BUSINESS & PROPERTY COURTS IN BRISTOL
TECHNOLOGY & CONSTRUCTION COURT (QBD)
2 Redcliff Street Bristol BS1 6GR |
||
B e f o r e :
(Sitting as a Judge of the High Court)
____________________
D R JONES YEOVIL LIMITED |
Claimant |
|
- and - |
||
DRAYTON BEAUMONT SERVICES LIMITED |
Defendant |
____________________
Peter Land (instructed by Beswicks Legal) for the Defendant
Hearing date: 11 June 2021
____________________
Crown Copyright ©
Covid-19 Protocol: This judgment was handed down by the judge remotely by circulation to the parties' representatives by email and release to BAILII. The date and time for hand-down is deemed to be 10.00 on 19 July 2021.
HHJ Russen QC:
INTRODUCTION
(a) to allege that DBS is responsible for any design defects in the fire dampers raised by Badby (paragraph 71D(1)) ("the Damper Design Claim") and
(b) to allege that DBS is responsible for any lack of fire-stopping to the pipework raised by Badby and/or Elysium (paragraph 71D(2)) ("the Pipework Fire-Stopping Claim").
"37. That is some evidence to indicate that there may (I emphasise may) be cause for thinking that the claimant's claim in respect of dampers is not to be reduced, as the gist of Mr Beaumont's communications with Mr Jones might indicate, but, nay, enhanced if in fact the defects are greater than initially perceived to be.
38. Whether what was done in November/December ameliorates the claim or enhances it brings me back to the fundamental point that whichever it is to be, or a combination of the two, Mr Doherty has not had an opportunity to investigate further. I am told in the evidence and have no difficulty accepting that in circumstances where Mr Hewitt will not complete his own investigations until 8 March 2019, and it would then take Mr Doherty a further five days on from that to update his report, that all of that leads to the impossible scenario of expert evidence being prepared almost on the eve of the trial commencing two weeks Monday. It is a totally unworkable position.
39. As to the risk that the claim by the claimant against the present defendant has increased, counsel have helpfully addressed me on the prospect that the circumstances and effect of what was done in November/December are such that the present owner of the property might have further cause for complaint against the claimant if indeed things are worse in relation to the alleged defects in these two items than were previously perceived to be. I have been shown a letter from DAC Beachcroft on behalf of the owner which in effect reserves the owner's position as against the present claimant for responsibility for all and any actual defects that may exist in relation to the works.
40. Miss Adams says on any view that cannot be a matter properly raised within these proceedings. She makes the point that whilst the present defendant was engaged as a subcontractor where the main contract was entered into in or around 2010, there was a further contract entered into by the claimant with the then owner in 2015 for completion of the works. So, how, Ms Adams rhetorically asks, can the present defendant, whose only contractual nexus with the property was under the first contract by way of a subcontractor [sic], can it be responsible for anything done under the later contract?
41. All of those matters, if they come about by prompting of the present owner, may well be worthy of further detailed argument, but the very essence of the submission by the defendant brings me back to the point that it is the oddity, on that analysis, of the former subcontractor returning to the property some six/seven years on from its last presence there when it left the site, to carry out works for the three reasons identified by Mr Beaumont in his witness statement. That situation leads to the predicament that I do have to address, here and now. The fact is, whether or not there are intermediate contracts that disrupted the present defendant's status as a subcontractor, it has gone back to undertake works on the very works that are the subject of the present claim. Although I form no final view upon the matter should it ever need to be addressed, there must be a strong argument that if the present claimant is exposed to wider claims by the owner of the property, then those claims are properly raised in the present proceedings."
LEGAL PRINCIPLES ON AMENDMENT
Limitation – the Conventional Approach
CPR 17.4(2)
"….. avoid placing a defendant in the position where if the amendment is allowed he will be obliged after expiration of the limitation period to investigate facts and obtain evidence of matters which are completely outside the ambit of, and unrelated to those facts which he could reasonably be assumed to have investigated for the purpose of defending the unamended claim."
The "Mastercard" Basis of Amendment
"20. [Counsel for D] accepted that an amendment whose effect was limited to a six year limitation period could be brought by amendment of the Particulars of Claim. In my judgment that is a sensible approach; it would be a quite unnecessary waste of costs for a separate claim to have to be brought and then for that claim to be consolidated with the present claim.
21. Accordingly, I will give leave for an amendment to plead the new claim on the basis that its effect is not to achieve a relation back to the start of the limitation period of the pre-existing claim but merely relates back to six years from today's date, 8 October 2013."
Discretion
THE PROPOSED AMENDMENTS
The Damper Design Claim
(a) changed the manufacturer, model and fixing method of the fire dampers and as a result assumed wholesale responsibility for the design of the fire dampers including the fact they were activated only by fire and not smoke. This was said to have been done without the approval of DRJ or Houghton Greenlees & Associates ("HGA"), the M&E engineers who had designed the M&E works required under the main contract;
(b) had an obligation to design and specify the dampers with skill and care and/or to carry out a design that complied with certain regulations and standards; and
(c) had a duty to warn DRJ if the design or specification for the dampers did not accord with those regulations and standards.
The Pipework Fire-Stopping Claim
DECISION
Limitation
The incorporation of DRJ's Conditions 3.0
"Where the Principal Contract is executed as a deed, the Sub-Contract will be deemed for the purpose only of the calculation of any period of limitation prescribed by law, to be executed as a deed and the Sub-Contractor will not assert in any action or arbitration any shorter period of limitation than is prescribed for contracts executed as a deed."
"… where there is a preliminary contract in words which is afterwards reduced into writing, or where there is a preliminary contract in writing which is afterwards reduced into a deed, the rights of the parties are governed in the first case entirely by the writing, and in the second case entirely by the deed; and if there be any difference between the words and the written document in the first case, or between the written agreement and the deed in the other case, the rights of the parties are entirely governed by the superior document and by the governing part of that document."
"The signature is, as it were, the party's seal upon the contract; and that remains the case even where, as here, the contract has already been made (in the fixture telexes). Prima facie a person does not sign a document without intending to be bound under it, or, to put that thought in the objective rather than subjective form, without properly being regarded as intending to be bound under it."
"Normally, in the absence of any misrepresentation, the signature of a contractual document must operate as an incorporation and acceptance of all its terms."
CPR 17.4(2)
Discretion
The Damper Design Claim
The Pipework Fire-Stopping Claim
"where waste pipework passes through a fire barrier, including floor slabs, the pipework shall be complete with an intumescent crush collar rated to the same specification as the barrier itself".
CONCLUSIONS
i) refuse DRJ permission to amend to bring the Damper Design Claim advanced in paragraphs 71B, 71C and 71D(1) of the RAPOC. However, although it is not clear to me that there are any such matters, I wish to clarify that I am refusing DRJ permission to advance the claim based upon the alleged design duty and the alleged duty to warn; and I do not intend to prevent DRJ from relying upon any matter mentioned in those paragraphs which might be relied upon in support of the existing claim in respect of allegedly incomplete or defective work which is summarised in paragraph 66 of the RAPOC; and
ii) grant permission to DRJ to bring the Pipework Fire-Stopping Claim advanced in paragraphs 71B, 71C and 71D(2) of the RAPOC.