Neutral citation [2006] CAT 36
IN THE COMPETITION APPEAL TRIBUNAL
Case No: 1046/2/4/04
1034/2/4/04 (IR)
Victoria House
Bloomsbury Place
London WC1A 2EB
18 December 2006
Before:
Sir Christopher Bellamy (President)
The Honourable Antony Lewis
Professor John Pickering
Sitting as a Tribunal in England and Wales
BETWEEN:
ALBION WATER LIMITED
Appellant
supported by
AQUAVITAE (UK) LIMITED
Intervener
-v-
WATER SERVICES REGULATION AUTHORITY
(formerly DIRECTOR GENERAL OF WATER SERVICES)
Respondent
supported by
(1) DWR CYMRU CYFYNGEDIG
and
(2) UNITED UTILITIES WATER PLC
Interveners
JUDGMENT
APPEARANCES
Dr. Jeremy Bryan, Managing Director of Albion Water Limited, and subsequently
Rhodri Thompson QC and John O'Flaherty appeared on behalf of the appellant, Albion Water Limited.
Michael O'Reilly (instructed by McKinnells, Lincoln) appeared on behalf of Aquavitae (UK) Limited.
Rupert Anderson QC and Valentina Sloane (instructed by the Director of Legal Services, OFWAT) appeared on behalf of the respondent.
Christopher Vajda QC and Meredith Pickford (instructed by Wilmer Hale) appeared on behalf of Dwr Cymru Cyfyngedig.
Fergus Randolph (instructed by the Group Legal Manager, United Utilities) appeared on behalf of United Utilities Water plc.
TABLE OF CONTENTS
I INTRODUCTION | 1 |
II DOMINANT POSITION: BACKGROUND AND ARGUMENTS | 6 |
The Decision | 9 |
The pleadings | 15 |
The submissions at the first hearing in May 2005 | 21 |
The Tribunal's interim judgment | 24 |
Evidence submitted by Dwr Cymru in February 2006 | 25 |
Dwr Cymru's application of 20 April 2006 | 29 |
The Authority's evidence for the hearing in June 2006 | 30 |
The parties' position at the June 2006 hearing | 34 |
The correspondence in June and July 2006 | 41 |
The main judgment of 6 October 2006 | 48 |
The hearing of 24 October 2006 | 49 |
The Tribunal's ruling of 24 October 2006 | 57 |
The arguments submitted subsequently to 24 October 2006 | 58 |
III DOMINANT POSITION: PRELIMINARY | 70 |
Should the Tribunal consider the issue of dominance? | 70 |
What are the Tribunal's powers to address dominance? | 77 |
Relevant law | 82 |
The standard of proof | 89 |
IV RELEVANT MARKET ISSUES | 90 |
The underlying facts | 96 |
The Authority's position on relevant market | 99 |
The relevant product market in the present case | 102 |
The geographic market | 108 |
Conclusion on relevant market | 116 |
V ANALYSIS OF DOMINANCE | 118 |
The initial analysis | 118 |
Private or self-supply | 129 |
An alternative pipeline from Heronbridge | 136 |
Summary at this stage of the analysis | 148 |
The reasoning in the Decision as regards an alternative pipeline | 150 |
– The United Utilities studies between 1997 and 1999 | 157 |
– The emails at the end of 2001 | 161 |
– The Director's desk top calculations | 164 |
Conclusion on the passages in the Decision relating to the possible viability of the construction of an alternative pipeline from Heronbridge |
169 |
Other alternatives | 177 |
Retaliatory action | 178 |
Buyer power | 179 |
Conduct | 180 |
VI CONCLUSION ON DOMINANCE | 183 |
VII RELIEF AND REMEDIES: BACKGROUND AND ARGUMENTS | 200 |
The factual situation | 200 |
Albion's submissions | 207 |
The Authority's submissions | 218 |
Dwr Cymru's submissions | 225 |
Aquavitae | 230 |
VIII THE EXCESSIVE PRICING ABUSE | 231 |
The Decision | 231 |
The main judgment | 234 |
The issue of abuse | 240 |
The mechanism | 275 |
Conclusion on the issue of the abuse of excessive pricing | 279 |
IX THE MARGIN SQUEEZE ABUSE | 282 |
The main judgment | 282 |
Should the Tribunal decide the issue of margin squeeze abuse? | 284 |
The facts | 285 |
The law to be applied | 290 |
X INTERIM RELIEF | 314 |
The present situation | 314 |
The statutory powers | 321 |
The relationship between the First Access Price and the Bulk Supply Price | 329 |
The need for interim measures | 336 |
The Tribunal's jurisdiction | 345 |
Albion's application | 355 |
Aquavitae | 356 |
Conclusion on interim relief | 359 |
XI CONCLUSIONS | 360 |
I INTRODUCTION
"(1) There is evidence before the Tribunal that the treatment cost of non-potable water on an average accounting cost basis was over-estimated in the Decision. However the Tribunal is prepared to assume, without deciding, that treatment costs are in the range 1.6p/m³ to 3.2p/m³.
(2) The matter of the "distribution" cost of non-potable water on an average accounting cost basis was not sufficiently investigated. In this respect the Decision is incorrect, or at least insufficient, from the point of view of the reasons given, the facts and analysis relied on, and the investigation undertaken, as regards in particular to the Director's conclusion in paragraph 302 of the Decision to the effect that it was not unreasonable to assume that the "distribution" costs of potable and non-potable water are the same.
(3) The evidence strongly suggests that the First Access Price was excessive in relation to the economic value of the services to be supplied, by reason of the absence of any convincing justification for the "distribution" costs included in the average accounting cost calculation.
(4) The cross-check as to the validity of the First Access Price by reference to ECPR in paragraphs 317 to 331 of the Decision cannot be safely relied on because (i) the 'retail' price used in the calculation is not shown to be cost-related, as regards the distribution element; (ii) the evidence strongly suggests that that price was itself excessive; (iii) the particular method of ECPR used in this case would eliminate existing competition and, in effect, preclude virtually any competitive entry, because the margins are insufficient; and (iv) the approach of the Authority in its evidence and submissions was not the same as that in the Decision. None of the justifications for an ECPR approach advanced by the Authority persuaded us that we could safely rely on the approach set out in the Decision in the circumstances of the present case.
(5) As regards the allegation of margin squeeze, the existence of a margin squeeze was not seriously disputed. The Director's finding at paragraph 352 of the Decision that nonetheless there was no breach of the Chapter II prohibition was erroneous in law and incorrect, or at least insufficient, from the point of view of the reasons given, the facts and analysis relied on and the investigation undertaken.
(6) It is unsafe to assume, as the Director does in paragraphs 331 and 338 of the Decision, that the Costs Principle set out in section 66E of the WIA91 supports the conclusion which the Director reached in the Decision, since (i) the retail price used in the calculation in the Decision is not shown to have been reasonably cost-based, and the evidence strongly suggests that that price was itself excessive; and (ii) the Director's interpretation of ARROW costs under section 66E(4) is open to serious question, since that interpretation would on the evidence preclude virtually any effective competition or market entry, and give rise to a potential conflict with the consumer objective under that Act and with the Chapter II prohibition."
II DOMINANT POSITION: BACKGROUND AND ARGUMENTS
The Decision
"In summary, in light of the above, we consider that the cost of constructing new infrastructure to serve Shotton would not be sufficient to constitute a barrier to entry."
"Although we would need to examine particularly the public policy questions in more detail, at this stage we do not believe that the Ashgrove system is an essential facility as Albion Water alleges. But in the light of our conclusions in this decision set out below, we have not found it necessary to rely on this view in this case." (paragraph 225)
The pleadings
"The Director was of the opinion that it was important to include his findings on the essential facilities question. The Appellant had argued that the relevant facility was essential and, given that this was the Director's first investigation into common carriage, it seemed appropriate to opine on this particular question. During the investigation the Director had explained to the Appellant that the case raised important issues relating to common carriage generally, and that it was important, both to the Appellant and the industry as a whole, that his detailed thinking on this issue was publicly available and open to challenge, if necessary".
The submissions at the first hearing in May 2005
The Tribunal's interim judgment
"145. Since [the existence of a dominant position] is the assumption upon which the Decision is predicated, we do not need to consider in detail the Director's analysis, at paragraphs 86 to 225 of the Decision, of the issue of dominance in the relevant market and the associated issue of whether the Ashgrove System is indeed an "essential facility" for the purposes of the Chapter II prohibition. We make it clear, however, that had we had to consider the issue of dominance, we would at first sight have had difficulty in agreeing with the Director's doubts as to whether Dwr Cymru had a dominant position within the meaning of the Chapter II prohibition, and in particular his view that the suggested possibility of constructing a new pipeline to serve Shotton Paper instead of the Ashgrove System would arguably negative any such dominant position. The Director was, in our view, correct to assume that Dwr Cymru had a relevant dominant position.
146. We would also observe that the Decision (at paragraph 213) is somewhat equivocal as to what is the precise ambit of the relevant market in which Dwr Cymru is assumed to be dominant. Like the Director in that paragraph, we accept as a starting point that Dwr Cymru is to be assumed to be dominant in the market for the transportation of non-potable water for supply to industrial customers in the geographical area served by the Ashgrove system (Decision, paragraphs 104 to 110).
147. We also accept that, as Albion suggests in its skeleton argument, if Dwr Cymru is assumed to be dominant in the (upstream) market for the transportation of non-potable water for supply to industrial customers in the geographical area served by the Ashgrove system, the principal issue in the case is whether Dwr Cymru has abused that dominant position so as to eliminate or significantly impede competition in the (downstream) market for the supply of non-potable water to industrial customers in that area, that downstream market for the supply of non-potable water being a market within which Albion and Dwr Cymru are actual or potential competitors. The distinction between the upstream supply of transportation services, on the one hand, and the downstream supply of the water itself, on the other hand, needs to be kept in mind."
Evidence submitted by Dwr Cymru in February 2006
"Option B: instead of taking water from Heronbridge, it may be possible to purchase the water from United Utilities at, or close to, its Sutton Hall treatment works, which itself is fed inter alia by United Utilities' side of the Heronbridge abstraction works. The attached map at Exhibit CJ-A shows the location of the works. Examination of this location on other maps of the surrounding area, such as the map provided by Albion in its Notice of Appeal (Annex 12/104), suggests that the Sutton Hall works is no more than 8km from the Shotton site, a distance over 8km shorter than the total length of the Ashgrove main. The effect of using a shorter length of main would be to save around £4.5m, assuming similar unit costs for the construction of the main to those presented in Annex 2 in connection with Option A. This would represent a reduction in the standalone price of around 9p/m³ (again using the assumptions presented for Option A – see Annex 2);
Option C: use of the boreholes owned by the steelworks next door to the Shotton site. Although Albion has asserted that this option is not feasible, the steelworks has been actively looking to exploit their potential for some time. It has now informed Dwr Cymru that it is re-starting the boreholes and intends shortly to install a reverse osmosis plant to treat the water. Based on my knowledge of typical costs, I estimate that water could be abstracted, treated for hardness (assuming that were necessary), and delivered to the Shotton site for less than 12 p/m³. This cost includes the water, as well as the transportation, and is therefore comparable with the whole price paid by Albion, not just the proposed price for the common carriage element (see Annex 3); and
Option D: direct abstraction from the Dee. Shotton is located no more than l km or so from the Dee estuary. In order to treat estuary water to acceptable standards, reverse osmosis would almost certainly be required. If, however, reverse osmosis is economically feasible for the steelworks (see Option C above) then in my view it is likely to be feasible as part of a direct abstraction option.
Further, it is clear that this list is by no means exhaustive. Both the Director and Albion have made references to potential alternative sources, such as the Milwr Tunnel."
"• the Deeside industrial park is not close to any significant towns or cities. Were either or both customers for non-potable water to shut down, it is possible that other potential water users would occupy the land in due course, but there is no guarantee that they would require much water at all, let alone non-potable water. Therefore, for the hypothetical service provider there would be a high probability that closure of the two plants would lead to the permanent "stranding" of the project, with no obvious alternative use for the non-potable water at Sealand in prospect;
• the market perception of the credit risks of the two customers is not very favourable. The parent company for the paper mill has a BBB credit rating with Standard & Poors, which means that it "exhibits adequate protection parameters", but "adverse economic conditions or changing circumstances are more likely to lead to a weakened capacity of the obligor to meet its financial commitment". The credit rating for the steelworks' parent company is B+ from Standard & Poors, which puts it in the category of "junk" status and implies that the company's credit has "significant speculative characteristics".
• since neither customer would be expected to be able to raise finance for a term anything like approaching the assumed life of the principal asset, the Ashgrove main, in practice it is similarly unlikely that an Ashgrove system service provider would be willing to extend, in effect, credit for the long term. In other words, in practice the provider would be looking to accelerate recovery of its investment, most probably by seeking a partial or full up-front capital contribution. This is common practice in the water industry. However, for the purposes of this exercise this complication is ignored, and we have assumed that a rate of return could be found that would be sufficient to satisfy investors and creditors that a long term investment was worthwhile;
• Albion's own inset appointment application provides evidence of a particularly high required rate of return. The application shows "proforma" annual profits after tax of £109,175 (of which the non-potable side would contribute £90,679) on a capital investment which is shown as £24,000. This represents a return of over 450 per cent. It is likely that Albion incurred "up-front" costs in preparing for the inset application which were not shown in the application, but even if these were as high as £100,000, the proposed rate of return would still have approached 90 per cent;
• it is my recollection that, during the late 1990s, when Dwr Cymru was part of a wider corporate group that carried out private water supply projects both in the UK and abroad, a hurdle rate of return of 12 per cent (post-tax) was commonly used to evaluate projects;
• according to Albion, this is similar to the required rate of return of Pennon Group plc, Albion's ultimate parent in 2000/01, for projects of this nature. Albion submits that the company required a post-tax rate of return of at least 14 per cent, equivalent to a pre-tax rate of return in excess of 20 per cent;
• Dwr Cymru's treasurer has made inquiries of a number of financial institutions with whom Dwr Cymru has relationships and was informed that typical market rates of return for "private finance initiative" sewage treatment works are in the "early teens". Such projects have the benefit of Government backing, and would therefore be indicative of what rate of return might be required by the Ashgrove service provider if the customers were Government-backed; and
• most recently, Suez Environment (former owners of various undertakers in England) reported that its rate of return on capital employed in its European water business in 2004 was 17.7 per cent.
"• the costs of compensation to landowners, land purchase costs, planning constraints/conditions, access costs, etc.
• any significant "in life" maintenance work which might be required for any of the assets;
• the lag between the time when capital expenditure is incurred, and revenues from the service begin to be earned;
• scientific services (i.e. water sampling and analysis) costs;
• regulatory costs, including the licence fee to Ofwat (if the service provider is an undertaker) and the costs of complying with regulatory requirements set by both Ofwat and the Environmental Agency;
• any contribution to other miscellaneous cost items, such as IT, administrative support, marketing, and research and development; and
• any contribution to the financing of the service provider' s (otherwise unviable) statutory obligations (if any)."
(Jones 2, paragraphs 28 to 29)
Dwr Cymru's application of 20 April 2006
The Authority's evidence for the hearing in June 2006
The parties' position at the June 2006 hearing
The correspondence in June and July 2006
"We do not accept that we have made a CA98 decision on the relevant issues. But I have spoken to Philip Fletcher and we both have some sympathy with your view that you need a fully reasoned decision. The case does appear to raise important issues relating to common carriage generally and the calculation of access prices. I agree that it is important, both to you and the industry as a whole, that our detailed thinking on this issue is publicly available, and open to challenge before the Competition Commission Appeal Tribunals ("CCAT"), if necessary.
I have therefore decided to re-open our file, investigate the points that concern you, and complete the further work necessary to issue a formal CA98 decision. This decision will be fully reasoned, will cover all the relevant aspects of your complaint, and will be published."
"The purpose of the Tribunal's letter of 20 June 2006 was to ascertain whether there was further evidence or submissions that the parties might wish to submit on the issue of market definition and dominance, should the need arise for the Tribunal to consider whether to address that issue. The Tribunal was, and is, of the view that as a matter of case management it is better, and fairer, for the Tribunal to ascertain whether there is further relevant factual material relevant to the issue of market definition and dominance, while the matters are still fresh in everyone's mind, given that the Tribunal in its judgment may make findings on matters that are relevant to issues of dominance (see Transcript, day 6, pp 94-95).
The position taken by the Authority and Dwr Cymru is, however that: (a) the Tribunal has no jurisdiction to consider any factual material on the issue of dominance; and (b) in any event, the Tribunal should not consider any such material. That stance clearly sets out the position of the parties with regard to the Tribunal's invitation.
Should the need arise, the Tribunal will rule on those points in a reasoned judgment which the parties may or may not wish to appeal. Unless and until it has reason to do so the Tribunal has not taken, and will not take, a decision either to accept or reject the submissions made by the parties in the letters of 30 June 2006 and 3 July 2006 (including those made by Dwr Cymru on 24 April 2006)."
The main judgment of 6 October 2006
"it is highly unsatisfactory for the issue of dominance to be left as it is, and for the issue of dominance to have become "detached" from the issues relating to abuse. A good deal of evidence bearing on the issue of dominance that was not before the Director is now before the Tribunal. In those circumstances the Tribunal proposes to consider with the parties how the matter of dominance should now be handled. To facilitate that consideration, Annex A to this judgment summarises non-exhaustively matters potentially relevant to the issue of dominance and to the most appropriate course to adopt in that regard."
The hearing of 24 October 2006
"Dwr Cymru is dominant in the market for transportation of non-potable water for supply to industrial customers in the geographic area served by the Ashgrove system".
The Tribunal's ruling of 24 October 2006
The arguments submitted subsequently to 24 October 2006
III DOMINANT POSITION: PRELIMINARY
Should the Tribunal consider the issue of dominance?
What are the Tribunal's powers to address dominance?
"(1) The Tribunal must determine the appeal on the merits by reference to the grounds of appeal set out in the notice of appeal.
(2) The Tribunal may confirm or set aside the decision which is the subject of the appeal, or any part of it, and may—
(a) remit the matter to the [Authority[2]],
(b) impose or revoke, or vary the amount of, a penalty,
(c) . . .
(d) give such directions, or take such other steps, as the [Authority] could itself have given or taken, or
(e) make any other decision which the [Authority] could itself have made.
(3) Any decision of the Tribunal on an appeal has the same effect, and may be enforced in the same manner, as a decision of the [Authority].
(4) If the Tribunal confirms the decision which is the subject of the appeal it may nevertheless set aside any finding of fact on which the decision was based."
Relevant law
"a position of economic strength enjoyed by an undertaking which enables it to prevent effective competition being maintained on the relevant market by allowing it the power to behave to an appreciable extent independently of its competitors, its customers and ultimately of the consumers".
(See Case 85/76 Hoffman-La Roche v Commission [1979] ECR 461, paragraph 38; Genzyme v OFT [2004] CAT 4, at paragraph 188.) However:
"such a [dominant] position does not preclude some competition … but enables the undertaking which profits by it, if not to determine, at least to have an appreciable influence on the conditions under which that competition will develop, and in any case to act largely in disregard of it so long as such conduct does not operate to its detriment."
(Hoffman-La Roche v Commission, cited above, at paragraph 39.)
"Market definition is a tool to identify and define the boundaries of competition between firms … The objective of defining a market in both its product and geographic dimension is to identify those actual competitors of the undertakings involved that are capable of constraining those undertakings' behaviour and of preventing them from behaving independently of effective competitive pressure."
"The key idea is that of a competitive constraint: do the other products alleged to form part of the same market act as a competitive constraint on the conduct of the allegedly dominant firm?"
"In most circumstances, in the Tribunal's view, a market share of 90% or above, which has continued throughout the period of infringement and is likely to continue for several years, will be sufficient, depending on the circumstances, to infer the existence of dominance: See Napp, cited above, at paragraphs [156] to [160], and Aberdeen Journals (No. 2), cited above, at [310], and the cases there cited."
The standard of proof
IV RELEVANT MARKET ISSUES
"in order to identify those actual competitors of the undertakings involved that are capable of constraining the undertakings' behaviour and of preventing them from behaving independently of effective competitive pressure"
(The European Commission's Notice on Market Definition, paragraph 2)
"The OFT will not factor supply side substitution into market definition unless it is reasonably likely to take place, and already has an impact by constraining the supplier of the product or group of products in question. What matters ultimately is that all competitive constraints from the supply side are properly taken into account in the analysis of market power. Whether a potential competitive constraint is labelled supply side substitution (and so part of market definition) or potential entry (and so not within the market) should not matter for the overall competitive assessment. If there is any serious doubt about whether or not to account for possible supply side substitution when defining the market and calculating market shares, the market will be defined only on the basis of demand side substitutability and the supply side constraint in question will be considered when analysing potential entry." (paragraph 3.18)
At footnote 36 to paragraph 3.18 the OFT states:
"Some competition authorities prefer to define markets solely on the demand side, leaving supply side issues to the analysis of new entry. Both approaches are valid and should produce the same conclusions on the question of market power, provided that supply side issues are examined at some point."
The underlying facts
The Authority's position on relevant market
"we have been prepared to start our analysis of this case on the basis that the market on which Albion Water alleges Dwr Cymru is dominant is that for the transportation via the Ashgrove System and partial treatment of water abstracted from the Heronbridge Abstraction Point to Shotton and Corus."
"the market for the transportation of non-potable water for supply to industrial customers in the geographical area served by the Ashgrove system." (Decision, paragraph 88)
The relevant product market in the present case
The geographic market
Conclusion on relevant market
V ANALYSIS OF DOMINANCE
The initial analysis
"Furthermore although the importance of the market shares may vary from one market to another, the view may legitimately be taken that very large shares are in themselves, and save in exceptional circumstances, evidence of the existence of a dominant position. An undertaking which has a very large market share and holds it for some time… is by virtue of that share in a position of strength…"
"With regard to market shares the Court has held that very large shares are in themselves, and save in exceptional circumstances, evidence of the existence of a dominant position (judgment in Case 85/76 Hoffman-La Roche v Commission [1979] ECR 461, paragraph 41). That is the situation where there is a market share of 50% such as that found to exist in this case."
"In most circumstances, in the Tribunal's view, a market share of 90% or above, which has continued throughout the period of infringement and is likely to continue for several years, will be sufficient, depending on the circumstances, to infer the existence of dominance."
Private or self-supply
An alternative pipeline from Heronbridge
Summary at this stage of the analysis
The reasoning in the Decision as regards an alternative pipeline
– The United Utilities studies between 1997 and 1999
"(i) it would be extremely costly to construct a pipeline and Shotton are not willing to contribute any funding; (ii) the [Director] would view as [sic] economically inefficient; (iii) it is unlikely that the regulator would approve of any move that would leave the first new entrant in the water industry without a customer; and (iv) constructing a pipeline would require longer timescales than a tariff option [sic]." (paragraph 148 of the Decision).
– The emails at the end of 2001
"152. In an e-mail from Albion Water to United Utilities Water dated 6 December 2001, Albion Water stated:
"We […] need to explore an alternative approach to supplies at Shotton to increase the pressure for a favourable decision, or as a last resort, to deliver our own alternative. Jerry [Bryan] has asked me to explore costs for an alternative supply to Shotton/Corus. I write to see of [sic] you can help to quantify the cost of doing so, and to see in principle whether [United Utilities Water] would wish to undertake the work."
153. The e-mail refers to two possible alternatives, namely the duplication of the Ashgrove Pipe and the construction of a pipe from Milwr Tunnel to Shotton. The e-mail continues:
'At this stage the initiative needs to be absolutely confidential, and exploratory…in the short term I have to be careful not to undermine our position that [Dwr Cymru] main is an essential facility. If we end up going for a new main to serve the site [Enviro-Logic] would have the support of the customer as long as we had exhausted other options first, but the financing options remain to be explored.'
154. United Utilities Water responded in an e-mail from John Lees dated 19 December 2001. It stated that:
'We would want to be involved in this. A fast and dirty look at the options shows them to be potentially viable to supply a competitively priced water at [sic] the volumes you have indicated. I would stress that it was not a detailed study, but the signs are good that it would be viable to provide a "concrete and steel" option to the existing asset usage option.'
155. This e-mail appears to imply that, on the basis of United Utilities Water's initial estimate, and subject to a more in-depth study being carried out, it appeared economic and feasible to install a duplicate pipeline running from the Heronbridge Abstraction Point to Shotton. Importantly, the e-mail dated 6 December 2001 also appears to show that Shotton would be prepared to provide the necessary support…."
– The Director's desk top calculations
Conclusion on the passages in the Decision relating to the possible viability of the construction of an alternative pipeline from Heronbridge
"In summary, in the light of the above, we calculate that the cost of constructing new infrastructure to serve Shotton would not be sufficient to constitute a barrier to entry."
"…that the length of time it would take for a WaSC or a WoC new entrant to construct the necessary infrastructure to supply Shotton would not amount to an insurmountable barrier to entry, and would not prevent a WaSC or WoC constraining an incumbent undertaker's market power through constructing, or threatening to construct, such infrastructure."
Other alternatives
Retaliatory action
Buyer power
Conduct
VI CONCLUSION ON DOMINANCE
"There are certain factors in this case which would point strongly to Dwr Cymru being in a dominant position on the relevant market. First, albeit depending very much on the precise market definition used, Dwr Cymru might have had a 100% market share at all material times. Second, for whatever reason, no company has yet duplicated the Ashgrove System. Third, we have not seen any evidence that Dwr Cymru itself felt constrained by the emergence of Albion Water during the Inset Application process (or by any other competitor), although we have not expressly sought such evidence."
"In our judgment, on the above basis the Tribunal should, if necessary, take its own decision rather than remit if (i) it has or can obtain all the necessary material (ii) the requirements of procedural fairness are respected and (iii) the course the Tribunal proposes to take is desirable from the point of view of the need for expedition and saving costs. Such an approach in our view is compatible with the overriding objective of deciding cases justly".
"138. As to procedural fairness, Austins/Harwood Park has participated fully in these proceedings and has been ably represented. At the case management conference on 19 October 2004 the Tribunal made it clear (transcript, page 14) that one option for the Tribunal was to take its own decision, and that Austins should file any evidence that it wished to file on the issues in the case. Austins, in our view, has had every opportunity to defend itself, knowing the options available to the Tribunal. In addition, as already pointed out, there is no question of a penalty being imposed upon Austins.
139. As to whether the Tribunal should proceed to take its own decision, a primary factor that weighs with the Tribunal is the regulatory delay that has already taken place. The facts of this case are not complex, but they do concern medium sized businesses serving a vulnerable class of consumer. We regard a delay of over two years in producing a decision in such circumstances as incompatible with the effective enforcement of the Act. To remit the matter now, for further investigation of indeterminate length, would not in our view be in the interests of the parties nor, more importantly, in the interests of the consumers concerned…"
"Indeed, in other contexts it is now commonplace for the Tribunal to act, in effect, as the decision-maker in cases where the evidence relied on by the OFT is challenged, very often on the basis of extensive new material introduced by the appellant and rebuttal evidence introduced by the OFT. For example, the Tribunal's role as, in effect, a primary decision-maker, is illustrated, albeit in a different context, by the extensive findings of fact made in the Tribunal's recent judgement on liability in JJB and Allsports, cited above".
VII RELIEF AND REMEDIES: BACKGROUND AND ARGUMENTS
The factual situation
Albion's submissions
The Authority's submissions
Dwr Cymru's submissions
Aquavitae
VIII THE EXCESSIVE PRICING ABUSE
The Decision
"248. The imposition by an undertaking in a dominant position directly or indirectly of unfair purchase or selling prices is an abuse to which exception can be taken under Article [82] of the Treaty.
249. It is advisable therefore to ascertain whether the dominant undertaking has made use of the opportunities arising out of its dominant position in such a way as to reap trading benefits which it would not have reaped if there had been normal or sufficiently effective competition.
250. In this case charging a price which is excessive because it has no reasonable relation to the economic value of the product supplied would be such an abuse.
251. This excess could, inter alia, be determined objectively if it were possible for it to be calculated by making a comparison between the selling price of the product in question and its cost of production, which would disclose the amount of the profit margin; however the Commission has not done this since it has not analysed UBC's costs structure.
252. The questions therefore to be determined are whether the difference between the costs actually incurred and the price actually charged is excessive, and, if the answer to this question is in the affirmative, whether a price has been imposed which is either unfair in itself or when compared to competing products.
253. Other ways may be devised – and economic theorists have not failed to think up several – of selecting the rules for determining whether the price of a product is unfair".
"(a) Did Dwr Cymru misallocate any costs when calculating the First Access Price?
(b) Does the First Access Price bear no reasonable relation to the economic value of the service provided, when judged by reference to the difference between the costs actually incurred by Dwr Cymru and the price charged?
(c) If the answer to (b) is in the affirmative, was the First Access Price unfair either in itself or when compared to competing services?"
"335. The second question we considered was whether the First Access Price could be said to bear no reasonable relation to the economic value of the service provided, when judged by reference to the difference between the costs actually incurred by Dwr Cymru and the price charged.
336. There is no legal definition of the "economic value" of a service. In United Brands, the ECJ simply referred to examining differences between costs and prices. Similarly, there is no definition of "excessive" in the context of pricing.
337. We have considered how best to assess costs, and whether the First Access price is excessive in relation to those costs. On the one hand, Dwr Cymru adopted a particular approach to calculating the First Access Price which, with our adjustments to correct cost misallocation, would point to costs closer to 19.2p/m³, than the 23.2 p/m³ of the First Access Price.
338. However, as discussed above, we think that there are dangers in accepting only one approach when assessing costs and whether or not an access price is excessive. We therefore had regard to the Second Bulk Supply Agreement, the Costs Principle, and ECPR. The access price resulting from an ECPR approach based on the Second Bulk Supply Agreement would be approximately 22.5p/m³. We think that the Costs Principle would produce the same price.
339. In light of the above, and despite our dissatisfaction with the fact that the First Access Price did contain cost misallocation, we have doubts about whether the First Access Price could be said to bear no reasonable relation to the economic value of the service provided, when judged by reference to the difference between the costs actually incurred by Dwr Cymru and the price charged.
…
341. We are therefore unable to answer our second question in the affirmative, we do not therefore need to address our third question, and we conclude that Dwr Cymru did not abuse a dominant position in breach of the Chapter II Prohibition by engaging in excessive pricing."
The main judgment
"For the reasons given above we have reached the following conclusions:
(1) There is evidence before the Tribunal that the treatment cost of non-potable water on an average accounting cost basis was over-estimated in the Decision. However the Tribunal is prepared to assume, without deciding, that treatment costs are in the range 1.6p/m³ to 3.2p/m³.
(2) The matter of the "distribution" cost of non-potable water on an average accounting cost basis was not sufficiently investigated. In this respect the Decision is incorrect, or at least insufficient, from the point of view of the reasons given, the facts and analysis relied on, and the investigation undertaken, as regards in particular to the Director's conclusion in paragraph 302 of the Decision to the effect that it was not unreasonable to assume that the "distribution" costs of potable and non-potable water are the same.
(3) The evidence strongly suggests that the First Access Price was excessive in relation to the economic value of the services to be supplied, by reason of the absence of any convincing justification for the "distribution" costs included in the average accounting cost calculation.
(4) The cross-check as to the validity of the First Access Price by reference to ECPR in paragraphs 317 to 331 of the Decision cannot be safely relied on because (i) the 'retail' price used in the calculation is not shown to be cost-related, as regards the distribution element; (ii) the evidence strongly suggests that that price was itself excessive; (iii) the particular method of ECPR used in this case would eliminate existing competition and, in effect, preclude virtually any competitive entry, because the margins are insufficient; and (iv) the approach of the Authority in its evidence and submissions was not the same as that in the Decision. None of the justifications for an ECPR approach advanced by the Authority persuaded us that we could safely rely on the approach set out in the Decision in the circumstances of the present case."
"For the reasons given above, the evidence before the Tribunal regarding actual costs incurred or attributable, strongly supports Albion's contention that a calculation of the actual costs attributable to the Ashgrove system would show that both the distribution cost of 16p/m³, and the total cost of 19.2p/m³, found in the Decision on an average accounting basis, were not related to "the costs actually incurred" by Dwr Cymru and accordingly were excessive."
"631. …In our judgment, the evidence we have referred to above, taken as a whole, shows on the balance of probabilities that it was not reasonable for Dwr Cymru to assume that the costs of "distribution" of non-potable and potable water were the same at 16p/m³.
632. By various routes, Albion arrives at a figure of no more than around 2p/m³ for distribution costs...The Authority did not adduce any evidence to show what the component elements of the cost structure of a typical non-potable system might be, even indicatively, on an average cost accounting basis. Apart from one document relating to the operating costs of the treatment works, no original or contemporaneous accounting material was produced by Dwr Cymru.
633. It must, in our view, have been obvious from the interim judgment that the Tribunal was seeking evidence in order to ascertain how, on an average accounting cost basis, the distribution cost of 16p/m³ could be justified, in its component elements, even indicatively. Instead of responding to the opportunity given to them by the Tribunal, Dwr Cymru, and later the Authority, produced quite different "stand-alone" calculations on a "new build" basis, even though it was accepted, rightly, in evidence that those calculations did not, and could not, form any basis for charging.
634. We find it difficult to believe that Dwr Cymru, and the Authority, would not have considered at an early stage of this case what accounting information was available that could be used to justify the average accounting cost figure of 16p/m³, even making various assumptions and estimates, but no such information has been produced. It is in our view significant that the only cost calculation produced by the respondent Authority, namely its "stand-alone" calculation of 25p/m³, comes within the "ball park" of the First Access Price of 23.2p/m³ only by assuming a rate of return some 15 times the rate that Dwr Cymru normally earns on its existing assets, and allocating to the Ashgrove system the entire overheads of a self-standing water company. That in itself, in our view, is strong evidence that the First Access Price was excessive. Dwr Cymru's higher figure of 32.4p/m³ is based on assuming an even higher rate of return, and inflating the MEA value of the pipeline at a time when, in our view, it must have known, or at least ought to have known, that the cost of mains laying was declining sharply.
635. This unfortunate history thus leaves the Tribunal, on the evidence, with a large unexplained gap between Albion's figure of 2p/m³ for distribution costs, which is supported by calculations on an average accounting cost basis, and the figure used in the Decision of 16p/m³, the components of which are not supported, even indicatively, by any calculations at all, either in the Decision or otherwise. We do not think that Dr. Bryan could have been expected to do more, since all the information is or should be in the hands of Dwr Cymru and the Authority.
636. In all those circumstances, and for the reasons given above, in our judgment the matter of the "distribution" cost of non-potable water on an average accounting cost basis was not sufficiently investigated. It follows, in our view, that on this aspect the Decision is incorrect, or at least insufficient, from the point of view of the reasons given, the facts and analysis relied on, and the investigation undertaken, as regards the conclusion set out in paragraph 302.
637. On the basis of Albion's estimate of distribution costs of around 2p/m³ and the range of some 1.6p/m³ to 3.2p/m³ for treatment costs, on Albion's figures the First Access Price should have been in round figures no more than 4p/m³ to 5p/m³. Even doubling Albion's figures to take account of elements possibly understated or omitted would produce a price broadly in the range of 8p/m³ to 10p/m³, less than half the First Access Price of 23p/m³. The evidence taken as a whole strongly suggests to the Tribunal that the First Access Price was excessive, in relation to the economic value of the services to be supplied, applying the United Brands test, by reason of the absence of any convincing justification for the "distribution" costs included in the average accounting cost calculation."
The issue of abuse
"(1) The Tribunal may at any time, on the request of any party or its own initiative, at a case management conference, pre-hearing review or otherwise, give such directions as are provided for in paragraph (2) below or other directions as it thinks fit to secure the just, expeditious and economical conduct of the proceedings.
(2) The Tribunal may give directions –
…
(j) to enable a disputed decision to be referred back in whole or part to the person by whom it was taken;…"
"(4) Tribunal rules may make provision enabling the Tribunal to refer any matter arising in any proceedings (other than proceedings under section 47A or 47B of the 1998 Act) back to the authority that made the decision to which the proceedings relate, if it appears that the matter has not been adequately investigated."
"have regard to the desirability of –
(a) facilitating effective competition within the water supply industry;
(b) the supplier's recovering the expenses of complying with its obligations by virtue of this section and securing a reasonable return on its capital;
(c) the supplier's being able to meet its existing obligations, and likely future obligations to supply water without having to incur unreasonable expenditure in carrying out works;
(d) not putting at risk the ability of the supplier to meet its existing obligations or likely obligations to supply water."
"As a result of the pricing methodology adopted by Dwr Cymru, there is consistency between the common carriage price offered to Albion Water and the bulk distribution and non-potable treatment components of the prices charged to other customers. In particular, the proposed access price for common carriage has the same basis as the current bulk supply price for the inset appointment to the Shotton Paper site, less the water resource component. This bulk supply price was set in 1999, at which time the Director General had the opportunity to dispute the basis for this price if he had seen sufficient grounds to do so. There are no material differences from the supply characteristics of the proposed common carriage arrangement as compared to the 1999 bulk supply agreement.
(Bold added by the Tribunal)
"The attached Appendix shows how the price has been calculated as well as the relationship between the potable Large Industrial Tariff and the non-potable price. The latter is the price which would currently be charged for the Albion Bulk Supply, any difference is due to the annual price adjustment clause in the agreement.
(Bold added by the Tribunal)
The mechanism
"If the appellant challenges a decision by a regulator, and establishes, on grounds taken in the notice of appeal, that the decision was wrong, whether as a matter of procedure or because of some misdirection of law or because the CAT takes a different view of the facts on the evidence before it, the Tribunal has a choice of a number of courses open to it. It may set aside the decision and remit the case to the regulator. It may feel able to decide itself what the correct result should have been, so that no remission or reference back is necessary. It may wish to retain for itself the task of deciding the eventual outcome but require further findings from the regulator, in which case it will not remit but may refer all or part of the decision back under rule 19(2)(j), with a view to deciding the appeal with the benefit of the result of that referral."
"It may wish to retain for itself the task of deciding the eventual outcome but require further findings from the regulator, in which case it will not remit but may refer all or part of the decision back under rule 19(2)(j), with a view to deciding the appeal with the benefit of the result of that referral."
Conclusion on the issue of the abuse of excessive pricing
IX THE MARGIN SQUEEZE ABUSE
The main judgment
"In the circumstances the Director's conclusion, at paragraph 352 of the Decision, that Dwr Cymru did not infringe the Chapter II prohibition by engaging in a margin squeeze or 'price squeezing' was in our view erroneous in law and incorrect, or at least insufficient, from the point of view of the reasons given, the facts and analysis relied on, and the investigation undertaken."
Should the Tribunal decide the issue of margin squeeze abuse?
The facts
"The issue of an alleged margin squeeze arises because, to operate the proposed common carriage arrangement, Albion would have to pay the First Access Price of 23.2p/m³, and also acquire the water from United Utilities. United Utilities submits that it was likely to wish to negotiate with Albion a higher water price than the price United Utilities currently pays Dwr Cymru but, even if Albion paid only the price currently paid by Dwr Cymru of some 3.3p/m³, Albion's total cost would still be some 26.5p/m³. Since the retail price currently offered by Dwr Cymru under the New Tariff is 26.6p/m³, the de facto position is that the difference between the input price set by Dwr Cymru (i.e. the First Access Price) and the price Dwr Cymru sets in the downstream market (i.e. Dwr Cymru's retail price of 26.6p/m³) is such that Albion would be unable to compete effectively and would be forced to exit the market. In effect, the difference between Dwr Cymru's upstream and downstream prices would leave Albion with a zero margin, and thus unable to compete unless Shotton Paper were prepared to pay Albion more than Dwr Cymru's retail price."
"772. However, it has not been seriously disputed by the Authority and Dwr Cymru that, if the Decision is correct, Albion's common carriage proposal is dead. Albion is expected under the Director's ECPR calculation to supply Shotton at a margin of 0 per cent. Whatever the debate about the size of the margin needed by Albion, it is not seriously suggested that it could survive on a zero margin, and it has only done so, so far, because of the support of Shotton Paper and the interim relief ordered by the Tribunal. As Mr Jeffery points out in his witness statement of 11 November 2004, Albion necessarily incurs some staff costs, office costs, insurance costs, regulatory costs associated with its statutory appointment as an inset appointee, and so on.
773. Similarly, and for the same reason, if the Director's approach is correct, Albion could not survive even under the existing arrangements: so long as Dwr Cymru's retail price is at or about 26p/m³ and the price under the Second Bulk Supply Agreement is the same, Albion's margin between these two prices is effectively squeezed to zero.
774. It follows that, in this particular case, the application of ECPR will prevent the development of a competitive supply situation as regards the Ashgrove system, and eliminate an existing new entrant. Under the 1998 Act, the Tribunal is not concerned with the interests of Albion as such, but it is concerned with the interests of the customer, here Shotton Paper (and possibly Corus) and the preservation of competitive choice. The adoption of a pricing rule which, in this particular case, would simply throw Shotton Paper back into the hands of its former monopoly supplier, would not seem to us compatible with the development of competition."
The law to be applied
"Moreover, in our view it is manifest that a "notional" retail business of Dwr Cymru could not trade profitably at a retail price of 26p/m³ and an input price of 23.2p/m³. It would still have to acquire the water (costing at least 3.3p/m³). At a retail price of 26p/m³, a notional "retail arm" of Dwr Cymru would itself have no margin to meet its costs, including overheads and profit. It follows that on this approach the alternative test for a margin squeeze is also met."
"178. The applicant therefore contends that PEM proceeded to apply what is known as 'price squeezing'. Price squeezing may be said to take place when an undertaking which is in a dominant position on the market for an unprocessed product and itself uses part of its production for the manufacture of a more processed product, while at the same time selling off surplus unprocessed product on the market, sets the price at which it sells the unprocessed product at such a level that those who purchase it do not have a sufficient profit margin on the processing to remain competitive on the market for the processed product.
179. None the less, it must be held that, in view of the arguments put forward above to the effect that the additional costs included in the price proposed by PEM in its offer of 21 June 1995 are justified, the applicant's complaints concerning the alleged exclusion effect of the price proposed by PEM must be rejected in view of the fact that the applicant has failed to prove even the very premiss on which its argument is predicated, namely, the existence of abusive pricing of the raw material. In the absence of abusive prices being charged by PEM for the raw material, namely low-oxygen primary calcium metal, or of predatory pricing for the derived product, namely broken calcium metal, the fact that the applicant cannot, seemingly because of its higher processing costs, remain competitive in the sale of the derived product cannot justify characterising PEM's pricing policy as abusive. In that regard, it must be pointed out that a producer, even in a dominant position, is not obliged to sell its products below its manufacturing costs.
X INTERIM RELIEF
The present situation
The statutory powers
"(1) Tribunal rules may provide for the Tribunal to make an order, on an interim basis –
…
(c) granting any remedy which the Tribunal would have had power to grant in its final decision.
(2) Tribunal rules may also make provision giving the Tribunal powers similar to those given to the OFT by section 35 of the 1998 Act."
"(1) The Tribunal may make an order on an interim basis –
…
(c) granting any remedy which the Tribunal would have the power to grant in its final decision.
(2) Without prejudice to the generality of the foregoing, if the Tribunal considers that it is necessary as a matter of urgency for the purpose of –
(a) preventing serious, irreparable damage to a particular person or category of person, or
(b) protecting the public interest,
the Tribunal may give such directions as it considers appropriate for that purpose
(3) The Tribunal shall exercise its power under this rule taking into account all the relevant circumstances, including –
(a) the urgency of the matter;
(b) the effect on the party making the request if the relief sought is not granted; and
(c) the effect on competition if the relief is granted.
(4) Any order or direction under this rule is subject to the Tribunal's further order, direction or final decision…"
"(1) This section applies if the OFT has begun an investigation under section 25 and not completed it (but only applies so long as the OFT has power under section 25 to conduct that investigation).
(2) If the OFT considers that it is necessary for it to act under this section as a matter of urgency for the purpose –
(a) of preventing serious, irreparable damage to a particular person or category of person, or
(b) of protecting the public interest,
it may give such directions as it considers appropriate for that purpose."
"(1) If the OFT has made a decision that conduct infringes the Chapter II prohibition or that it infringes the prohibition in Article 82, it may give to such person or persons as it considers appropriate such directions as it considers appropriate to bring the infringement to an end."
"(a) a decision falling within paragraphs (a) to (f) of section 46(3)
…
(e) a decision of the OFT not to make directions under section 35."
The relationship between the First Access Price and the Bulk Supply Price
"It seems to us that if the First Access Price of 23.2p/m³ is not shown to be reasonably related to costs, it must equally be the case that the even higher price of 26p/m³ under the Second Bulk Supply Agreement, used as the basis of the ECPR calculation in the Decision, is not shown to be reasonably cost-based either. The only difference between the First Access Price and the Second Bulk Supply Agreement price is that the resource cost of water is included in the latter and not in the former. Similarly, if the evidence strongly suggests that the First Access Price of 23.2p/m³ was excessive, the same must be true of the price of 26 p/m³ under the Second Bulk Supply Agreement. Those facts in our view fatally undermine the ECPR calculation set out in the Decision."
"757. In those circumstances, the central problem facing the Tribunal is that there is no evidence that the prices in these various special agreements relied on as comparators in setting the price in the Second Bulk Supply Agreement were related to the costs of supply, and if so in what way. To the extent that the non-potable customers in question were being charged prices similar to those charged to Shotton Paper, we have already shown in the first part of this judgment that the First Access price of 23p/m³ is not shown to be reasonably related to costs, on the evidence before the Tribunal. A fortiori that applies to the Second Bulk Supply Agreement price of the order of 26p/m³. If the price in the Second Bulk Supply Agreement of 26p/m³ is not cost-justified, and since the evidence strongly suggests that that price was excessive, it does not in our view assist that that price is based on a comparison with other prices which are not cost-justified either. We add that the only contemporary evidence we have which purported to give some cost justification for the price under the Second Bulk Supply Agreement (D21 to the Reply) has been abandoned by Dwr Cymru, with the Authority's support, as not offering "incremental insight" (Jones 2, paragraph 16).
…
760. The price in the Second Bulk Supply Agreement of 26p/m³ is not, as such, under challenge in these proceedings. What is, however, under challenge is whether that price can safely be used, in a Decision adopted eight years later, as the basis for an ECPR calculation. Albion could not have foreseen that the price under the Second Bulk Supply Agreement indicated by the Director in 1996 would be used as the basis for an ECPR calculation in 2004. In our view, that price cannot be used for that purpose, essentially because that price has not been shown to be, even approximately, reasonably related to costs, as discussed in the earlier part of this judgment. The evidence also strongly suggests that that price is excessive in relation to costs as regards the distribution element. The same applies, by necessary implication, to Dwr Cymru's earlier retail price to Shotton Paper of 27.2p/m³, and what we understand to be Dwr Cymru's current offer price under the New Tariff of 26.6p/m³, to both of which the same objections apply."
"Similarly, and for the same reason, if the Director's approach is correct, Albion could not survive even under the existing arrangements: so long as Dwr Cymru's retail price is at or about 26p/m³ and the price under the Second Bulk Supply Agreement is the same, Albion's margin between these two prices is effectively squeezed to zero."
The need for interim measures
The Tribunal's jurisdiction
Albion's application
Aquavitae
"In our view, an interpretation of section 66E(4) which gives rise to a minus element which, in effect, precludes virtually any effective competition or market entry, is in potential conflict with the consumer objective set out in sections 2(2A)(a) and (2B) of the WIA91, and with the Chapter II prohibition, and thus open to serious question." (paragraph 976)
Conclusion on interim relief
XI CONCLUSIONS
(i) sets aside paragraphs 93 (first sentence), 97 to 99, 131, 132, 138, 144, 150, 160 to 165, 176 to 177, 182 to 187, 189 to 191, 199 to 203, 209, 211, 213 to 215, 216 to 225, 300 to 302, 317 to 331, 338 to 341, 345 to 352, 360 to 361, 371, and Annex I of the Decision.
(ii) confirms as correct the Director's assumption as to dominant position at paragraphs 212 and 215, last sentence, of the Decision, and finds on the facts that Dwr Cymru had at all material times a dominant position on the relevant market within the meaning of the Chapter II prohibition.
(iii) refers back to the Authority under Rule 19(2)(j) of the Tribunal's Rules for further investigation the matter of the costs reasonably attributable to the service of the transportation and partial treatment of water by Dwr Cymru, generally and through the Ashgrove system in particular, together with the associated question of whether, in the light of those costs, the First Access Price was an unfair price within the meaning of the Chapter II prohibition.
(iv) declares that by quoting the First Access Price of 23.2p/m³, at the same time as offering a retail price of some 26p/m³, Dwr Cymru imposed on Albion a margin squeeze which constituted an abuse of a dominant position within the meaning of the Chapter II prohibition.
(v) continues until further order the Tribunal's interim order of 20 November 2006 reducing Dwr Cymru's existing Bulk Supply Price to Albion by 3.55p/m³.
Christopher Bellamy Antony Lewis John Pickering
Charles Dhanowa 18 December 2006
Registrar
Note 1 The extent of the “water resource zone” is not deliniated in the Decision or elsewhere. [Back] Note 2 The Authority in this case exercises the power of the OFT pursuant to section 54 of the 1998 Act. [Back] Note 3 United Utilities has a management contract to manage facilities, including Ashgrove, on behalf of Dwr Cymru but that is a different point. [Back] Note 4 The document refers to Enviro-Logic, but the agreement would have had to be with Albion, the inset appointee. [Back] Note 5 Annex I uses shorter asset lives than those assumed in the calculations put before the Tribunal by Dwr Cymru and the Authority and makes allowance for “residual values”. We have not considered the validity of this. [Back] Note 6 See United States v. EL DuPont Nemours & Co. 351 US 377 (1956) discussed e.g. by O’Donoghue and Padilla The Law and Economics of Article 82 EC (OUP 2006), pp. 81-84. [Back] Note 7 We do not need to deal with Dwr Cymru’s assertion in a letter to the Director dated 5 July 1996 that the cost of duplicating the Ashgrove system would be 35p/m3 , discussed in paragraphs 166 to 170 of the Decision save to note that Dwr Cymru’s evidence before the Tribunal is that the cost would be at least 32p/m3 . Nor do we need to deal with the possible duplication of the treatment works alone, discussed at paragraphs 171 to 174 of the Decision. That suggestion, and other possibilities mentioned at paragraph 175, have never occurred and would not obviate the need for any potential supplier to use the Ashgrove main unless an alternative main were constructed. [Back] Note 8 In the main judgment, the Bulk Supply Price is referred to more compendiously as “the price under the Second Bulk Supply Agreement”. [Back]