QUEEN’S BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT
HIS HONOUR JUDGE HUMPHREY LLOYD Q.C.
133-137,FetterLane, London, EC4A 1HD | ||
B e f o r e :
____________________
BALFOUR BEATTY CONSTRUCTION LTD | Claimant | |
- and - | ||
THE MAYOR AND BURGESSES OF THE LONDON BOROUGH OF LAMBETH | Defendant |
Jonathan Acton Davis QC appeared for the defendant, instructed by Knowles Lawyers Limited.
____________________
Crown Copyright ©
His Honour Judge Humphrey LLoyd QC
“45. Balfour Beatty had a contractual obligation pursuant to clause 250 of the specification as follows:Monitoring: Record progress on a copy of the programme kept on site. If any circumstances arise which may affect the progress of the works put forward proposals or take other action as appropriate to minimise any delay and to recover any lost time.
46. In breach of contract BB failed to record progress on any programme, on site, or otherwise, and/or in breach of contract BB failed to put forward proposals to minimise delay and/or to recover lost time. Lambeth submits that in consequence of the failure of BB to comply with its contractual obligations it is now not possible with any degree of certainty to determine the date or duration that the various activities were undertaken by BB, nor the impact or effect on other linked or non-linked activities. Lambeth submits that this being the case it is impossible to properly assess the true causes of the delay to the completion of the works and the dates and durations of the delays claimed by BB are nothing less than speculation.
47. BB has submitted the following “final as-build programmes”.
F0315/FAB1 – Critical Trade Activities
FAB2 – Stripping Out and Demolition Works
FAB3 – Brick and Block Works
FAB4 – Asphalt and Pitched Roofing Works
FAB5 – Carpentry Works
FAB6 – Window Installation Works
FAB7 – Drylining Works
FAB8 – Decoration Works
FAB9 – Insulated Render Works
FAB10 – Concierge Area Works.
48. As stated above, Lambeth submits that it is only when you review the “final as-built programmes” does the reason for the “filter programmes” become evident. Lambeth say that the inadequate record keeping by BB means that it can only report “progress” on a floor by floor basis. Lambeth submits that such general records are hopelessly vague and inadequate. By way of an example, a variation in one flat on one floor may have a delaying effect on that flat but it is submitted would have no impact or effect on the other non-affected flats on the same floor. The manner in which BB has recorded progress is that it is simply not possible to isolate any individual event. Thus an event in one trade in one flat on the one floor is depicted as a delay to all of the entire floor. This is simply not credible and calls into question the entire reliability of all of the programmes.
49. BB programmed the works on a flat type basis (albeit without identifying the critical path for same) and at the very least BB should have measured progress against these same flat types. That way it would have been possible to compare the planned progress with the actual progress in a meaningful way. Instead all that BB have provided is an aggregate of all the planned time and compared with all the actual time on a trade by trade basis. No attempt has even been made by BB to demonstrate any link between the trades.
50. Lambeth would also observe that as with the “as-planned” programmes, the “Final as-built programmes” also fail to identify any critical path.
51. Before looking at the “final as-built programmes” exhibited by BB, Lambeth would make passing reference to the delay analysis methods most widely recognised and used:
(I) Time Impact Analysis (or “time slice” of “snapshot” analysis). This method is used to map out the impacts of particular delays at the point in time at which they occur permitting the discrete effects of individual events to be determined.
(II) Window analysis. For this method the programme is divided into consecutive time “windows” where the delay occurring in each window is analysed and attributed to the events occurring in that window.
(III) Collapsed as-built. This method is used so as to permit the effect of events to be “subtracted” from the as-built programme to determine what would have occurred but for those events.
(IV) Impacted plan where the original programme is taken as the basis of the delay calculation, and delay defaults are added into the programme to determine when the work should have finished as a result of those delays.
(V) Global assessment. This is not a proper or acceptable method to analyse delay.
52. It is Lambeth’s case that the programme of BB do not conform or comply with any of the recognised and accepted delays analysis methods. Further all that it has provided by BB is a claim in the most global of natures. It is observed that BB has provided no explanation whatsoever as to why it has not used any of the above mentioned delay analysis techniques, nor even why it has pleaded its case on a global basis. Lambeth suggest that this is because none of the above methods would not substantiate the delays claimed by BB.
53. Lambeth submits that it would be of assistance to the adjudicator to provide its comments on the “as-built” programmes submitted by BB.”
“It appears to me from the Notice of Adjudication that the dispute concerns substantial issues that may not be capable of being determined in 28 days. I do not currently, but may request the Referring Party to extend the time for the making of my decision by 14 days. I will issue directions once I have seen the Referral and I look forward to both parties’ co-operation in this matter.Dependent on the content of the Referring parties’ referral document, it seems to me that I may require assistance in my investigations. Such assistance will be limited to determination of fact and will be called upon only if likely to result in a saving of my fees”.
“MOUCHEL ADJUDICATION AGREEMENTAGREEMENT
THIS Agreement is made on the.........day of.........20..
Between
1. Balfour Beatty Construction Ltd of 23 Ravelston Terrace, Edinburgh, EH4 3TN
(“the Referring Party”)”
2. The Mayor and Alderman of The London Borough of Lambeth of Harnbrook House, Porden Road, London SW2 1RW (“the Other Party”)
(together called “the Parties”)
And
3. David M Richards of Mouchel Consulting Limited, West Hall, Parvis Road, West Byfleet, Surrey KT14 6EZ
(“the Adjudicator”)
A dispute has arisen between the Parties under a Contract between them. This dispute has been referred to adjudication in accordance with a clause of the contract between the Parties and the Adjudicator has been requested to act.
IT IS AGREED that
1. The rights and obligations of the Adjudicator and the Parties shall be set out in this Agreement.
2. The Adjudicator agrees to adjudicate the dispute in accordance with the Procedure.
3. The Parties agree jointly and severally to pay the Adjudicator’s fees and expenses as set out in the attached schedule and in accordance with the Procedure.
4. The Parties acknowledge that the Adjudicator shall not be liable for anything done or omitted in the discharge or purported discharge of his functions as Adjudicator (whether in negligence or otherwise) unless the act or omission is in bad faith. Any employee or agent of the Adjudicator shall be similarly protected from liability.
5. This Agreement shall be interpreted in accordance with the law of England and Wales.
6. The adjudication and all matters connected with it are and will be kept confidential by the Parties and the Adjudicator except in so far as it is necessary to enable a party to implement or enforce the decision of the Adjudicator or for the purpose of any proceedings subsequent to the adjudication.
7. The Adjudicator shall inform the Parties if he intends to destroy the documents which have been sent to him in relation to the adjudication and he shall retain documents for a further period at the request of either Party.
8. The Parties allow the Adjudicator to employ assistants at rates that will be advised.
9. The Adjudicator’s fees shall be paid prior to release of his decision.
SCHEDULE
1. Appointment Fee (if requested) UK £2,700.00
(To include preliminary reading, etc, by which time charges will be abated). The appointment fee is payable in the first instance by the Claimant, if requested. Up to fifty per cent of this fee of refundable in the event of settlement and if less time has been spent on the matter.
2. Hours worked outside hearing: UK £135.00 per hour (including preliminary reading, meetings, views and preparation of decision).
3. Clerk UK £51.00 per hour
I have a legally qualified clerk as well as a secretary. My clerk undertakes administrative work that I would otherwise do.
4. Fees for hearing (if applicable): UK £1,050 per day. Part days charged at UK £135.00 per hour with a minimum of UK £675.00
5. Rendering of Fee Notes:
Fees will be invoiced in Sterling, plus VAT as applicable, and will be payable in that currency to Mouchel Consulting Limited. The due date for payment is on presentation of the invoice and interest will be charged at 15% p/a on the full invoice should any sum remain outstanding fourteen days after the due date.
6. Travelling Expenses and Disbursements:
These will be charged on the basis of my being resident in West Byfleet, England and are payable as and when incurred. Air travel will be business class and rail travel will be first class. Travelling time will be charged as reading time.
7. Notification of Decision
I will make my Decision on or by the date that I am required to do so and will notify the Parties and their Representatives that my Decision will be dispatched to them on full payment of my fees."
In an e-mail of 13 December 2001 Mr Richards made it clear that the Procedure referred to in the proposed agreement was that set out in clause 41A of the JCT conditions. The agreement as proposed was accepted by the parties.
“Having now read the referral notice together with appendices (but I have not yet read the other four files) I should be grateful if the Referring Party would produce a schedule setting out, for each relevant event: the date of the event, the activity (or activities) directly affected by the event, the nature of that effect (i.e. delay to start, extension to duration, delay to finish), the timing or date of that effect and any comment necessary.Further, I note the Referring Party’s contention that all material has been previously supplied to the Respondent, and this seems to me to be the case for the material delivered to me. I would also be grateful, therefore, if the Referring Party can reference each piece of information in the suggested schedule to the documents delivered to me – this will prevent any possibility of ‘ambush’. If this was restricted to the events described in Appendix 13, the Extension of Time Summary Document, that may help to limit the work necessary but I do not wish to restrict the Referring Party’s case if it is made on a wider basis (I have not considered the aspect of similarity between the documents submitted).
I expect that the information is all included within the documents provided to me, but such a schedule will assist me to assimilate the material and come to a decision as speedily as possible. Please advise by return if you will not be able to provide the schedule by Christmas as I will then need to consider requesting an extension of time and/or employing an assistant to help me.
With regard to information from the Respondent, in case such information is not intended to be submitted with its response to the Referral Notice (tomorrow), I should be grateful if the Respondent would provide me with details of the Architect’s extension of time analysis and reasons for not allowing extensions of time claimed. I would like this by Christmas, as well.”
“I have read the responding party’s defence and I do not consider there to be any points arising out of that document upon which a reply is needed other than the issue of law surrounding relevant event 25, the flood in December 2000.The responding party does not appear to have accepted the as-built programme on the basis of the substantiation provided by the referring party. I will therefore require the assistance of a colleague to provide a check in order that I may be satisfied.
I propose to use Mr Richard Leakey at the rate of £50 per hour."
Mr Wicks replied immediately stating that it was intended to reply to the details sent on 28 December. Mr Wicks asked Mr Richards “in the interest of costs may we you request that your colleague waits for our document before undertaking his checks". On the same day Mr Wicks sent the answers to BB’s letter of 3 January including some criticisms of the material relied upon by BB to support its as-built programme.
“We note that Balfour Beatty will be making a response to Lambeth’s reply in the above matter. We understand that despite your facsimile of yesterday you are minded to allow Balfour Beatty to present such further details as will be in its response. Lambeth believes that this response will contain new argument and/or change the basis upon which Balfour Beatty has presented its case.
This being the situation Lambeth will wish to make a further submission, the timing of which is likely to put even more strain on the already tight timescale. In view of this may we propose that the parties agree to allow you more time in which to make your Decision. Can we further suggest that in the event that Balfour Beatty refuses this proposal that you decline to look at any information they subsequently provide."
(At that time it had been agreed that Mr Richards should have until 25 January instead of 8 January 2002, to make his decision.) Mr Wicks’ proposal was refused by BB. On 16 January BB replied to Lambeth’s letter of 15 January. As forecast in its letter to Mr Richards of 15 January Lambeth delivered, on 21 January, a 21-page submission (which included the passage that I have already quoted.) On 22 January Lambeth sent the first part of his reply in response to BB’s submission of 17 January (at 6.20 pm) which was followed by the second part at 11.04 am on the next day (23 January).
"5. Law.5.1 The Referring Party relies on the existence of relevant events for its entitlement to extension of time and has no regard for any delay for which it may be culpable and which may impact at the same time as the relevant event. This approach follows that adopted in the case of Balfour Beatty Building Ltd v Chestermount Properties Ltd (1993) 62 BLR 12 where the only limitation placed on the approach was that the net delay of the event should be added to the time for completion, rather than the gross delay including prior culpable delay. However, insofar as the Referring Party relies on the timing of an instruction for additional work as preventing completion by a certain date then, while the contention may be correct in itself, that does not give rise to an entitlement to extension of time other than on the basis decided in Chestermount.
5.2 The Respondent relies, to a degree, on a limited quotation from the judgment of HHJ Dyson [sic] in Henry Boot Construction v Malmaison Hotel (Manchester) Ltd (1999) 70 Con LR 32 to content that the Chestermount approach is wrong. However, the Malmaison judgment is founded on the Parties' agreement that Chestermount, as summarised above, is correct.
5.3 The Respondent also relies on the dictum of HHJ Seymour in Royal Brompton Hospital National Health Service Trust v Frederick Alexander Hammond & Others (2000) Lloyd’s Rep 643. This case contradicts the principle that a contractor should have the benefit of a relevant event if it is in culpable delay, as approved in Chestermount.
5.4 On the basis that the first instance authorities, as contended by the Respondent, conflict and these points were not considered in the appellate decisions, I decline to follow the Respondent’s view of Brompton Hospital. Those cases have been said by some legal commentators to support each other to the opposite effect of that contended for by the Respondent. Further, the Society of Construction Law’s draft Protocol for Determining Extensions of Time and Compensation for Delay and Disruption recommends a contrary position to Brompton Hospital.
5.5 In addition to the above, the Respondent's case is predominantly that the Referring Party has failed to properly make its case. However, it does not advance any positive case such as may be made with the assistance of its Architect and I am aware that this may be due to some difficulties between the Respondent and the Architect. The Respondent contends that the Referring Party has failed to give proper notices. I do not need to investigate this allegation in detail as, in the absence of any assistance from the Respondent’s Architect, I must make my own determination on the basis of the papers before me and on the balance of probability.
6. Relevant Events.
6.1 I have had some difficulty in reviewing the relevant events contended for by the Referring Party against its programmes and progress. While it is clear that the Referring party intended to progress its tradesmen sequentially down through the building, the Referring Party advised, in my meeting with it and the Respondent, that its programmes were drawn rather than linked. Those programmes must therefore be regarded as a statement of intent for general utilisation of resource rather than a detailed forecast of location of resource utilisation. In this regard I accept the Respondent’s point that a delay in one location will not necessarily prevent work in another location, and would not necessarily cause a delay. Rather, the project must be reviewed in the round.
6.2 While a degree of float may exist in the activities of a particular trade, a contractor will always seek to minimise the float by reducing its resources appropriately – a contractor will always seek optimum utilisation of its resources. In the circumstances of this project, that would mean use of reduced workforce rather than intermittent use of the workforce. Consequently, bearing in mind that a contractor has no obligation to accelerate its work, it appears to me that the most likely causes of delay will be such events that prevent a trade from working entirely or from working efficiently, or such events that increase the work of a trade.
6.3 The Parties are aware of the Society of Construction Law Protocol [the adjudicator added in a footnote: Society of Construction Law Protocol For Determining Extension Of Time And Compensation For Delay And Disruption, Consultation Version, November 2001, paragraph 3.9.4, pp 18 & 19] which sets out a reasonable hierarchy for the methodologies available for the delay analysis. In order of preference, these are:
1. Time Impact Analysis
2. Windows Analysis
3. Collapsed As-built Analysis
4. Impacted Plan Analysis
The use of a particular method is determined by the information available, with least information allowing the least preferred method and giving rise to the least accurate answer. That does not mean that if all information is available, the answer determined by a less accurate method is not valid or that, if little information is available, an assessment is not valid. Rather the answer is less likely to be accurate.
6.4 Given the nature of the project and the construction programme, any evaluation of extension of time in this case must necessarily be relatively coarse. That does not disentitle the Referring Party to an evaluation of its extension of time. Rather, it means that any inaccuracy in determination will cut both ways.
6.5 It is not possible to make an assessment on the basis of time impact analysis and therefore I have reviewed the As-Built programme. I find it a reasonable representation of work being carried out at various locations on the project. I have also reviewed it for impact of events, similar to a ‘collapsed as-built’ method. Where issues between the Parties fall away as a result of the work that is the subject of that issue not being on the critical path, I have not necessarily set out my decision on the particular issue.
6.6 The project had two basic components, the Flats and the Concierge. Each element had its own critical path and must initially be considered separately in reviewing entitlement to extension of time.
6.7 From the As-built programme for the Flats, my summary of which is attached, the sequence of work was as follows.....[the adjudicator then considered the sequence].
6.8 The critical path for the work to the Flats seems tome to have run through the stripping out and demolition activity, then through brickwork and blockwork. Following that, the critical path went either through fourth and fifth window installation or dry liming works generally, before continuing predominantly through dry lining work. The Minaret boarding was the predominant subsequent activity, followed by remedial and decoration works, consequent upon the flood in December 2000.
6.9 It appears to me that the Referring Party was unable to fully realise its aim of working in an orderly fashion in the Flats, progressing from floor to floor with continuous working on each floor.
6.10 On the basis of the information presented, I determine that the Concierge works initially had five weeks float. By the time the basement slab commenced, three weeks’ float had been used and, at completion of the basement slab, the original five weeks’ float was extinguished.
6.11 The critical path through the Concierge work appears to me to have run through the structural concrete work and into the brickwork and blockwork until commencement of plastering to the Concierge. At this point both the plastering and windows were critical until brickwork and blockwork became critical again, prior to commencement of carpentry. Carpentry was concurrently critical with plastering up to the Christmas (2000) break. Thereafter the M&E and CCTV works were critical through to completion.
6.12 With regard to the combined position of the Flats and the Concierge works, the Flats work was critical up to four weeks before actual completion of the drylining, at which point the critical path moved to the plastering in the Concierge. This results from the Flats having only four weeks of work scheduled following dry lining completion and from the Concierge having six weeks of work due from commencement of plastering, with the Concierge plastering, alone, continuing for eight weeks until the flood in early December 2000. At that point, it appears to me, from the lack of recorded as-built work for the whole project, that the flood and its effects were critical for a period of four weeks. Thereafter, the M&E and CCTV work to the Concierge was critical.
6.13 Considering in chronological order of potential effect, the relevant events (RE’s) contended for by the Referring Party against the background set out above, I find as follows [the adjudicator then dealt with the Relevant Events]... .
...
6.41 I consider that the above analysis is such as could have been carried out by the Architect in the absence of the detailed particulars that should always be preferred.
6.42 No evidence has been produced to support the Respondent’s allegation that the Referring Party failed to use its best endeavours to prevent delay to the works. Neither has any evidence been produced to establish that, to any material degree, the Referring Party failed to properly proceed with the works – note of failure to work in a particular area is not sufficient without demonstration that the project was under-resourced by comparison with the contracted requirements. Nor should an as-built programme show any more than shown on those of the Referring Party. All contractors experience a degree of set-back in constructing work that is their responsibility but I see nothing that is out of the ordinary in this case, in that regard. Consequently these defences fail, except insofar as I have determined a date for completion that is earlier than the date actually achieved.
6.43 I determine that the Referring Party is entitled to an extension of time of thirty five weeks and one day, creating a Date For Completion, in the terms of the contract, of 10 April 2001, some six weeks and two days prior to the Date of Practical Completion.
6.44 Of the thirty five weeks and one day, all are due to variation or late instruction or information, none is due to ‘weather’ (if such is what the Referring Party refers to as a neutral event) and none is due to water damage. Further, on that basis, the Referring Party is entitled to reimbursement of such loss and expense as may be due to relevant events, which may be more than those impacting on the critical path, pursuant to clause 26 of the conditions of contract.
7. Liquidated and Ascertained Damages.
7.1 The Referring Party seeks repayment of damages deducted. The amount deducted by the Respondent is £355,831.71 in respect of thirty weeks and three days delay. That amount should be £71,834.57 in respect of six weeks and two days delay. The Referring Party is entitled to reimbursement of the difference in the sum of £283,997.14.
8 Interest and/or Financing.
8.1 I have discretion as to interest and do not accept the Respondent’s contention that interest should be reviewed in the context of the entire account. I determine that the Referring Party is entitled to £18,355.51 by way of interest.
9 Costs.
9.1 I have discretion as to the apportionment of my fees. I determine that, taking into account all of the above and on the basis that costs should follow the event, the Respondent shall bear my fees.
10. Adjudicator’s Decision.
10.1 The Date for Completion is 10 April 2001.
10.2 The Respondent shall pay £283,997.14, plus VAT, if applicable and at the appropriate rate, to the Referring Party within fourteen days of the date hereof as reimbursement of damages incorrectly deducted.
10.3 The Respondent shall pay £18,355.51, plus VAT, if applicable and at the appropriate rate, to the Referring Party within fourteen days of the date hereof as damages for the incorrect deduction.
10.4 The Respondent shall bear and pay my fees in the total of £11,267.96 inclusive of VAT. Provided always that, if the Referring Party shall have paid some or all of my fees, the Respondent shall reimburse the Referring Party within fourteen days of the date hereof”.
“David M Richards: 47.4 hours
Geoff Bewsey: 5.2 hours
Bob Neill: 1 hour
Maria M Smith: 3.8 hours”
Mr Bewsey and Mr Neill were said to have assisted Mr Richards in the “consolidation of the as-built programme”. (Ms Smith was Mr Richards' administrative assistant.) After the decision had been given Mr Richards informed the parties of the breakdown of the time spent in the matter. Apart from Mr Richards’ time the only significant amount of time was that of Mr Richard Leakey who had spent 7.5 hours in the week ending 18 January 2002. In a further letter of 29 January Mr Richards said that Mr Leakey, a senior quantity surveyor, had been engaged in “checking compilation of referring party’s as-built programme”; Mr Neill as a “senior dispute manager/programmer” had been engaged on “translation of Power Project file to Excel”; Mr Geoff Bewsey, who occupied a similar position had been engaged in the “translation of Excel files to access database in loading CSP plan and software”.
Case for Defendant
“If the expert arbitrator, as he may be entitled to do, forms a view of the facts different from that given in the evidence which might produce a contrary result to that which emerges from the evidence, then he should bring that view to the attention of the parties. This is especially so where there is only one party and the arbitrator is in effect putting the alternative case for the party not present at the arbitration.Similarly if an arbitrator as a result of a view of the premises reaches a conclusion contrary to or inconsistent with the evidence given at the hearing, then before incorporating that conclusion in his award he should bring it to the attention of the parties so that they may have an opportunity of dealing with it.”
In Interbulk Limited v Aiden Shipping Co Limited (The “Vimeira”) [1984] 2 Lloyd's Reports 66 at page 75 Robert Goff LJ said:
“In truth, we are simply talking about fairness. It is not fair to decide a case against a party on an issue which has never been raised in the case without drawing the point to his attention so that he may have an opportunity of dealing with it, either by calling further evidence or by addressing argument on the facts or the law to the tribunal.”
Ackner LJ also said at page 76:-
“Where there is a breach of natural justice as a general proposition it is not for the courts to speculate what would have been the result if the principles of fairness had been applied. I adopt, with respect, the words of Mr Justice Megarry in John v Rees [1969] 2 All ER 275 at p 309 where he said:As everybody who has anything to do with the law well knows, the path of the law is strewn with examples of open and shut cases which, somehow, were not; of unanswerable charges which, in the event, were completely answered; of inexplicable conduct which was fully explained; of fixed and unalterable determinations that, by discussion, suffered a change."But, in this case, speculation does not arise. If the arbitrators had informed the parties of what they had in mind, the consequences would have been obvious. Firstly, the charterers would have sought to persuade the arbitrators that it was common ground on the evidence that there was adequate room to turn the vessel and that, therefore, the arbitrators should decide the dispute according to the evidence. If they failed so to persuade the arbitrators, they would have sought, and would have been entitled to, an adjournment. Having obtained an adjournment, the charterers would have called the evidence which in fact was called at the sub-arbitration and would have satisfied the arbitrators that the turning area was adequate.”
Mr Acton Davis also referred to a passage in Gbangbola v Smith & Sherriff [1988] 3 All ER 730 at page 740B where I said:-
“A tribunal does not act fairly and impartially if it does not give a party an opportunity of dealing with arguments which have not been advanced by either party”.
Mr Acton Davis drew attention to paragraph 40 of the judgment of His Honour Judge Bowsher QC in Discain (No 2) in which he had said:-
“While the Arbitration Act does not apply to adjudications, some help may be obtained from that Act by way of analogy. As a result of that Act, serious irregularity on the part of the arbitrator (including failure to act fairly and impartially as between the parties) is not a sufficient ground for the court to interfere in an arbitrator’s decision unless the court is satisfied that the irregularity “has caused or will cause substantial injustice to the applicant”: See Egmatra AG v Marco Trading Corporation [1999] 1 Lloyd's Rep 862 at page 865.”
(1) Neither party had presented a critical path analysis to the adjudicator.(2) Lambeth had submitted to the adjudicator that the material provided by BB did not establish its claim.
(3) The adjudicator himself constructed or had constructed for him a chart (an "as-built programme") which combined the as-built record on one sheet and had drawn on that chart a representation of a critical path through the work as actually carried out.
(4) That conclusion from the as-built chart had not been presented to the parties for their comment.
(5) The decision and the extension of time had been based on that critical path since the decision contained numerous reference to “critical” and “non-critical” matters.
(6) In addition the adjudicator apparently adopted a “collapsed as-built” analysis from which he arrived at his conclusion as to what was “critical” and “non-critical” for the purposes of his decision.
(7) Lambeth was not given any opportunity to comment on the propriety of such an analysis which the adjudicator elected to adopt or on its use even though it had in its submissions drawn attention to the fact that there were four possible ways of analysing the delay.
(8) Finally, Lambeth were not given the opportunity to deal with the conclusions which the adjudicator intended to draw or in fact drew from the application of that analysis.
Lambeth relied on John Barker Construction Ltd v London Portman Hotel Ltd (1996) 83 BLR 31 in which Mr Recorder Toulson QC held that an architect who had to decide whether to grant an extension of time under clause 25 of the JCT conditions would not have acted fairly and lawfully and his decision would be fundamentally flawed if he had not carried out a logical analysis in a methodical way of the impact of the relevant events on the contractor's programme and made only "an impressionistic, rather than a calculated, assessment" (see page 62). The judge said also (see the same page):
"I accept that the assessment of a fair and reasonable extension involves an exercise of judgment, but that judgment must be fairly and rationally based."
As the assessment was not fair or based on a proper application of the terms of the contract it was submitted that it was invalid. (In the context of a dispute about the time for completion a logical analysis includes the logic required in the establishment of a CPN.) Lambeth tendered evidence from a planner, Mr D. C. Bentley, which criticised Mr Richard's work, for example, that it was impossible to establish a critical path on the basis on observations of an " as built" record programme. Mr Bentley's evidence is in my judgment irrelevant and thus inadmissible in so far as it is intended to show that Mr Richards made errors or on the main grounds relied on by Lambeth. I have therefore disregarded them.
Case for the Claimant
Decision
“I do understand that adjudicators have great difficulties in operating this statutory scheme, and I am not in any way detracting from the decision in Macob. It would be quite wrong for the parties to search around for breaches of the rules of natural justice. It is a question of fact and degree in each case, and in this case the adjudicator overstretched the rules.”....
“That Scheme makes regard for the rules of natural justice more rather than less important. Because there is no appeal on fact or law from the adjudicator’s decision, it is all the more important that the manner in which he reaches his decision should be beyond reproach. At the same time, one has to recognise that the adjudicator is working under pressure of time and circumstance which makes it extremely difficult to comply with the rules of natural justice in the manner of a court or an arbitrator. Repugnant as it may be to one's approach to judicial decision-making, I think that the system created by the [HGCRA] can only be made to work in practice if some breaches of the rules of natural justice which have no demonstrable consequence are disregarded."
The last sentence shows that the question that I posed cannot be given an unqualified answer as the facts have to be taken into account.
Extracts from JCT Conditions
the Architect/the Contract Administrator has issued a certificate under clause 24.1; and
the Employer has informed the Contractor in writing before the date of the Final Certificate that he may require payment of, or may withhold or deduct, liquidated and ascertained damages,
then the Employer may, not later than 5 days before the final date for payment of the debt due under the Final Certificate:
either
.1 .1 require in writing the Contractor to pay to the Employer liquidated and ascertained damages at the rate stated in the Appendix (or at such lesser rate as may be specified in writing by the Employer) for the period between the Completion Date and the date of Practical Completion and the Employer may recover the same as a debt;
or
.1 .2 give a notice pursuant to clause 30.1.1.4 or clause 30.8.3 to the Contractor that he will deduct from monies due to the Contractor liquidated and ascertained damages at the rate stated in the Appendix (or at such lesser rate as may be specified in the notice) for the period between the Completion Date and the date of Practical Completion.
24.2 .2 If, under clause 25.3.3, the Architect/the Contract Administrator fixed a later Completion Date or a later Completion Date is stated in a confirmed acceptance of a 13A Quotation, the Employer shall pay or repay to the Contractor any amounts recovered, allowed or paid under clause 24.2.1 for the period up to such later Completion Date.
24.2 .3 Notwithstanding the issue of any further certificate of the Architect/the Contract Administrator under clause 24.1 any requirement of the Employer which has been previously stated in writing in accordance with clause 24.2.1 shall remain effective unless withdrawn by the Employer.
25.2 .1 .1 If and whenever it becomes reasonably apparent that the progress of the Work is being or is likely to be delayed the Contractor shall forthwith give written notice to the Architect/the Contract Administrator of the material circumstances including the cause or causes of the delay and identify in such notice any event which in his opinion is a Relevant Event.
.1 .2 Where the material circumstances of which written notice has been given under clause 25.2.1.1 include reference to a Nominated Sub-Contractor, the Contractor shall forthwith send a copy of such written notice to the Nominated Sub-Contractor concerned.
25.2 .2 In respect of each and every Relevant Event identified in the notice given in accordance with clause 25.2.1.1 the Contractor shall, if practicable in such notice, or otherwise in writing as soon as possible after such notice:
.2 .1 give particulars of the expected effects thereof; and
.2 .2 estimate the extent, if any, of the expected delay in the completion of the Works beyond the Completion Date resulting therefrom whether or not concurrently with delay resulting from any other Relevant Event
and shall give such particulars and estimate to any Nominated Sub-Contractor to whom a copy of any written notice has been given under clause 25.2.1.2.
25.2 .3 The Contractor shall give such further written notices to the Architect/the Contract Administrator, and send a copy to any Nominated Sub-Contractor to whom a copy of any written notice has been given under clause 25.2.1.2, as may be reasonably necessary or as the Architect/the Contract Administrator may reasonably require for keeping up-to-date the particulars and estimate referred to in clauses 25.2.2.1 and 25.2.2.2 including any material change in such particulars or estimate.
25.3 .1 If, in the opinion of the Architect/the Contract Administrator, upon receipt of any notice, particulars and estimate under clauses 25.2.1.1, 25.2.2.2 and 25.2.3,
.1 .1 any of the events which are stated by the Contractor to be the cause of the delay is a Relevant Event and
.1 .2 the completion of the Works is likely to be delayed thereby beyond the Completion Date
the Architect/the Contract Administrator shall in writing to the Contractor give an extension of time by fixing such later date as the Completion Date as he then estimates to be fair and reasonable. The Architect/the Contract Administrator shall, in fixing such new Completion Date, state:
.1 .3 which of the Relevant Events he has taken into account and
.1 .4 the extent, if any, to which he has had regard to any instructions issued under clause 13.2 which require as a Variation the omission of any work or obligation and/or under clause 13.3 in regard to the expenditure of a provisional sum for defined work or for Performance Specified Work which results in the omission of any such work,
and shall, if reasonably practicable having regard to the sufficiency of the aforesaid notice, particulars and estimate, fix such new Completion Date not later than 12 weeks from receipt of the notice and of reasonably sufficient particulars and estimate, or, where the period between receipt thereof and the Completion Date is less than 12 weeks, not later than the Completion Date.
If, in the opinion of the Architect/the Contract Administrator, upon receipt of any such notice, particulars and estimate, it is not fair and reasonable to fix a later date as a new Completion Date, the Architect/the Contract Administrator shall if reasonably practicable having regard to the sufficiency of the aforesaid notice, particulars and estimate so notify the Contractor in writing not later than 12 weeks from receipt of the notice, particulars and estimate, or, where the period between receipt thereof and the Completion Date is less than 12 weeks, not later than the Completion Date.
25.3 .3 After the Completion Date, if this occurs before the date of Practical Completion, the Architect/the Contract Administrator may, and not later than the expiry of 12 weeks after the date of Practical Completion shall, in writing to the Contractor either
.3 .1 fix a Completion Date later than that previously fixed if in his opinion the fixing of such later Completion Date is fair and reasonable having regard to any of the Relevant Events, whether upon reviewing a previous decision or otherwise and whether or not the Relevant Event has been specifically notified by the Contractor under clause 25.2.1.1; or
.3 .2 fix a Completion Date earlier than that previously fixed under clause 25 or stated in a confirmed acceptance of a 13A Quotation if in his opinion the fixing of such earlier Completion Date is fair and reasonable having regard to any instructions issued after the last occasion on which the Architect/the Contract Administrator fixed a new Completion Date
- under clause 13.2 which require or sanction as a Variation the omission of any work or obligation; and/or
- under clause 13.3 in regard to the expenditure of a provisional sum for defined work or for Performance Specified Work which result in the omission of any such work; or
.3 .3 confirm to the Contractor the Completion Date previously fixed or stated in a confirmed acceptance of a 13A Quotation.
Provided that no decision under clause 25.3.3.1 or clause 25.3.3.2 shall alter the length of any adjustment to the time required by the Contractor for the completion of the Works in respect of a Variation for which a 13A Quotation has been given and which has been stated in a confirmed acceptance of a 13A Quotation.
25.3 .4 Provided always that:
.4 .1 the Contractor shall use constantly his best endeavours to prevent delay in the progress of the Works, howsoever caused, and to prevent the completion of the Works being delayed or further delayed beyond the Completion Date;
.4 .2 the Contractor shall do all that may reasonably be required to the satisfaction of the Architect/the Contract Administrator to proceed with the Works.
41A Adjudication
41A.1 Clause 41A applies where, pursuant to article 5, either Party refers any dispute or difference arising under this Contract to adjudication.
41A.2 The Adjudicator to decide the dispute or difference shall be either an individual agreed by the Parties or, on the application of either Party, an individual to be nominated as the Adjudicator by the person named in the Appendix (‘the nominator’). Provided that
41A .2 .1 no Adjudicator shall be agreed or nominated under clause 41A.2 or clause 41A.3 who will not execute the Standard Agreement for the appointment of an Adjudicator issued by the JCT (the ‘JCT Adjudication Agreement’) with the Parties, and
41A .2 .2 where either Party has given notice of his intention to refer a dispute or difference to adjudication then
- any agreement by the Parties on the appointment of an adjudicator must be reached with the object of securing the appointment of, and the referral of the dispute or difference to, the Adjudicator within 7 days of the date of the notice of intention to refer (see clause 41A.4.1);
- any application to the nominator must be made with the object of securing the appointment of, and the referral of the dispute or difference to, the Adjudicator within 7 days of the date of the notice of intention to refer.
Upon agreement by the Parties on the appointment of the Adjudicator or upon receipt by the Parties from the nominator of the name of the nominated Adjudicator the Parties shall thereupon execute with the Adjudicator the JCT Adjudication Agreement.
41A.3 If the Adjudicator dies or becomes ill or is unavailable for some other cause and is thus unable to adjudicate on a dispute or difference referred to him, then either Parties may agree upon an individual to replace the Adjudicator or either Party may apply to the nominator for the nomination of an adjudicator to adjudicator that dispute or difference; and the Parties shall execute the JCT Adjudication Agreement with the agreed or nominated Adjudicator.
41A.4 .1 When pursuant to article 5 a Party requires a dispute or difference to be referred to adjudication then that Party shall give notice to the other Party of his intention to refer the dispute or difference, briefly identified in the notice, to adjudication. If an Adjudicator is agreed or appointed within 7 days of the notice then the Party giving the notice shall refer the dispute or difference to the Adjudicator (‘the referral’) within 7 days of the notice. If an Adjudicator is not agreed or appointed within 7 days of the notice the referral shall be made immediately on such agreement or appointment. The said Party shall include with that referral particulars of the dispute or difference together with a summary of the contentions on which he relies, a statement of the relief or remedy summary of the contentions on which he relies, a statement on the relief or remedy which is sought and any material he wishes the Adjudicator to consider. The referral and its accompanying documentation shall be copied simultaneously to the other Party.
41A.4 .2 The referral by a Party with its accompanying documentation to the Adjudicator and the copies thereof to be provided to the other Party shall be given by actual delivery or by fax or by special delivery or recorded delivery. If given by fax then, for record purposes, the referral and its accompanying documentation must forthwith be sent by first class post or given by actual delivery. If sent by special delivery or recorded delivery the referral and its accompanying documentation shall, subject to proof to the contrary, be deemed to have been received 48 hours after the date of posting subject to the exclusion of Sundays and any Public Holiday.
41A.5 .1 The Adjudicator shall immediately upon receipt of the referral and its accompanying documentation confirm the date of that receipt to the Parties.
41A.5 .2 The Party not making the referral may, by the same means stated in clause 41A.4.2, send to the Adjudicator within 7 days of the date of the referral, with a copy to the other Party, a written statement of the contentions on which he relies and any material he wishes the Adjudicator to consider.
41A.5 .3 The Adjudicator shall within 28 days of the referral under clause 41A.4.1 and acting as an Adjudicator for the purposes of S.108 of the Housing Grants, Construction and Regeneration Act 1996 and not as an expert or an arbitrator reach his decision and forthwith send that decision in writing to the Parties. Provided that the Party who has made the referral may consent to allowing the Adjudicator to extend the period of 28 days by up to 14 days; and that by agreement between the Parties after the referral has been made a longer period than 28 days may be notified jointly by the Parties to the Adjudicator within which to reach his decision.
41A.5 .4 The Adjudicator shall not be obliged to give reasons for his decision.
41A.5 .5 In reaching his decision the Adjudicator shall act impartially and set his own procedure; and at his absolute discretion may take the initiative in ascertaining the facts and the law as he considers necessary in respect of the referral which may include the following:
.5 .1 using his own knowledge and/or experience;
.5 .2 opening up, reviewing and revising any certificate, opinion, decision, requirement or notice issued, given or made under this Contract as if no such certificate, opinion, decision, requirement or notice had been issued, given or made;
.5 .3 requiring from the Parties information than that contained in the notice of referral and its accompanying documentation or in any written statement provided by the Parties including the results of any tests that have been made or of any opening up;
.5 .4 requiring the Parties to carry out tests or additional tests or to open up work or further open up work;
.5 .5 visiting the site of the Works or any workshop where work is being or has been prepared for this Contract;
.5 .6 obtaining such information as he considers necessary from any employee or representative of the Parties provided that before obtaining information from an employee of a Party he has given prior notice to that Party;
.5 .7 obtaining from others such information and advice as he considers necessary on technical and on legal matters subject to giving prior notice to the Parties together with a statement or estimate of the cost involved;
.5 .8 having regard to any term of this Contract relating to the payment of interest, deciding the circumstances in which or the period for which a simple rate of interest shall be paid.
41A.5 .6 Any failure by either Party to enter into the JCT Adjudication Agreement or to comply with any requirement of the Adjudicator under clause 41A.5.5 or with any provision in or requirement under clause 41A shall not invalidate the decision of the Adjudicator.
41A.5 .7 The Parties shall meet their own costs of the adjudication except that the Adjudicator may direct as to who should pay the cost of any test or opening up if required pursuant to clause 41A.5.5.4.
41A.6 .1 The Adjudicator in his decision shall state how payment of his fee and reasonable expenses is to be apportioned as between the Parties. In default of such statement the Parties shall bear the cost of the Adjudicator’s fees and reasonable expenses in equal proportions.
41A.6 .2 The Parties shall be jointly and severally liable to the Adjudicator for his fee and for all expenses reasonably incurred by the Adjudicator pursuant to the adjudication.
41A.7 .1 The decision of the Adjudicator shall be binding on the Parties until the dispute or difference is finally determined by arbitration or by legal proceedings or by an agreement in writing between the Parties made after the decision of the Adjudicator has been given.
41A.7 .2 The Parties shall, without prejudice to their other rights under this Contract, comply with the decision of the Adjudicator; and the Employer and the Contractor shall ensure that the decision of the Adjudicator is given effect.
41A.7 .3 If either Party does not comply with the decision of the Adjudicator the other Party shall be entitled to take legal proceedings to secure such compliance pending any final determination of the referred dispute or difference pursuant to clause 41A.7.1.
41A.8 The Adjudicator shall not be liable for anything done or omitted in the discharge or purported discharge of his functions as Adjudicator unless the act or omission is in bad faith and this protection from liability shall similarly extend to any employee or agent of the Adjudicator.