Transcript of Proceedings
JUDGMENT
Revised
For the Appellant | The Appellant in person |
For the Respondent | Mr P Harrington Representative M & W Pearce Ltd Great Western Court Hunts Ground Road Stoke Gifford Bristol BS34 8HP |
MR COMMISSIONER HOWELL QC
"(a) On a date towards the end of September 1998 the respondent's management took the decision to dismiss the applicant. This decision was communicated to Des Pike, the respondent's project manager, in Dresden.
(b) On 30 September 1998 Des Pike met the applicant, explained the position to him telling him that his employment would terminate on 30 October 1998;
(c) On 1 October 1998 Des Pike wrote to the applicant on notepaper of Meissner & Wurst giving written confirmation of the notice that had been given and thanking him the applicant on behalf of the respondent for his efforts and commitment on the Dresden project ….. This letter was a letter from the respondent written on third party stationery;
(d) Following the giving of notice the respondent made efforts to relocate the applicant on a job in Portugal but this proved to be impossible and the notice was not rescinded."
"Dear Hamish
AMD FAB 30 - DRESDEN
Notification of Leaving FAB 30 Dresden
Further to our recent discussions p/m 39-09-98 regarding the above mentioned, this is to confirm that your current employment on this project will cease with effect from Friday, 30th October 1998.
Whilst M + W Pearce will endeavour to find alternative employment within the company or one of the other operating companies controlled by the Pearce Group this unfortunately cannot be guaranteed.
We trust that you will continue to serve "the company" throughout your notice period as you have during the period of your current contract of employment.
We thank you on behalf of M + W Pearce Ltd for your efforts and commitment throughout your period on this project.
Yours sincerely
Des G Pike
Project Manager
FAB 30 Dresden"
17 Tax and social security
17.1 The employer will operate a tax and social security equalisation scheme during the Term. This means that, in general terms, the employee will pay the equivalent of the UK tax and social security contributions that he/she would have paid, had he/she remained in the UK.
17.2 Under this method, an amount similar to that which the employee would have paid to the UK tax and social security authorities, on his/her base pay, uplift and normal UK taxable benefits and expenses, will be deducted monthly, from his/her gross salary. The employee will therefore receive each month a net amount on which no further tax or social security will be payable by the employee. In return, the employer will pay the employee's actual tax and social security liabilities arising on his/her employment in Germany."
"(j) The respondent had undertaken to pay "the employee's actual tax and social security liabilities arising on his employment in Germany." The circumstances of the applicant's employment resulted in the tax liability arising in Germany and the social security liability arising in the UK."