ON APPEAL FROM THE HIGH COURT OF JUSTICE, QUEEN'S BENCH DIVISION
HIS HONOUR JUDGE THORNTON QC
HQ09X002074
HQ09X002077
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE JACKSON
and
LORD JUSTICE MCFARLANE
____________________
(1) MR BALA CHANDRA (2) MRS MARIA CHANDRA |
Claimants/ Respondents |
|
- and - |
||
(1) BROOKE NORTH (A FIRM) (2) BROOKE NORTH LLP |
Defendants/ Appellants |
|
AND BETWEEN: |
||
BPC HOTELS LIMITED |
Claimant/ Respondent |
|
- and - |
||
(1) BROOKE NORTH (A FIRM) (2) BROOKE NORTH LLP |
Defendants/ Appellants |
____________________
Mr and Mrs Chandra appeared in person. Mr Chandra appeared on behalf of BPC Hotels Ltd.
Hearing date: Thursday 24th October 2013
____________________
Crown Copyright ©
Lord Justice Jackson:
Part 1. Introduction,
Part 2. The facts,
Part 3. The present proceedings,
Part 4. The appeal to the Court of Appeal,
Part 5. Was the judge right to refuse to set aside the claimants' amendments in reliance upon section 14 A of the Limitation Act 1980?
Part 6. Could the amendments be justified on the basis that they fell within the scope of the original claim forms?
Part 7. The remaining issues
Part 8. Conclusion.
"Special time limit for negligence actions where facts relevant to cause of action are not known at date of accrual.
(1) This section applies to any action for damages for negligence, other than one to which section 11 of this Act applies, where the starting date for reckoning the period of limitation under subsection (4)(b) below falls after the date on which the cause of action accrued.
(2) Section 2 of this Act shall not apply to an action to which this section applies.
(3) An action to which this section applies shall not be brought after the expiration of the period applicable in accordance with subsection (4) below.
(4) That period is either —
(a) six years from the date on which the cause of action accrued; or
(b) three years from the starting date as defined by subsection (5) below, if that period expires later than the period mentioned in paragraph (a) above.
(5) For the purposes of this section, the starting date for reckoning the period of limitation under subsection (4)(b) above is the earliest date on which the plaintiff or any person in whom the cause of action was vested before him first had both the knowledge required for bringing an action for damages in respect of the relevant damage and a right to bring such an action.
(6) In subsection (5) above "the knowledge required for bringing an action for damages in respect of the relevant damage" means knowledge both—
(a) of the material facts about the damage in respect of which damages are claimed; and
(b) of the other facts relevant to the current action mentioned in subsection (8) below.
(7) For the purposes of subsection (6)(a) above, the material facts about the damage are such facts about the damage as would lead a reasonable person who had suffered such damage to consider it sufficiently serious to justify his instituting proceedings for damages against a defendant who did not dispute liability and was able to satisfy a judgment.
(8) The other facts referred to in subsection (6)(b) above are—
(a) that the damage was attributable in whole or in part to the act or omission which is alleged to constitute negligence; and
(b) the identity of the defendant; and
(c) if it is alleged that the act or omission was that of a person other than the defendant, the identity of that person and the additional facts supporting the bringing of an action against the defendant.
(9) Knowledge that any acts or omissions did or did not, as a matter of law, involve negligence is irrelevant for the purposes of subsection (5) above.
(10) For the purposes of this section a person's knowledge includes knowledge which he might reasonably have been expected to acquire —
(a) from facts observable or ascertainable by him; or
(b) from facts ascertainable by him with the help of appropriate expert advice which it is reasonable for him to seek;
but a person shall not be taken by virtue of this subsection to have knowledge of a fact ascertainable only with the help of expert advice so long as he has taken all reasonable steps to obtain (and, where appropriate, to act on) that advice."
"New claims in pending actions: rules of court.
(1) For the purposes of this Act, any new claim made in the course of any action shall be deemed to be a separate action and to have been commenced—
(a) in the case of a new claim made in or by way of third party proceedings, on the date on which those proceedings were commenced; and
(b) in the case of any other new claim, on the same date as the original action.
(2) In this section a new claim means any claim by way of set-off or counterclaim, and any claim involving either —
(a) the addition or substitution of a new cause of action; or
(b) the addition or substitution of a new party;
…
(3) Except as provided by section 33 of this Act or by rules of court, neither the High Court nor any county court shall allow a new claim within subsection (1)(b) above, other than an original set-off or counterclaim, to be made in the course of any action after the expiry of any time limit under this Act which would affect a new action to enforce that claim.
…
(4) Rules of court may provide for allowing a new claim to which subsection (3) above applies to be made as there mentioned, but only if the conditions specified in subsection (5) below are satisfied, and subject to any further restrictions the rules may impose.
(5) The conditions referred to in subsection (4) above are the following —
(a) in the case of a claim involving a new cause of action, if the new cause of action arises out of the same facts or substantially the same facts as are already in issue on any claim previously made in the original action; and
(b) in the case of a claim involving a new party, if the addition or substitution of the new party is necessary for the determination of the original action."
"(2) Where an application to the Court for leave to make the amendment mentioned in paragraph (3), (4) or (5) is made after any relevant period of limitation current at the date of issue of the writ has expired, the Court may nevertheless grant such leave in the circumstances mentioned in that paragraph if it thinks it just to do so.
…
(5) An amendment may be allowed under paragraph (2) notwithstanding that the effect of the amendment will be to add or substitute a new cause of action if the new cause of action arises out of the same facts or substantially the same facts as a cause of action in respect of which relief has already been claimed in the action by the party applying for leave to make the amendment."
"Amendments to statements of case after the end of a relevant limitation period
(1) This rule applies where –
(a) a party applies to amend his statement of case in one of the ways mentioned in this rule; and
(b) a period of limitation has expired under –
(i) the Limitation Act 19801;
…
(2) The court may allow an amendment whose effect will be to add or substitute a new claim, but only if the new claim arises out of the same facts or substantially the same facts as a claim in respect of which the party applying for permission has already claimed a remedy in the proceedings."
"Application to set aside or vary order made without notice
(1) A person who was not served with a copy of the application notice before an order was made under rule 23.9, may apply to have the order set aside or varied.
(2) An application under this rule must be made within 7 days after the date on which the order was served on the person making the application."
"9.1 Subject to Clause 8.3, the Beneficiary [i.e. RBS] shall give notice to the Main Contractor within that period of not less than 21 days specified in the notice under Clause 8.1:
9.1.1 requiring it to continue its obligations under the Main Contract in relation to the Project; and
9.1.2 acknowledging that the Beneficiary is assuming all the existing and future obligations of the Employer under the Main Contract;
then upon determination of the Main Contractor's employment under the Main Contract the provisions of Clause 9.2 shall apply.
9.2 Subject to Clause 8.3, and in the event that a notice is served in accordance with Clause 9.1, notwithstanding determination of the Main Contractor's employment as specified in Clause 9.1 the Main Contract shall be deemed (as between the Main Contractor and the Beneficiary or the Beneficiary's nominee) to continue in full force and effect as if the right of determination on the part of the Main Contractor had not arisen and in all respects as if the Main Contract had been made between the Main Contractor and the Beneficiary to the exclusion of the Employer whereby:
(a) the Beneficiary assumes all the existing and future obligations of the Employer under the Main Contract; and
(b) the Main Contractor acknowledges all of is obligations under the Main Contract in favour of the Beneficiary."
"Many thanks, and in the circumstances the orders will not be made without a hearing. For that purpose, the claimants must complete and submit a request for a private-room appointment."
"a. The claims and causes of action set out in the amended Claim Forms and the amended and re-amended Particulars of Claim in the Actions were brought within 3 years of the starting date as defined in section 14A of the Limitation Act 1980.
b. Both Defendants were joined into the Actions upon their commencement on 18 May 2009, both Defendants have been parties ever since and both Defendants remain parties to the Actions at the date of this Order."
The judge ordered that the action be transferred to the Technology and Construction court.
i) Master Eyre granted permission for the claimants' first round of amendments to the particulars of claim. Master Eyre did not subsequently revoke his order granting such permission.
ii) The claimants' new claims were being brought outside the primary limitation period. They did not arise out of similar facts. Nevertheless the claimants were saved by provisions of section 14A of the 1980 Act. The claimants only had sufficient knowledge to start time running under section 14A (5) on or soon after 28th January 2010. This was when they learnt that BN's alleged negligence had exposed them to huge and unquantifiable liabilities. The claimants did not know this until they had read and digested the judgment in the Chancery action: see paragraph 79 of the judge's judgment.
iii) The original claim form in the BPC action was broad enough to encompass the new claims pleaded. It was arguable whether or not the original claim form in the Chandra action was broad enough to encompass the new claims brought. The proposed amendments to that claim form were appropriate.
iv) Accordingly Master Eyre's order allowing amendments would not be set aside. The proposed re-amendments would be allowed.
v) Alternatively, if the foregoing analysis is wrong, the judge had a residual discretion to dismiss the applications to set aside Master Eyre's order of 15th November 2011. He would exercise that discretion in favour of the claimants.
vi) The defendants' case on limitation having failed, the court would grant declarations to that effect.
i) Master Eyre had revoked his order of 15th November 2011. Therefore the primary issue before Judge Thornton was the claimants' application to amend, not the defendants' application to set aside.
ii) The judge wrongly treated the hearing as the trial of a preliminary issue on limitation rather than an application to make or set aside amendments to pleadings.
iii) Applying the correct approach the judge ought to have held that the claimants' amendments arguably raised new causes of action outside the limitation period. Therefore those amendments could not be allowed.
iv) The claim form in the Chandra action did not encompass the new claims raised by amendment. The BPC claim form was broader. However, BPC narrowed the scope of their original claims by the particulars of claim which they served in September 2009. Therefore the claimants cannot rely upon their claim forms in order to justify the amendments to the particulars of claim.
v) The re-amendments should not have been allowed because (a) those concerning BN were statute barred; (b) those concerning BNLLP raised no cause of action against that party.
vi) In those circumstances the judge had no residual discretion to allow the amendments and he should not have done so.
"For my part I am doubtful whether there is any sufficient legal basis for holding in favour of the simple doctrine of 'abandonment' which was referred to in the Lewis case. Cargill's case, as I think, was different. That was one, properly looked at, of election between two inconsistent remedies, and of course when one looks at it in that way, there was an abandonment of that which one has not elected. Be that as it may, I would wish to avoid these subtleties in this sort of context. When a plaintiff seeks leave to serve a re-amended statement of claim, and one has to consider and contrast it with the earlier amended statement of claim for the purposes, for instance, of s.35 of the Limitation Act 1980, one realistically looks at the two statements of claim. One does not look truly to the endorsement on the writ – in which the plaintiff by Order 6,r2(1)(a) need not 'plead' any cause of action at all (if 'plead' is the correct word)."
"Contents of the claim form
(1) The claim form must –
(a) contain a concise statement of the nature of the claim;
(b) specify the remedy which the claimant seeks;
…"
Lord Justice McFarlane:
Lord Justice Laws: