BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Rolls Building, London, EC4A 1NL |
||
B e f o r e :
(sitting as a Deputy High Court Judge)
____________________
BILTON & JOHNSON (BUILDING) CO LIMITED |
Claimant |
|
- and |
||
THREE RIVERS PROPERTY INVESTMENTS LIMITED |
Defendant |
____________________
Rachael O'Hagan (instructed by Clyde & Co) for the Defendant
Hearing date: 2 December 2021
____________________
Crown Copyright ©
Covid-19 Protocol: This judgment was handed down by the judge remotely by circulation to the parties' representatives by email and release to BAILII. The date and time for hand-down is deemed to be 14 January 2022 at 10.30am.
Jason Coppel QC:
Background
i) On 10 August 2018, the Claimant submitted a formal tender in the sum of £1,902,633.30 to carry out works consisting of the refurbishment of an industrial estate owned by the Defendant at Jefferson Way, Thame, Oxfordshire ("the Works").
ii) The Employer's Requirements for the Works included that the Works would be carried out in four sections, corresponding to three groups of units in the industrial estate and site works. Among the Contract Particulars to be included in the contract which would be the JCT Design and Build Contract 2016 was that there would be completion dates for each section of the Works and a rate of liquidated damages for delay in completing each section of £2500 per week (§28).
iii) The Form of Tender drafted by the Defendant's agent, Brown & Lee surveyors ("B&L"), after referring to the JCT Design and Build Contract 2016, stated that: "We agree that unless and until this formal agreement is prepared and executed this Tender, together with your written acceptance thereof, shall constitute a binding contract between us". On 15 August 2018, B&L communicated by letter to the Claimant that written acceptance and a contract between them came into being (§30). This contract was referred to by the Adjudicator as "the Original Contract" (§31).
iv) The Works commenced on 17 September 2018.
v) As anticipated in the Form of Tender, on 12 October 2018 B&L issued the Claimant with a formal JCT Design and Build Contract 2016 to sign and return. This contract was dated 15 August 2018. It was signed and returned by the Claimant on 9 January 2019. This contract was referred to by the Adjudicator as "the Signed Contract" (§32). The Signed Contract was found by him to have superseded the Original Contract (§163).
vi) The Contract Particulars of the Signed Contract specified a single date of completion of the Works as 26 April 2019, in contrast to the Contract Particulars in the Original Contract, which had contemplated different completion dates for the different sections of the Works. Relatedly, and in further contrast to the Contract Particulars in the Original Contract, liquidated damages were stated to be £2500 per week (as opposed to £2500 per section per week) (§34).
vii) Subsequently, in June 2019, B&L noticed these and other discrepancies between the Signed Contract and the Contract Particulars as originally issued and issued an amended contract for the Claimant to sign. The Claimant did not sign or otherwise consent to these amendments and the Signed Contract was not amended (§204).
viii) Consequently, the contractual rate of liquidated damages for delay was £2500 per week, which was capable of being apportioned between various units and sections of the Works in the event that some were completed before others.
ix) In the course of the Works, the Claimant sought and was granted certain extensions of time but only in respect of the individual section of the Works which had been affected by the relevant delay. This was incorrect: the contract did not provide for a completion date for each section and any relevant delay which affected the timing of the Works as a whole should have given rise to an extension for completion of the Works (§167).
x) The Claimant achieved Practical Completion of the Works on 13 December 2019 (§305). However, the Defendant had taken partial possession of certain aspects of the Works in August and December 2019.
xi) The Defendant withheld £234,641.56 in purported application of the contractual provisions on liquidated damages. That figure was founded upon a damages rate of £2500 per section per week of delay and did not take account of the fact that the Defendant had taken certain parts of the Works into possession at an earlier date than other parts (§179).
xii) There had been a number of delays to the Works (§306) which had not been the responsibility of the Claimant and which together entitled the Claimant to an extension of time to the Date for Completion of the Works from 26 April 2019 to 14 November 2019 (§329).
xiii) The Defendant was entitled to liquidated damages for delay in completing the Works. Having regard to (a) the contractual rate of £2500 per week and (b) apportionment of damages between the units/sections completed on the date of Practical Completion and those completed prior to 14 November 2019, the Defendant had been entitled to withhold £6368.08 (§331).
xiv) The Adjudicator did not accept the Defendant's argument that the defence of rectification had entitled it to proceed on the basis that the liquidated damages provisions of the Signed Contract entitled it to £2500 per section per week, as per the Original Contract (§§209-217).
xv) Since the Defendant had deducted £234,641.56 in respect of liquidated damages, the Defendant was required to pay £228,273.48 to the Claimant (§332). The Defendant was also required to pay £25,387.82 in interest (§337) and the Adjudicator's fees and expenses (§339).
The relevant law
"1. The adjudication procedure does not involve the final determination of anybody's rights (unless all the parties so wish)";
2. The Court of Appeal has repeatedly emphasised that adjudicators' decisions must be enforced, even if they result from errors of procedure, fact or law;
3. Where an adjudicator has acted in excess of his jurisdiction or in serious breach of the rules of natural justice, the court will not enforce his decision.
4. Judges must be astute to examine technical defences with a degree of scepticism consonant with the policy of the [Housing Grants, Construction and Regeneration Act 1996]. Errors of law, fact or procedure by an adjudicator must be examined critically before the Court accepts that such errors constitute excess of jurisdiction or serious breaches of the rules of natural justice."
"The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator's decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator...
In short, in the overwhelming majority of cases, the proper course for the party who is unsuccessful in an adjudication under the scheme must be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator's decision as correct (whether on the facts or in law), he can take legal or arbitration proceedings in order to establish the true position. To seek to challenge the adjudicator's decision on the ground that he has exceeded his jurisdiction or breached the rules of natural justice (save in the plainest cases) is likely to lead to a substantial waste of time and expense "
"If an adjudicator intends to use a method which was not agreed and has not been put forward as appropriate by either party he ought to inform the parties and to obtain their views as it is his choice of how the dispute might be decided. An adjudicator is of course entitled to use the powers available him but he may not of his own volition use them to make good fundamental deficiencies in the material presented by one party without first giving the other party a proper opportunity of dealing both with that intention and with the results. The principles of natural justice applied to an adjudication may not require a party to be aware of "the case that it has to meet" in the fullest sense since adjudication may be "inquisitorial" or investigative rather than "adversarial". That does not however mean that each party need not be confronted with the main points relevant to the dispute and to the decision."
"An adjudicator cannot, and is not required to, consult the parties on every element of his thinking leading up to a decision, even if some elements of his reasoning may be derived from, rather than expressly set out in, the parties' submissions. But where, as here, an adjudicator considers that the referring party's claims as made cannot be sustained, yet he himself identifies a possible alternative way in which a claim of some sort could be advanced, he will normally be obliged to raise that point with the parties in advance of his decision".
"The adjudicator must attempt to answer the question referred to him. The question may consist of a number of separate sub-issues. If the adjudicator has endeavoured generally to address those issues in order to answer the question then, whether right or wrong, his decision is enforceable.
If the adjudicator fails to address the question referred to him because he has taken an erroneously restrictive view of his jurisdiction (and has, for example, failed even to consider the defence to the claim or some fundamental element of it), then that may make his decision unenforceable, either on grounds of jurisdiction or natural justice.
However, for that result to obtain, the adjudicator's failure must be deliberate. If there has simply been an inadvertent failure to consider one of a number of issues embraced by the single dispute that the adjudicator has to decide, then such a failure will not ordinarily render the decision unenforceable.
It goes without saying that any such failure must also be material. In other words, the error must be shown to have had a potentially significant effect on the overall result of the adjudication."
Ground 1: breach of natural justice in identifying the relevant contractual terms
Ground 2: failure to address rectification
"209. The dispute to be decided therefore included whether the Signed Contract should be rectified so that it provided for liquidated damages at the rate of £2,500 per week for each of the four sections (notwithstanding being grotesquely out of all proportion to the legitimate interest that TRP had for late completion as the innocent party) rather than the £2,500 per week actually provided in the Contract. ..
210. TRP could only have legitimately deducted liquidated damages on the basis of £2,500 per week for each of the four sections if it was entitled to have the Contract rectified, that such rectification and the remaining contract as drafted facilitated such deduction and, equally importantly, was TRP entitled to deduct liquidated damages in advance of the deed being rectified, notwithstanding being grotesquely out of all proportion to the legitimate interest that TRP had sought to protect against as the innocent party, as a consequence of late completion by BJB and therefore unenforceable.
211. Accordingly, I am to decide whether any deduction could be made on the basis of a possible entitlement to rectification prior to that rectification occurring and, if so, whether TRP had made out such an entitlement to rectification by the court. It is only in this sense that I am concerned with the remedy of rectification since it was not necessary for myself to rectify the Contract to decide the dispute referred to me.
212. Whilst I have not been provided with evidence to demonstrate that TRP has brought proceedings seeking rectification TRP has nevertheless raised it as a defence. Since this point is fundamental to TRP's right to deduct the liquidated damages it has claimed I consider that it is necessarily connected with the dispute.
213. In this dispute the situation is that it is TRP who had the Contract prepared on its behalf by the Employer's Agent, for execution as a Deed by BJB, which now seeks rectification on the grounds that its own draft was in error. The situation is rendered more complicated because I have decided that the liquidated damages that TRP wishes to apply are grotesquely out of all proportion to the legitimate interest that TRP had sought to protect against as the innocent party as a consequence of late completion by BJB and therefore unenforceable.
214. Notwithstanding my decision as to the proportionality and enforceability of the liquidated damages upon which TRP wishes to rely as expressed within the Employer's Requirements and/or my decision that such is a penalty in any event, I decide that the contemporaneous evidence, including the BJB's Formal Tender dated 10 August 2018, the Original Contract and the Employer's Requirements, the last of which was common to the Original Contract and the Signed Contract, clearly demonstrates that the Employer's Agent made a mistake in the preparation of the Signed Contract and that objectively viewed BJB was aware that a mistake had been made by the Employer's Agent. However, as I have already decided had the Employer's Agent not made such a mistake in the preparation of the Signed Contract, the liquidated damages the Employer's Agent had intended to insert would have been extravagantly disproportionate and therefore a penalty and thus unenforceable.
215. In my opinion it is arguable that rectification may be ordered on the facts of the case so that the applicable liquidated damages rate might possibly be corrected to £2,500 per week for each of the four sections, but such would be grotesquely out of all proportion to the legitimate interest that TRP had sought to protect against, as the innocent party, as a consequence of late completion by BJB and/or a penalty and thus unenforceable.
216. The second question therefore is whether a prima facie possible entitlement to rectification provides TRP with an entitlement to deduct liquidated damages at the rate of £2,500 per week for each of the four sections in the meantime. I decide that it does not because TRP has not relieved itself of the burden of proof in regard to such claim, legal authority for doing so has not been cited and I have already decided that such would be extravagantly disproportionate and therefore a penalty and thus unenforceable.
217. Lest there be doubt, in any event I do not consider that I am empowered to order rectification of the Contract in the absence of either the Parties' agreement or cited legal authority for me to do so as an Adjudicator."
i) Whether or not the Defendant had been entitled to withhold liquidated damages at the higher rate of £2500 per section per week on the basis that the Signed Contract fell to be rectified was part of the dispute before him (§§209, 212).
ii) It was arguable that the Defendant was entitled to rectification on account of there having been a mistake made in the preparation of the Signed Contract of which the Claimant was aware (§§214-215).
iii) But that prima facie possible entitlement to rectification did not entitle the Defendant to withhold liquidated damages at the higher rate at a time when the Signed Contract had not been rectified and in fact provided for liquidated damages at the rate of £2500 per week (§216). The Defendant had not cited authority to establish that entitlement and, further, the higher rate of liquidated damages was a penalty and unenforceable.
iv) Since the key question was whether the Defendant had been entitled to withhold liquidated damages at a time when the Signed Contract had not been rectified, it was not necessary for the Adjudicator himself to decide whether to rectify the contract (§211).
v) If it had been necessary for the Adjudicator to decide whether to order rectification of the contract, he did not consider that he had the power to do so (§217).
Conclusion