BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
KING'S BENCH DIVISION
COMMERCIAL COURT
Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
(1) PEREGRINE AVIATION BRAVO LIMITED (a company incorporated in Ireland) (2) AERCAP IRELAND LIMITED (a company incorporated in Ireland) (3) AERCAP IRELAND CAPITAL DESIGNATED ACTIVITY COMPANY (a company incorporated in Ireland) |
Claimants |
|
- and - |
||
(1) LAUDAMOTION GMBH (a company incorporated in Austria) (2) RYANAIR HOLDINGS PLC (a company incorporated in Ireland) |
Defendants |
____________________
John Taylor KC and Giles Robertson (instructed by Cleary Gottlieb, Steen & Hamilton LLP) for the Defendants
Hearing dates: 28 April, 3-5 May, 9-12 May, 16-18 May and 25 and 29 July 2022
Draft judgment circulated to parties: 28 December 2022
Further written submissions received: 9 January 2022
____________________
Crown Copyright ©
Mr Justice Henshaw:
(A) INTRODUCTION
i) Correspondence sent by Laudamotion in March and April 2020 gave rise to Events of Default under each of the aircraft leases, entitled Peregrine and AIL to terminate them and recover their losses.
ii) In addition, Peregrine validly tendered MSN 3361 for delivery on 7 May 2020 but Laudamotion refused to take delivery.
iii) Laudamotion did not "demonstrate" the existence of any "Material Deviations" under the lease for MSN 3361. Laudamotion was therefore obliged to take delivery of that aircraft.
iv) Laudamotion's failure to take delivery amounted to a further Event of Default, entitling Peregrine validly to terminate the lease for MSN 3361, which it did on 15 May 2020.
v) That triggered cross-defaults in respect of the other three leases (in addition to the Events of Default arising from Laudamotion's letters of 18 March 2020 and 20 April 2020), by reference to which Peregrine and AIL validly terminated those leases too on 15 May 2020.
vi) Peregrine and AIL are entitled to be indemnified in respect of the rental stream they have lost and the other expenses they have incurred. The net lost rental stream is the rent that would have been received from Laudamotion, less what was received from Flynas (the previous lessor) after the relevant Final Delivery Dates for the four aircraft, less what has been received from SmartLynx (to whom the Claimants leased the aircraft after terminating the Laudamotion leases), less what is to be received from SmartLynx over the remainder of what would have been the term of the leases to Laudamotion.
vii) Ryanair is liable along with Laudamotion because of the guarantees it gave in 2018 and 2019.
(B) PRINCIPAL ISSUES
i) whether Peregrine and AIL were entitled to terminate the 2019 leases pursuant to Article 24.2(n) of the leases (for threats to suspend payment of debts), and (if so) to bring claims against Laudamotion and Ryanair on that basis;
ii) whether Laudamotion was obliged to take delivery of MSN 3361 on 7 May 2020 and wrongfully failed to do so (thereby entitling the Claimants to terminate the leases);
iii) (if relevant) whether the Claimants would, but for the termination, have delivered the other three 2019 aircraft by their respective Final Delivery Dates;
iv) (if relevant) how much the Claimants are entitled to recover from Laudamotion; and
v) (if relevant) whether Ryanair is liable as guarantor in respect of the Claimants' claims under all four of the 2019 leases or only the lease relating to MSN 3361.
(C) WITNESSES
(D) KEY TERMS OF THE 2019 LEASES
(1) Article 3: place and date of delivery
"LESSOR will deliver the Aircraft to LESSEE at the maintenance facility … where the Aircraft is redelivered by Previous Lessee or such other place as may be agreed in writing between the parties (the 'Delivery Location'). …"
The reference to "Previous Lessee" is a drafting mistake for "Prior Lessee", and refers to Flynas.
"As of the date of this Lease, delivery of the Aircraft from Prior Lessee to LESSOR and LESSOR to LESSEE is scheduled to occur during March 2020. LESSOR will notify LESSEE from time to time and in a timely manner of the exact date on which LESSOR expects Delivery to take place (and LESSOR agrees to consult with LESSEE prior to making such a determination as to such date and shall provide LESSEE with reasonable notice in respect of such date), (the 'Scheduled Delivery Date')."
"Without prejudice to LESSEE's right to terminate the Lease under Article 3.6 and to the return of any Base Rent following any such termination, LESSOR and LESSEE expressly acknowledge that Delivery is subject to and conditioned upon redelivery of the Aircraft by Prior Lessee in accordance with the terms of the Prior Lessee Lease Agreement."
"Promptly after LESSOR becomes aware that a delay will cause Delivery to be delayed beyond the Final Delivery Date, LESSOR will notify LESSEE. By written notice given to the other party within 10 Business Days after LESSEE's receipt of such LESSOR notice, either party may terminate this Lease and this Lease will terminate on the date of receipt of such notice. In the event of such termination, neither party will have any liability to the other party except that LESSOR will pay to LESSEE an amount equal to the amount of any prepaid Base Rent. If neither party gives notice of termination within such 10 Business Days, both parties lose all right to terminate under this Article 3.6 unless otherwise agreed in writing by the parties. Without prejudice to the foregoing, LESSOR and LESSEE agree to co-operate with each other to ensure that, to the extent reasonably possible, any such delay is minimized."
(2) Articles 6 and 7: delivery and acceptance of aircraft
"If LESSEE is able to demonstrate that at Delivery there are deviations from the condition set forth in Exhibit B which are material or affect the airworthiness of the Aircraft ('Material Deviations'), LESSEE will not be obligated to accept the Aircraft unless LESSOR corrects such Material Deviations at its own cost. In the event that any Material Deviations have not been corrected by the Final Delivery Date, either party may terminate this Lease within 10 Business Days of the Final Delivery Date and in the event of such termination, neither party will have any further liability to the other party except that LESSOR will pay to LESSEE an amount equal to the amount of any prepaid Base Rent. If neither party gives notice of termination within such 10 Business Days, both parties lose all right to terminate under this Article 6.2 unless otherwise agreed in writing by the parties. Without prejudice to the foregoing, LESSOR and LESSEE agree to co-operate with each other to ensure that, to the extent reasonably possible, any such delay is minimized.
If LESSEE is able to demonstrate that at Delivery there are deviations from the condition set forth in Exhibit B and such deviations do not affect the airworthiness of the Aircraft or such deviations are not material, then (a) LESSEE will be obligated to accept the Aircraft in its "AS IS" condition with such deviations, and subject to each and every disclaimer and waiver set forth in Article 8, and (b) LESSOR and LESSEE will at Delivery (by express statement by LESSOR on the Acceptance Certificate and not otherwise) mutually agree an appropriate amount of compensation payable to LESSEE for the cost of rectifying each such deviation or adjust the return conditions of the Aircraft set forth in Article 22 accordingly." (paragraph break interpolated)
"7.4.8 Delivery Conditions: the Aircraft conforms to the conditions set forth in Exhibit B or otherwise conforms to such condition whereby LESSEE is obligated, pursuant to Article 6.2, to accept delivery of the Aircraft."
Though this does not on its face require production of a document, it should be noted that the "Aircraft" is defined in § 2.1 as having the following meaning (except where the context otherwise requires):
""Aircraft" may also mean the Airframe, any Engine, the APU, any Part, the Aircraft Documentation or any part thereof individually. For example, in the context of return to LESSOR the term "Aircraft" means the Airframe, Engines, APU, Parts and Aircraft Documentation collectively, yet in the context of LESSEE not creating any Security Interests other than Permitted Liens on the Aircraft, the term "Aircraft" means any of the Airframe, any Engine, the APU, any Part or the Aircraft Documentation individually."
"Aircraft Documentation" is defined as meaning (except where the context otherwise requires):
"all (a) log books, Aircraft records, manuals and other documents provided to LESSEE in connection with the Aircraft either at or prior to Delivery or during the Lease Term, (b) documents listed in the Acceptance Certificate and Exhibit N and (c) any other documents required to be maintained during the Lease Term and until the Termination Date by the Aviation Authority, the Maintenance Program or this Lease."
(3) Exhibit B: aircraft condition at delivery
"For a period commencing at least 10 Business Days prior to the Scheduled Delivery Date and continuing until the date on which the Aircraft is delivered to LESSEE, LESSOR will provide for the review of LESSEE and/or its representative all of the Aircraft records and historical documents described in Exhibit N. The Aircraft records and historical documents may have been maintained in an Electronic Records Format, in which case such Aircraft records and historical documents will be provided to LESSEE in CD or other electronic format at the commencement of such period. Any Aircraft records and historical documents not maintained in an Electronic Records Format will be provided for the review of LESSEE and/or its representative in one central room at the Delivery Location at the commencement of such period."
It appears to be common ground that the process of records review is usually, and was in this case, commenced far earlier than 10 business days before the projected delivery date.
"(a) On or before the Delivery Date, LESSOR will provide LESSEE a valid export certificate of airworthiness with respect to the Aircraft.
(b) At LESSEE's request, LESSOR at its cost will demonstrate that the Aircraft meets the requirements for issuance of an EASA Certificate of Airworthiness for transport category aircraft issued by an EASA member country by delivering to LESSEE at LESSOR's option either a Certificate of Airworthiness issued by an EASA member country (if the Aircraft is already or is to be registered in an EASA member country) or a letter or other document signed by an aviation authority of an EASA member country or another Person acceptable to LESSEE stating that such Person has inspected the Aircraft and Aircraft Documentation (including records and manuals) and has found that the Aircraft meets the requirements for issuance of a Certificate of Airworthiness for transport category aircraft issued by an EASA member country in accordance with EASA Part 21 and, in addition, meets the operating requirements of AIR OPS Part-CAT.IDE and Eurocontrol with no restrictions imposed."
"Delivery Date" is defined as "the date on which Delivery takes place" (except where the context otherwise requires).
"(b) Aircraft Documentation (including records and manuals) will have been maintained in English and in an up to date status, and may have been maintained in an Electronic Records Format, in accordance with the rules and regulations of the Civil Aviation Authority of the Cayman Islands and in a form necessary in order to meet the requirements of this Exhibit B. The records and historical documents set forth in Exhibit N will be in English."
(c) All hard time and life limited Parts which are installed on the Aircraft (other than Parts installed by Manufacturer during the manufacture of the Aircraft) will have an FAA Form 8130-3 or EASA Form 1 evidencing the airworthiness of such Part at the time of installation on the Aircraft. In the case of life limited Parts, the documentation will also state the total Flight Hours, Cycles or calendar days, as applicable, since new. In the case of hard time Parts, the documentation will also state the time since last Overhaul or refurbishment, will have a reference to the relevant section of the Component Maintenance Manual under which the Part was overhauled or refurbished, as applicable, and will identify the FAA-approved repair agency or EASA-approved repair agency, as applicable, which performed the last Overhaul or refurbishment.
(d) All Parts (other than those referred to in the immediately preceding subparagraph) installed on the Aircraft will have EASA-acceptable or FAA- acceptable documentation.
…
(f) The Aircraft will be airworthy, conform to type design and be in a condition for safe operation, with all Aircraft equipment, components and systems operating in accordance with their intended use and within limits approved by Manufacturer, the aviation authority and the EASA.
…
(i) All repairs to the Aircraft will have been accomplished in accordance with Manufacturer's Structural Repair Manual (or EASA-approved data supported by DGAC Repair Design Approval Sheets or its EASA equivalent).
…
(m) All Modifications which must be performed prior to Delivery of the Aircraft or within six months after Delivery in order to meet the EASA requirements applicable to AIR-OPS Part-CAT.IDE and Eurocontrol operations will have been incorporated on the Aircraft at LESSOR's cost.…"
(4) Article 8: disclaimers and waivers
"8.1 "As Is, Where Is". LESSEE AGREES THAT IT IS LEASING THE AIRCRAFT AND THAT THE AIRCRAFT IS DELIVERED "AS IS, WHERE IS". LESSEE UNCONDITIONALLY ACKNOWLEDGES AND AGREES THAT NEITHER LESSOR NOR ANY OTHER RELEVANT PARTY NOR ANY OF THEIR RESPECTIVE OFFICERS, DIRECTORS, EMPLOYEES, AFFILIATES, AGENTS OR REPRESENTATIVES HAVE MADE OR WILL BE DEEMED TO HAVE MADE ANY TERM, CONDITION, REPRESENTATION, WARRANTY OR COVENANT EXPRESS OR IMPLIED (WHETHER STATUTORY OR OTHERWISE) AS TO, AND LESSEE HEREBY WAIVES ANY EXPRESS OR IMPLIED WARRANTY OR COVENANT (WHETHER STATUTORY OR OTHERWISE) AS TO (a) THE CAPACITY, AGE, AIRWORTHINESS, VALUE, QUALITY, DURABILITY, CONFORMITY TO THE PROVISIONS OF THIS LEASE AND THE OTHER OPERATIVE DOCUMENTS, DESCRIPTION, CONDITION (WHETHER OF THE AIRCRAFT, ANY ENGINE, ANY PART THEREOF OR THE AIRCRAFT DOCUMENTATION), DESIGN, WORKMANSHIP, MATERIALS, MANUFACTURE, CONSTRUCTION, OPERATION, STATE, MERCHANTABILITY, PERFORMANCE, FITNESS FOR ANY PARTICULAR USE OR PURPOSE (INCLUDING THE ABILITY TO OPERATE OR REGISTER THE AIRCRAFT OR USE THE AIRCRAFT DOCUMENTATION IN ANY OR ALL JURISDICTIONS), SUITABILITY OF THE AIRCRAFT OR ANY PART THEREOF OR THE ABSENCE OF LATENT OR OTHER DEFECTS, WHETHER OR NOT DISCOVERABLE, KNOWN OR UNKNOWN, APPARENT OR CONCEALED, EXTERIOR OR INTERIOR, (b) THE ABSENCE OF ANY INFRINGEMENT OF ANY PATENT, TRADEMARK, COPYRIGHT OR OTHER INTELLECTUAL PROPERTY RIGHTS, (c) ANY IMPLIED WARRANTY ARISING FROM COURSE OF PERFORMANCE, COURSE OF DEALING OR USAGE OF TRADE OR (d) ANY OTHER REPRESENTATION OR WARRANTY WHATSOEVER, EXPRESS OR IMPLIED, WITH RESPECT TO THE AIRCRAFT OR ANY PART THEREOF, ALL OF WHICH ARE HEREBY EXPRESSLY, UNCONDITIONALLY AND IRREVOCABLY EXCLUDED AND EXTINGUISHED."
"8.4 Conclusive Proof. DELIVERY BY LESSEE TO LESSOR OF THE ACCEPTANCE CERTIFICATE WILL BE, CONCLUSIVE PROOF AS BETWEEN LESSOR AND EACH OTHER RELEVANT PARTY, ON THE ONE HAND, AND LESSEE, ON THE OTHER HAND, THAT LESSEE'S TECHNICAL EXPERTS HAVE EXAMINED AND INVESTIGATED THE AIRCRAFT AND ENGINES AND (a) EACH IS AIRWORTHY AND IN GOOD WORKING ORDER AND REPAIR AND (b) THE AIRCRAFT AND ENGINES AND THE AIRCRAFT DOCUMENTATION ARE WITHOUT DEFECT (WHETHER OR NOT DISCOVERABLE AT DELIVERY) AND IN EVERY WAY SATISFACTORY TO LESSEE AND IN SUITABLE CONDITION FOR DELIVERY TO AND ACCEPTANCE BY LESSEE. THIS ARTICLE 8.4, AND ARTICLES 8.1, 8.2 AND 8.3 ARE WITHOUT PREJUDICE TO LESSOR'S OBLIGATION TO TAKE SUCH ACTIONS (IF ANY) AS EXPRESSLY SET FORTH IN THE LIST OF OTHER OBLIGATIONS ATTACHED TO THE ACCEPTANCE CERTIFICATE."
(5) Article 24: default by Lessee
"24.2 Events of Default. The occurrence of any of the following will constitute an Event of Default and material repudiatory breach of this Lease by LESSEE:
(a) Delivery. LESSEE fails to take delivery of the Aircraft when obligated to do so under the terms of this Lease and such failure continues for 5 Business Days; (b) Non-Payment. (i) LESSEE fails to make a payment of Basic Rent or Agreed Value within five Business Days after the same has become due or (ii) LESSEE fails to make a payment of any other amount due under this Lease or any of the other Operative Documents (including amounts expressed to be payable on demand) after the same has become due and such failure continues for seven Business Days;
…
(f) Breach. LESSEE fails to perform or observe any other covenant or obligation to be performed or observed by LESSEE under this Lease or any other Operative Document, which failure is not cured within 21 days after written notice thereof to LESSEE, provided that, if such failure cannot by its nature be cured within 21 days, LESSEE will have the reasonable number of days necessary to cure such failure (not to exceed a period of 30 days) so long as LESSEE uses diligent and all reasonable efforts to do so;
…
(k) Material Adverse Change. Subsequent to the date of execution of this Lease and measured in relation thereto, any event or series of events occurs (other than a Total Loss) or circumstances arise which has, or may reasonably be expected to have, a prejudicial effect on any Relevant Party's title and interest in and to the Aircraft or any of the rights of a Relevant Party under the Operative Documents or a material adverse effect on the business, assets or financial condition of (A) LESSEE or on the ability of LESSEE to perform all of its obligations under, or otherwise to comply with the terms of, this Lease or any other Operative Document or (B) Guarantor on its the ability to perform all of its obligations under, or otherwise to comply with the terms of the Guarantee;
…
(n) Insolvency. LESSEE or Guarantor (i) is or becomes, or is deemed for the purposes of any Law to be, insolvent or unable to pay its debts or other obligations as they fall due, or admits its inability to pay its debts or other obligations as they fall due, (ii) suspends or threatens in writing to suspend payment with respect to all or any of its debts or other payment obligations or a moratorium is declared in respect of all or any of LESSEE's or Guarantor's debts or other payment obligations or (iii) proposes, enters into or is a party to any proceeding regarding (or takes any corporate action to authorize or facilitate) any arrangement or composition with, or any assignment for the benefit of, its creditors; (o) Voluntary Bankruptcy. LESSEE or Guarantor commences a voluntary case or other proceeding seeking liquidation, reorganization, protection from creditors or other relief with respect to LESSEE or Guarantor or such party's debts under any bankruptcy, insolvency or similar Laws, or seeking the appointment of a trustee, examiner, liquidator, administrator, receiver, custodian or similar official of LESSEE or Guarantor or any material part of the business or assets of LESSEE or Guarantor, or seeking the sequestration of a material part of the business or assets of LESSEE or Guarantor, or consents to any such relief or to the appointment of or taking possession by any such official, or takes any corporate action to authorize or facilitate any of the foregoing;
(p) Involuntary Bankruptcy. An involuntary case or other proceeding is commenced against LESSEE or Guarantor seeking liquidation, reorganization, protection from creditors or other relief with respect to LESSEE or Guarantor's or such party's debts under any bankruptcy, insolvency or similar Laws, or seeking the appointment of a trustee, examiner, liquidator, administrator, receiver, custodian or similar official of LESSEE or Guarantor's or any material part of the business or assets of LESSEE or Guarantor's, or seeking the sequestration of a material part of the business or assets of LESSEE or Guarantor's, and (i) such involuntary case or other proceeding is not withdrawn or dismissed within 45 days thereafter, (ii) a decree, judgment or order for relief is entered by any court of competent jurisdiction in connection with any such involuntary case or other proceeding and such decree, judgment or order for relief is not withdrawn or dismissed within 45 days thereafter, or (iii) LESSEE or Guarantor consents to any such relief or to the appointment of or taking possession by any such official;
(q) Cross-Default.
(i) any Financial Indebtedness of LESSEE in an aggregate amount of US$2,000,000 or more (or its equivalent in other currencies) is not paid when due (subject to any applicable cure periods) or becomes due and payable prior to its stated maturity;
(ii) any final un-appealable judgment, award or order is made against LESSEE for an amount in excess of US$2,000,000 or more (or its equivalent in other currencies) that is not stayed or complied with or for which an adequate bond has not been provided as soon as practicable and in any event by the earlier of (A) the time required under such judgment, award or order and (B) 30 days from the day of such judgment, award or order;
(iii) An event of default is existing and continuing under any Other Agreement and the same is not cured within the specified cure period;
…"
i) an Event of Default in respect of all four aircraft under Article 24.2(n);
ii) an Event of Default in respect of MSN 3361 under Article 24.2(a); and
iii) an Event of Default under Article 24.2(q) in respect of each of the last three aircraft, as a result of Laudamotion's failure to accept MSN 3361. Peregrine relies on Article 24.2(q)(iii) in relation to MSN 3396. AIL relies on Article 24.2(q)(i), rather than 24.2(q)(iii), because it says it is not an Affiliate (etc.) of Peregrine, so that the lease of MSN 3361 is not an "Other Agreement" for the purposes of the two leases in respect of which AIL was the Lessor.
"24.3 LESSOR's General Rights. Upon the occurrence of any Event of Default and so long as the same shall be continuing, LESSOR may do all or any of the following at its option (in addition to such other rights and remedies which LESSOR may have by statute or otherwise):
(a) if such Event of Default occurs prior to Delivery, and by written notice to LESSEE, terminate LESSEE's right to lease the Aircraft and terminate LESSOR's obligations hereunder (but without prejudice to the indemnity obligations and any continuing obligations of LESSEE under this Lease and any other Operative Document, including the obligations set forth in Articles 15 and 16);
(b) by written notice to LESSEE, terminate the leasing of the Aircraft whereupon (as LESSEE hereby acknowledges and agrees) all rights of LESSEE to possess and operate the Aircraft will immediately cease and terminate and in which case LESSEE's obligations under this Lease will continue in full force and effect (including the obligations set forth in Articles 10.5, 15, 16 and 17); provided, however, that upon the occurrence of an Event of Default under any of Articles 24.2(n), 24.2(o) or 24.2(p), such termination will occur automatically and with immediate effect without any notice or further action from LESSOR;
…"
"(e) enter upon the premises where the Airframe, the APU or any or all Engines or any or all Parts or Aircraft Documents are (or are believed to be) located without liability and take immediate possession of and remove them or cause the Aircraft to be returned to LESSOR at the location specified in Article 22.4 (or such other location as LESSOR may require) or, by serving notice require LESSEE to return the Aircraft to LESSOR at the location specified in Article 22.4 (or such other location as LESSOR may require) and LESSEE hereby irrevocably by way of security for LESSEE's obligations under this Lease appoints LESSOR as LESSEE's attorney and agent in causing the return or in directing the pilots of LESSEE or other pilots to fly the Aircraft to an airport designated by LESSOR and LESSOR will have all the powers and authorizations necessary for taking that action, with the foregoing power of attorney being granted by LESSEE as a deed;"
…
"(i) with or without taking possession of the Aircraft, sell all or any part of the Aircraft at public or private sale, with or without advertisement, or otherwise dispose of, hold, use, operate, lease to another Person or keep idle all or any part of the Aircraft as LESSOR in its sole discretion may determine appropriate, all free and clear of any rights of LESSEE and without any duty to account to LESSEE with respect to such action or inaction or for any proceeds thereof, all in such manner and on such terms as LESSOR considers appropriate in its absolute discretion, as if LESSOR and LESSEE had never entered into this Lease;"
…
"(j) for LESSEE's account, do anything that may be necessary or advisable to cure any default and recover from LESSEE all costs and expenses (including legal fees and expenses incurred) in doing so".
"If an Event of Default has occurred and is continuing and as a result thereof, the leasing of the Aircraft has been terminated, LESSOR may take all steps necessary to deregister the Aircraft in and export the Aircraft from the State of Registration, the Habitual Base and/or any other applicable jurisdiction. LESSOR shall not invoke the Deregistration Power of Attorney unless an Event of Default shall have occurred and be continuing."
"24.6 LESSEE Liability for Damages. If an Event of Default occurs, in addition to all other remedies available under applicable Law, LESSOR and each other Indemnitee has the right to recover from LESSEE, and LESSEE will indemnify LESSOR and each other Indemnitee on LESSOR's first written demand against, any Expenses which LESSOR or any other Indemnitee may sustain or incur directly as a result, including:
(a) any losses suffered by LESSOR as a result of a delay in Delivery of the Aircraft to LESSEE, including Aircraft parking, maintenance costs and insurance costs during the period of delay;
(b) all amounts which are then due and unpaid hereunder or under any other Operative Document or which become due prior to LESSOR's recovery of possession of the Aircraft;
(c) any losses suffered by LESSOR or Owner because of an inability by LESSOR or Owner to place the Aircraft on lease with another lessee or to otherwise utilize the Aircraft on financial terms as favorable to LESSOR as the terms of this Lease and the other Operative Documents (and LESSOR will be entitled to accelerate any and all Rent which would have been due from the date of LESSOR's recovery of possession of the Aircraft through the Expiration Date);
…
(i) any additional amount(s) as may be necessary to place LESSOR in the same economic position, on an after tax basis, as LESSOR would have been in if LESSEE had properly and fully performed each of its obligations under this Lease and the other Operative Documents.
24.7 Mitigation of Damages. LESSOR will take such reasonable commercial actions insofar as and to the extent that such a corresponding defense exists under English Law to mitigate any damages or losses it may incur as a result of the occurrence of an Event of Default, provided that (a) LESSOR will not be obliged to consult with LESSEE concerning any proposed course of action or to notify LESSEE of the taking of any particular action, (b) LESSOR will not be obligated to take any step that, in its reasonable discretion, could prejudice LESSOR, and (c) this provision is without prejudice to LESSOR's rights under Article 24.6.
24.8 Waiver of Default. By written notice to LESSEE, LESSOR may at its election waive any Default or Event of Default and its consequences (with or without conditions, at LESSOR's sole discretion). The respective rights of the parties will then be as they would have been had no Default or Event of Default occurred. LESSOR's waiver of any Default or Event of Default will not constitute a waiver of any subsequent Default or Event of Default.
24.9 Present Value of Payments. In calculating LESSOR's damages hereunder, on the Termination Date all Rent and other amounts which would have been due hereunder during the Lease Term if an Event of Default had not occurred will be calculated on a present value basis using a discounting rate of the prime rate announced by LESSOR's Bank discounted to the date on which LESSOR recovers possession of the Aircraft."
(6) Maintenance and redelivery: Article 12
"12.2.4 With respect to any shop visit of an Engine during the Lease Term, LESSEE will submit to LESSOR (a) at least 30 days in advance of the scheduled induction date, the intended workscope of such shop visit and (b) prior to the actual induction date, and if such shop visit is to be performed by a third party vendor, a disclaimer of Security Interests from such vendor in a form reasonably acceptable to LESSOR. LESSEE will ensure that the tasks comprising each such workscope are in accordance with the recommendations of Engine Manufacturer and are sufficient to restore the subject Engine to a full operating interval (which will be determined in accordance with the recommendations of Engine Manufacturer). Within 10 days of receipt by LESSOR of such intended workscope, LESSOR in its reasonable discretion may elect to provide a replacement engine to LESSEE in place of the Engine and in lieu of performance of such intended shop visit on the Engine. Upon such replacement, the replacement engine will become an "Engine" under this Lease and the Engine which requires a shop visit will cease to be an "Engine" and will be returned to LESSOR (and this Lease will be amended as may be appropriate to reflect such exchange). If LESSOR requests, LESSEE will perform additional work at such shop visit at LESSOR's cost."
(7) Article 22: return of aircraft
(8) Article 25: notices
"Any notice, request or information required or permissible under this Lease will be in writing and in English. Notices will be delivered in person or sent by fax, e-mail, letter (mailed airmail, certified and return receipt requested), or by express courier addressed to the parties as set forth in Article 25.2. In the case of a fax, notice will be deemed received on the date set forth on the confirmation of receipt produced by the sender's fax machine immediately after the fax is sent. In the case of an e-mail, notice will be deemed received at the time the sender sends such e-mail, unless the sender receives an automated e-mail error message. In the case of a mailed letter, notice will be deemed received upon actual receipt. In the case of a notice sent by expedited delivery, notice will be deemed received on the date of delivery set forth in the records of the Person which accomplished the delivery. If any notice is sent by more than one of the above listed methods, notice will be deemed received on the earliest possible date in accordance with the above provisions."
(E) MAIN FACTS
(1) Parties
(2) Events from late 2018 to mid 2019
(3) Late 2019 and early 2020
(4) Early and mid March 2020
i) On 24 February 2020, AustroControl (the air navigation services provider which controls Austrian airspace) and Celairion (the Continuing Airworthiness Management Organisation ("CAMO") retained by the Claimants) had completed their inspection of MSN 3361. The findings from the inspection were addressed to the satisfaction of Celairion, to which AustroControl had delegated authority, prior to the demo flight referred to below. Laudamotion had also given its approval for a consultant from Eirtech Aviation Services ("Eirtech") to go on site in a bid to try and close out the remaining records items for the aircraft.
ii) As at 2 March 2020, documents internal to the Claimants suggested an expectation that the records review for MSN 3361 could be finalised by Laudamotion within a week.
iii) As at 4 March 2020, the parties appear to have been targeting around 20 March 2020 for the delivery of MSN 3361 to Laudamotion.
iv) Between 4 and 9 March 2020, the Claimants and the Defendants exchanged outstanding condition precedent documents in anticipation of the delivery of MSN 3361, including a parent company guarantee from Ryanair to Peregrine which was entered into on 5 March 2020.
v) On 9 March 2020, Fokker issued a Certificate of Release to Service for MSN 3361 and the demo (demonstration) flight was completed. (The evidence of the Defendants' technical expert, Mr Goatcher, was that a demo flight would usually be carried out approximately two weeks prior to delivery.) The demo flight was observed by a pilot from Laudamotion, Mr Pitschmann, who noted that no re-flight was necessary. Mr Pitschmann said in his witness statement that this was because "all of the problems that I had identified could be fixed and checked on the ground and a further flight was not necessary in order to check the repair."
vi) On 10 March 2020, Mr Faust of Laudamotion (Deputy Nominated Postholder for Continuing Airworthiness) raised a query with Mr Spencer of Ryanair (Deputy Director of Technical Services) as to whether Laudamotion should increase the number of personnel assigned to the records review for MSN 3361. Mr Spencer responded that there was "no need".
vii) On 10-11 March 2020, the engine borescope checks for MSN 3361 were completed with no major defects recorded.
(5) Mid to late March 2020
"• Spoke with John Norton Group Treasurer. FR [Ryanair] has 4bn in cash to see them through.
• O'Leary is looking at scenarios that includes grounding 50% of the Group fleet and more.
• For the 2020 deliveries to Lauda (~12 aircraft) incl our 4, John wanted not to take delivery until a future date when there is business for them. I said no.
• Long story short FR will work with us to take delivery (3 due in March, 1 in April), then they would be parked either in the current MROs (Fokker/Vallair) or in Vienna. Rent would start when they start flying which is likely end of the summer but possibly before depending on how long this situation lasts. Monthly run rate for these four aircraft is $720k.
• Our five delivered aircraft will continue to be paid in full even they are subsequently grounded. Monthly run rate is $990k.
• I believe having them delivered is a priority and we don't want AOGs. They are still in check and I also want FlyNas out of the loop so we are not stuck in the middle. If they are parked for 4-6 months on Ryanair's ticket it's a better outcome for us than having a fight now where they are not delivered and we bear all the risk. Moreover, FR will want first mover advantage in Vienna when this passes and so having them delivered means they can take advantage of that.
• This has not been agreed with John yet but let me know if you disagree with my approach."
"The MRO [Vallair] has not yet closed and they continue to work the aircraft. There are restrictions in place for customers to the MRO, but work is continuing… I would ask your team to continue the return work on the aircraft."
On 17 March 2020, Fokker emailed various parties involved in the delivery of the 2019 aircraft (including the Claimants and Flynas) saying:
"At present there is no lockdown @ Fokker Techniek - our teams continue to work…We have decided to minimize movements in the hangars in our attempt to protect everyone's health which is our top priority. That is why we arrange meetings with our project managers in your offices. We are convinced you will understand and appreciate our actions and we remain at your disposal for any additional support or info you require…"
"Due to continued Corona Virus situation, the Cayman Islands CAA has cancelled all overseas travel. Therefore my trip to Brussels will not take place and I will carry out the Export C of A's as a desk top exercise. I have advised Flynas of this decision."
"I refer you to the extraordinary and unprecedented events of recent days due to the rapid spread of the Covid-19 Virus, which has led to all EU states imposing flight and/or travel bans at short or no notice causing catastrophic cancellations to all airline programs and mass aircraft groundings. We now expect the entire Ryanair Group fleet to be grounded by EU Government flight restrictions over the corning weekend.
In these unprecedented circumstances, the Ryanair Group must immediately take all actions to preserve liquidity in order to survive the next 3 or 4 months of uncertainty. In this regard, we write to advise that Laudamotion is deferring the lease of MSN: 3361, 3396, 3425 & 3475 until we see a return to normal flight services, which we hope will be in a 2 or 3 month time frame. As such we are postponing this lease until at least the end of June. We will update you again at that time.
We thank you for your understanding and support during these difficult times as we trade through this Force Majeure grounding of the EU airline industry caused directly by EU Governments emergency response to the Covid-19 Virus pandemic across Europe."
"Q. Just standing back, looking at this letter, Ryanair was first of all asserting that Lauda would postpone delivery of the 2019 aircraft until at least the end of June, correct?
A. Yes.
Q. By definition, that meant Lauda would not take delivery of the 2019 aircraft prior to each of their final delivery dates?
A. I think what it was intended to do was to get into a negotiation with AerCap around how we can restructure the lease.
Q. But on its face, the letter was saying Lauda would not take delivery of the 2019 aircraft prior to their final delivery dates?
A. We were looking to engage with AerCap around how we can meaningfully take delivery of the aircraft.
Q. Yes but in terms, the letter was saying Lauda would not perform its contractual obligations, correct?
A. As I say, the letter was intended in terms of that we were trying to engage with AerCap in terms of getting to a point of negotiation with them.
Q. It doesn't say that, does it?
A. That is my recollection at the time in terms of how we were dealing with them in terms of trying to get solidarity and support from them."
"Just following up on [Ryanair's letter dated 18 March 2020]. This will need to be documented. Suggest I send you over a draft amendment for the first one which we can clone for the others. We should have the tech guys on the call to plan the logistics on the four aircraft."
"Apologies we did not attend the call yesterday. We have been asked to pause all activity on these aircraft for the moment due to the Covid-19 situation. All our focus is on the grounded operational fleets, therefore the records and physical review are paused. Once I have instruction to continue, we will be back in contact."
"not good news but being dictated by the situation. We need to do a simple amendment to the lease on the back of Neil's letter to Gus that amends the delivery date per Ryanair's request and the rent start date. Gus will look for that comfort. Can I send you something over?"
"Alex Faust from Laudamotion has just advised me that all deliveries are being suspended with immediate effect.
This means that you are required to stop working these aircraft today or tomorrow at latest. Before finishing can you please ensure the following:
Open item lists are all up to date
All available documents are uploaded to the LDM cloud.
Manpower Log has been updated with your days.
I would appreciate if all of you would confirm with me when all of the above is complete.
Thanks to each of you for [sic] your hard work and making this project as successful as it has been. Hopefully this project will re-commence in the not too distant future."
"Q. But there was no need, was there, to ask the external consultants to down tools, particularly those conducting a remote document review?
A. As I said, in terms of all of the workstreams that were going on, there was people moving around and they were going home. In terms of correspondence, here we were focusing on what we were seeing as priority which was the existing fleet.
Q. But why did you need to stand down the consultants working on the delivery of the 2019 aircraft?
A. I wasn't involved in that correspondence.
Q. Doesn't it reflect a decision within Ryanair that you were not going to be taking these aircraft?
A. In terms of the delivery of the aircraft, there is no one more than myself who worked around trying to get an agreement with AerCap around delivering the aircraft.
Q. We'll come on to that. But what I really want you to focus on is why, if at all, there was any need to stand down the external consultants working on the documents?
A. Alex's priority was in terms of looking at the existing Lauda fleet in terms of management consultants. It was not his priority.
Q. I don't see how the consultants one way or the other had any effect on managing the general fleet. They were specifically working in relation to the delivery of these aircraft?
A. I could probably say the same about AerCap's consultants on the other side and delivery of what they needed to attend to around delivering the aircraft and we were not reciprocated in terms of what was outstanding that needed to be delivered.
Q. We see nothing in the documents from any of the Eirtech records consultants suggesting that there were any practical obstacles to them continuing to perform their review. Can you comment on that?
A. I can't comment on that.
Q. Indeed, as at 26 March, the consultants are being asked to make sure the open items lists are all up to date and "available documents are uploaded to the Lauda cloud", all exercises that should have been done remotely, aren't they?
A. In terms of how they were operating, that is obviously the way they were working.
Q. The only reason that these consultants stop work is because Lauda instructed them to suspend work; correct?
A. As I said, all our attention was going to our existing fleet and our people and our resources were completely focused on that.
Q. If Lauda had not instructed the Eirtech consultants to cease work, the records review could and would have continued, wouldn't it?
A. I mean, if we were getting to a process of delivering and that, AerCap could make -- deliver everything that we knew that was outstanding at the time, I mean, we would have -- and as well as that, if they had tendered the aircraft for delivery, you know, we would obviously work to a process of meeting what was required under the lease for us to take the aircraft."
Here again Mr Norton was reluctant to give a direct answer to the question about why the records review needed to be stopped. The evidence as a whole points to the conclusion that the Defendants made a decision to do so, not because the review could not continue for practical reasons, but because they chose to focus their attention on their grounded fleet, and possibly also as part of the strategy of seeking to renegotiate the terms of the leases in view of the economic problems created by the pandemic.
"Q. You see, from what we can discern from the documents, apart from one specifically authorised visit on the part of Mr Aras, an Eirtech consultant, the Eirtech consultant working on the records review did so entirely remotely. You don't know?
A. In terms of -- that is what I was told? In terms of what I have said is based on the knowledge that I have from working with our technical guys.
Q. I suggest to you that Covid-19 had no impact on the ability of the Eirtech consultants to perform the records review because it was being performed remotely?
A. Well, it would have impacted because we were struggling to get the records because we were reliant on AerCap who were -- Mr Akhrif was obviously working from the Middle East and we were working with him around getting what we needed to get from Flynas to effectively continue the review of the aircraft and that was just continuing to be laborious and hence my communication with Colin around this.
Q. You say you were dependent on AerCap loading documents onto the Box for review; yes?
A. Yes.
Q. That review was done remotely, wasn't it, the documents on the Box?
A. The Box is a convenient way of just putting records up. Whether that is done physically, on site or remotely, it is irrelevant.
Q. Yes.
A. It is an ability of being -- ease of use around getting access to records –
Q. I think you would agree with me –
A. -- between both [sides], it is a two-way process.
Q. -- Mr Norton that as far as documents were available online there was nothing post the onset of the Covid pandemic which prevented the remote review of documents continuing, was there?
A. Remotely being able to review documents, assuming they are delivered to us.
Q. Thank you. And it was quite a rare event when an Eirtech consultant actually did the review of the documents physically on site. Are you aware of that?
A. As I said, I mean in terms of what their actual movements were, I wasn't tracking what they are doing, whether --
Q. Thank you. If you go to {D/64/1}, you see an email of 25 February from Mr Murphy to Mr Aras copied to -- well, an email to Mr Aras and Mr Faust. Do you see that?
A. Yes.
Q. And Mr Murphy, can you remind me who Mr Murphy is?
A. Presumably he is someone in Eirtech, I have had no dealings with him.
Q. As I understand it, he is the project lead at Eirtech. Does that make sense?
A. I assume so, yes.
Q. "Hi Alex, Ilhan.
"Khalid from AerCap has called me and is requesting that llhan go onsite to the Netherlands next week (Monday 2nd March) in a bid to try and close out open items."
And he asks whether it is possible for Mr Aras to go to the Netherlands and he asks whether Mr Faust whether he approves for this to happen. Do you see that?
A. Yes.
Q. And then over the page, Mr Faust approves that. {D/64/1} Now, this is the only occasion -- I think the visit lasted about four or five days, the only indication we've seen in the documents where someone went on site to perform any part of the document review. Does that accord with your recollection?
A. As I said, I don't track their activities in terms of whether they are on site or off site. It is in terms of --"
In my view, Mr Norton overreached himself by suggesting that the Covid restrictions impeded the records review, a proposition which the contemporary document did not bear out. Mr Norton had no sound basis on which to make that assertion in his witness statement. It evidently was not based on any first-hand personal knowledge, and he did not identify any source for the information.
"Q. …So it is right that from the end of March, Lauda ceased to attend the weekly calls?
A. Yes.
Q. It is right that Eirtech ceased to be any work on the four aircraft; yes?
A. They stopped work end of March, yes.
Q. And the work that Eirtech ceased doing included updating the OIL and closing out items?
A. Including closing items, yes.
[…]
Q. As far as you were aware, did Mr Spencer ever get back in touch and say "we are resuming the process"?
A. I am not aware of any, no."
"Q. I suggest to you in those circumstances that you have just described to the court, you couldn't reasonably expect AerCap to keep providing updates on the aircraft.
A. No, I have not -- no.
Q. There would be no point, would there, because you weren't engaged in the process?
A. Yes.
Q. You agree with me."
(6) April 2020
"Main parts of records are reviewed and appear satisfactory.
186 open items are remaining.
Updated statuses are awaited.
LDND will need to be revisited regarding calendar time items.
Estimate 10 days to complete this aircraft."
The Claimants point out that a large number of the 186 open items appear to have been added to the OIL on or shortly before 26 March.
i) In its March 2020 report to Peregrine, AIL stated:
"due to the impact of COVID 19 Lauda Motion has requested that delivery of each aircraft be deferred until the end of June. Discussions remain in progress with an expectation that related lease amendment agreements will be executed to include a condition that existing walkaway rights will not apply due to the delayed deliveries. Discussions are also in progress with Flynas to retain both [MSN 3361 and MSN 3396] on the existing register (Cayman) and on their operating certificate. This will avoid additional re-registration costs. It will require the leases to remain in place following technical acceptance of each aircraft (at which point rent will no longer be payable). Both aircraft will be stored at their current location (Fokker facility in the Netherlands)."
ii) On 1 April 2020, Mr Akhrif asked Celairion to provide a quote to be shadow CAMO for MSN 3361 and MSN 3396, since "the delivery of the four A320s to Lauda is delayed till June, exact date yet to be agreed".
iii) By 1 April 2020, AustroControl had been told by the Claimants' consultants that the delivery of MSN 3361 would be delayed until June.
i) Flynas had ceased to operate the aircraft prior to the aircraft being flown to the MROs in late 2019/early 2020.
ii) Flynas had, however, failed to redeliver each of the 2019 aircraft in redelivery condition by their respective contractual redelivery dates. As a result, the Claimants had the right to terminate the Flynas leases at will if they wished to do so.
iii) If Laudamotion had re-engaged, the Claimants could have terminated the Flynas leases in order to effect delivery to Laudamotion. Mr Anderson and Mr Peacock said in evidence:
(Anderson) "A. You couldn't have two leases running at exactly the same time, but we would have terminated the Lauda lease -- terminated the Flynas lease and delivered to Lauda.
[…]
A. …It is the ordinary course of business. We terminate leases and start new ones every single day."
(Peacock) "Q. Well, if there was any intention to terminate the Flynas lease, which I think is what you are saying, is it, would have happened?
A. Immediately before or shortly before tender to or acceptance by Laudamotion, yes, that is what would happen."
Mr Anderson's evidence is consistent with an email of 2 March 2020 from Mr Akhrif confirming internally that the aircraft would be redelivered from Flynas and delivered to Laudamotion on the same day. I accept his and Mr Peacock's evidence on this point.
iv) Unless and until Laudamotion re-engaged, it was in the Claimants' interests to keep the aircraft on lease to Flynas so that Flynas, and not the Claimants, would bear costs such as maintenance, parking and/or storage, and insurance.
"…For the 4 aircraft in the table below [including MSN 3361], Eirtech will complete the records review…To limit the man-days Eirtech suggested the lessors first close out the OIL, and then the reps can come back in. Can you contact…AerCap…
[…]
…I discussed this with Karsten, and according to him the decision from MOL [Michael O'Leary] was not to send any staff to rep the checks…KM was very specific that the records review for the aircraft near completion should continue using the current inspectors."
"Karsten" and "KM" referred to Mr Muhlenfeld, Ryanair's Director of Maintenance & Engineering.
"…AerCap…will be the most impacted A320 lessor with 6 A30s [sic] delivered & 4 on the way…It may make more sense to continue cancelling undelivered A320s with AerCap…before we get into lease holidays with them."
"Further to Neil's letter to Gus and as discussed between us, AerCap is willing to support Ryanair and Lauda during this time.
We continue to spend money on these aircraft in order to prepare them for delivery to Lauda.
The deferred deliveries need to be documented, something also required by Gus and I have attached a draft amendment agreement. Some of the calendar items will obviously have a few months burned as a result of this delay but we can accept the same at return."
"As you are aware, the Covid-19 crisis has led to an unprecedented EU Government mandated grounding of the aircraft fleets of most EU airlines to stem the spread of the virus on public health grounds. Airlines across Europe are implementing unprecedented measures including bankruptcies, administration, and/or mass layoffs for the foreseeable future. No one knows when Europe's airlines will be allowed to return to service, or how much capacity will be allowed to return, or under what Government restrictions.
As a result of the above, aircraft values and lease rentals have collapsed. Many airlines are defaulting on their lease obligations, and many lessors have seen a sharp decline in lease payments since this crisis erupted in March 2020.
Laudamotion must respond to these market conditions by preserving cash and cutting our payment obligations to reflect the fact that we have no flights, no passengers, and no revenues for the foreseeable future. We hereby advise you that with effect from 1 April we will be reducing the monthly rental of MSN 2502,3105,3270,3131,3153 from its present rate to $150,000 per month. This reduced rental will be reflected in the next (May) rent payment, which will incorporate the April catch up.
This market rate reduction is a sensible and realistic solution to the current unprecedented Covid-19 crisis and we expect, as our lessor, that you will work with us to agree this reduced rental, which will apply for the remainder of these aircraft leases. If this rent reduction is not acceptable, then we are prepared to redeliver your aircraft by agreement with immediate effect without the payment of any further monthly rentals.
We also refer to the A320 aircraft that Lauda had hoped to take delivery of later this year. Since Lauda has been completely grounded since 17 March last, and will be forced to substantially downsize its operation (and future growth plans) as a direct response to the Covid-19 crisis, it is clear that Lauda cannot accept delivery of these aircraft, and accordingly, you are now free to re-market these aircraft elsewhere.
We sincerely regret these unprecedented, emergency actions, which are a direct result of the Covid-19 crisis, which has grounded Europe's airlines from mid-March for the foreseeable future. We will continue to work with you to try to find some work for these leased aircraft at this reduced monthly rental, which will enable Lauda – unlike many other airline customers – to continue to generate monthly lease revenue for you despite the fact that these aircraft are grounded and earning no revenue for Lauda for the foreseeable future.
Please confirm your agreement by return."
"Q. At this point in time, Lauda is telling AerCap that it will not comply with its contractual obligations to accept delivery of the 2019 aircraft and pay rent under the leases when it became due, correct?
A. I would clarify that it was part of a commercial letter that went to each of our lessors, not just AerCap, around trying to find a way of getting an amendment of our existing leases and also our own delivered aircraft. Because we were well aware that there was movement in the market around other airlines getting rent reductions and deferrals and non-delivery of aircraft and we were no different to anybody else, that we were looking for that solidarity from each of the lessors around it.
Q. Leaving aside, I hear what you say, that this letter is written in the context of commercial negotiations but in terms of what the letter says on its face, it is telling AerCap that it will not comply with its contractual obligations to accept [the] 2019 aircraft and pay rent under the leases when it became due, correct?
A. I think it is the difference between saying one thing and actually doing another and I think what it led to was we got engagement across the board from all of our lessors around what we needed to do around having a partnership with each of the lessors around trying to find a solution to the issues that we were dealing with.
Q. I understand the distinction you point to, between telling and doing. Yes. But in terms of telling, that is what the letter is saying, isn't it?
A. Yes, but in terms of what actually transpired …is that we got on a path around finding solutions with each of our lessors, except for our relationship with AerCap, on the basis that we continued to pay the rents as they fell due, granted under protest. But none of those leases went into default.
Q. I understand what you are saying about what transpired and I am asking you to keep focusing on what this letter says?
A. I can only talk about the facts of what actually happened. Whereas when that letter went out as a commercial letter at a point in time, the events that moved were very different."
Mr Norton thus eventually accepted (in the third answer quoted above) that the letter amounted to telling AerCap that Laudamotion would not comply with its contractual obligations to accept the 2019 aircraft and pay rent under the leases when it fell due. His answer in substance was that, whilst the Defendants were saying that, what they were seeking to achieve in practice (and did achieve with other lessors) was a consensual amendment to the lease terms. As he put it slightly later in cross-examination, he regarded it as "part of trying to get commercial agreement and a negotiation with AerCap".
"…This letter is in response to your letter to Colin Merry of AerCap dated 20 April 2020 ("20 April Letter"). While AerCap is sympathetic to the harm caused by COVID-19, we cannot accept the requests or statements made in the 20 April Letter which violate both the terms of the Lease Agreements as well as the spirit of the relationship between our companies to date.
Specifically, to the extent that the 20 April Letter purports to unilaterally vary the amount of Base Rent payable under the 2018 Lease Agreements or unilaterally terminate the 2019 Lease Agreements, we remind Lessee that it has no right to do so. Lessee remains fully obligated to comply with its obligations under the Lease Agreements, including paying all amounts when due, and taking delivery of the 2019 Aircraft in accordance with, the Lease Agreements. Any failure by Lessee to do so will constitute an Event of Default under each Lease Agreement.
Moreover, we note that there have been recent discussions and correspondence between AerCap, Guarantor and Lessee regarding a potential deferred delivery of the 2019 Aircraft in order to accommodate Lessee. These discussions culminated in a good faith proposal from AerCap in such respect. The 20 April Letter appears to reject this proposal. For the avoidance of doubt, the 2019 Aircraft will be tendered for Delivery in accordance with the 2019 Lease Agreements."
"Letter received from Aercap, will not agree to unilateral rent reduction or non delivery of the 4 aircraft. Aircraft will be tendered for delivery and under the terms of the lease they will force delivery of the aircraft in accordance with the lease."
Thus it appears that the Defendants appreciated from at least 22 April 2020 that the Claimants intended to tender the 2019 aircraft for delivery, and Mr Norton accepted in cross-examination that the Defendants were aware that MSN 3361 would be tendered first, though there is no indication that the Defendants knew the date on which this would occur.
"We discussed with Gus [Aengus Kelly] who spoke with Ryanair last night. We are going to tender 3361 ASAP. I told Gus we can do this in 7-10 days subject to Cayman CAA …. 3361 will be shot across the bow. Plan is to tender all aircraft. This must be front and centre of all decisions we make. Keep this in mind in all comms. Talk at 2pm but get the ball rolling".
Mr Akhrif agreed in cross-examination that the reference to "7-10 days subject to Cayman CAA" was to the need to obtain an export certificate of airworthiness ("ECoA"), one of the documents required by Exhibit B § 4 of the lease.
"…We welcome your acknowledgement of the difficulties that the current crisis is having on Laudamotion Gmbh ("Lauda") and your willingness to discuss ways to assist. We continue to believe, however, that the solution set out in our letter of 20 April 2020 is a sensible and realistic one given the current circumstances.
On the understanding that you will engage constructively with us to deliver a mutually agreeable position by 15 May 2020, we will pay the lease rentals due on 6,7, 8th and 21st May 2020 without deduction.
These payments will be made under protest and without prejudice to the position set out in my letter of 20 April 2020 and all of Lauda's legal rights and entitlements, including in relation to the leases, all of which are reserved."
"Q. The agreement to pay continuing rent on the 2018 leases is stated to be expressly conditional upon some mutually agreeable position being reached on 15 May, wasn't it?
A. Yes.
Q. That wasn't really an option, was it?
A. As I said in terms of where we got to and where the existing leases are continuing to be in full force and effect and we continue to pay on the basis that as they fall due, we meet the payment of them.
Q. So I think you would agree with me that it was not really open to make those payments conditional on anything?
A. As I said, we were looking to try and find a way that we can get agreement also on the delivered aircraft where we were paying leases on.
Q. I will ask you the question again. It was not open to you to make those payments conditional upon anything else, was it?
A. As I said, we continued to pay those leases. We were trying to constructively work with AerCap to try and find an overall solution around the existing leases and the undelivered aircraft."
The short answer, which Mr Norton ought to have conceded, was that payment of rent under the 2018 leases was not optional. However, I accept the point that the Defendants were continuing to seek a renegotiation and (backtracking in this respect on their 20 April letter) continued to pay the 2018 lease payments in full in furtherance of that strategy.
"John Norton looking for a status of the A320s for MOL. I have expanded out the summary I did at the end of March per below
I have advised him we have not been in touch with Lessors since approx.. mid-March so some aircraft may have progressed since we were last engaged in the project"
"…This letter is in response to your letter to Colin Merry of AerCap dated 28 April 2020 ("28 April Letter"). AerCap will continue discussions with Lessee and Guarantor regarding potential modifications to the Lease Agreements to accommodate Lessee on the following basis: (i) any such discussions will be held on a without prejudice basis; (ii) Lessors reserve all rights and remedies under the Lease Agreements, including their right to deliver each 2019 Aircraft to Lessee in accordance with the terms of the 2019 Lease Agreements; (iii) such discussions must be concluded as soon as practicable given that the 2019 Aircraft are or will shortly be ready to be delivered to Lessee; and (iv) any agreement to modify any of the Lease Agreements is conditional upon the execution of a binding agreement which documents the commercial agreement reached.
With respect to the statement made in the 28 April Letter that the payment of lease rentals in May 2020 is conditional on AerCap engaging constructively with you on potential modifications to the Lease Agreements, Lessors do not agree to any such conditions being placed upon Lessee's obligations to pay Rent under the Lease Agreements…"
(7) May 2020
"Q. I suggest to you that the call on 1 May was a final attempt by AerCap to reach a sensible compromise; yes?
A. I think that phone call that happened was that Colin expressly asked me how we were getting on with the other lessors and he seemed to have a particular focus of GECAS in terms of have we anything agreed with them and I said to him that, well, things have moved forward significantly since we last talked on the basis that we had one lessor in particular that asked us for a short deferral on the basis that they were going to come back with a fully comprehensive solution that they believed was going to work quite well for us. And it seemed to change the whole conversation.
Q. If we go to {B/5/4}, this is Mr Merry's statement. And at paragraph 18, we see he refers to various letters that we have been looking at. And then says:
"Following these letters, there were further telephone conversations between Mr Norton and me including a call on the morning of 1 May 2020 during which it was clear that no agreement on an amendment on the 2019 leases was going to be reached in the short-term."
That is an accurate description of what happened on the call, isn't it?
A. It is accurate on the basis that we had, as I said, made significant progress with the other lessors around rent deferrals and rent reductions and that way was the progress that we were moving towards around our negotiations with AerCap. And obviously trying to find a solution on the 2019 leases.
Q. But Mr Merry was right to conclude, wasn't he, that there was unlikely to be an agreement on amending the 2019 leases in the short-term?
A. I would say that we had stated to him in terms of where we were with everybody else and what we had asked him to do is to consider that based on we were seeing solidarity from our other relationships and that we were hoping that he was going to take it away internally and see if we could get to a common position with everybody.
Q. So you wanted AerCap to go down the same route as other lessors?
A. That is where the path forward was seemingly tracking with everybody.
Q. You wanted AerCap to reach the same point?
A. It would be helpful for us around meeting the business in terms of what we were experiencing if we could get everybody working together to find the right solution.
Q. But it is right to say that AerCap had proposed deferrals of the scheduled delivery dates and the final delivery dates in relation to all four aircraft?
A. Yes and I think as I said, we had proposed to AerCap around the reductions of the rent around the existing leases and then also a rent reduction on the undelivered aircraft as a way forward of getting a solution because that is what the way was tracking with our other leasing arrangements.
Q. And that is what you were asking for on 1 May?
A. Yes."
I find that a broadly plausible explanation of the conversation, in the context of the dealings between the parties shown by the contemporary documents, and also not necessarily inconsistent with the statement in Mr Merry's witness statement that he concluded no deal would be reached in the short term (depending on what Mr Merry meant by the 'short term'). In simple terms, the Claimants were willing to discuss lease deferrals, but the Defendants were also hoping to achieve rent reductions as, they said, they were achieving with other lessors.
"upon tender of the Aircraft by LESSOR to LESSEE in accordance with the Lease Agreement, LESSEE is obligated to accept the Aircraft and the date of tender by LESSOR to LESSEE will be deemed to be the Delivery Date for all purposes under the Lease Agreement, including the commencement of LESSEE's obligation to pay Rent thereunder".
"Clause 3.2 of the Lease Agreement requires the Lessor to do three things:
(a) notify the Lessee from time to time and in a timely manner of the exact date on which the Lessor expects Delivery to take place;
(b) consult with Lessee prior to making a determination as to such date; and
(c) provide reasonable notice of such date.
The Lessor has failed to do all three things.
In reality, there has been no engagement from AerCap, the Lessor and their respective teams in relation to the delivery process for this Aircraft for a number of weeks with no recent contact whatsoever with the Lauda/ team in relation to the technical acceptance and Delivery process.
The Lessor has therefore breached all of its obligations under Clause 3.2 of the Lease Agreement and we reserve all of our rights at law and under the Lease Agreement in relation to such breach.
We also consider AerCap's lack of engagement and communication and attention in respect of its material obligations to be unreasonable and we reserve all rights in relation to such unreasonable behaviour.
Further, and without prejudice to all of our rights at law and under the documents, Clause 7.4.8 of the Lease Agreement requires the Aircraft to conform to the condition set forth in Exhibit B thereto. Exhibit B sets out various requirements that must be complied with before Delivery can occur. These conditions have not been satisfied by the Lessor. In particular, without limitation, we refer to Article 1 (Technical Report), Article 2 (Full Aircraft Documentation Review), Article 3 (Aircraft Inspection) and Article 4 (Certificate of Airworthiness Matters) of such Exhibit B, none of which have been complied with by the Lessor as required by the Lease Agreement.
Arising from the foregoing, Lauda does not consider that it has been validly notified of the Scheduled Delivery Date, as required pursuant to the Lease Agreement, and will not be taking delivery of the Aircraft on 7 May 2020 as requested, and accordingly, we dispute that any Event of Default or obligation to pay Base Rent pursuant to the terms of Clause 6.5 (Delay or Failure in Acceptance) of the Lease Agreement arises or could arise.
Furthermore, we maintain the position outlined in our most recent letter to you - namely that the current crisis, which has led to the grounding of airlines, including Lauda, with no certainty in relation to when, if ever, normal service will resume, is clearly unprecedented. In this regard, we would note Norwegian Air's rescue plan whereby aircraft lessors (actively led by AerCap) have agreed to a debt-for-equity swap alongside bondholders, which bears clear testimony to this. The current crisis has radically changed the commercial and legal position since the time the Lease Agreement and those lease agreements in respect of three additional Airbus A320-200 aircraft (namely MSNs 3425, 3475 & 3396) (together with the Lease Agreement, the "AerCap Lease Agreements") were entered into, in ways that were not and could not have been contemplated by the parties. Accordingly, and without prejudice to all of the above and to all of our rights at law, we take the view that the Covid-19 crisis is an unforeseeable change in circumstances, not contemplated by the parties or within their control and has made performance of the AerCap Lease Agreements impossible or radically different from that contemplated by the parties when they entered them, all of which would render the AerCap Lease Agreements void."
(8) Technical status of the 2019 aircraft following termination
i) As regards MSN 3396 (Final Delivery Date 30 June 2020):
a) On 10 June 2020, Fokker issued a Certificate of Release to Service and the demo flight was completed.
b) On 15-16 June 2020, the engine and APU (auxiliary power unit) borescopes were completed.
c) On 27 July 2020, the Export Certificate of Airworthiness was issued.
ii) As regards MSN 3425 (Final Delivery Date 31 May 2020):
a) On 28 May 2020, Vallair issued a Certificate of Release to Service.
b) On 29 May 2020, the demo flight was completed.
c) On 2-3 June 2020, the engine and APU borescopes were completed.
d) On 21 July 2020, the Export Certificate of Airworthiness was issued.
iii) As regards MSN 3475 (Final Delivery Date 30 June 2020):
a) Around 27 October 2020, the demo flight was completed.
b) Around 6 November 2020, the engine borescopes were completed.
c) On 10 November 2020, the Export Certificate of Airworthiness was issued.
(9) SmartLynx leases
(F) WERE CLAIMANTS ENTITLED TO TERMINATE UNDER ART. 24.2(N)?
(1) Meaning of Article 24.2(n)
"24.2 Events of Default. The occurrence of any of the following will constitute an Event of Default and material repudiatory breach of this Lease by LESSEE:
…
(n) Insolvency. LESSEE or Guarantor
(i) is or becomes, or is deemed for the purposes of any Law to be, insolvent or unable to pay its debts or other obligations as they fall due, or admits its inability to pay its debts or other obligations as they fall due,
(ii) suspends or threatens in writing to suspend payment with respect to all or any of its debts or other payment obligations or a moratorium is declared in respect of all or any of LESSEE's or Guarantor's debts or other payment obligations or
(iii) proposes, enters into or is a party to any proceeding regarding (or takes any corporate action to authorize or facilitate) any arrangement or composition with, or any assignment for the benefit of, its creditors"
(paragraph breaks interpolated)
"24.3 … Upon the occurrence of any Event of Default and so long as the same shall be continuing, LESSOR may do all or any of the following at its option …:
(a) … by written notice to LESSEE, terminate LESSEE's right to lease the Aircraft and terminate LESSOR's obligations hereunder (but without prejudice to the indemnity obligations and any continuing obligations of LESSEE under this Lease and any other Operative Document, including the obligations set forth in Articles 15 and 16)"
i) The heading "Insolvency" at the start of the clause is not an aid to construction of the substantive part, because Article 27.15 provides that "All article and paragraph headings and captions are purely for convenience and will not affect the interpretation of this Lease."
ii) Article 24.2(n) as a whole is not confined to insolvency situations. One of the triggers in (iii) is an "arrangement". That covers both schemes of arrangement under Part 26 of the Companies Act 2006 and a CVA under Part I of the Insolvency Act 1986 (and analogous proceedings abroad). Neither of these requires the company to be insolvent: a scheme of arrangement may be sanctioned in respect of a solvent company (see Palmer, "Company Law", § 12.017) and a CVA can involve a solvent company (see Sealy & Millman, "Annotated Guide to the Insolvency Legislation" (24th ed), notes to IA 1986, Part I: "It is not a prerequisite for the application of this Part of the Act that the company should be "insolvent" or "unable to pay its debts" within the statutory definitions of those terms.")
iii) Proper weight must be given to the structure of the clause, which involves three distinct species of Event of Default:
a) Limb (i) deals with insolvency in the technical sense.
b) Limb (ii) deals with two things: (1) suspension, or threat of suspension, of payment; and (2) a "moratorium". The reference to a "moratorium" cannot be to the procedure now in Part A1 of the Insolvency Act 1986, because that was inserted by the Corporate Insolvency and Governance Act 2020. It is presumably intended to cover procedures such as the US Chapter 11 bankruptcy procedure.
c) Limb (iii) deals with "any arrangement or composition with, or any assignment for the benefit of, its creditors". As noted above, whilst this class of events may involve insolvency in the technical sense, it does not necessarily do so.
There is, in view of this structure, no reason to read down the words in Article 24.2(n) limb (ii) so that they only apply in a situation of insolvency.
iv) Article 24.2(n) is followed by two provisions ((o) and (p)) addressing "Voluntary Bankruptcy" and "Involuntary Bankruptcy", so it is not the only Event of Default potentially applicable in an insolvency situation.
v) The words "suspends or threatens in writing to suspend…" should be given their natural meaning. They serve an obvious commercial purpose and there is no reason to read them down. The Claimants refer to the statement of the Supreme Court in Lambeth London Borough Council v Secretary of State for Housing, Communities and Local Government [2019] UKSC 33 (in the context of a planning case) that:
"In summary, whatever the legal character of the document in question, the starting point, and usually the end point, is to find "the natural and ordinary meaning" of the words there used, viewed in their particular context (statutory or otherwise) and in the light of common sense." (§ 19)
vi) The Claimants accept that § 24.2(n) is directed at more general suspensions/threats of suspension of payments than particular payments under a particular contract; they say it is aimed at indicators of financial difficulties, which may or may not be a prelude to more formal insolvency-type events. However, the words "all or any" indicate that it is unnecessary for the suspension or threat to relate to the Lessee's debts as a whole: it is sufficient that it relates to a category of them, such as aircraft lease payments.
vii) The opening words of Article 24.3, referring to what the Lessor "may" do "at its option", mean that the Lessor is entitled to elect not to rely on the lease having automatically terminated, or to affirm the lease. (For example, the Claimants did not rely on automatic termination of the 2018 leases.) There is no need to restrict the meaning of § 24.2(n) by reason of the fact that, post delivery of an aircraft, it can operate automatically.
i) The task is to identify the intention of the parties by reference to what a reasonable person, having all the background knowledge which would have been available to the parties, would have understood them to be using the language in the contract to mean. The court does this by focussing on the meaning of the relevant words in their documentary, factual and commercial context. The meaning has to be assessed in the light of (a) the natural and ordinary meaning of the clause, (b) any other relevant provisions of the contract, (c) the overall purpose of the clause and the contract, (d) the facts and circumstances known or assumed by the parties at the time that the contract was made, and (e) commercial common sense, but disregarding subjective evidence of any party's intentions. (Arnold v Britton [2015] UKSC 36, [2015] AC 1619, § 15).
ii) The court has to ascertain the objective meaning of the language used, within the context of the contract as a whole and, depending on the nature, formality, and quality of the contract, give more or less weight to the wider context in reaching a view on objective meaning (Wood v Capita Insurance Services [2017] UKSC 24 § 10).
iii) The unitary exercise of construction is an iterative process by which rival constructions are checked against the provision of the contract, business common sense, and their commercial consequences. It does not matter whether the court's analysis commences with the factual background and the implications of rival constructions or a close examination of the relevant language in the contract, so long as the court balances the indications given by each. However, the extent to which each tool will assist the court in its task will vary according to the circumstances of the particular agreement. Sophisticated and complex agreements or those negotiated and prepared with the assistance of skilled professionals should be interpreted principally by textual analysis (Wood v Capita §§ 11-13).
iv) Subsequent conduct and contracts are generally inadmissible as an aid to construction: see Lewison, "The Interpretation of Contracts" §§ 3.183-3.187, and Hyundai Merchant Marine Co Ltd v Daelim Corp [2012] 1 Lloyd's Rep 211: "reliance on a subsequent contract to construe a written contract is, to say the least, a heretical approach to construction… The inadmissibility of a subsequent contract as an aid to construction of a written contract is merely one aspect of the general principle of English contract law that… the subsequent conduct of the parties cannot be looked at to interpret a written contract… It seems to me that the principle that the subsequent contract is inadmissible is equally applicable whether it is made the following day or long after." (§ 13)
"This Lease and the other Operative Documents are the result of negotiations between LESSEE and LESSOR and are the product of both parties. Accordingly this Lease and the other Operative Documents or any uncertainty or ambiguity in any such agreements will be interpreted to fairly accomplish the purposes and intentions of LESSEE and LESSOR and will not be construed or resolved against LESSOR merely because of LESSOR's involvement in the preparation of this Lease and the other Operative Documents, regardless of any rule of construction."
"(1) Notwithstanding a provision in an executory contract or unexpired lease, or in applicable law, an executory contract or unexpired lease of the debtor may not be terminated or modified, and any right or obligation under such contract or lease may not be terminated or modified, at any time after the commencement of the case solely because of a provision in such contract or lease that is conditioned on— (A) the insolvency or financial condition of the debtor at any time before the closing of the case; (B) the commencement of a case under this title; or (C) the appointment of or taking possession by a trustee in a case under this title or a custodian before such commencement".
In Canada section 34 of the Companies Creditors Arrangement Act 1985 provides:
"(1) No person may terminate or amend, or claim an accelerated payment or forfeiture of the term under, any agreement, including a security agreement, with a debtor company by reason only that proceedings commenced under this Act or that the company is insolvent. (2) If the agreement referred to in subsection (1) is a lease, the lessor may not terminate or amend the lease by reason only that proceedings commenced under this Act, that the company is insolvent or that the company has not paid rent in respect of any period before the commencement of those proceedings.
In Australia, where a compromise or arrangement is proposed between a company and its creditors under section 411 of the Corporations Act 2001, section 415D imposes a stay on enforcing rights when there is an announcement that the company will be making an application under section 411, or an application is made under section 411 or the compromise or arrangement is approved. One effect of the restriction is that a right to terminate a contract will not be enforceable to the extent that those rights are triggered by the body becoming the subject of such an announcement, application, compromise or arrangement.
"(a) Delivery. LESSEE fails to take delivery of the Aircraft when obligated to do so under the terms of this Lease and such failure continues for 5 Business Days;"
"(b) Non-Payment. (i) LESSEE fails to make a payment of Basic Rent or Agreed Value within five Business Days after the same has become due or (ii) LESSEE fails to make a payment of any other amount due under this Lease or any of the other Operative Documents (including amounts expressed to be payable on demand) after the same has become due and such failure continues for seven Business Days;"
…
"(f) Breach. LESSEE fails to perform or observe any other covenant or obligation to be performed or observed by LESSEE under this Lease or any other Operative Document, which failure is not cured within 21 days after written notice thereof to LESSEE, provided that, if such failure cannot by its nature be cured within 21 days, LESSEE will have the reasonable number of days necessary to cure such failure (not to exceed a period of 30 days) so long as LESSEE uses diligent and all reasonable efforts to do so;"
(2) Application to present case
i) Ryanair's 18 March 2020 letter was a statement of unilateral intent, not a mere proposal for discussion. It was a statement of Laudamotion's then-present intention and therefore a "threat" as to future action.
ii) It is irrelevant that the Claimants thereafter discussed a commercial resolution with Ryanair which would have taken the form of a Global Amendment Agreement.
iii) The fact that the threat was merely to defer the start date of the Leases makes no difference. The contractual obligation on the part of the Lessee was to start paying rent from a date shortly before the Scheduled Delivery Date (see Article 5.2.2). What Laudamotion was threatening to do was not to pay what was due when it was due. This may be illustrated by the case of MSN 3425. The Final Delivery Date was (Sunday) 31 May 2020. Three Business Days before that was 27 May 2020. Thus Laudamotion's obligation was to pay the first instalment of Base Rent of $180,000 at the latest on 27 May 2020. Its letter was an absolute statement that it would not pay that sum when due.
iv) The 20 April 2020 letter was also a threat not to pay monies when they fell due, and did not amount to a mere proposal. In respect of the 2018 aircraft, Laudamotion was unequivocally stating that it would not continue to pay what was contractually due each month. In respect of the 2019 aircraft, it was a categorical statement that Laudamotion would not take delivery at any time. That was necessarily a statement that Laudamotion would not pay what was due by way of rent, both before and after the Scheduled Delivery Date. The concluding words "Please confirm your agreement" cannot be said to convert a unilateral statement of intent into any sort of meaningful proposal. No rational commercial party would be expected to agree to a "proposal" to extinguish all its rights in relation to the 2019 leases (more so in the context of the total collapse of the relevant market).
v) There was in the present case a threat to suspend payments in general, or at least aircraft lease payments in general. The Defendants' letters set out their approach to their lessors in general, not only the Claimants, and Mr Norton said in evidence that the 20 April letter was "a commercial letter that went to not just AerCap but to all of our lessors around all of the aircraft that we had, each one of them, around looking for rent reductions and then we were looking to get to a point where we could negotiate the existing leases and the delivered leases" and "part of a commercial letter that went to each of our lessors, not just AerCap, around trying to find a way of getting an amendment of our existing leases and also our own delivered aircraft".
vi) The Claimants' further correspondence before terminating did not waive their rights to do so. Article 27.10 provides that:
"The rights of LESSOR hereunder are cumulative, not exclusive, may be exercised as often as the LESSOR considers appropriate and are in addition to its rights under general Law. The rights of LESSOR are not capable of being waived or amended except by an express waiver or amendment in writing. Any failure to exercise or any delay in exercising any of such LESSOR's rights will not operate as a waiver or amendment of that or any other such right. Any defective or partial exercise of any rights of LESSOR will not preclude any other or further exercise of that or any other such right and no act or course of conduct or negotiation on LESSOR's part or on its behalf will in any way preclude LESSOR from exercising any such right or constitute a suspension or any amendment of any such right."
vii) The Claimants accepted that such a clause would not prevent affirmation of the lease, and said they had done so in relation to the 2018 leases. The Court of Appeal in Tele2 International Card Company v Post Office [2009] EWCA Civ 9 held that a similarly worded clause could not prevent the fact of an election to abandon a right to terminate from existing: the general law demands that a party who has a contractual right to terminate a contract must elect whether or not to do so. At most, the clause emphasised the requirement that election to abandon a right requires a clear and unequivocal communication of an election to abandon the right to terminate and to continue the contract. The continued performance of the contract, without any protest regarding the breach giving rise to the right to terminate and without any reservation of rights, was such an election.
viii) Nonetheless, the Claimants were entitled, before terminating, to a 'grace period' during which they called on the Defendants to perform their obligation (see, e.g., Yukong Line v Rendsburg Investments [1996] 2 Lloyd's Rep. 604, 608, albeit that case was not cited before me). That is all the Claimants were doing in the period between the Defendants' letters of 18 March and 20 April 2020, and the Claimants' termination notice on 15 May 2020.
i) The letter was not wholly unequivocal about those payments. Although some of the language indicated that Laudamotion was determined to make these reductions, the relevant paragraphs also indicated a wish to "work with us to agree this reduced rental", and ended by seeking confirmation of AerCap's agreement. The sentence about redelivering the aircraft if the rent reductions were not acceptable indicated that Laudamotion was "prepared" to do so "by agreement", but did not state in terms that Laudamotion would necessarily take the unilateral step of walking away from the 2018 leases.
ii) The letter did not say that Laudamotion would be implementing rent reductions in relation to all its existing leases, still less that it was suspending payment of its debts more generally. It is true that Mr Norton said in evidence that a letter in such terms was being sent to all Laudamotion's other lessors, but (leaving aside the fact that the Claimants' had no knowledge of that at the time) all the letter said was that Laudamotion needed to respond by "preserving cash and cutting out payment obligations". There is no evidence in the letter, or from Mr Norton, about precisely what approach Laudamotion was taking to other lessors, including its stance with other lessors as regards the need to reach agreement on a case by case basis before reducing or postponing rental payments.
iii) By the date of purported termination, 15 May 2020, any threat in relation to the 2018 leases was much attenuated and still less unequivocal. Laudamotion had in fact continued paying the rent in full. It is true that it purported to do so only "[o]n the understanding that you will engage constructively with us to deliver a mutually agreeable position by 15 May 2020", but (a) that was an obviously commercial posture, far too vague to have been considered a purported legal condition, and (b) after the Claimants on 29 April rejected Laudamotion's purported precondition, Laudamotion nonetheless continued to pay rent in full on 6, 7 and 8 May 2020.
(3) Effect of the Claimants' termination notice
"1. Reference is made to the Leases. Capitalized terms used herein and not otherwise defined have the meanings ascribed to such terms in the Leases.
Lease MSN 3361
2. Reference is also made to: (i) the letter from Lessor to Lessee dated 1 May 2020 wherein Lessee was informed that, pursuant to Article 3.2 (Scheduled Delivery Date) of Lease MSN 3361, the Scheduled Delivery Date would be 7 May 2020; and (ii) the letter from Lessor to Lessee dated 7 May 2020 wherein Lessor tendered Aircraft MSN 3361 for Delivery on 7 May 2020 at the Delivery Location.
3. Lessee failed to take Delivery of Aircraft MSN 3361 at the time and manner specified in Lease MSN 3361. Lessee's failure to take Delivery of Aircraft MSN 3361 constitutes an Event of Default under Article 24.2(a) of Lease MSN 3361 (the "Lease MSN 3361 Delivery Default"). Without prejudice to the foregoing, as of the date of this Notice certain additional Events of Default and breaches have occurred and remain outstanding under Lease MSN 3361. Lessor is therefore entitled to exercise any or all of its rights and remedies under Lease MSN 3361 and/or applicable Law including its rights under Article 24 (Default of Lessee) of Lease MSN 3361.
4. By this Notice and pursuant to Article 24.6(c) of Lease MSN 3361, Lessor hereby demands immediate payment of the amount of $10,014,824 being the sum of all Base Rent which would have been due during the Lease Term of Lease MSN 3361, discounted in accordance with Article 24.9 (Present Value of Payments) of Lease MSN 3361.
Lease MSN 3396
5. The occurrence and continuation of the Lease MSN 3361 Delivery Default and the additional ongoing Events of Default under Lease MSN 3361 constitute an Event of Default under Article 24.2(q)(iii) of Lease MSN 3396. Without prejudice to the foregoing, as of the date of this Notice certain additional Events of Default and breaches have occurred and remain outstanding under Lease MSN 3396. Lessor is therefore entitled to exercise any or all of its rights and remedies under Lease MSN 3396 and/or applicable Law including its rights under Article 24 (Default of Lessee) of Lease MSN 3396.
6. By this Notice and pursuant to Article 24.6(c) of Lease MSN 3396, Lessor hereby demands immediate payment of the amount of $9,999,665 being the sum of all Base Rent which would have been due during the Lease Term of Lease MSN 3396, discounted in accordance with Article 24.9 (Present Value of Payments) of Lease MSN 3396.
IN THE FURTHER EXERCISE OF ITS RIGHTS UNDER ARTICLE 24.3(a) OF EACH LEASE, LESSOR: (I) HEREBY TERMINATES LESSEE'S RIGHT TO LEASE AIRCRAFT MSN 3361 AND LESSOR's OBLIGATIONS UNDER LEASE MSN 3361; AND (II) HEREBY TERMINATES LESSEE'S RIGHT TO LEASE AIRCRAFT MSN 3396 AND LESSOR'S OBLIGATIONS UNDER LEASE MSN 3396.
This Notice does not terminate Lessee's obligations under the Leases and such obligations (including Lessee's indemnification obligations) are ongoing. This Notice and Lessor's actions hereunder and instructions set forth herein are without prejudice to, and Lessor hereby expressly reserve and does not waive, all other rights and remedies of Lessor under the Leases, at law and at equity, with respect to Lessee's defaults under each Lease including, but not limited to, Lessor's rights to recover all past and future damages on account of Lessee's defaults. No failure or delay on the part of Lessor to exercise or enforce any right, power or remedy under any Lease shall operate as a waiver thereof, nor shall any single or partial exercise or enforcement by Lessor of any right, power or remedy under a Lease preclude any other further exercise or enforcement thereof or the exercise of enforcement of any other right. For the avoidance of doubt, the omission of a reference to any Event of Default or breach which has also occurred does not and will not prejudice, nor constitute a waiver of, any rights Lessor may have either generally, under the Leases or in respect of this Notice. This Notice will be governed by Articles 26.1 (Governing Law) and 26.2 (Jurisdiction) of each Lease, which will be deemed to be incorporated by reference herein."
"Without prejudice to the foregoing, as of the date of this Notice certain additional Events of Default and breaches have occurred and remain outstanding under Lease MSN 3361. Lessor is therefore entitled to exercise any or all of its rights and remedies under Lease MSN 3361 and/or applicable Law including its rights under Article 24 (Default of Lessee) of Lease MSN 3361."
i) there is no contractual obligation in Article 24 to identify the Events of Default relied upon: a valid notice under Article 24.3(a) could validly assert the existence of an Event of Default without specifying it;
ii) the present case is distinguishable from cases (such as ED&F Man Commodity Advisers Ltd v Fluxo-Cane Overseas Ltd [2010] EWHC 212 (Comm) and Sucden Financial Ltd v Fluxo-Cane Overseas Ltd [2010] EWHC 2133 (Comm), [2012] 2 CLC 216) where the relevant event of default involved a subjective judgement on the part of the party invoking it (in ED&F Man, it provided "we reasonably consider it necessary or desirable for our own protection"), in relation to which it has been held that it is necessary that the relevant party had in mind and relied upon the relevant event of default even though he did not mention it expressly; and
iii) that principle does not apply to Article 24.2(n) which involves no element of judgement or opinion. Here, the general principle in Boston Deep Sea Fishing & Ice Co v Ansell (1888) LR 39 Ch D 339 applies: the terminating party is entitled later to rely upon, in justifying termination, any breach which it did not rely upon or even know about at the time that it treated its counterparty's conduct as entitling it to bring the contract to an end.
"The general rule is well established that, if a party refuses to perform a contract, giving a wrong or inadequate reason or no reason at all, he may yet justify his refusal if there were at the time facts in existence which would have provided a good reason, even if he did not know of them at the time of his refusal." (§ 27-067)
"It is said if the transaction be one of very old date, that in some way deprives the master of his right to treat it as a breach of faith. As the Lord Justice has pointed out, the age of the fraud may be a reason in the master's mind for not acting on his rights; but it is impossible to say that because a fraud has been concealed for six years, therefore the master has not a right when he discovers it to act upon his discovery, and to put an end to the relation of employer and employed with which such fraud was inconsistent. I, therefore, find it impossible to adopt Mr. Justice Kekewich's view, or to come to any other conclusion except that the managing director having been guilty of a fraud on his employers was rightly dismissed by them, and dismissed by them rightly even though they did not discover the fraud until after they had actually pronounced the sentence of dismissal."
Boston was thus a case of relying on an unknown ground in order to resist a claim for breach of contract.
"143. The same conduct may be such as to give rise to a contractual right to terminate and a common law entitlement to accept a repudiatory breach. This will typically be so if (i) the guilty party has failed to make the payments stipulated by the contract, (ii) that failure either amounts to a repudiation or is, by the terms of the contract, to be treated as such, and (iii) there is a contractual right to terminate which is applicable to the circumstances giving rise to the breach. In such a case the innocent party can exercise either his contractual or his common law right of termination. Prima facie he can rely on both. He is not disentitled to rely on the latter on the ground that recourse to the former constitutes an af?rmation of the contract since in both cases he is electing to terminate the contract for the future (ie to bring to an end the primary obligations of the parties remaining unperformed) in accordance with rights that are either given to him expressly by contract or arise in his favour by implication of law. If he can rely on both there is no reason in principle why, if he terminates the contract without stating the basis on which he does so, he cannot be treated as doing so under any clause which entitles him to do so and in accordance with his rights at common law. ''Termination'' is capable of meaning both a termination pursuant to a contractual clause and the acceptance of a repudiation: Aktieselskabet Dampskibsselskabet Svendborg v Mobil North Sea Ltd [2001] 2 Lloyd's Rep 127. Even if he refers to a particular clause upon which he relies, that would not inevitably mean that he was only relying on that clause. If that were so an innocent party who, in the face of a repudiatory breach, terminated the contract by reference to a clause which was in fact inapplicable, might, on that account, ?nd himself disentitled to terminate at all.
144. The fact that service of a contractual notice of termination is not inconsistent with the acceptance of a repudiation does not, however, mean that in all cases such a notice amounts to such an acceptance. If the notice makes explicit reference to a particular contractual clause, and nothing else, that may, in context, show that the giver of the notice was not intending to accept the repudiation and was only relying on the contractual clause; for instance if the claim made under the notice of termination is inconsistent with, and not simply less than, that which arises on acceptance of a repudiation: United Dominions Trust (Commercial) Ltd v Ennis [1968] 1 QB 54, 65, 68. In the present case markedly different consequences would arise according to whether or not there was a termination under clause 14.4 or an acceptance of a repudiation. … In those circumstances it should take effect in, and only in accordance with its express terms, namely as a determination under clause 14.4."
"The Appellant's contention is inconsistent with the general principle of contract law that if a party refuses to perform a contract, giving a reason which is wrong or inadequate, or giving no reason at all, or terminates a contract under a contractual provision to that effect, the refusal or termination may nevertheless be justified if there were at the time facts in existence which would have provided a good reason for the refusal: Chitty on Contracts 29th ed paragraph 24-014. That principle is often used in relation to facts unknown to the party refusing at the time of its refusal, but there is no reason why it should not be used in relation to facts which were known to that party at that time. Waiver can apply to qualify that principle, but only in cases of, in effect, estoppel."
"Acceptance of repudiation
43. The arbitrator held that the yard had repudiated each of the contracts by the time Gearbulk sent its letter of termination. As a result counsel on both sides addressed the court at some length on whether the letters of 7 November 2003 and 4 August 2004, neither of which purported in terms to accept the yard's conduct as a repudiatory breach discharging the contract, was none the less effective to bring about that result. We were referred in that connection to a number of authorities, including Stocznia Gdanska SA v Latvian Shipping Co [2001] 1 Lloyd's Rep 537; [2002] 2 Lloyd's Rep 436 (Court of Appeal), and Dalkia Utilities Services plc v Celtech International Ltd [2006] 1 Lloyd's Rep 599. In view of the conclusion to which I have come on the construction of the contracts this question does not arise in the present case and I therefore propose to express my view on it shortly.
44. It must be borne in mind that all that is required for acceptance of a repudiation at common law is for the injured party to communicate clearly and unequivocally his intention to treat the contract as discharged: see Vitol SA v Norelf Ltd [1996] 2 Lloyd's Rep 225; [1996] AC 800, pages 810G to 811B per Lord Steyn. If the contract and the general law provide the injured party with alternative rights which have different consequences, as was held to be the case in Dalkia Utilities v Celtech, he will necessarily have to elect between them and the precise terms in which he informs the other party of his decision will be signi?cant, but where the contract provides a right to terminate which corresponds to a right under the general law (because the breach goes to the root of the contract or the parties have agreed that it should be treated as doing so) no election is necessary. In such cases it is suf?cient for the injured party simply to make it clear that he is treating the contract as discharged: see Dalkia Utilities v Celtech, para 143 per Christopher Clarke J. If he gives a bad reason for doing so, his action is nonetheless effective if the circumstances support it. That, as I understand it, is what Rix LJ was saying in Stocznia Gdanska SA v Latvian Shipping Co [2002] 2 Lloyd's Rep 436, para 32, with which I respectfully agree.
45. In the present case the parties accept, and indeed the arbitrator has found, that the breaches on the part of the yard which entitled Gearbulk to terminate the contracts were in each case suf?cient to amount to a repudiation. … in its letters of 7 November 2003 and 4 August 2004 Gearbulk purported to terminate the contract pursuant to article 10.1(b) and (c) and not under the general law, but each of the letters made it clear that it was treating the contract as discharged and in those circumstances each was suf?cient to amount to an acceptance of the yard's repudiation. In its letter of 30 November 2004 Gearbulk sought to rely on both. Mr Dunning said that letter was equivocal as between reliance on the terms of the contract and reliance on the general law. Perhaps it was, but it was quite unequivocal as to Gearbulk's intention to treat the contract as discharged and that was all that was necessary."
"31. Thus in the case of contracts 3-6, they did not come to an end pursuant to clause 5.05 by reason of the yard's notices of rescission, even if those notices may have acted at common law as marking an acceptance of Latreefers' repudiation of those contracts by way of anticipatory breach. The judge indeed found that that was what had happened. He said (at para 179):
"It is clear that no particular form or formality is required for the acceptance of a repudiation. Although the letters referred to the termination under clause 5 of the contract, they made it clear that the Yard considered the contract at an end and neither party was under an obligation of any further performance. If the Yard had a right to terminate for repudiation, the fact that they did not set that out does not in my view make any difference, as it is well established that a party terminating a contract can rely on grounds other than those he gives. The important matter is that the letters unequivocally stated that the contractual obligations were at an end. I therefore conclude that there was an acceptance by the Yard."
32. It is established law that, where one party to a contract has repudiated it, the other may validly accept that repudiation by bringing the contract to an end, even if he gives a wrong reason for doing so or no reason at all. Mr Glennie did not dispute that principle. …"
"The principle underlying the Boston Deep Sea Fishing case has never been put forward as being that the unknown but justified ground for accepting a repudiation is to be read into the letter or other communication by which the unjustified reason is asserted. I do not see that the principle can or should be understood as extending that far. It does not allow the innocent party to assert that it did accept repudiation on the correct (though unknown) ground; rather it allows that party to meet a claim that its conduct in terminating the contract, though apparently unjustified because done on the wrong ground, is to be taken as justified because it could have been done on the right ground, not because it was done on the right ground. It operates as a shield against a claim for damages on the basis of wrongful termination, not as a sword to claim damages (for the future) on the basis of justified termination. For that reason it seems to me that, if Leofelis is to overcome the problem of its reliance on the German injunction in the letters of 14 and 28 September 2007, which is a causation issue, it must do so by showing that the German injunction was so closely connected with the wrongful SIA arrangements that the termination of the contract by the letter of 28 September 2007 cannot be seen as independent of Lonsdale's breach of contract, but rather that it was part of the chain of causation connecting Lonsdale's repudiatory breach with Leofelis' termination of the contract. In effect Leofelis would need to prove that, if Lonsdale had not undertaken its course of action aimed at interfering with Leofelis' exclusivity under the 2002 licence and favouring Mr Schotsman's companies, it would not have sought or obtained the German injunction, or at any rate that, once Evans-Lombe J had held it to have been unjustified, Lonsdale would have had it discharged." (§ 33)
Lewison LJ and Pill LJ agreed. Pill LJ added:
"… If the premature determination of the contract is for reasons other than those that subsequently emerge, a claim for post-termination loss cannot be sustained. Here, it is submitted, the reasons are sufficiently linked with those relied on at the time to enable a claim for post-termination loss to be brought." (§ 44)
Leofelis was given permission to seek to reformulate its claim on that basis, i.e. to plead facts that could arguably show the necessary causal link between the alleged repudiatory breach of contract and its own termination of the licence (§ 37).
"… The loss of bargain damages claim requires EE to show that the termination of the contract, which created the loss of bargain, resulted from the repudiatory breach or renunciation by Phones 4U that it is presently to be assumed EE might prove at trial. That in turn requires EE to show that the contract was terminated by its exercise of its common law right to terminate for that breach, respectively that renunciation. (No allegation is made, akin to that made in Leofelis v Lonsdale on appeal, that the termination resulted in any event from (the facts constituting) the alleged repudiation.) If, as Phones 4U says, EE's termination letter communicated only a termination under clause 14.1.2 independent of the repudiatory breach or renunciation now alleged, then the contract was not terminated at common law for repudiation. That it could have been so terminated (if EE makes good its allegation of repudiation) cannot be used to re-characterise the facts." (§ 117)
"Shell Egypt was also criticised by Liu [2011] LMCLQ 4 …. Leaving aside the point actually decided by Tomlinson J (as to the purport of Shell's termination letter, on its proper construction), Liu's criticism of the judge's approach as a matter of principle seems to me to have depended on the proposition that it is sufficient, for the loss of bargain claim at common law, that the claimant should have communicated unequivocally that it treated the contract as discharged, whatever it might say as to why. There were dicta that could be read as supporting that proposition (e.g. per Rix LJ in Stocznia v Latvian Shipping at [32], per Moore-Bick LJ in Stocznia v Gearbulk at [44]-[45]). However, it has now been authoritatively rejected by Leofelis v Lonsdale. It remains true, as Liu emphasised, that 'acceptance' of a repudiation requires no particular formality or form of words (see Vitol v Norelf). But it must communicate a decision to terminate for the repudiation later said to found the claim, in exercise of the common law right to terminate arising upon that repudiation, if a normal loss of bargain claim at common law is to be viable (i.e. leaving aside the inventive alternative claim suggested on appeal in Leofelis v Lonsdale). Otherwise, the claimant cannot say the termination and therefore its loss of bargain resulted from the repudiation sued upon." (§ 122)
Andrew Baker J held that if a termination letter communicates clearly a decision to terminate only under an express contractual right that has arisen irrespective of any breach, then it cannot be said that the contract was terminated for breach, so a claim for damages for loss of bargain at common law cannot run (§ 121).
"103. Lombard accepts that a party who wishes to exercise a contractual right of termination by notice must strictly comply with any conditions for the exercise of the right: Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd [1997] AC 749, 773 and 776. Ascertaining what those conditions are is an exercise in the construction of the contractual right (embracing within that term both the interpretation of the words used and any implications which the law requires to be made).
104. Reverting to clause 9.2(a), it requires that:
i) the Notice be sent after the occurrence of an Event of Default; and
ii) the Notice must cancel the Facility and require the Borrower immediately to repay the loan together with accrued interest and all other sums payable under this Agreement.
105. Clause 8.1 of the Mortgage provides that "upon the occurrence of an Event of Default and at any time thereafter, the Lender may by written notice to the Borrower declare the security constituted by this Mortgage to have become enforceable".
106. Neither provision requires the Event of Default to be identified, and I am not persuaded that this is a necessary implication. There is no "cure period" provided for, such that it might be said that the borrower needs to know what default is being contended for in order to address it. In circumstances in which it is possible to terminate at common law for breach without identifying (or correctly identifying) the breaches justifying termination (Boston Deep Sea Fishing v Ansell (1888) 39 Ch D 352, 364), and where this is the usual position so far as contractual termination clauses are concerned (Reinwood Ltd v L Brown & Sons Ltd [2008] EWCA Civ 1090, [51]) I am satisfied that it cannot be said to be so obvious a requirement of clause 9.2 that the Event of Default justifying termination is identified that this goes without saying. Those conclusions derived from first principles are amply supported by authority:
i) In Byblos Bank SAL v Al-Khudhairy [1986] 2 BCC 99, 548, Nichols LJ permitted the bank to rely on a ground for accelerating the debt and appointing a receiver (the borrower's inability to pay its debts) which had not been invoked prior to appointment.
ii) In Brampton Manor (Leisure) Ltd v McLean [2007] BCC 640, Evans-Lombe J made a finding to similar effect: see [11], [43] and [52].
107. In circumstances in which clauses 9.2 of the Loan Agreement and 8.1 of the Mortgage do not require Lombard to identify the Event(s) of Default relied upon in the Notice I am satisfied that the validity of the Notice is not impugned if Lombard chooses to mention one such ground which has not in fact arisen. As I have stated, clause 9.2 does not form part of a machinery which envisages Skyjets having an opportunity to consider and cure any breach (nor does clause 8.1 of the Mortgage). In these circumstances, Skyjets is no worse off by reason of the inclusion of an invalid ground than if nothing had been said at all."
"24.6 LESSEE Liability for Damages. If an Event of Default occurs, in addition to all other remedies available under applicable Law, LESSOR and each other Indemnitee has the right to recover from LESSEE, and LESSEE will indemnify LESSOR and each other Indemnitee on LESSOR's first written demand against, any Expenses which LESSOR or any other Indemnitee may sustain or incur directly as a result, including …" (my emphasis)
The clause thus contemplates that the ensuing heads of recoverable expenses, including accelerated rent under Article 24.6(c), are items recoverable "as a result of" the Event of Default.
(G) WAS LAUDAMOTION OBLIGED TO TAKE MSN 3361 ON 7 MAY 2020?
i) whether Peregrine validly set a Scheduled Delivery Date of 7 May 2020, or whether (as Defendants suggest) its tender of MSN 3361 on that date was invalid because it had failed to consult Laudamotion, or to notify or give it reasonable notice of the delivery date, pursuant to Article 3.2;
ii) whether MSN 3361 was, or (more precisely) was contractually to be regarded as being, in deliverable condition on 7 May 2020, having regard to:
a) the lack of the documents referred to in Exhibit B § 4, i.e. an ECoA, CAT.IDE statement and EASA letter;
b) the fact that it was still on lease to Flynas;
c) the Claimants having prepared it for storage; and
d) the condition of the aircraft including (in particular) its documentation.
(1) Consultation, notification and reasonable notice
"As of the date of this Lease, delivery of the Aircraft from Prior Lessee to LESSOR and LESSOR to LESSEEE is scheduled to occur during March 2020. LESSOR will notify LESSEE from time to time and in a timely manner of the exact date on which LESSOR expects Delivery to take place (and LESSOR agrees to consult with LESSEE prior to making such a determination as to such date and shall provide LESSEE with reasonable notice in respect of such date), (the 'Scheduled Delivery Date')."
i) A Scheduled Delivery Date, giving rise to an obligation to accept delivery of the aircraft, could only be validly set by complying with Article 3.2. Alternatively, the Lessor could not take advantage of its own breach of contract by tendering an aircraft for delivery on a date that had been set without complying with the obligations to consult and provide timely and reasonable notice set out in Article 3.2.
ii) By way of further alternative, compliance with Article 3.2 of the Scheduled Delivery Date was a condition precedent to any obligation to take delivery of the aircraft, cf. Lewison, "Interpretation of Contracts", §16.11:
"The expression condition precedent is also used to describe a contingency which must be fulfilled in order to bring a particular contractual obligation into operation. That contingency may be the performance by one party of a contractual obligation of his own, or it may be some other event (such as the giving of a notice)".
As Flaux J stated in AstraZeneca UK Ltd v Albemarle International Corp [2011] EWHC 1574 (Comm),:
"… in the absence of an express term, performance of one obligation will only be a condition precedent to another obligation where either the first obligation must for practical reasons clearly be performed before the second obligation can arise or the second obligation is the direct quid pro quo of the first, in the sense that only performance of the first earns entitlement to the second." (emphasis added)
That was obviously the case here. Otherwise, the Lessee would have the invidious choice of risking an Event of Default by refusing to accept the aircraft, or accepting the aircraft without having had a chance to complete its verification exercise and finding itself without recourse for any defects by reason of the "as is, where is" and "conclusive proof" provisions of Articles 8.1 and 8.4 (quoted earlier).
iii) Article 3.2 obliged the Lessor to "consult" the Lessee "prior to making a determination as to such date", i.e. the exact date on which Lessor expects delivery to take place.
iv) However, there was no consultation about 7 May 2020 being the delivery date, even though there was nothing to prevent such consultation (as Mr Anderson accepted in cross-examination). Peregrine simply informed Laudamotion on 5 (or 1) May 2020 that it would tender the aircraft for delivery on 7 May. Peregrine had never asked Laudamotion about that date, or any other around that time, still less with an open mind. The lease anticipated delivery in or around March 2020, and there had been some discussions of June delivery, but no suggestion of delivery in early May.
v) Peregrine was also obliged under Article 3.2 to give "reasonable notice" of the delivery date. What constituted "reasonable notice" is to be determined objectively, as at the time of giving notice, having regard to the purpose for which notice was required (cf. Hamsard 3147 v Boots [2013] EWHC 3251 (Pat)). Here, after receiving notice of the delivery date, Laudamotion would need time to arrange for representatives to return to Fokker during the midst of a global pandemic, physically inspect MSN 3361, complete its document review, ensure that all issues concerning the condition of the aircraft and its documents had been resolved (so that Laudamotion could be satisfied that it could sign a Technical Acceptance Certificate accepting the aircraft "as is, where is"), and arrange for two pilots to attend Fokker for the ferry flight.
vi) Very short notice was given despite the Defendants having made clear to the Claimants, on 25 March 2020, that "Lauda will still require a final physical inspection prior to TA [technical acceptance], since they're aware the aircraft wasn't ready the last day I was onsite i.e. Saturday 14th March." As at 27 March 2020, there were 186 open items in the OIL which included the review of documents concerning 41 repairs, 40 mandatory service bulletins, dealing with missing DFPs and certificates, reviewing a revised electrical load report, loose equipment inventory, the records inventory and engine fan DFPs, reviewing the final statements and statuses, and being ready and able to sign off the Technical Acceptance Certificate. The best evidence of the amount of time Laudamotion needed to complete its records inspection was Eirtech's email of 1 April 2020 to Ryanair, when Eirtech's Head of Technical Services told Ryanair's Mr Clear that it would take Eirtech 10 days to complete work on the 186 open items assuming the documents were readily available. Laudamotion also needed time to input the information onto its systems.
vii) Under Exhibit B § 2, Peregrine was obliged to provide for review all the aircraft's records for a period of 10 Business Days "prior to the Scheduled Delivery Date". "Reasonable notice" must allow Laudamotion to know at least 10 Business Days prior to the Scheduled Delivery Date when that date is, so it can exercise its right to 10 Business Days' inspection of the documents.
viii) Even if Laudamotion's 1 May 2020 letter is deemed to have been delivered on that date, it was sent at 5.51pm on the Friday evening before a Bank Holiday weekend and gave only two Business Days' notice of the delivery date. ("Business Day" is defined in the lease as a weekday on which the banks are open for business where the Lessor's bank is located (the US) and in Austria. Austria observes a public holiday on 1 May.)
ix) It is incorrect to take account of the Claimants' letter dated 22 April 2020. That letter merely said that "the 2019 Aircraft will be tendered for Delivery in accordance with the Lease Agreements", but gave no date and did not fulfil any of the requirements of Article 3.2.
x) The Claimants are wrong, on the facts and the law, to suggest that their obligations under Article 3.2 were modified or obviated in some way by Laudamotion having by early May stopped work on the document review for five weeks and indicated that it would not complete it because it would not accept the four aircraft; and wrong to suggest that Peregrine was not required to give a longer period of notice for Laudamotion to complete a task it had made clear it would not complete and which it in fact made no attempt to complete.
xi) As to the facts, Mr Anderson "invented" a call between Mr Kelly and Mr Sorahan which he said "superseded" any conversation between Mr Merry and Mr Norton; and Mr Peacock "made up" the content of the conversation between Mr Norton and Mr Merry on 1 May 2020, by saying Mr Norton had told Mr Merry that Laudamotion would not take the four aircraft: neither of those matters having been pleaded or put to Mr Norton. Mr Norton made clear that Laudamotion did not say to Mr Merry it would not take the four aircraft, and that Laudamotion was trying to find an agreed way forward with the Claimants. Mr Akhrif said in his email to Mr Spencer dated 27 March 2020 "I'm sure Colin Merry and John Norton will be discussing the way forward/new arrangements for these transitions so we will react/plan when we hear back from them". During the discussions between Mr Merry and Mr Norton it is common ground that they were discussing June delivery dates. No-one ever suggested that Laudamotion go back to Fokker or start reviewing documents again. Laudamotion did not say it would not accept the aircraft and would not complete its review of the documents. On the contrary, on 27 April and 1 May 2020 Mr Norton asked Mr Merry whether the Claimants were willing to accept rent reductions on all four aircraft (and the evidence shows Mr Anderson considering the financial implications of this).
xii) As to the law, none of those matters obviated the need for Peregrine to consult and give timely and reasonable notice if it wanted to make an earlier delivery of MSN 3361 in May 2020. The underlying purpose of that consultation and reasonable notice was to give Laudamotion a meaningful opportunity to participate in the delivery process and in particular to decide whether it could accept the aircraft.
xiii) The Claimants cite Lewison, "Interpretation of Contracts" § 6.135, stating that "where performance of the contract cannot take place without the cooperation of both parties, it is implied that cooperation will be forthcoming". However, Article 3.2 expressly obliged the Claimants to "consult with the LESSEE prior to making a determination" about the Scheduled Delivery Date and to give reasonable notice.
xiv) A duty to cooperate will be implied into a contract only if it is necessary to make the contact workable: see the general test stated in Marks & Spencer Plc v BNP Paribas Securities Services Trust Co (Jersey) Ltd [2015] UKSC 72; and, in relation to duties of cooperation in particular, Mona Oil Equipment & Supply Co Ltd v Rhodesia Railways Ltd [1949] 2 All ER 1014, 1018E and Ukraine v Law Debenture Trust Corp Plc [2018] EWCA Civ 2026 § 207. Proof of mere normality of practice, or even of a high degree of desirability, falls far short of establishing the existence of a contractual duty owed by the buyer to be implied as a contractual term (Siporex Trade S.A. v. Banque Indosuez [1986] 2 Lloyd's Rep 146, 161-162 per Hirst J). There is no need to imply any such term into Article 3.2: the Claimants were able to comply with it, without needing the Defendants' cooperation.
xv) Moreover, there is also no need to imply a term that the Lessee would proceed diligently with the document review and other pre-delivery processes. The terms of the lease required the Lessor to put the aircraft in deliverable condition (Article 7.4.8), and Exhibit B §§ 2 and 3 give the Lessee the right, rather than the duty, to inspect the aircraft and its documents. The duties imposed on the Lessee in relation to delivery (by Articles 6.5, 7.1 and 7.2) of the lease do not include a duty of the kind the Claimants propose. The lease is workable without the need to imply such a term. The proposed implied term would in any event be too vague.
xvi) These points apply a fortiori where, as here, the lease contains an express term relating, in substance, to cooperation and which requires a request first to be made by the other party. Article 27.11 provides:
"Further Assurances. Each party hereto agrees from time to time to do and perform such other and further acts and execute and deliver any and all such other instruments as may be required by Law, reasonably requested by the auditors of the other party or requested by the other party to establish, maintain, protect or perfect the rights, interests and remedies of the requesting party or any Relevant Party or to carry out and effect the intent and purpose of this Lease and the other Operative Documents."
The Claimants' proposed implied term would cut across this scheme.
"I understood that Mr Merry had a discussion with Mr Norton in the morning of 1 May to find out if there was a commercial resolution and the answer was they weren't taking the aircraft. A deal team – our meeting was convened after that call. Again, the contents are privileged, but the outcome of that was we were going to proceed and deliver, because everything was in place."
Mr Peacock did not refer to the Norton/Merry 1 May conversation in his witness statement, but plainly that conversation did occur, and, as Mr Peacock went on to say, he was the individual in legal and leasing responsible for Ryanair and generally informed by Mr Merry of correspondence and discussions. The Claimants did not waive privilege over the subsequent conversation between Mr Merry and Mr Peacock, and hence cannot rely on Mr Peacock's account of what Mr Merry told him about the conversation with Mr Norton. However, there was and is no proper basis for the suggestion that Mr Peacock lied.
i) The Defendants did not attempt to lead any factual evidence that it was impossible for the Claimants to deliver, or for the Defendants to take delivery of, the 2019 aircraft because of Covid-19. The highest that it is put in the Defendants' witness evidence (which is not, in any event, evidence from anyone involved in the technical side of delivery) is that the delivery of aircraft became slower from March 2020.
ii) No Material Deviations are alleged by the Defendants in respect of the physical condition of the 2019 aircraft. All the pleaded complaints relate to alleged deficiencies in aircraft documentation. However, the records review was conducted almost entirely remotely by the Claimants' and the Defendants' consultants, and (as Mr Gwihs accepted in cross-examination) that records review could have continued despite Covid-19.
iii) The unchallenged evidence of Mr Anderson and Mr Akhrif was that the Claimants continued to deliver and take redelivery of aircraft throughout the pandemic. Moreover, the documents show, and Mr Norton accepted in cross-examination, that Laudamotion itself took delivery of an Airbus A320 aircraft (MSN 5015) from another major lessor, Avalon, in or around June 2020. This exposes the lack of realism in the Defendants' approach. It cannot sensibly be said that the pandemic caused any insurmountable difficulties in delivering the 2019 aircraft. The evidence suggests that the MROs continued to function throughout, and that parts and materials continued to be moved across the world, albeit with some delays from time to time.
iv) The real relevance of the pandemic is that it explains the Defendants' commercial motivation for unilaterally disengaging from the delivery process for the 2019 aircraft in late March 2020 and wrongly refusing to accept delivery of MSN 3361 when it was tendered by Peregrine on 7 May 2020.
v) It is common ground on the statements of case that the process of delivery of a commercial aircraft is one "requiring the active participation, cooperation and collaboration" of the lessor, lessee, and others; and thus the lessor's and lessee's technical teams work together to identify, record and correct deviations from the requirements of the lease. The leases are premised on a willing lessee: they simply do not envisage a situation in which the lessee disengages from the delivery process, withdraws its technical team, refuses to accept the aircraft, and then seeks to justify that by reference to alleged deviations not articulated before or even at the time of tender.
vi) Once the process of delivery commences, and until it concludes, each party owes the other a contractual duty of co-operation. That is "an ordinary implication in any contract for the performance of which co-operation is required" (Swallowfalls Ltd v Monaco Yachting & Technologies SAM [2014] EWCA Civ 186 § 32). Here, it is common ground that co-operation was at a practical level essential; and it follows that there was an implied contractual obligation to co-operate, owed by both lessor and lessee. Thus once the delivery process commenced, neither party was entitled unilaterally to withdraw its co-operation unless and until the lease were terminated.
vii) Laudamotion's withdrawal of its technical team on 26 March 2020 involved the unilateral cessation to comply with its contractual duty of co-operation. As a result, its failure to progress matters after 26 March 2020 was entirely due to its failure to comply with a critical obligation. Laudamotion is not entitled to rely on that failure on its part to say that it required more time to accept delivery of the aircraft by early May 2020, particularly where it had indicated that it had no intention of accepting the aircraft and withdrawn from the steps necessary to accept the aircraft.
viii) The Article 3.2 duty to notify to Lessee from time to time when delivery is expected contemplates a lessee willing to take delivery. While Laudamotion was engaged, there was a dialogue about delivery dates. For example, the documents show discussions in early March about possible delivery dates including 20 March, consistent with the timing of the borescope tests and demo flight (usually done about two weeks before delivery). But once Laudamotion instructed its technical team to disengage, Laudamotion withdrew from that dialogue. Far from Peregrine having decided not to tell Laudamotion what the revised schedule was, Ryanair told the technical team not to engage. Mr Spencer's e-mail of 26 March 2020 made clear that they would only be back in contact if instructed to re-engage. This never happened.
ix) In any event, a failure to update on developments in relation to likely delivery dates would not render invalid a determination by Peregrine of the Scheduled Delivery Date under Article 3.2 even if Laudamotion had wanted the aircraft.
x) Similarly, an obligation to "consult" only works in relation to a party who is engaged in the delivery process. It is a co-operative process and once Laudamotion withdrew its co-operation any "consultation" would have involved whistling in the wind. By 1 May 2020, Laudamotion had not merely disengaged from the delivery process but made it abundantly clear that in no circumstances would it accept delivery. One cannot realistically continue to consult with someone who is not engaging and does not want the aircraft. In that situation, there cannot be meaningful consultation with the Lessee because of the Lessee's own stance; and of that the Lessee cannot complain.
xi) In any event, a failure to consult does not invalidate the appointment by the Lessor of the Scheduled Delivery Date.
xii) As to notice, Article 3.2 provides for the giving of "reasonable" notice rather than requiring a fixed amount of notice. What is reasonable for the purposes of Art 3.2 is contextual and depends on the circumstances pertaining at the time. Moreover, what is reasonable at a particular point in time must take account of what has gone before as well as what remains to be done, including that on 22 April 2020 the Lessor had made clear it would tender the aircraft for delivery. Before Laudamotion disengaged from the delivery process, what the parties had in mind was a delivery in short order, by the end of March 2020. By 1 May 2020, the demonstration flight had long since taken place and MSN 3361 was physically ready. All that remained was for Laudamotion to satisfy certain conditions precedent on its side (which in the event were waived by Peregrine tendering the aircraft without their being met) and complete its document review.
xiii) As noted above, the Lessee cannot, having failed to comply with its duty of co-operation and failed to progress the delivery process, then say that it ought to be allowed more time to do the things it would have done had it not withdrawn its co-operation (especially where it indicates that it has no intention of accepting the aircraft and invites the Lessor to seek other lessees for the aircraft). By early May, not merely had Laudamotion spent approximately five weeks not working on that document review but it had made plain that it would not complete it because it would not accept the aircraft. In these circumstances, Laudamotion was not entitled to a longer notice period than it was given.
(2) 'Deliverable' condition: the Exhibit B § 4 documents (ECoA etc.)
(a) Relevant provisions
"Nothing in this Lease will obligate …. (ii) LESSEE to accept delivery of the Aircraft from LESSOR, if the other party has not complied with its respective obligations contained in Articles 7.1, 7.2 and 7.4."
"7.4 Conditions Precedent to be Satisfied by LESSOR. On or before the Scheduled Delivery Date, LESSOR shall deliver the following to LESSEE, each in a form and substance reasonably satisfactory to LESSEE and at no cost to LESSEE:
…
7.4.8 the Aircraft conforms to the condition set forth in Exhibit B or otherwise conforms to such condition whereby LESSEE is obligated, pursuant to Article 6.2, to accept delivery of the Aircraft".
"(a) On or before the Delivery Date, LESSOR will provide LESSEE a valid export certificate of airworthiness with respect to the Aircraft.
(b) At LESSEE's request, LESSOR at its cost will demonstrate that the Aircraft meets the requirements for issuance of an EASA Certificate of Airworthiness for transport category aircraft issued by an EASA member country by delivering to LESSEE at LESSOR's option either a Certificate of Airworthiness issued by an EASA member country (if the Aircraft is already or is to be registered in an EASA member country) or a letter or other document signed by an aviation authority of an EASA member country or another Person acceptable to LESSEE stating that such Person has inspected the Aircraft and Aircraft Documentation (including records and manuals) and has found that the Aircraft meets the requirements for issuance of a Certificate of Airworthiness for transport category aircraft issued by an EASA member country in accordance with EASA Part 21 and, in addition, meets the operating requirements of AIR OPS Part-CAT.IDE and Eurocontrol with no restrictions imposed."
(b) Facts
i) an ECoA (subparagraph (a));
ii) a CAT.IDE statement (subparagraph (b)); and
iii) an EASA compliance statement (subparagraph (b)).
The lease imposed no obligation on Laudamotion to make a specific request for these items. However, Laudamotion did in fact identify the first two as being required, in the OIL: on 3 January 2020 for the ECoA (item FS004) and on 20 March 2020 for the CAT.IDE statement (item FS109). In addition, an internal email from Mr Akhrif dated 27 April 2020 stated "The CAMO will have the ARC ready this week, this was requested by Lauda, as for compliance with ops mod CAMO the Lauda consultant had asked for it and the CAMO is ready to issue it." Mr Akhrif explained in his oral evidence that the ARC recommendation is a document sent to AustroControl recommending the issue of a certificate of airworthiness, and that it includes the EASA compliance statement.
i) On 24 April 2020, the Claimants' Deputy Chief Technical Officer, Mr Burke, sent an email to Mr Akhrif underlining that delivery of MSN 3361 was "subject to Cayman CAA".
ii) On 30 April 2020, Mr Akhrif asked the Cayman CAA whether Flynas had submitted the application for an ECoA. The Cayman CAA responded the same day, saying the application was still being prepared.
iii) On 7 May 2020, MSN 3361 was tendered at 9.18am and Laudamotion responded at 10.25am.
iv) Thereafter, at 18.34 on 7 May 2020, Mr Akhrif sent an email to the Cayman CAA stating, "can you please advise when we can expect the ECoA to be issued", and the next day said, "We badly need this ECoA, so anything we can do from our side as Lessor, please let us know".
v) On Sunday 10 May 2020, the Cayman CAA informed Mr Akhrif that Flynas had provided it with additional information for the ECoA.
vi) The ECoA was issued on 12 May 2020. However, it was never provided to Laudamotion.
i) In the evening of 7 May 2020, Mr Akhrif chased Celairion (the CAMO) to generate the EASA compliance letter and CAT.IDE statement, stating "Lauda is arguing these items are holding the delivery".
ii) They then had a call, and Mr Akhrif sent an email to Ms Bettinger of Celairion quoting part of the language of Exhibit B § 4 to indicate what Mr Akhrif was seeking.
iii) Celairion responded late on 7 May saying that they would draft a letter for Mr Akhrif's review and would sign it once he was happy with it.
iv) At 11.20am on 8 May, Celairion sent an unsigned draft to Mr Akhrif. There were then exchanges about the content of the draft before it was signed on 13 May 2020.
v) The CAT.IDE statement and EASA compliance letter were never provided to Laudamotion.
(c) Whether the documents needed to be provided on 7 May 2020
i) The use of "Delivery Date" in Exhibit B § 4 is deliberate and is to be contrasted with the use of "Scheduled Delivery Date" in § 2. The obligation is to provide the document, at the latest, "On" the Delivery Date – that is, the date of Delivery, which as defined includes "acceptance of the Aircraft by LESSEE". This formulation "On or before" a particular date rather than "Prior to" (used in § 1) is important: the baseline obligation on the Lessor is not to provide the ECoA prior to Delivery taking place, but rather to provide it on the day that Delivery is intended to take place consensually. It assumes a willing Lessee. If Delivery is not feasible as envisaged by the lease, because the Lessee is not prepared to accept the aircraft at all, there can be no Delivery Date as defined.
ii) In other words, the obligation to "provide" the ECoA arises if the Lessee is willing in principle to take delivery. If the Lessee makes plain prior to the time fixed for delivery that it will not, whatever is done, take delivery, there is necessarily no obligation to provide the ECoA because the Delivery Date will never occur.
iii) In the present case, Laudamotion made entirely clear well before 7 May (in particular, by the letter dated 20 April 2020) and on 7 May 2020 itself (by its letter of that date, which asserted that the lease was void) that it would not take delivery whatever the state of the documents in relation to MSN 3361. The result was that there was no contractual obligation to provide the ECoA as at 7 May 2020.
iv) The same analysis applies to the CAT.IDE statement and EASA compliance letter. Exhibit B § 4(b) does not refer to a specific time for compliance. By implication, the relevant time is the same as provided by para 4(a), that is, no later than the Delivery Date.
v) Thus the fact that the experts agreed that the absence of the documents required by Exhibit B § 4 can be regarded as material is not determinative. Whilst the documents were not actually available on 7 May 2020, each was available in short order thereafter. If it had been the case that the documents could not be available (for example, because the condition of the aircraft as at 7 May 2020 meant that they could be issued), that would have been a Material Deviation. But in circumstances where there was nothing about the condition of MSN 3361 or its documents to prevent the documents required by Exhibit B § 4 from being issued then, looked at as at 7 May 2020, their being issued in short order was an inevitability. The Claimants were plainly willing and able to obtain these documents in short order at their own expense and certainly within the meaning and timescale envisaged by Article 6.2.
vi) The process of delivering the aircraft was one requiring the co-operation of both parties. Had Laudamotion been engaged in the process (that is, had it been performing its contractual duty to co-operate, rather than simply refusing to engage in or take any meaningful part in the delivery process after 26 March 2020), then the position in relation to the Exhibit B § 4 documents would have been the subject of dialogue. Dialogue between the parties would have demonstrated that the documents would become available in very short order. Their absence at 7 May 2020 was therefore not a Material Deviation.
vii) Where the Defendants were not willing to accept the aircraft and any deviation which might have been demonstrated could have been cured in short order (in this case well in advance of the Final Delivery Date), there was no non-compliance with Exhibit B and certainly not one which could properly be deemed material.
viii) Moreover, Article 6.2 requires that "LESSOR and LESSEE agree to co-operate with each other to ensure that, to the extent reasonably possible, any such delay is minimized" (the reference here to "any such delay" being to any delay to delivery caused by the existence of properly demonstrated Material Deviations). This recognises that it is in the interest of neither party for there to be unnecessary delay. In a case in which a particular document is absent at the time the aircraft is tendered, but will shortly be available, that duty requires the Lessee to accept the aircraft with the document to follow once it is available, subject to the Lessee's rights referred to in the preceding sub-paragraph.
"If LESSEE is able to demonstrate that at Delivery there are deviations from the condition set forth in Exhibit B which are material or affect the airworthiness of the Aircraft ('Material Deviations'), LESSEE will not be obligated to accept the Aircraft unless LESSOR corrects such Material Deviations at its own cost. …"
(d) Did Laudamotion demonstrate a Material Deviation at the required time
"If LESSEE is able to demonstrate that at Delivery there are deviations from the condition set forth in Exhibit B which are material or affect the airworthiness of the Aircraft ('Material Deviations'), LESSEE will not be obligated to accept the Aircraft unless LESSOR corrects such Material Deviations at its own cost. In the event that any Material Deviations have not been corrected by the Final Delivery Date, either party may terminate this Lease within 10 Business Days of the Final Delivery Date and in the event of such termination, neither party will have any further liability to the other party except that LESSOR will pay to LESSEE an amount equal to the amount of any prepaid Base Rent. If neither party gives notice of termination within such 10 Business Days, both parties lose all right to terminate under this Article 6.2 unless otherwise agreed in writing by the parties. Without prejudice to the foregoing, LESSOR and LESSEE agree to co-operate with each other to ensure that, to the extent reasonably possible, any such delay is minimized.
If LESSEE is able to demonstrate that at Delivery there are deviations from the condition set forth in Exhibit B and such deviations do not affect the airworthiness of the Aircraft or such deviations are not material, then (a) LESSEE will be obligated to accept the Aircraft in its "AS IS" condition with such deviations, and subject to each and every disclaimer and waiver set forth in Article 8, and (b) LESSOR and LESSEE will at Delivery (by express statement by LESSOR on the Acceptance Certificate and not otherwise) mutually agree an appropriate amount of compensation payable to LESSEE for the cost of rectifying each such deviation or adjust the return conditions of the Aircraft set forth in Article 22 accordingly." (paragraph break interpolated)
"Exhibit B sets out various conditions that must be complied with before Delivery can occur. These conditions have not been satisfied by the Lessor. In particular, without limitation, we refer to Article 1 (Technical Report), Article 2 (Full Aircraft Documentation Review), Article 3 (Aircraft Inspection) and Article 4 (Certificate of Airworthiness Matters) of Exhibit B, none of which have been complied with by the Lessor as required by the Lease Agreement."
i) The demonstration must be made at the time of tender. It is not enough, for example, that there was an item in an OIL at some point in the past, particularly in circumstances where the Lessee has withdrawn its technical team and ceased to update the OIL (it being the Lessee's responsibility to update the OIL by closing items).
ii) Article 6.2 requires co-operation. There is, first, an express obligation in the middle of the clause to co-operate to minimise delay. Secondly, in relation to non-material deviations, the clause requires a process of agreement between the parties: either to agree monetary compensation or an adjustment of the return conditions.
iii) The process of identifying those Material Deviations is part of the overall co-operative process of delivery. For the Lessee to "demonstrate" the existence of Material Deviations requires (a) that it has in fact ascertained their existence as at the time of the purported demonstration, and (b) that it then identifies them with specificity. It is not open to a Lessee to assert in a state of ignorance the existence of Material Deviations in a wholly scattergun manner without regard to its actual state of knowledge or the duty of co-operation. Such "demonstration" would allow the Defendants to take advantage of the wholesale unilateral disengagement from the process of delivery since late March 2020. The Defendants effectively disabled themselves from demonstrating anything about the prevailing condition of MSN 3361 or its records after 26 March 2020.
I return to these submissions later, after considering the Defendants' case on this issue.
i) Nothing in Article 6.2 either (a) says the Lessee must demonstrate anything, or (b) says that unless it does so, it must accept the aircraft.
ii) The focus is on the state of the aircraft, not what the Lessee does: the words used are not 'If Lessee demonstrates', but 'If Lessee is able to demonstrate', that is, what it could do rather than what it actually does do. No time for the demonstration is specified: 'at Delivery' relates to when the condition of the aircraft is measured, not when the demonstration is made (it is 'if Lessee is able to demonstrate that at Delivery there are deviations…', not 'if at Delivery, Lessee is able to demonstrate that there are deviations').
iii) On that interpretation, it does not matter that the word 'Delivery' is a defined term which includes acceptance.
iv) The lease provides no contractual standard for how any demonstration must occur. "Demonstrate" does not ordinarily mean allege with specificity as the Claimants suggest. If it is given its ordinary meaning, then the Claimants' approach to Article 6.2 would mean that a Lessee who could identify a Material Deviation but not prove it would be stuck with a materially deviant aircraft.
v) Article 7.4.8 states the following condition precedent to delivery:
"Delivery Conditions: the Aircraft conforms to the conditions set forth in Exhibit B or otherwise conforms to such condition whereby LESSEE is obligated, pursuant to Article 6.2, to accept delivery of the Aircraft."
The words "otherwise conforms to such condition whereby LESSEE is obligated, pursuant to Article 6.2, to accept delivery" refer to the state of the aircraft (and thus what the Lessee is 'able to' demonstrate), not the demonstration the Lessee may have made (which is not a property of the condition of the aircraft). The phrase "condition whereby LESSEE is obligated" refers to the position where the deviations are in fact immaterial and do not affect airworthiness.
vi) Article 6.4 provides that "upon tender of the Aircraft by LESSOR to LESSEE in accordance with this Lease, LESSEE will accept the Aircraft subject to each and every disclaimer and waiver set forth in Article 8". That is inconsistent with the view that the obligation to accept depends, not upon whether the aircraft (or the tender) is 'in accordance with this Lease', but on whether the Lessee makes the 'demonstration' which the Claimants suggest is the critical point.
vii) If the Lessee were always obliged to accept the aircraft unless it 'demonstrates' a Material Deviation 'at Delivery', then there would be no point to Article 7.4.8 at all. The Claimants' approach would mean that the aircraft always 'conforms to the condition set forth in Exhibit B or otherwise conforms to such condition whereby LESSEE is obligated, pursuant to Article 6.2, to accept delivery', since Lessee would always be obliged to accept it unless and until the Lessee made the demonstration 'at Delivery'. So even if the aircraft were in pieces on the hangar floor, the Lessee would be obliged to accept delivery unless it objected.
viii) The Claimants' approach would be grossly unfair to the Lessee, in the light of Article 8. If the Lessee accepts the aircraft, Article 8 requires it to accept the aircraft "as is, where is" and sign an Acceptance Certificate waiving all claims against the Lessor arising out of failure to comply with Delivery Condition, including waiving claims arising because Lessee "accepted the aircraft without discovering the nonconformity but Lessee's acceptance of the aircraft was reasonably induced by either by the assurances of the Lessor of any other relevant third party of by the difficulty of discovering any defect prior to acceptance" (Article 8.2). (For example, in ACG v Olympic [2013] 1 Lloyd's Rep 658, a lessee was stuck with an unairworthy aircraft with corroded flight control cables because it had signed an acceptance certificate.) It is easily possible to foresee a situation in which a Lessee is unhappy with the aircraft (or its documents, or the MRO which has been maintaining it) and believes (but cannot at the moment of delivery 'demonstrate') that it is materially deviant. This is particularly likely if the Lessee is given the contractual minimum of ten days to inspect the aircraft documents and may therefore have to 'take a view' without having had the time to look at all the detail.
(3) Aircraft on lease to Flynas
"Without prejudice to LESSEE's right to terminate the Lease under Article 3.6 and to the return of any Base Rent following any such termination, LESSOR and LESSEE expressly acknowledge that Delivery is subject to and conditioned upon redelivery of the Aircraft by Prior Lessee in accordance with the terms of the Prior Lessee Lease Agreement."
i) Article 7.4.5 states:
"On or before the Scheduled Delivery Date [7 May 2020], LESSOR shall deliver the following to LESSEE, each in a form and substance reasonably satisfactory to LESSEE and at no cost to LESSEE….a certificate signed by an officer of LESSOR stating that the representations and warranties contained in Article 20.1 are true and accurate on and as of the Delivery Date [7 May 2020] as though made on and as of such date".
ii) Under Article 20.1:
"LESSOR represents and warrants the following to LESSEE as of the date of execution of the Lease and as of the Delivery Date [7 May 2020] …. As of Delivery…. (b) LESSOR will be able to lease the Aircraft to LESSEE".
iii) Under cover of the 1 May 2020 letter, Peregrine enclosed a certificate signed by Mr Treacy, stating that "As of Delivery…(b) LESSOR will able to lease the Aircraft to LESSEE and (c) there will be no Security Interests in the Aircraft other than Permitted Liens".
iv) However, the certificate was inaccurate because the Flynas lease was not terminated on 7 May. Peregrine therefore did not comply with the condition precedent in Article 7.4.5.
v) Further, the Claimants took none of the preparatory steps one would expect to see if Peregrine was to be in a position to terminate the Flynas lease on 7 May 2020. There was no draft termination notice prepared, no communication with the legal and contracts department over the right to terminate, no prior communication with Flynas about security deposits and maintenance rent reserves, and no communication with Fokker about the lien it had on the aircraft due to Flynas' indebtedness.
(4) 'Deliverable condition': storage
"The Aircraft will be airworthy, conform to type design and be in a condition for safe operation, with all Aircraft equipment, components and systems operating in accordance with their intended use and within limits approved by Manufacturer, the aviation authority and the EASA."
As a result, pursuant to Article 6.2 Laudamotion was not obliged to accept it.
"Counsel were unable to refer me to any authority which considered the meaning of airworthiness. However, the meaning of seaworthiness in the context of the carriage of goods by sea is well established. The classic test of unseaworthiness, as explained in Scrutton on Charterparties (22nd edn) at paragraph 7-020 is: 'Would a prudent owner have required that the defect should be made good before sending his ship to sea, had he known of it. If he would the ship was not seaworthy.' Notwithstanding that aircraft maintenance appears to be more detailed, more regulated and more heavily prescribed than ship maintenance (such that one should be cautious in drawing analogies between ships and aircraft, cf Pindell Ltd v AirAsia [2010] EWHC 2516 (Comm); [2012] 2 CLC 1 at paragraph 78), I am unable to see any reason for understanding airworthiness in a materially different manner from seaworthiness. On that basis an appropriate test for airworthiness is: 'Would a prudent operator of an aircraft have required that the defect should be made good before permitting the aircraft to fly, had he known of it. If he would the aircraft was not airworthy.'" (§ 119)
"The aircraft and its records have been maintained in accordance with the provisions of Regulation EU 1321/2014 (including rules and guidance issued pursuant thereto) and no maintenance or repair required pursuant to that Regulation (including rules and guidance issued pursuant thereto) remains outstanding."
"as the aircraft was not in operation it was an airworthiness requirement for the Aircraft to be stored and preserved in accordance with the requirements of Airbus".
(5) 'Deliverable condition': aircraft documentation
(a) Absence of demonstration pursuant to Article 6.2
(b) The Defendants' approach
(c) Contractual and regulatory regime
"2. Full Aircraft Documentation Review
For a period commencing at least 10 Business Days prior to the Scheduled Delivery Date and continuing until the date on which the Aircraft is delivered to LESSEE, LESSOR will provide for the review of LESSEE and/or its representative all of the Aircraft records and historical documents described in Exhibit N. The Aircraft records and historical documents may have been maintained in an Electronic Records Format, in which case such Aircraft records and historical documents will be provided to LESSEE in CD or other electronic format at the commencement of such period. Any Aircraft records and historical documents not maintained in an Electronic Records Format will be provided for the review of LESSEE and/or its representative in one central room at the Delivery Location at the commencement of such period."
…
"5. General Condition of Aircraft at Delivery
(a) The Aircraft, Engines, APU and Parts will have been maintained and repaired in accordance with Prior Lessee's maintenance program and the rules and regulations of the Civil Aviation Authority of the Cayman Islands.
(b) Aircraft Documentation (including records and manuals) will have been maintained in English and in an up to date status, and may have been maintained in an Electronic Records Format, in accordance with the rules and regulations of the Civil Aviation Authority of the Cayman Islands and in a form necessary in order to meet the requirements of this Exhibit B. The records and historical documents set forth in Exhibit N will be in English.
…
(f) The Aircraft will be airworthy, conform to type design and be in a condition for safe operation, with all Aircraft equipment, components and systems operating in accordance with their intended use and within limits approved by Manufacturer, the aviation authority and the EASA.
…
(i) All repairs to the Aircraft will have been accomplished in accordance with Manufacturer's Structural Repair Manual (or EASA-approved data supported by DGAC Repair Design Approval Sheets or its EASA equivalent)."
The list of Aircraft Documentation in Exhibit N included:
"10. Routine and non-routine job cards of the Return Check
11. Routine and non-routine maintenance work cards for tasks performed during the Lease Term that were not repeated at or superseded by the Return Check
…
13. Major and Minor structural repairs with applicable approvals"
"A person or organisation repairing an aircraft or a component, shall assess any damage. Modifications and repairs shall be carried out using, as appropriate, the following data:
(a) approved by the Agency;
(b) approved by a design organisation complying with Annex I (Part-21) to Regulation (EU) No 748/2012;
…"
Limb (b) would in this instance include the Structural Repair Manual ("SRM") promulgated by Airbus in relation to its aircraft.
"(a) At the completion of any maintenance, aircraft certificate of release to service ('CRS') required by point M.A.801 or point 145.A.50, as applicable, shall be entered in the aircraft continuing airworthiness record system, as soon as practicable and no later than 30 days after the completion of any maintenance.
(b) The aircraft continuing airworthiness record system shall contain the following:
1. the date of the entry, the total in-service life accumulated in the applicable parameter for aircraft, engine(s) and/or propeller(s);
2. the aircraft continuing airworthiness records described in points (c) and (d) below together with the supporting detailed maintenance records described in point (e) below;
…
(e) The owner or operator shall establish a system to keep the following documents and data in a form acceptable to the competent authority and for the periods specified below:
1. aircraft technical log system: the technical log or other data equivalent in scope and detail, covering the 36 months period prior to the last entry,
2. the CRS and detailed maintenance records:
(i) demonstrating compliance with ADs and measures mandated by the competent authority in immediate reaction to a safety problem applicable to the aircraft, engine(s), propeller(s) and components fitted thereto, as appropriate, until such time as the information contained therein is superseded by new information equivalent in scope and detail but covering a period not shorter than 36 months;
(ii) demonstrating compliance with the applicable data in accordance with point M.A.304 for current modifications and repairs to the aircraft, engine(s), propeller(s) and any component subject to airworthiness limitations; and
(iii) of all scheduled maintenance or other maintenance required for continuing airworthiness of aircraft, engine(s), propeller(s), as appropriate, until such time as the information contained therein is superseded by new information equivalent in scope and detail but covering a period not shorter than 36 months.
…"
"(a) The aircraft continuing airworthiness records are the means to assess the airworthiness status of a product and its components. An aircraft continuing airworthiness record system includes the processes to keep and manage those records and should be proportionate to the subject aircraft. Aircraft continuing airworthiness records should provide the owner/CAO/CAMO of an aircraft with the information needed:
(1) to demonstrate that the aircraft is in compliance with the applicable airworthiness requirements; and
(2) to schedule all future maintenance as required by the aircraft maintenance programme based, if any, on the last accomplishment of the specific maintenance as recorded in the aircraft continuing airworthiness records.
…
(g) 'Detailed maintenance records' in this part refers to those records required to be kept by the person or organisation responsible for the aircraft continuing airworthiness in accordance with M.A.201 [i.e. the owner or lessee, per MA 201] in order that they may be able to fulfil their obligations under Part M.
These are only a part of the detailed maintenance records required to be kept by a maintenance organisation under M.A.614, CAO.A.090(a) or 145.A.55(c). Maintenance organisations are required to retain all detailed records to demonstrate that they worked in compliance with their respective requirements and quality procedures.
Not all records need to be transferred from the maintenance organisation to the person or organisation responsible for the aircraft continuing airworthiness in accordance with M.A.201 unless they specifically contain information relevant to aircraft configuration and future maintenance. Thus, incoming certificates of conformity, batch number references and individual task card sign-offs verified by and/or generated by the maintenance organisation are not required to be retained by the person or organisation responsible in accordance with M.A.201. However, dimensional information contained in the task card sign-off or work pack may be requested by the owner/CAO/CAMO in order to verify and demonstrate the effectiveness of the aircraft maintenance programme.
Information relevant to future maintenance may be contained in specific documents related to:
- modifications;
- airworthiness directives;
- repaired and non-repaired damage;
- components referred in M.A.305(d); and
- measurements relating to defects.
…"
"(a) EASA Form 1 and the Certificate of Conformity of the components used to perform a modification/repair are not part of the substantiation data for a modification/repair. These certificates are retained by the maintenance organisation. …"
i) The 'location of repair that should be recorded in repair data form', including a 'sketch or drawing', 'photograph (optional)', 'detailed location –e.g. between FR XX and FR YY, Stringer A and Stringer B or 200 mm (7.87 in) from STA XXX etc.'.
ii) 'Proximity to adjacent repairs, original doubles, modifications or production joints should be recorded', including 'any repair(s) or damage located on the same or adjacent component (e.g. within one stringer, rib or frame bay of the primary repair'.
iii) 'Dimensions of the repair' include 'length, width or diameter, orientation and any additional dimensions defining the damage or repair geometry'; the repair form Airbus gives also requires 'edge distance in the repair doubler and to cut out in the original part'.
iv) Details of the repair are then to be recorded, including 'fastener type (solid, blind, head shape) including material and number of fastener rows', 'surface protection'.
(d) The alleged defects
"Location of repair that should be recorded in repair data form:
- Sketch or drawing
…
NOTE: Refer to Chapter 51-11-13 for more details."
The further details were not, however, provided. Mr Bull's evidence was that modern practice is often not to sketch with a pencil and paper, but to annotate the aircraft and take a photograph. Since the purpose of a sketch is to provide information in graphic form for practical purposes, it does not appear to me that a suitable photograph of an annotated section of the aircraft fails to comply with the requirement: indeed, it seems likely to be more informative. The fact that a reputable MRO such as Fokker adopts this practice tends to support the view that it is not inappropriate. Pressed on this issue, Mr Goatcher resorted to the suggestion that, rather than sketches, there should in fact be "detailed drawings" for every repair. However, that is not what the requirement states. I prefer Mr Bull's evidence on this point.
i) Item 3361/8 concerns a dent to the left outboard flap repaired by filling. The only pleaded complaint was about the absence of a "Material list and its COC [certificate of conformity]/BN [batch number] (resin repair)" . However, the list of materials was not required to be provided to the operator, and would be retained by the MRO. In any event, Mr Goatcher accepted that the DFP shows that Fokker certified that it used the grade of filler prescribed by the SRM. There was no Material Deviation.
ii) Item 3361/10 involved the assessment of an existing blend above an existing repair to the left-hand engine cowl lipskin. Mr Goatcher's complaints about this item were (a) a lack of dimensions as to the repairs' proximity to each other, and (b) a lack of "approved source data references" (pleaded as Rohr/OEM SRM, Rohr being the component manufacturer). However, the DFP and photograph considered with Mr Goatcher in cross-examination gave a clear view of the relative positions of the two repairs, which almost touched each other; and that Fokker had stated the Rohr SRM (or "Goodrich SRM", Rohr and Goodrich being part of a combined group) in accordance with which they had carried out the task. The item in question was, Mr Goatcher agreed, a "tiny blend repair". Any deficiency was immaterial.
iii) Item 3361/15 is the item I mention above about a repair to the left-hand fuselage, where the only pleaded complaint (per the Defendants' 5 July 2021 Schedule) related to an obvious typo which required correction. It was immaterial.
iv) Item 3361/19 concerns a repair to the APU door. The pleaded complaint was that the task card cited the wrong SRM reference. The Claimants pointed out in response that Fokker had issued approval for the repair pursuant to their status as an EASA Design Organisation. In any event, Mr Goatcher did not in his evidence pursue the pleaded complaint, instead seeking to advance other matters, on which the Defendants are not entitled to rely even if they had any merit.
v) Items 3361/6, 25, 26, 27 and 28 all concern damage to the Trimmable Horizontal Stabiliser ("THS"). In relation to one of these items, 3361/6, Mr Goatcher initially said that it gave rise to a Material Deviation, but in the experts' Joint Statement he agreed with Mr Bull that it did not. Mr Goatcher then, at the start of his oral evidence, rowed back from that and reverted to his original opinion, agreeing that he had done so due to a concern that if he had made a reasonable concession at the joint expert meeting, he would appear unreasonable in continuing to dispute the similar items 26-28 (repair numbers 56, 57 and 58). As to the substance, the complaint in the OIL was "no damage mapping to show proximity of dents. Photo shows more than 1 dent". This complaint had an air of unreality, since the THS is a component close to the ground which commonly sustains debris damage in the form of tiny dents, and for that reason has a protective steel cover as opposed to the aluminium used for other parts of the aircraft body. Peregrine's response indicated that the MRO had confirmed that the damaged area was assessed in accordance with the SRM 55-12-11-283-003, which allowed multiple dents to be considered as single damage. Fokker had assessed the damage and found it to be within SMR allowable damage limits, and certified this on the task card. Details in relation to the deepest dent were also recorded, and there were no nearby repairs. There is nothing in this point. There was no Material Deviation.
"All these observations were addressed prior to the Demo Flight to the satisfaction of the CAMO (and also AustroControl, who had delegated to the CAMO responsibility for ensuring that their observations from the physical inspection were addressed)";
The demo flight took place on 9 March 2020. Similarly, in oral evidence he said:
"The inspection was done on 25 February. There were observations raised provided to AerCap and AerCap provided all the answers to the CAMO showing the defect they rectified during their visit to Fokker, the CAMO, they were satisfied, only when the CAMO they decided to go ahead and issue -- submit an ARC to the authority at a later stage, it would be decided to move the aircraft to Austrian Registry, then the authority they start raising queries and clarification regarding this defect or these observations."
He was not challenged on this evidence.
"What may have happened -- and it happened -- it happens very often when you have major check ongoing with hundreds of papers, sometimes the MRO, it does happen, it is very common, they will lose job card, routine card and they will have to reprint them and have them resigned for the original sign-off date.
…
I have no reason to believe that the document did not exist and then it was signed off by the MRO on March 6th. I believe that was the original sign-off by the mechanic when the work was done and that would have been part of their tally sheet as part of the return check."
Mr Akhrif also said it was very common to find missing job cards during any return check, which would then have to be replaced, duplicated and signed off by the engineer; and that the only person who could answer the question about these specific documents would be the MRO. There is nothing implausible in that evidence. Had the Defendants raised the point on a timely basis, it could have been addressed in more detail. As it is, the Defendants' point does not assist them, and their criticisms of Mr Akhrif are entirely unfounded.
(e) Conclusion
(H) CLAIMS IN RESPECT OF THE OTHER THREE 2019 AIRCRAFT
i) under Article 24.2(q)(iii) in relation to MSN 3396; and
ii) under Article 24.2(q)(i) in relation to MSN 3425 and MSN 3475.
"(i) any Financial Indebtedness of LESSEE in an aggregate amount of US$2,000,000 or more (or its equivalent in other currencies) is not paid when due (subject to any applicable cure periods) or becomes due and payable prior to its stated maturity"
and
"(iii) An event of default is existing and continuing under any Other Agreement and the same is not cured within the specified cure period"
with "Other Agreements" meaning aircraft/engine leases between the Lessee and the Lessor, its Affiliates, and trustees of the Lessor and its Affiliates, and "Financial Indebtedness" covering "obligations under capitalized or operating leases … in respect of aircraft or aircraft equipment" but excluding "any indebtedness under any Other Agreements".
i) insofar as the Claimants rely on failure to pay the accelerated rents demanded under the MSN 3361 lease (following the alleged Events of Default under that lease) as constituting an Event of Default under Article 24.2(q) of other leases, they cannot do so because (a) Articles 24.2(q)(i) and (iii) both require any cure periods to have elapsed, and (b) following their 15 May 2020 termination notice and demand under MSN 3361, the Claimants did not allow for the cure period provided for in Article 24.2(b): the notices in relation to all four aircraft were served on the same day; and
ii) in any event, the Claimants could not have delivered the last three aircraft by their respective Final Delivery Dates.
(1) Relevance of cure periods to alleged cross-defaults
"24.2 Events of Default. The occurrence of any of the following will constitute an Event of Default and material repudiatory breach of this Lease by LESSEE:
…
(b) Non-Payment. … (ii) LESSEE fails to make a payment of any other amount due under this Lease or any of the other Operative Documents (including amounts expressed to be payable on demand) after the same has become due and such failure continues for seven Business Days"
(2) Whether the Claimants could have delivered the last three aircraft on time
i) MSN 3396: The demo flight took place on 10 June 2020, albeit (necessarily) without Laudamotion representatives present. By mid-June 2020, no physical work or borescope inspections remained: that had all been completed by 16 June 2020. The 22 alleged Material Deviations on which the Defendants rely all relate to documentation issues. Thus the Defendants' case in relation to MSN 3396 comes down to asserting that in the not insignificant amount of time available before the Final Delivery Date in respect of MSN 3396, these documentation issues could not have been resolved had Laudamotion wished to take delivery of the aircraft.
ii) MSN 3425: By the Final Delivery Date, 31 May 2020, no physical work remained to be done to the aircraft. On 28 May 2020, Vallair had signed an unconditional Certificate of Release to Service (as Mr Bull explains, this "certifies completion of the Aircraft maintenance"). All that remained were final engine and APU borescope inspections: the No. 2 engine passed its borescope inspection on 2 June 2020, the APU passed its borescope inspection on 2 June 2020 and the No. 1 engine passed its borescope inspection on 3 June 2020. The 26 alleged Material Deviations on which the Defendants rely all relate to documentation issues. Thus the Defendants' case comes down to the improbable assertion that had they wanted to take delivery of the aircraft, AIL could not have brought forward the borescope inspections by a few days and resolved the other documentary points.
iii) MSN 3475: By the Final Delivery Date, 30 June 2020, the aircraft had been painted, but the maintenance check was still underway and some work remained to be done. However, only shortly before arriving at the MRO, in November-December 2019, MSN 3475 had undergone an extensive 6-year and 12-year check. On the basis of that, it is Mr Bull's assessment that "it is reasonable to assume that the pre-delivery maintenance work required for MSN 3475 would be a relatively 'light' check plus the painting." The vast majority of the 41 alleged Material Deviations are documentary points. Mr Goatcher's report does not explain why he says that the remaining maintenance work could not have been completed by 30 June 2020 if Laudamotion had wished to take the aircraft. As with the other aircraft, the Defendants' case involves the assertion that the outstanding documentary matters could not have been resolved in the time available had Laudamotion had any interest in accepting the aircraft.
i) In many instances, the allegations that certain documents were not available prior to the relevant Final Delivery Date are incorrect.
ii) It is accepted that certain documents were not available by the relevant Final Delivery Date. However, the Claimants deny that this is documentation that would not have been available to the Defendants prior to the relevant Final Delivery Dates.
iii) In circumstances where the leases were terminated prior to their respective Final Delivery Dates, and no new lessee for these aircraft was immediately identifiable, it is unsurprising (and in line with their duties of mitigation) that the Claimants slowed the pace of work on these aircraft. It is for this reason that in some cases documents were only available after the relevant Final Delivery Date. The Claimants deny that the delay in the production of these documents is indicative of the general difficulties it is alleged they would have faced in producing satisfactory documents within the time available.
iv) It is the Claimants' position that had the 2019 leases remained on foot, they would have been in a position to deliver these three aircraft by their respective Final Delivery Dates, by allocating additional resources (such as other AerCap employees, external consultants and additional resources from Fokker and Vallair) to ensure that the technical and documentary records of the aircraft were in delivery condition by the relevant Final Delivery Date.
i) There was no evidence, in particular from the Claimants' witnesses of fact, that the Claimants would in fact have asked Celairion to step in in this way.
ii) The documents suggest that Celairion had not been heavily involved with these three aircraft by the relevant times. There are indications that Celairion stopped work on MSN 3425 on 2 April 2020, and there are no documents establishing that Celairion was working on MSN 3396 before 30 June or on MSN 3475 before October 2020.
iii) Mr Bull accepted that documents would be required from Flynas, but did not know what would be involved in getting them.
iv) Mr Goatcher's opinion was that:
"looking at the status of the records that were available to review as of early May 2020, it would have been a considerable task for any CAMO to take over the management of the records from Flynas and prepare for the deliveries of the Last 3 Aircraft. Whilst it is difficult to be precise, I would see this task taking 2-3 months, provided good co-operation was made available with Flynas, which, in my view, was unlikely to be extended. The CAMO would have needed to recover, rebuild and validate all the required reports, records and documents required to put the Last 3 Aircraft into a condition for delivery. Looking at the basic Flynas document formats (Microsoft Word, PDF and Microsoft Excel-based), this process would have been time consuming and largely manual in nature."
"We tendered 3361 for delivery and as a result of that, it made -- as a result of that delivery not going forward, it made no sense to continue preparing the other aircraft for Lauda because it was clear they weren't coming to take delivery."
Mr Akhrif said:
"I have to mention after the [leases], they were terminated, we were not acting or pushing Flynas in the same way we were doing before…
[…]
…we were taking a lot of actions where we were interfering with Flynas in their process. After the leases were terminated, we stopped doing that because that was costing us money.
[…]
And before 15 May, we had consultants involved, more consultants, after the 15th we did not see the need to keep incurring costs for additional consultants.
[…]
The same for parts. Before 15 May, we were discussing the case, we were told Fokker, go ahead and buy the parts and we take the decision. After May 15, we were not doing that any longer."
Mr Peacock said:
"…by the end of May, the foot was definitely off the gas in terms of serving these aircraft up to Laudamotion."
and Mr Mallon said:
"We allowed Flynas to dictate the time from early May. And we allowed them to slow things down. So we didn't -- we did not -- we stopped putting pressure on Flynas to put the aircraft in a condition that was ready for redelivery or delivery." ]
"As you know, I have been working from home during 5 weeks, as most of us have done. Since I came back 2 weeks ago, I have been correcting, re-printing, signing and scanning WOs [work orders] for you (31 to be precise), sending them to Stephen for review and adding D&B item number, I cannot let you write that I don't want to do much. … I am working mostly on this A/C (mostly but not 100% because we still have 15 A/C on site) and Stephen is helping me remotely since he is the one with all the details. There are only very few WOs still open for structures and they all shall be closed very soon."
(I) HOW MUCH CAN THE CLAIMANTS RECOVER FROM LAUDAMOTION?
i) the net amount received and to be received under the SmartLynx leases in respect of what would have been the lease term of the Laudamotion leases had Laudamotion accepted delivery of the aircraft; and
ii) any rent paid by Flynas after the Final Delivery Dates under the Laudamotion leases.
It is no longer suggested that by entering into the SmartLynx leases, the Claimants failed to mitigate their losses.
i) If Laudamotion had taken delivery of the aircraft, what is the net amount that the Lessors would have received as a result?
ii) How much of the amounts that the Lessors will receive from SmartLynx must they give credit for, i.e. what is the appropriate 'cut-off date'?
iii) What is the net amount that the Lessors will receive from SmartLynx?
iv) How much are the Claimants obliged to give credit for in respect of Flynas?
v) What additional expenses are the Lessors entitled to recover?
i) The burden is on a defendant to show that the claimant ought, as a reasonable person, to have taken a particular step, and that had it taken that step it would have reduced the loss: see Standard Chartered Bank v Pakistan National Shipping Corp [2001] CLC 825 §§ 22(k), 33 and 38.
ii) When considering the value of the SmartLynx leases (and the value of a hypothetical further lease, if the court were to conclude that acting reasonably the Lessors should exercise the break option at some future date), the court is not assessing the quantum of the Lessors' loss, but rather the value of the mitigation which goes to reduce that loss. Accordingly the Defendants bear the burden of proof: see Thai Airways v KI Holdings Co Ltd [2015] EWHC 1250 (Comm) §§ 83-92.
iii) In a case of this sort (where the value of the replacement lease depends on utilisation, rather than being at a fixed rent), absolute precision is impossible and the search may be disproportionate: see Sainsbury's Supermarkets Ltd v Visa Europe Services LLC [2020] UKSC 24, [2020] Bus LR 1196 §§ 217-218. It is proper to apply fairly broad assumptions rather than attempt to map out what would have happened had Laudamotion taken delivery, and what will happen in relation to the SmartLynx leases, in the level of detail that would be necessary to make an assessment of the end of lease condition under the leases.
iv) The court will make reasonable assumptions, erring on the side of the Claimants if necessary: see Yam Seng Pte Ltd v International Trade Corp Ltd [2013] EWHC 111 (QB) § 189 per Leggatt J:
"… the court will attempt so far as it reasonably can to assess the claimant's loss even where precise calculation is impossible. The court is aided in this task by what may be called the principle of reasonable assumptions – namely, that it is fair to resolve uncertainties about what would have happened but for the defendant's wrongdoing by making reasonable assumptions which err if anything on the side of generosity to the claimant where it is the defendant's wrongdoing which has created those uncertainties."
v) Damages are calculated on the assumption that a claimant has taken reasonable steps in mitigation, whether it has in fact done so or not: see Golden Strait Corp v Nippon Yusen Kubishika Kaisha [2007] 2 AC 353, §10.
vi) In the present case, Article 24.7 of the leases imposes an express duty on the Lessors to mitigate their losses:
"Mitigation of Damages. LESSOR will take such reasonable commercial actions insofar as and to the extent that such a corresponding defense exists under English Law to mitigate any damages or losses it may incur as a result of the occurrence of an Event of Default, provided that (a) LESSOR will not be obliged to consult with LESSEE concerning any proposed course of action or to notify LESSEE of the taking of any particular action, (b) LESSOR will not be obligated to take any step that, in its reasonable discretion, could prejudice LESSOR, and (c) this provision is without prejudice to LESSOR's rights under Article 24.6.
I agree with the Defendants that neither sub (a) nor (b) detracts from the requirement for the Lessor to act reasonably.
vii) The claimant need not take unreasonable steps: thus, in James Finlay & Co v NV Kwik Hoo Tong [1929] 1 KB 400, the claimant was not obliged to recover its loss by enforcing a contract selling the relevant goods to a third party, when to do so it would have had to rely on a conclusive evidence clause in a way that would injure his commercial reputation. See also, to similar effect, Banco de Portugal v Waterlow [1932] AC 452, 471. Nor is a claimant required to take steps other than in the ordinary course of business: British Westinghouse Electric & Manufacturing Co v Underground Electric Railways Co of London [1912] AC 673, 689.
viii) The court should not take an unduly demanding approach to the innocent party's acts or omissions:
"Now I think a Court of Justice ought to be very slow in countenancing any attempt by a wrong-doer to make captious objections to the methods by which those whom he has injured have sought to repair the injury. When a road is let down or land let down, those entitled to have it repaired find themselves saddled with a business which they did not seek, and for which they are not to blame. Errors of judgment may be committed in this as in other affairs of life. It would be intolerable if persons so situated could be called to account by the wrong-doer in a minute scrutiny of the expense, as though they were his agents, for any mistake or miscalculation, provided they act honestly and reasonably. In judging whether they have acted reasonably, I think a Court should be very indulgent and always bear in mind who was to blame." (Lodge Holes Colliery Company v Wednesbury Corporation [1908] AC 323, 325 per Lord Loreburn LC)
ix) In London and South East Building Society v Stone [1983] 1 W.L.R. 1242 a building society which had lent on the basis of a valuation that negligently failed to warn of subsidence was not obliged to sue its borrowers (who had repaid the sum advanced) under their personal covenant to keep the property in repair. That was because the innocent party is not obliged to take the risk of starting an uncertain litigation against a third party: including litigation that may be reasonably certain in outcome but where there is no certainty that the judgment will be satisfied (§§ 204-205). See also Natixis SA v Marex Financial [2019] EWHC 2549 (Comm) §§ 549-556, holding that proceedings need not be brought under a personal guarantee because (a) the opportunities for technical defences to such claims were well known, making the outcome uncertain, and (b) even if the claim succeeded, there would be no certainty as to what sums, if any, could be recovered in enforcement proceedings.
x) In Western Trust & Savings Ltd v Clive Travers & Co [1997] PNLR 295, the Court of Appeal held (distinguishing Stone) that the building society there should have at least enforced the security under the mortgage before claiming from the negligent solicitors who failed to advise that there was a pre-existing mortgage in favour of a third party. Phillips LJ said:
"Where a plaintiff enforces his security he will be in a good position to prove his loss, having regard to these considerations. Where he does not enforce his security, proof of loss presents greater difficulties. In the latter situation it is not easy to distinguish between the duty of the plaintiff to prove his loss and the duty of a defendant who alleges failure to mitigate to prove the extent to which failure to mitigate has affected the financial position of the plaintiff, it seems to me that essentially there are two sides of the same coin."
The Defendants submit that this means that a claimant who has a straightforward claim must advance it: it is prima facie reasonable for a claimant to enforce straightforward rights under his existing contracts. However, Western Trust was in a way a special case, since irrecoverability under the claimant's mortgage was the basis of the loss. Hence Stone was distinguished on the basis that in Western, the plaintiffs should have had recourse to the very security that was the subject of the dispute: that was necessary in order to establish a loss in the first place. In my view, it is unnecessary to apply a presumption of the kind the Defendants propose. The test, including in relation to the pursuit of claims, is whether the defendant can show that the claimant has failed to act reasonably.
(1) The sums which would have been received from Laudamotion
"In calculating LESSOR's damages hereunder, on the Termination Date all Rent and other amounts which would have been due hereunder during the Lease Term if an Event of Default had not occurred will be calculated on a present value basis using a discounting rate of the prime rate announced by LESSOR's Bank discounted to the date on which LESSOR recovers possession of the aircraft."
(2) SmartLynx leases: cut-off date
(3) Sums to be received from SmartLynx
(a) Base Rent
Period | Utilisation Projection (per month) | |
1 | December 2021 to December 2022 | 165 flight hours / 50 cycles |
2 | January 2023 to lease end | 208 flight hours / 68 cycles |
i) Mr Dimitroff's benchmark period June 2021 to June 2022 included downturns in passenger numbers due to Covid, and the month of June 2021 when the SmartLynx leases had just started and the four aircraft flew very little;
ii) we now have the actual utilisation figures for the period December 2021 to December 2022, indicating an average monthly utilisation of 164.06 hours;
iii) Mr Dimitroff agreed that the ACMI market will grow in the long term as global traffic grows;
iv) an article in AeroTime on 5 February 2022, shown to Mr Dimitroff in cross-examination, referred to a recent Market Monitor Global report predicting global ACMI growth of 6.9% compound per annum and the ACMI market by 2027 being almost double its size in 2020: Mr Dimitroff had not been shown the underlying data and could not comment in detail, but said the predictions did not seem wildly unreasonable to him. He noted that the 6.9% predicted annual increase might be based partly on new aircraft and partly on higher utilisation;
v) SmartLynx itself reported in May 2022 that "Aviation support services and passenger ACMI expected to show significant improvement in 2022 following dropped pandemic restrictions". There is an indication in the documents that SmartLynx is expanding its existing fleet of 33 aircraft by a further 22 aircraft; and
vi) Mr Dimitroff agreed that SmartLynx is one of the pre-eminent A320 ACMI operators in Europe, Middle East, and Africa, and that SmartLynx has a number of quality customers including easyJet, Tui and Jet2.
(b) The Call Option
i) by June 2023, the Lessors will be receiving US$85,000 a month in base rent and US$60,000 in profit share, and will therefore be receiving almost US$150,000 already (or about US$1.75 million per annum); and
ii) the Lessors will be able to show that they have offers in excess of US$150,000 per month, which SmartLynx will wish to match (or accept a PBH rate of around US$750 per hour which Mr Seymour presumably believes would equate to around US$150,000 per month).
(c) Maintenance rent
(d) Change in maintenance condition
(e) SmartLynx Profit Share
(f) Discount rate
(4) The Flynas Payments
i) Must the Claimants give credit from the date when the Laudamotion leases were terminated or the Final Delivery Dates?
ii) Are the Claimants obliged to give credit for the double rent and default interest provided for in the Flynas leases?
iii) If not, should the Claimants be obliged to give credit for more single rent than they current offer?
(a) Start date
(b) and (c) Single and double rent
(5) Additional expenses
(J) FOR HOW MUCH IS RYANAIR LIABLE AS GUARANTOR?
(1) MSN 3396
"If an event of Default occurs … LESSOR and each other Indemnitee has the right to recover from LESSEE, and LESSEE will indemnify LESSOR and each other Indemnitee on LESSOR's first written demand against, any Expenses which LESSOR or any other Indemnitee may sustain or incur directly as a result, including [without limitation] …."
I have interpolated the words "without limitation" because Article 27.14 provides that the word "including" is "used in this Lease without limitation".
"any and all liabilities, obligations, losses, damages, fines (whether criminal or civil), penalties, claims, demands, actions, suits, proceedings, judgments, orders, or other sanctions, payments, charges, fees, costs, disbursements and expenses (including legal fees and expenses) of every kind and nature".
and defines "Indemnitee" as including the Lessor's Affiliates.
i) The Event of Default in relation to MSN 3361 triggered an Event of Default in relation to MSN 3396.
ii) The Expenses suffered in relation to MSN 3396 were sustained or incurred "directly as a result" of the MSN 3361 Event of Default.
iii) Laudamotion is therefore liable under the indemnity in the MSN 3361 lease in relation to MSN 3396; and in turn Ryanair is liable on the guarantee it gave in relation to the MSN 3361 lease.
"… in order to comprise a novus actus interveniens, so breaking the chain of causation, the conduct of the claimant "must constitute an event of such impact that it 'obliterates' the wrongdoing…" of the defendant: Clerk & Lindsell on Torts (19th ed.), at para. 2-78. The same test applies in contract. For there to be a break in the chain of causation, the true cause of the loss must be the conduct of the claimant rather than the breach of contract on the part of the defendant; if the breach of contract by the defendant and the claimant's subsequent conduct are concurrent causes, it must be unlikely that the chain of causation will be broken. In circumstances where the defendant's breach of contract remains an effective cause of the loss, at least ordinarily, the chain of causation will not be broken…."
"… it is difficult to conceive that anything less than unreasonable conduct on the part of the claimant would be capable of breaking the chain of causation. It is, however, also plain that mere unreasonable conduct on a claimant's part will not necessarily do so…."
In the present case, it was both reasonable and foreseeable that Peregrine could call an Event of Default under the MSN 3396 lease based on the cross-default provision, and it was directly based upon and flowed from the original wrongdoing. It is no answer to say the loss arose from a concurrent cause outside the scope of the clause: see Financial Conduct Authority v Arch Insurance (UK) Ltd [2021] UKSC 1, [2021] AC 649, at §§ 162-176.
(2) MSNs 3425 and 3475
i) The failure to pay the sums due following the event of Default in relation to MSN 3361 amounted to an Event of Default in relation to the 2018 leases, including the lease of MSN 3131, under Article 24.2(q)(i) (considered earlier). That triggered Events of Default under AIL's leases in respect of MSNs 3425 and 3475.
ii) AIL is an Affiliate of AICDAC, the lessor of MSN 3131, so AIL is an Indemnitee for the purposes of Article 24.6 of the MSN 3131 lease.
iii) The Expenses suffered in relation to MSN 3425 and 3475 were sustained or incurred "directly as a result" of the MSN 3131 Event of Default.
iv) Laudamotion is therefore liable under the indemnity in the MSN 3131 lease and in turn Ryanair is liable on the guarantee it gave in relation to that lease.
(K) CONCLUSION