score of 91.48% and CFP a score of only 85.56%.
(a) Under article 2a(2) of the Remedies Directive, a standstill period of at least ten days was required, from the date of receipt of a telephone or letter communication to an economic operator (such as ATK) that it had not been awarded the contract; during the standstill period the relevant contracting authority (here the NDA) could not enter into the contract; as implemented domestically by regulations 32(1) and 32A(5) of the 2006 Regulations, the standstill period was fixed as exactly ten days from the date of such receipt.
(b) Under article 2c of the Remedies Directive, the United Kingdom was required to allow a period of at least ten days from any such communication for the economic operator to issue proceedings seeking a review of the authority’s decision; it implemented this requirement under regulation 47D(2) by allowing 30 days beginning with the date on which the economic operator first knew or ought to have known that grounds for starting proceedings had arisen; this was coupled with a proviso under regulation 47D(3) that it did not require proceedings to be started before the end of a defined period, corresponding with that stated in article 2c. (Article 2f in fact required that domestic law allow a period of at least 30 days, from publication of a contract award notice or information given by the contracting authority about the conclusion of the contract, for challenges based on limited grounds of “ineffectiveness” identified in article 2d; this may, perhaps, have been an inspiration for the more general 30 day period in regulation 47D(2).)
(c) Under article 2(3) of the Remedies Directive, as implemented by regulation 47G, the authority, on becoming aware of the issue of a claim form relating to its decision to award the contract to CFP, was required to refrain from entering into the contract, if not already entered into, until court order or disposal of the proceedings.
7. Preliminary issues ordered by Akenhead J on 10 October 2014 were decided by Edwards-Stuart J on 23 January 2015 ([2015] PTSR 1106), leading to an appeal determined by the Court of Appeal (Lord Dyson MR, Tomlinson and Vos LJJ) by judgment dated 15 December 2015: [2016] PTSR 689. The shape of the arguments has changed, leading to a position where three main issues are now presented in the Statement of Facts and Issues as arising on this appeal. Slightly reformulated to reflect the submissions before the Supreme Court, they are:
(i)(a) whether the Remedies Directive only requires an award of damages to be made when any breach of the PP Directive is “sufficiently serious” and (b) whether the answer to this question is acte clair, so that it need not be referred to the Court of Justice?
(ii) whether regulation 47J(2)(c) of the 2006 Regulations confers a power to award damages in respect of any loss or damage suffered by an economic operator (a) in the case of any breach, or (b) only in the case of a “sufficiently serious” breach, of the Regulations?
(iii) whether (and, if so, when) an award of damages under regulation 47J(2)(c) of the 2006 Regulations may be refused on the ground that an economic operator, who issued a claim form in respect of a contract award decision within the 30 day time limit prescribed by regulation 47D of the 2006 Regulations, did not do so and inform the contracting authority that it had done so before the contracting authority entered into the contract?
8. Before Edwards-Stuart J issue (i) only appears to have arisen tangentially to an argument, which no longer directly arises, that damages were discretionary. So far as he addressed it, his answer appears to have been negative (para 86). Issue (ii), he answered: (a) Yes; (b) No (para 71). Issue (iii), he held, involved a question of fact, not suitable for resolution as a preliminary issue in this case, though his views were generally discouraging of the idea that damages would be refused on any such basis (paras 42-54). In the Court of Appeal, Vos LJ, in a judgment with which the other members concurred, determined these issues to the following effect: (i)(a) Yes. (b) Yes (para 55). (ii)(a) Yes. (b) No (paras 66-70). (iii) No (paras 71-77).
Issue (i) - Francovich condition (2) in EU law
10. Articles 1 to 3 of the Remedies Directive read:
“1(1). … Member states shall take the measures necessary to ensure that, as regards contracts falling within the scope of Directive 2004/18/EC, decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in articles 2 to 2f of this Directive on the grounds that such decisions have infringed Community law in the field of public procurement or national rules transposing that law.
…
2(1) Member states shall ensure that the measures taken concerning the review procedures specified in Article 1 include provision for powers to:
(a) take, at the earliest opportunity and by way of interlocutory procedures, interim measures with the aim of correcting the alleged infringement or preventing further damage to the interests concerned, including measures to suspend or to ensure the suspension of the procedure for the award of a public contract or the implementation of any decision taken by the contracting authority;
(b) either set aside or ensure the setting aside of decisions taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the invitation to tender, the contract documents or in any other document relating to the contract award procedure;
(c) award damages to persons harmed by an infringement.
…
(7) … except where a decision must be set aside prior to the award of damages, a member state may provide that, after the conclusion of a contract …, the powers of the body responsible for review procedures shall be limited to awarding damages to any person harmed by an infringement.
3(1) The Commission may invoke the procedure provided for in paras 2 to 5 when, prior to a contract being concluded, it considers that a serious infringement of Community law in the field of public procurement has been committed during a contract award procedure falling within the scope of Directive 2004/18/EC.”
11. The Francovich conditions derive from the Court of Justice’s decisions in Francovich v Italian Republic (Joined Cases C-6/90 and C-9/90) [1995] ICR 722; [1991] ECR I-5357 and Brasserie du Pêcheur SA v Federal Republic of Germany, R v Secretary of State for Transport, Ex p Factortame Ltd (No 4) (Joined Cases C-46/93 and C-48/93) [1996] QB 404 (“Brasserie du Pêcheur”). These were decisions on state liability, in Francovich itself for failure to transpose a directive and in Brasserie du Pêcheur for domestic laws which violated European law. In the latter case, the Court of Justice set out the three Francovich conditions at para 51, remarking in this respect that “Community law confers a right to reparation where three conditions are met”, and went on:
“55. As to the second condition, as regards both Community liability under article 215 and member state liability for breaches of Community law, the decisive test for finding that a breach of Community law is sufficiently serious is whether the member state or the Community institution concerned manifestly and gravely disregarded the limits on its discretion.
56. The factors which the competent court may take into consideration include the clarity and precision of the rule breached; the measure of discretion left by that rule to the national or Community authorities; whether the infringement and the damage caused was intentional or involuntary; whether any error of law was excusable or inexcusable; the fact that the position taken by a Community institution may have contributed towards the omission, and the adoption or retention of national measures or practices contrary to Community law.
57. On any view, a breach of Community law will clearly be sufficiently serious if it has persisted despite a judgment finding the infringement in question to be established, or a preliminary ruling or settled case law of the court on the matter from which it is clear that the conduct in question constituted an infringement. …
66. The aforementioned three conditions are necessary and sufficient to found a right in individuals to obtain redress, although this does not mean that the state cannot incur liability under less strict conditions on the basis of national law.”
“78. So, certain objective and subjective factors connected with the concept of fault under a national legal system may well be relevant for the purpose of determining whether or not a given breach of Community law is serious: see the factors mentioned in paras 56 and 57 above.
79. The obligation to make reparation for loss or damage caused to individuals cannot, however, depend on a condition based on any concept of fault going beyond that of a sufficiently serious breach of Community law. …
80. Accordingly, … reparation of loss or damage cannot be made conditional on fault (intentional or negligent) on the part of the organ of the state responsible for the breach, going beyond that of a sufficiently serious breach of Community law.”
13. The three Francovich conditions were in Köbler v Republik Österreich (Case C-224/01) [2004] QB 848, para 51, deployed in the context of state liability for failure by a final state court to apply European Union law, with the gloss (para 53) that, having regard to the specific nature of the judicial function and the legitimate requirements of legal certainty, the second condition could only be met “in the exceptional case where the court has manifestly infringed the applicable law”.
“Challenge procedures shall provide for:
(a) rapid interim measures to correct breaches of the Agreement ...;
(b) an assessment and a possibility for a decision on the justification of the challenge;
(c) correction of the breach of the Agreement or compensation for the loss or damages suffered, which may be limited to costs for tender preparation or protest.”
A similar provision appears in the more recent revised GPA to which the EU became party on 6 April 2014: Council Decision 2014/115/EU (OJ 2014 L68, p1). ATK submits that article XX(7) contemplates that damages must always be recoverable for a breach (and cannot be restricted to cases of serious breach), even if they may be limited to costs for tender preparation or protest. It points to the principle, endorsed in Řízení Letového Provozu ČR, sp v Bundesamt für Finanzen (Case C-335/05) [2007] STC 1509, para 16, and Association Justice & Environment zs v Commission of the European Communities (Case T-727/15) 23 January 2017, para 77, that secondary EU legislation should, so far as possible, be interpreted consistently with international agreements concluded by the European Union.
“33. … Directive 89/665 lays down only the minimum conditions to be satisfied by the review procedures established in domestic law to ensure compliance with the requirements of EU law concerning public procurement … If there is no specific provision governing the matter, it is therefore for the domestic law of each member state to determine the measures necessary to ensure that the review procedures effectively award damages to persons harmed by an infringement of the law on public contracts …
34. Although, therefore, the implementation of article 2(1)(c) of Directive 89/665 in principle comes under the procedural autonomy of the member states, limited by the principles of equivalence and effectiveness, it is necessary to examine whether that provision, interpreted in the light of the general context and aim of the judicial remedy of damages, precludes a national provision such as that at issue in the main proceedings from making the award of damages conditional, in the circumstances …, on a finding that the contracting authority’s infringement of the law on public contracts is culpable.
35. In that regard, it should first be noted that the wording of article 1(1), article 2(1), (5) and (6), and the sixth recital in the preamble to Directive 89/665 in no way indicates that the infringement of the public procurement legislation liable to give rise to a right to damages in favour of the person harmed should have specific features, such as being connected to fault - proved or presumed - on the part of the contracting authority, or not being covered by any ground for exemption from liability.
36. That assessment is supported by the general context and aim of the judicial remedy of damages, as provided for in Directive 89/665
37. According to settled case law, while the member states are required to provide legal remedies enabling the annulment of a decision of a contracting authority which infringes the law relating to public contracts, they are entitled in the light of the objective of rapidity pursued by Directive 89/665 to couple that type of review with reasonable limitation periods for bringing proceedings, so as to prevent the candidates and tenderers from being able, at any moment, to invoke infringements of that legislation, thus obliging the contracting authority to restart the entire procedure in order to correct such infringements …
38. Furthermore, the second subparagraph of article 2(6) of Directive 89/665 reserves to the member states the right to limit the powers of the body responsible for the review procedures, after the conclusion of a contract following its award, to the award of damages.
39. Against that background, the remedy of damages provided for in article 2(1)(c) of Directive 89/665 can constitute, where appropriate, a procedural alternative which is compatible with the principle of effectiveness underlying the objective pursued by that directive of ensuring effective review procedures … only where the possibility of damages being awarded in the event of infringement of the public procurement rules is no more dependent than the other legal remedies provided for in article 2(1) of Directive 89/665 on a finding that the contracting authority is at fault.
40. ... it makes little difference in that regard that, by contrast with the national legislation referred to in Commission of the European Communities v Portugal (Case C-275/03), the legislation at issue in the main proceedings does not impose on the person harmed the burden of proving that the contracting authority is at fault, but requires the latter to rebut the presumption that it is at fault, while limiting the grounds on which it can rely for that purpose.
41. The reason is that that legislation, too, creates the risk that the tenderer who has been harmed by an unlawful decision of a contracting authority is nevertheless deprived of the right to damages in respect of the damage caused by that decision, where the contracting authority is able to rebut the presumption that it is at fault. …
42. At the very least, that tenderer runs the risk, under that legislation, of only belatedly being able to obtain damages, in view of the possible duration of civil proceedings seeking a finding that the alleged infringement is culpable.”
“(c) If [the] authority is required to pay damages, does Community law set criteria for determining and estimating those damages, and if so, what are they?
(d) If the contracting public authority cannot be deemed liable, is it possible, under Community law, for some other person to be shown to be liable, and on what basis?”
20. Advocate General Cruz Villalón said (para 5), in connection with question 4(c) that:
“the present case offers the opportunity to clarify certain points of Directive 89/665 which are of great significance for the purpose of upholding the legality which European Union law requires in the context of public procurement.”
In the course of his opinion, he said (para 77) that:
“In my view, it is solely for the Rechtbank to assess(40) points such as whether there was any liability and whether, where appropriate, it must be attributed to the Provincie, to the State - on account of the actions of the judge dealing with interim relief proceedings - or to any other person taking into consideration the evidence which has been shown to be relevant: the fact that the Provincie did not wait before making the award or appeal against the interim measures; the possible alternatives (if any) to making the award to MFE; the circumstances surrounding the provisional enforcement of the order of the judge dealing with interim relief proceedings, and the Combinatie’s voluntary withdrawal of the appeal lodged against that order.”
Footnote 40 to this passage read:
“40. In order to do so, it must take into account all the factors which characterise the situation which has been brought before it, ‘in particular, the degree of clarity and precision of the rule infringed, whether the infringement was intentional, whether the error of law was excusable or inexcusable, the position taken, where applicable, by a Community institution and non-compliance by the court in question with its obligation to make a reference for a preliminary ruling under … article [267 TFEU]’ (Case C-224/01 Köbler [2003] ECR I‑10239, para 55), a sufficiently serious infringement of European Union law occurring ‘where the decision concerned was made in manifest breach of the case law of the court in the matter’.” (Joined Cases C‑46/93 and C‑48/93 Brasserie du pêcheur and Factortame [1996] ECR I‑1029, para 57, and Köbler, para 56.)
21. The Court addressed question 4(c) as follows:
“85. By its fourth question, part (c), the referring court asks, in essence, whether, if the awarding authority has to make good the damage arising from an infringement of EU law on the award of public contracts, EU law provides criteria on the basis of which the damage may be determined and estimated and, if so, what those criteria are.
86. Article 2(1)(c) of [the Remedies Directive] clearly indicates that member states must make provision for the possibility of awarding damages in the case of infringement of EU law on the award of public contracts, but contains no detailed statement either as to the conditions under which an awarding authority may be held liable or as to the determination of the amount of the damages which it may be ordered to pay.
87. That provision gives concrete expression to the principle of State liability for loss and damage caused to individuals as a result of breaches of EU law for which the State can be held responsible. According to case law developed since the adoption of the [Remedies Directive], but which is now consistent, that principle is inherent in the legal order of the Union. The Court has held that individuals harmed have a right to reparation where three conditions are met: the rule of EU law infringed must be intended to confer rights on them; the breach of that rule must be sufficiently serious; and there must be a direct causal link between the breach and the loss or damage sustained by the individuals ([the Francovich case] para 35, the Brasserie du Pêcheur case] paras 31 and 51; and [the Danske Slagterier case] paras 19 and 20).
88. As matters stand at present, the case law of the Court of Justice has not yet set out, as regards review of the award of public contracts, more detailed criteria on the basis of which damage must be determined and estimated.
89. As regards EU legislation, it should be noted that Directive 89/665 has been largely amended by Directive 2007/66/EC of the European Parliament and of the Council of 11 December 2007 amending Council Directives 89/665/EEC and 92/13/EEC (OJ 2007 L 335, p 31), adopted after the date of the facts which gave rise to the dispute in the main proceedings. However, on that occasion, the EU legislature refrained from adopting any provisions on that point.
90. In the absence of EU provisions in that area, it is for the legal order of each member state to determine the criteria on the basis of which damage arising from an infringement of EU law on the award of public contracts must be determined and estimated (see, by analogy, Case C-315/01 GAT [2003] ECR I-6351, para 46; and Case C-314/09 [the Stadt Graz case [2010] ECR I-8769], para 33) provided the principles of equivalence and effectiveness are complied with (see, to that effect, Joined Cases C-295/04 to C-298/04 Manfredi and others [2006] ECR I-6619, para 98).
91. It is apparent from well-established case law that the detailed procedural rules governing actions for safeguarding an individual’s rights under EU law must be no less favourable than those governing similar domestic actions (principle of equivalence) and must not render practically impossible or excessively difficult the exercise of rights conferred by EU law (principle of effectiveness) ...
92. Therefore, the answer to the fourth question, part (c) is that, as regards state liability for damage caused to individuals by infringements of EU law for which the state may be held responsible, the individuals harmed have a right to redress where the rule of EU law which has been infringed is intended to confer rights on them, the breach of that rule is sufficiently serious, and there is a direct causal link between the breach and the loss or damage sustained by the individuals. In the absence of any provision of EU law in that area, it is for the internal legal order of each member state, once those conditions have been complied with, to determine the criteria on the basis of which the damage arising from an infringement of EU law on the award of public contracts must be determined and estimated, provided the principles of equivalence and effectiveness are complied with.
93. In view of that answer, there is no need to reply to part (d) of the fourth question.”
“… the requirements that the rule breached must be intended to confer rights on individuals and that the breach of such a rule must be ‘sufficiently serious’, means that not every legal error in the course of an award procedure can ground an action in damages.”
This article reinforces my view that there is no uncertainty or confusion in the Court of Justice’s case law, and that the Supreme Court can be safe in relying on the clear language and ruling in Spijker as settling the position, whatever may have been previous doubts or differences of view at national level.
Issue (ii) - Francovich condition (ii) at domestic law level
29. The relevant Regulations read as follows:
“32.- Information about contract award procedures
[Award decision notice]
(1) Subject to paragraph (13), a contracting authority shall, as soon as possible after the decision has been made, inform the tenderers and candidates of its decision to -
(a) award the contract; or
(b) conclude the framework agreement,
and shall do so by notice in writing by the most rapid means of communication practicable.
(2) Where it is to be sent to a tenderer, the notice referred to in paragraph (1) shall include -
(a) the criteria for the award of the contract;
(b) the reasons for the decision, including the characteristics and relative advantages of the successful tender, the score (if any) obtained by -
(i) the economic operator which is to receive the notice; and
(ii) the economic operator
(aa) to be awarded the contract; or
(bb) to become party to the framework agreement,
and anything required by paragraph (10);
(c) the name of the economic operator -
(i) to be awarded the contract; or
(ii) to become a party to the framework agreement; and
(d) a precise statement of either -
(i) when, in accordance with regulation 32A, the standstill period is expected to end and, if relevant, how the timing of its ending might be affected by any and, if so what, contingencies; or
(ii) the date before which the contracting authority will not, in conformity with regulation 32A, enter into the contract or conclude the framework agreement.
(2A) Where it is to be sent to a candidate, the notice referred to in paragraph (1) shall include -
(a) the reasons why the candidate was unsuccessful; and
(b) the information mentioned in paragraph (2), but as if the words “and relative advantages” were omitted from sub-paragraph (b).
…
47A. Duty owed to economic operators
(1) This regulation applies to the obligation on -
(a) a contracting authority to comply with -
i. the provisions of these Regulations, other than regulations 14(2), 30(9), 32(14),40 and 41(1); and
ii. any enforceable [EU] obligation in respect of a contract or design contest (other than one excluded from the application of these Regulations by regulation 6, 8 or 33); and
(b) a concessionaire to comply with the provisions of regulation 37(3).
…
47C. Enforcement of duties through the Court
(1) A breach of the duty owed in accordance with regulation 47A or 47B is actionable by any economic operator which, in consequence, suffers, or risks suffering, loss or damage.
(2) Proceedings for that purpose must be started in the High Court, and regulations 47D to 47P apply to such proceedings.
…
47I. Remedies where the contract has not been entered into
(1) Paragraph (2) applies where -
(a) the Court is satisfied that a decision or action taken by a contracting authority was in breach of the duty owed in accordance with regulation 47A or 47B; and
(b) the contract has not yet been entered into.
(2) In those circumstances, the Court may do one or more of the following-
(a) order the setting aside of the decision or action concerned;
(b) order the contracting authority to amend any document;
(c) award damages to an economic operator which has suffered loss or damage as a consequence of the breach.
(3) This regulation does not prejudice any other powers of the Court.
47J. Remedies where the contract has been entered into
(1) Paragraph (2) applies if -
(a) the Court is satisfied that a decision or action taken by a contracting authority was in breach of the duty owed in accordance with regulation 47A or 47B; and
(b) the contract has already been entered into.
(2) In those circumstances, the Court -
(a) must, if it is satisfied that any of the grounds for ineffectiveness applies, make a declaration of ineffectiveness in respect of the contract unless regulation 47L requires the Court not to do so;
(b) must, where required by regulation 47N, impose penalties in accordance with that regulation;
(c) may award damages to an economic operator which has suffered loss or damage as a consequence of the breach, regardless of whether the Court also acts as described in sub-paragraphs (a) and (b);
(d) must not order any other remedies.
…”
These Regulations were all introduced by the 2009 Amendment Regulations, to implement the 2007 Directive.
30. The 2006 Regulations and 2009 Amendment Regulations were made under the power contained in section 2(2) of the European Communities Act 1972, to make provision for the purpose of implementing EU obligations of the United Kingdom and/or dealing with matters arising out of or related to any such obligation. The Francovich conditions are no more than minimum conditions, which domestic law is free to relax or ignore. There is therefore no Marleasing presumption that the United Kingdom legislator intended to reflect the Francovich conditions (Marleasing SA v La Comercial Internacional de Alimentación SA (Case C-106/89) [1990] ECR I-4135). Further, it is not suggested that it would be outside the scope of section 2(2) for the United Kingdom legislator to provide for the recovery of damages in respect of breaches which were not sufficiently serious to meet the EU law minimum requirement that a damages remedy be available: see United States v Nolan [2015] UKSC 63; [2016] AC 463, para 63.
35. The Explanatory Note, the Explanatory Memorandum and the Impact Assessment are all potentially admissible as aids to the understanding of the legislator’s intentions in 2009, on the principle identified by the House of Lords in R v Montila [2004] UKHL 50; [2004] 1 WLR 3141, para 35. However, ATK submits that 2009 is not the relevant date. It points out that, although regulations 47A through to 47P (Part 9) of the 2006 Regulations as amended by the 2009 Amendment Regulations were introduced as a complete substitute for the previous section 47 (Part 9) and were the product of extensive re-writing of previous text with many new elements, the bare outline of regulations 47A to 47C, 47I and 47J can still be detected in the much more limited language of regulation 47(1), (6), (8) and (9) of the earlier 2006 Regulations, which can in turn be traced back to the Public Services Contracts Regulations 1993 (SI 1993/3228), regulation 32(1), (2), (4) and (5). ATK submits that there is no reason to suggest that the legislator in 2009 intended any different approach to the damages recoverable under the earlier 1993 and 2006 Regulations, and that there is no material to show that avoidance of “gold-plating” had the same weight at those earlier dates. As to this, it is true that there is no material bearing directly on the legislator’s intentions at those earlier dates (though there is equally nothing to show that it was necessarily any different). But in my view it is unrealistic, when construing regulations 47A through to 47P, to ignore the legislator’s intention in 2009 to introduce a whole new package of substituted provisions which should, save where a deliberate choice to the contrary appeared, have no greater force than EU law requires. What happened in 2009 was effectively a new start, based on the Remedies Directive.
36. ATK also points to Matra Communications SAS v Home Office [1999] 1 WLR 1646. There the Court of Appeal specifically expressed the view (p 1655B) that damages under the Remedies Directive 89/665/EEC were not subject to the Francovich conditions (described by the Court of Appeal as Norbrook conditions, after Norbrook Laboratories Ltd v Ministry of Agriculture, Fisheries and Food (Case C-127/95) [1998] ECR I-1531). The Court of Appeal went on (para 1655D-G) to express the view that the “damages provided by domestic law remain damages on the basis envisaged by Directive (89/665/EEC); but regulation 32(5)(b)(ii) none the less thereby creates a private law, non-discretionary, remedy, because within the national legal order any remedy in damages necessarily has those qualities”. The Court of Appeal in Matra can now be seen to have been wrong in treating the Francovich conditions as irrelevant. Its further view that domestic law damages “remain damages on the basis envisaged by [the] Directive” might however be read as consistent with the NDA’s case on the present issue.
38. Sir Andrew Morritt put the matter correctly, with references to past authority, when he said in Phonographic Performance Ltd v Department of Trade and Industry [2004] 1 WLR 2893, paras 11 to 12:
“11. At the outset it is necessary to consider the nature of PPL’s claim. The decisions of the European Court of Justice in Francovich v Italian Republic (Joined Cases C-6/90 and C-9/90) [1995] ICR 722 and Brasserie du Pêcheur SA v Federal Republic of Germany (Joined Cases C-46 and C-48/93) [1996] QB 404 have established, and it is not disputed, that a member state may incur liability to a person under Community law where three conditions are satisfied. They are that (1) the rule of Community law infringed is intended to confer rights on individuals; (2) the breach is sufficiently serious, and in particular that there was a manifest and grave disregard by the member state of its discretion; and (3) there is a direct causal link between the breach of the obligation resting on the member state and the damage sustained by the injured party. As I have already pointed out for the purposes of these preliminary issues I have to assume that all those conditions will be established.
12. The nature of such a claim in English law was considered by Hobhouse LJ in R v Secretary of State for Transport, Ex p Factortame Ltd (No 5) [1998] 1 CMLR 1353. In that case the Divisional Court concluded that liability had been established and went on to consider whether exemplary damages could and should be awarded. It was in that context that Hobhouse LJ considered (para 173) that the liability was best understood as a breach of statutory duty. In so doing he relied on the dictum to the same effect of Lord Diplock in Garden Cottage Foods v Milk Marketing Board [1984] AC 130, 141 and the conclusion of Mann J in Bourgoin v Ministry of Agriculture, Fisheries and Food [1986] QB 716, 733 that the duty was imposed by the relevant article and section 2(1) European Communities Act 1972. Transposed to the facts of this case the duty for the breach of which the Crown is sued is that imposed by article 8.2 of the Rental Directive and section 2(1) [of the] European Communities Act 1972.”
Issue (iii) - failure to claim before the contract was made
(a) the NDA would have been required under regulation 47G(1) to refrain from entering into the contract;
(b) If this requirement to refrain continued, and ATK’s challenge succeeded, ATK would in due course be awarded the contract and avoid the GBP 100m loss claimed.
However, it should be noted that:
(c) the NDA could have applied under regulation 47H(1) to bring the requirement to an end;
(d) the court would then under regulation 47H(2) have been obliged to consider whether, apart from regulation 47G(1) it would be appropriate to make an interim order requiring the NDA to refrain from entering into the contract;
(e) assuming that the court concluded that ATK’s challenge had some merit (which it would in this case presumably have been seen as having, since it ultimately succeeded), the court would have considered whether “it would not be appropriate to make an interim order … in the absence of undertakings or conditions” (regulation 47H(3)), and would have had the power to require or impose undertakings or conditions in relation to the requirement that the NDA refrain from entering into the contract;
(f) the NDA would in this way, assuming that it was ordered to continue to refrain from entering into the contract while ATK’s challenge was resolved, have had the benefit of a cross-undertaking and/or security, which would, if the NDA defeated ATK’s challenge, cover loss or damage which the NDA suffered through not being able to enter into the contract.
“83. In the absence of relevant Community provisions, it is for the domestic legal system of each member state to set the criteria for determining the extent of reparation. However, those criteria must not be less favourable than those applying to similar claims based on domestic law and must not be such as in practice to make it impossible or excessively difficult to obtain reparation.
84. In particular, in order to determine the loss or damage for which reparation may be granted, the national court may inquire whether the injured person showed reasonable diligence in order to avoid the loss or damage or limit its extent and whether, in particular, he availed himself in time of all the legal remedies available to him.
85. Indeed, it is a general principle common to the legal systems of the member states that the injured party must show reasonable diligence in limiting the extent of the loss or damage, or risk having to bear the damage himself Mulder v Council and Commission of the European Communities (Joined Cases C-104/89 and C-37/90) [1992] ECR I-3061, 3136-3137, para 33.”
The court reiterated the substance of these paragraphs in Danske Slagterier v Bundesrepublik Deutschland (Case C-445/06) [2010] All ER (EC) 74, paras 59-61.
48. That the so-called duty to mitigate may in some circumstances require the victim of a breach to take steps by way of legal action is, in my opinion, clear. Lord Pannick QC, representing the NDA, was able to refer to cases in which English courts have held that the victim of a breach of duty should, by way of mitigation, pursue available legal remedies, before, for example, suing his professional advisers for negligence: Western Trust & Savings Ltd v Travers & Co (1998) 75 P & CR 200; Walker v Geo H Medlicott & Son [1999] 1 WLR 727. See also the discussion of these and other cases in Jackson & Powell on Professional Liability 8th ed (2017), paras 11.336-11.339. The principle that a breach may call for mitigation, by third party action of this sort, is therefore uncontroversial. If my builder leaves my front door open and squatters enter, I cannot say that I have lost my house. I must take steps, legal steps if necessary, to recover possession.
“The [NDA] makes no bones about the fact that, because of the financial implications of delay, it would have applied to lift the suspension and (if successful) signed the contract, had [ATK] sought to trigger and maintain the suspension without offering a cross-undertaking in damages. The [NDA] does not know what it would have done if a cross-undertaking had been offered - it would have depended upon advice that was not in fact sought, and factors such as the likely date of an expedited trial that did not become known, because of the way that [ATK] in fact acted.”
The second sentence indicates that the NDA might have sought to remove any stop on its entry into of the contract, even if ATK had offered a suitable cross-undertaking in order to achieve its continuation. In other words, the NDA may, even in that context, have preferred to run the same risk that it did by entering into the contract in this case.
Conclusion