QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
PANTELLI ASSOCIATES LIMITED |
Claimant |
|
- and - |
||
CORPORATE CITY DEVELOPMENTS NUMBER TWO LIMITED |
Defendant |
____________________
Mr Crispin Winser (instructed by GH Canfield LLP) for the Defendant
Hearing date: 26 November 2010
____________________
Crown Copyright ©
Mr Justice Coulson :
(1) Introduction
(2) Background
"Unless by 4pm on 12 November 2010 the Defendant do make an application to amend its Defence and Counterclaim properly explaining the nature of its Defence and Counterclaim and providing proper particulars of any alleged defence or cause of action, paragraphs 6, 7, 9(e), 10(e), 14-17 and 20-22 (including the prayer) of the Defendant's Defence and Counterclaim shall be struck out."
The paragraphs specifically identified in the order were those setting out the case, such as it was, as to professional negligence, causation and loss.
(3) The Proposed Amendments
"Performance
16. Paragraph 10 is denied. It is averred that the Claimant failed to perform to the contractual standard and is in breach of the QS Contracts and the PM Contracts.
PARTICULARS OF BREACH OF THE QS CONTRACTS
16.1 Failing adequately or at all to identify or determine the Defendant's initial requirements and subsequently develop the full brief.
16.2 Failing adequately or at all to advise on feasibility and procurement.
16.3 Failing adequately or at all to establish the Defendant's order of priorities for quality, time and cost.
16.4 Failing to prepare adequate and/or accurate initial budget estimates.
16.5 Failing to prepare or develop a proper and/or accurate preliminary cost plan.
…
PARTICULARS OF BREACH OF THE PM CONTRACTS
16.13 Failing to select or appoint appropriate consultants.
16.14 Failing adequately or at all to co-ordinate and review the progress of design work.
16.15 Failing adequately or at all to facilitate communications between the Defendant and the Consultants.
…
36. As a result of the Claimant's breaches of the QS Contracts and the PM Contracts, the Defendant has suffered loss and damage.
PARTICULARS OF LOSS AND DAMAGE
36.1 The Defendant has incurred additional and/or wasted costs of approximately £300,000. These include the costs of engaging additional consultants including structural engineers, CMP consultants and transport consultants.
36.2 As a result of the delay to the projects, the Defendant has incurred additional costs servicing loans for an extended period."
(4) Proper Particulars
(5) Expert Input
(6) Effect
(7) Conclusions