|
||
|
||
Neutral citation [2008] CAT 3
IN THE COMPETITION
Case No: 1046/2/4/04
APPEAL TRIBUNAL
Victoria House
Bloomsbury Place
17 January 2008
London WC1A 2EB
Before:
Marion Simmons QC
(Chairman)
The Honourable Antony
Lewis
Professor John
Pickering
Sitting as a Tribunal in England and
Wales |
||
|
||
BETWEEN:
(1) ALBION WATER
LIMITED
- and -
(2) ALBION WATER GROUP
LIMITED
Appellants
- v -
WATER SERVICES REGULATION
AUTHORITY
Respondent - supported by
-
(1) DŴR CYMRU
CYFYNGEDIG
- and -
(2) UNITED UTILITIES WATER
PLC
Interveners |
||
|
||
JUDGMENT (Application for
disclosure) |
||
|
||
|
||
I INTRODUCTION
1.
There is an appeal before the Tribunal against the Decision of the
Director General of Water Services, now the Water Services Regulatory
Authority (“the Authority”)1 of 26 May 2004 (“the Decision”).
In that Decision the Authority decided that Dŵr Cymru Cyfyngedig (“Dŵr
Cymru”) did not abuse a dominant position in breach of the Chapter II
Prohibition by engaging in excessive pricing (see paragraph
341).
2.
In this appeal Albion Water Limited (“Albion”) has made a written
application dated 23 November 2007 for the specific disclosure of the
following documents, which it requested the Tribunal to consider on the
papers:
(a) A letter
from Dŵr Cymru, dated 17 March 2003, (hereinafter referred to as “the
letter of 17 March 2003”);
(b) Copies of Dŵr
Cymru document “LCE/01/001” and the email dated 30 April 2001 in
unredacted form (hereinafter referred to as “the unredacted Dŵr Cymru
documents”); and
(c) Accounting
documents relating to the cost of the construction of the LG Philips main
(hereinafter referred to as “the LG main costs”).
3.
By letter of 27 November 2007 to the parties the Tribunal invited
observations on Albion’s disclosure application. The Tribunal received
written submissions from the Authority and Dŵr Cymru on 3 December 2007.
Albion replied to these submissions in its letter to the Tribunal of 10
December 2007.
4.
Having carefully considered the submissions of the parties, and for
the reasons set out below, our conclusion is that Albion’s application for
disclosure should be granted in relation to the letter of 17 March 2003
and the unredacted Dŵr Cymru documents, but refused in relation to the LG
main costs. |
||
|
||
1 Since 1 April 2006
the functions of the Director General of Water Services have been assumed
by the Authority pursuant to the provisions of the Water Act 2003. Where
necessary, references in this judgment to the Authority are to be taken as
referring to the Director General of Water Services and vice
versa. |
||
|
||
1 |
||
|
||
|
||
II BACKGROUND |
||
|
||
5.
The history of these proceedings is set out in the judgments of the
Tribunal of 6 October 2006 and 18 December 2006 in Albion Water v Water
Services Regulation Authority [2006] CAT 23 (“the main judgment”) and
[2006] CAT 36 (“the further judgment”) respectively.
6.
In the Decision the Authority considered the question whether the
First Access Price of 23.2p/m³ (“the First Access Price”) offered by Dŵr
Cymru to Albion on 2 March 2001 for the “common carriage” of non-potable
water via the so-called Ashgrove system could be said to bear no
reasonable relation to the economic value of the service provided, when
judged by reference to the difference between the costs actually incurred
by Dŵr Cymru and the price charged (see paragraph 339 of the Decision).
The Authority was unable to answer this question in the affirmative, and
accordingly concluded that Dŵr Cymru did not abuse a dominant position in
breach of the Chapter II Prohibition by engaging in excessive pricing (see
paragraph 341 of the Decision).
7.
In the main judgment, the Tribunal found at paragraph 637 that the
evidence before it, taken
as a whole, “strongly suggests”
that the First Access Price was excessive. At paragraph 981
of the main judgment the Tribunal
concluded as follows:
“For the reasons given above we
have reached the following conclusions:
(1) There is
evidence before the Tribunal that the treatment cost of non-potable water
on an average accounting cost basis was over-estimated in the Decision.
However the Tribunal is prepared to assume, without deciding, that
treatment costs are in the range 1.6p/m³ to 3.2p/m³.
(2) The matter of
the “distribution” cost of non-potable water on an average accounting cost
basis was not sufficiently investigated. In this respect the Decision is
incorrect, or at least insufficient, from the point of view of the reasons
given, the facts and analysis relied on, and the investigation undertaken,
as regards in particular to the Director’s conclusion in paragraph 302 of
the Decision to the effect that it was not unreasonable to assume that the
“distribution” costs of potable and non-potable water are the
same.
(3) The evidence
strongly suggests that the First Access Price was excessive in relation to
the economic value of the services to be supplied, by reason of the
absence of any convincing justification |
||
|
||
2 |
||
|
||
|
||
for the “distribution” costs
included in the average accounting cost calculation”.
8.
The Excessive Pricing Abuse issue is considered in paragraphs 231 –
281 of the further judgment. For the reasons stated in paragraph 240 of
the further judgment the Tribunal considered that the issue of abuse by
reason of excessive pricing would be better reached by the Tribunal taking
its own decision under paragraph 3(2)(e) of Schedule 8 to the Competition
Act 1998 (“the 1998 Act”). In paragraph 241 and 279 of the further
judgment the Tribunal considered that it would be preferable if certain
matters were first further investigated by the Authority under rule 19(1)
and 19(2)(j) of the Tribunal Rules notably to determine the extent to
which the First Access Price was unrelated to costs, and to consider
whether the price was unfair within the meaning of section 18(2)(a) of the
1998 Act. In paragraph 277 of the further judgment the Tribunal stated
that it took the view that it was very close to being in a position to
decide the issue of excessive price abuse and that it would be appropriate
for the Tribunal to do so. The Tribunal stated in paragraph 280 that it
decided to refer back to the Authority under rule 19(2)(j) of the Tribunal
Rules for further investigation the matter of the calculation of the costs
reasonably attributable to the service of the transportation and partial
treatment of water by Dŵr Cymru, generally and through the Ashgrove system
in particular, together with the associated question of whether in the
light of those costs, the First Access Price was an unfair price within
the meaning of the Chapter II prohibition.
9. At paragraph 281 of the
further judgment the Tribunal stated:
“In investigating those matters
the Authority shall give Dŵr Cymru and Albion a full opportunity to
comment on the Authority’s preliminary views before reaching any
conclusions. There is no reason why that investigation should not proceed
in parallel with the determination of the Bulk Supply Price where similar
issues are likely to arise. The Authority is requested to report the
results of its investigations to the Tribunal within six months of the
date of this judgment [i.e. 18 June 2007], subject to any further
direction of the Tribunal. The Tribunal will then determine the matter
under paragraph 3(2)(e) of Schedule 8 of the 1998 Act”.
10. At paragraph 360(iii) of the
further judgment, the Tribunal referred:
“back to the Authority under Rule
19(2)(j) of the Tribunal’s Rules for further investigation the matter of
the costs reasonably attributable to the service of the transportation and
partial treatment of water by Dŵr Cymru, generally and through the
Ashgrove system in particular, |
||
|
||
3 |
||
|
||
|
||
together with the associated
question of whether, in the light of those costs, the First Access Price
was an unfair price within the meaning of the Chapter II
prohibition”.
11. On 18 June 2007 the Authority
lodged with the Tribunal Registry its “Final Report” containing the
results of its further investigation. The Final Report contains the
methodology adopted by the Authority and its conclusions on the matters
referred to it. In summary, the Authority reported that, whilst the First
Access Price was excessive, since it exceeds the costs attributable to the
relevant services by a material extent, the Authority did not consider
that there was cogent evidence in the circumstances of this case that the
excess is, on the balance of probabilities, unfair in itself and could not
therefore be categorised as an abuse. Both Albion and Dŵr Cymru challenge
the Authority’s Final Report.
By an Order dated 23 October 2007
(as amended on 30 October 2007), the Tribunal ordered
that written submissions be filed
and served in respect of the following issues which now
arise in this
appeal:
“Heading 1: The specific
components of cost which should not have been included or should have been
but were not included in the costs calculation in the Final
Report
Heading 2: Arithmetical errors
allegedly committed by the respondent in the Final Report
Heading 3: Methodological errors
and errors of economic assessment allegedly committed by the respondent in
the Final Report”.
Following receipt of the Final
Report Albion in correspondence has sought voluntary disclosure of
documents from the Authority and Dŵr Cymru. Although we have read this
correspondence copied to the Tribunal, in deciding this application we
have focused on the written submissions provided by the parties for the
purposes of this disclosure application.
III THE DISCLOSURE APPLICATION
14. Specific disclosure is sought of
three categories of documents as described below.
The Letter of 17 March 2003
15.
Daniel Mark Elliot (“Dr Elliot”), a director of Frontier Economics
Limited, an economics consulting firm, made a witness statement dated 16
February 2006 as a witness for Corus UK
4 |
||
|
||
|
||
Limited (“Corus”) in a High Court
action Dŵr Cymru Cyfyngedig v Corus UK Limited & Another (see
[2006] EWHC 1183 (Ch), 26 May 2006) (hereafter “the Corus
proceedings”)
16. Albion sought voluntary
disclosure of Dr Elliot’s witness statement from the parties to
the
Corus proceedings. On 20 June 2007 Dŵr Cymru replied to Albion
as follows:
“For the avoidance of doubt,
irrespective of whether or not Corus write to us to the effect that they
are content to share with you material prepared in connection with our
claim against them, we do not give our consent to the disclosure of any
such material”.
17. On
14 November 2007 the solicitors acting for Corus wrote to Albion, copied
to the Tribunal and Dŵr Cymru, enclosing a copy of Dr Elliot’s witness
statement for Albion’s information and use in the present
proceedings.
18. In
Dr Elliot’s witness statement reference is made to the letter of 17 March
2003 from Dŵr
Cymru to the Authority. Albion’s
application for disclosure of the letter of 17 March 2003 is
founded on the information
contained in paragraph 64 of Dr Elliot’s witness statement,
which, in so far as material,
reads:
“Finally, I note that, in the
letter of 17 March 2003 it appears that, for the first time, Welsh Water
attempted to calculate the cost of its distribution assets for non-potable
water. This calculation produces a figure of 7.86 pence per cubic metre.
In the absence of detailed workings, I cannot comment on the accuracy of
this figure. However, it seems to provide a further indication that the
figure of 16 pence per cubic metre, used all along as the basis for the
bulk distribution costs, may be too high”.
The unredacted Dŵr Cymru documents
19. The
Authority received the Dŵr Cymru documents from Dŵr Cymru in an unredacted
form pursuant to a formal notice dated 29 June 2001 given under section 26
of the 1998 Act. The unredacted Dŵr Cymru documents are internal documents
which concern the calculation and proposal of the First Access Price in
January 2001. The solicitors for Dŵr Cymru in a letter to the Authority
dated 21 September 2007 stated that these documents are not Board
documents; that they were prepared for an internal management committee
known as the “licensed company executive” (“LCE”), hence the title of the
document “LCE/01/001”. |
||
|
||
5 |
||
|
||
|
||
20. On
6 August 2007 Albion sought voluntary disclosure of the Board paper and
minute relating to Dŵr Cymru’s January 2001 Board meeting at which the
First Access Price was approved. On 21 September 2007 Dŵr Cymru provided
Albion with a redacted copy of the minutes of a Board meeting which took
place on 15 January 2001 and a document marked “To: LCE”. Albion
subsequently sought voluntary disclosure of a document entitled
“LCE/01/001” which was referred to in document “To: LCE”.
21. On
11 October 2007 the Authority disclosed a redacted copy of document
“LCE/01/001” to Albion. Document LCE/01/001 was prepared by Mr Dave Holton
who was at the time a commercial manager employed by Dŵr Cymru. The title
of document LCE/01/001 is “Common Carriage Application at Ashgrove,
Deeside” and contains various matters relating to a proposed common
carriage price to cover the partial treatment and transport of water
through the Ashgrove system.
22. At
the same time as disclosing document “LCE/01/001” to Albion the Authority
also disclosed two other documents. These were: (a) an unredacted copy of
document called “LCE/01/0XX” and (b) a redacted copy of the email dated 30
April 2001 from Mr Dave Holton. According to the Authority these documents
were relevant to “the question of what was in Dŵr Cymru’s mind when it
approved the First Access Price”. The email of 30 April 2001 records the
results of a meeting held between Albion, Dŵr Cymru and United Utilities
in or around April 2001. It appears that the purpose of the meeting was to
discuss a proposed change in the treatment of the water supplied to, among
others, Albion’s non-potable customer: Shotton Paper. It appears that
issues relating to the security of supply and quality of water were also
discussed.
The LG main costs
23. The
LG Philips semiconductor plant in Newport is supplied with non-potable
water via a pipeline, which was constructed by Dŵr Cymru in 1997 (“the LG
main”). The LG main consists of a pipeline supplying non-potable water
from Dŵr Cymru’s treatment works at Court Farm to the LG Philips
development.
24. Dŵr
Cymru first mentioned to the Authority the LG main costs in a confidential
letter dated 4 April 2007. |
||
|
||
6 |
||
|
||
|
||
25. The
Authority did not investigate the costs of laying the LG main during its
further investigation.
26. In
its written submissions for the case management conference on 23 October
2007 the Authority informed the Tribunal that Albion did not make it aware
that it considered that costs information regarding the LG main was
relevant to the Authority’s then investigation until five days prior to
the deadline for submission of the Final Report to the
Tribunal.
27. The
letter of 4 April 2007 from Dŵr Cymru to the Authority came to the
attention of Albion when it was disclosed as an annex to the Authority’s
Final Report.
28.
Albion now applies to the Tribunal for disclosure of accounting
evidence relating to the cost of laying the LG main.
IV THE PARTIES’ SUBMISSIONS
29. It
is common ground that the principles to be applied in applications for
disclosure before the Tribunal are set out in the case-law of the
Tribunal, in particular in Claymore v OFT (Recovery and Inspection)
[2004] CAT 16 and Cityhook v OFT (Disclosure) [2006] CAT 32.
The Tribunal observed in Claymore that an application for
disclosure should only be granted if the disclosure sought is necessary,
relevant and proportionate ([2006] CAT 32, at paragraph 113).
30.
Albion submits that disclosure of the documents requested is both
relevant and necessary to its appeal. The Authority and Dŵr Cymru oppose
the application on both of these grounds. Dŵr Cymru further relies on what
it submits is the highly confidential nature of the redacted parts of the
unredacted Dŵr Cymru documents. The parties’ submissions in respect of the
individual documents which are the subject of the disclosure application
are set out below. |
||
|
||
7 |
||
|
||
|
||
The Letter of 17 March 2003
31.
Albion seeks disclosure of the letter of 17 March 2003 because it
appears to contain relevant costs calculations in respect of the New
Tariff2. According to Albion, the costs calculations are
relevant because, first, the Decision refers to the New Tariff when
analysing the First Access Price (see in particular paragraph recital 248
of the Decision) and, secondly, because those calculations appear to lead
to a figure (7.86 p/m³) of less than half the figure of 16p/m³, on which
the Authority relied in its Decision. What is of crucial importance, says
Albion, is an understanding of how this accounting costs information has
been used to produce results on which Dŵr Cymru and the Authority rely,
and the consistency of that approach over time. Albion submits that the
letter of 17 March 2003 will shed light on this important issue. Albion
adds that, in its view, the withholding of the information contained in
the letter of 17 March 2003 justifies the Tribunal’s comment at paragraph
254 of the further judgment, cited below.
32. The
Authority submits that the letter relates to confidential discussions
between the Authority and Dŵr Cymru in a regulatory context over possible
revisions to its charges scheme and that, as a matter of policy, such
correspondence is not disclosed to other water companies. Furthermore, in
the Authority’s view, the letter is of limited relevance since it is
neither contemporaneous to the First Access Price negotiations in 2001 nor
to the Authority’s more recent calculations in the Final Report in
2007.
33. Dŵr
Cymru resists the application on three grounds. First, Dŵr Cymru submits
that the reference to the letter of 17 March 2003 in a witness statement
served in the Corus proceedings is irrelevant to the question of
disclosure before the Tribunal. Second, Dŵr Cymru submits that the
question of whether it provided all the accounting information that it
could during the earlier proceedings in this case, including the letter of
17 March 2003, does not fall within the scope of the issues identified by
the Tribunal’s Order of 23 October 2007. Third, Dŵr Cymru submits that
Albion is wrong to infer that the letter of 17 March 2003 and the material
underlying it amounts to additional accounting information that should
have been disclosed, but was not. In that regard, Dŵr Cymru notes that the
cost analyses for the New Tariff drew on the same publicly available
regulatory accounting
2 Dŵr Cymru proposed a
new tariff for 2003/2004 including volumetric charges for raw water and
partially treated water. That tariff, as it would apply to Shotton Paper
were Dŵr Cymru ever to supply Shotton directly again, is referred to as
the “New Tariff” in the Decision (see paragraph 198 of the
Decision). |
||
|
||
8 |
||
|
||
|
||
information used for the First
Access Price and that information has already been provided to the
Tribunal. Dŵr Cymru also points out that the New Tariff is far from new
and had the underlying basis for that tariff ever been relevant, the
Tribunal or any of the parties could have sought further information at
the outset of these proceedings, over three years ago.
The unredacted Dŵr Cymru documents
34.
Albion submits that disclosure of the unredacted Dŵr Cymru documents
is necessary, relevant and proportionate to ensure a just, expeditious and
economical consideration of the matters that are before the Tribunal. In
Albion’s submission the documents are contemporaneous with the creation of
the First Access Price and aid an understanding of the steps leading to
the First Access Price and Dŵr Cymru’s actions immediately thereafter.
Moreover Albion submits that this is particularly relevant to whether the
First Access Price was only “indicative”, as Dŵr Cymru contends, or the
First Access Price was a “firm” price intended to be Dŵr Cymru’s standard
common carriage price. Given the age of the documents in question – six
years after the event – Albion submits that confidentiality cannot and
should not be a bar to disclosure, at least to the Tribunal and to counsel
for Albion.
35. The
redacted Dŵr Cymru documents disclosed by the Authority excluded certain
commercially confidential information, pursuant to section 237 of the
Enterprise Act 2002. Accordingly, the Authority claims it is not in a
position to release the unredacted copies of LCE/01/001 and the email
dated 30 April 2001. The Authority adds that, in its view, the redacted
material is not relevant to the assessment of whether the First Access
Price was excessive or unfair in the sense used in the Final
Report.
36. Dŵr
Cymru submits that no order for disclosure should be made in respect of
the unredacted Dŵr Cymru documents. Dŵr Cymru submits that the redacted
sections of LCE/01/001 and of the email dated 30 April 2001 are both
irrelevant to the current proceedings and, as accepted by the Authority
contain commercially sensitive information whose disclosure would
significantly harm Dŵr Cymru’s business interests. The redactions to
LCE/01/001 relate to “live” commercial arrangements between Dŵr Cymru and
United Utilities and have no bearing on issues relevant to the setting of
the First Access Price. The excisions to the email dated 30 April 2001
remove information which relates to the strategic thinking of Dŵr Cymru
concerning current bulk supply negotiations between Albion and itself. In
the event |
||
|
||
9 |
||
|
||
|
||
that the Tribunal were minded to
accede to Albion’s request, Dŵr Cymru submits that the appropriate course
would be for the President of the Tribunal or another chairman of the
Tribunal to decide whether there should be limited or full disclosure of
the documents in question.
The LG main costs
37.
Albion submits that it will be of considerable value to the Tribunal
to have contemporary evidence in respect of the actual cost of a closely
comparable project to the Ashgrove system, namely the LG main. Albion
notes the reliance by the Authority in the Final Report on several
comparators to cross-check its capital cost calculations. Albion further
submits that the importance of access to the underlying LG costs data is
underlined by the fact that pipeline unit costs of the LG main are
approximately 50% of those relied upon by the Authority in its Final
Report. Essentially, Albion submits, it needs the accounting evidence so
as to be able to show errors in the further investigation and that those
errors had a consequence.
38. The
Authority states that it possesses no information on the actual
construction costs of the LG main and is therefore unable to disclose any
documents relating to this issue.
39.
Dŵr Cymru resists disclosure of the LG main costs. Its view is that
information about the LG main arose too late for the Authority to consider
it. To accede to Albion’s request for disclosure of accounting information
about the LG main would transform the Tribunal into a primary fact-finder
in respect of the LG main which would be contrary to the purpose of the
Tribunal’s referral back. Dŵr Cymru also disputes Albion’s claims that the
LG main costs suggest a significantly lower unit cost for mains-laying
than that implied by the Authority in the Final Report. In any event, Dŵr
Cymru submits that Albion has the key information on the costs of the LG
main so far as they are relevant to mains-laying.
IV THE TRIBUNAL’S ANALYSIS
40. The
procedural rules governing proceedings in the Tribunal are contained in
the Competition Appeal Tribunal Rules 2003 (S.I. No. 1372 of 2003, as
amended by S.I. No. 2068 of 2004). |
||
|
||
10 |
||
|
||
|
||
Disclosure is governed by rule 19 of the Tribunal Rules which
provides, in so far as material,
that:
“(1) The Tribunal may at any
time, on the request of a party or of its own initiative, at a case
management conference, pre-hearing review or otherwise, give such
directions as are provided for in paragraph (2) below or such other
directions as it thinks fit to secure the just, expeditious and economical
conduct of the proceedings.
(2) The Tribunal may give directions- …
(k) for the disclosure between,
or the production by, the parties of documents or classes of
documents…”
41. The
object of a disclosure application under rule 19(2)(k) is to obtain
production of specified documents. Accordingly, the application must
specifically identify the documents sought; it must not be of a fishing or
speculative nature.
42. A
disclosure application will be rejected if the documents are not relevant
and necessary for the fair and just disposal of the proceedings
(see, to that effect, Claymore, cited above, at [108] and
[113]).
43.
While the criteria of relevance and necessity are entitled to
individual consideration, the Tribunal will of course also look at the
matter as a whole. |
||
|
||
44. In this case, we bear in mind
the concerns that have already been expressed by the Tribunal
about the evidence made available
in the proceedings to date. In paragraph 291 of the main
judgment the Tribunal
stated:
“…We note, however, that in this
particular case most of the relevant information is in the hands of the
Director and Dŵr Cymru, and that Albion has had access only to information
which is publicly available, or has been obtained by disclosure in these
proceedings. Although Dr Bryan has considerable experience of the water
industry, Albion is a company with limited resources, in part as a result
of the effect of the present dispute. While Dŵr Cymru has given some
considerable disclosure, a troubling feature of the present case is that
on a number of occasions information supplied has had to be corrected, and
on other occasions assertions have been made that have proved difficult to
verify. On important issues such as costs there is little by way of
contemporaneous information or original
documentation” |
||
|
||
11 |
||
|
||
|
||
In paragraph 464 of the main
judgment the Tribunal stated: Lack of information on
costs
A striking feature of the present
case has been the lack of any detailed, or verifiable, break down of the
components of the cost of “distribution” here in question. The Decision
arrives at a figure of 16p/m³ for the “distribution” cost to non-potable
users, but gives no details of what that figure comprises. Dŵr Cymru has
produced no original accounting information to support the figure of
16p/m³”.
45. In paragraph 254 of the further
judgment the Tribunal also noted that:
“… Albion is a small company
which has been trying for some six years to have its complaint determined,
and has so far succeeded on the substance. In our view, it would not be in
accordance with justice if that result, achieved by tenacity and force of
argument against the combined forces of the Authority and an incumbent
monopolist, should become an empty victory because some cost information
is still not available and a few points remain to be decided. To conclude
otherwise would simply mean that Dŵr Cymru’s tactical approach in
declining to supply accounting information in support of the claimed
“distribution” costs of 16p/m³ would have paid off, leaving Albion with a
Pyrrhic victory. Dŵr Cymru’s claim that it is not possible to provide even
estimated accounting information to support the figure of 16p/m³ for
“distribution” costs is not, in our view, credible”.
46. We
have borne the foregoing comments in mind when considering Albion’s
application for disclosure. We shall now consider whether disclosure of
the individual documents the subject of the application, set out in
paragraph 2 above, would be relevant, necessary and proportionate in the
particular circumstances of this appeal.
47. In this judgment it is important
to note that the Tribunal is not making any findings of
fact. |
||
|
||
Letter of 17 March 2003
48. The Tribunal understands that
Albion’s sole source of knowledge of the existence of the letter of 17
March 2003 and of the information contained in it is from Dr Elliot’s
witness statement. That witness statement was disclosed in the Corus
proceedings and the general rule is that it may only be used for the
purpose of those proceedings: see Civil Procedure Volume 1 (The White
Book Service 2007), Part 31, rule 31.22(1). One of the exceptions to
the general rule is where the party who disclosed the document and the
person to whom the document belongs agree: rule 31.22(1)(c). That
exception applies in this case since Corus |
||
|
||
12 |
||
|
||
|
||
disclosed the document to Albion
and is the person3 to whom the document belongs. The fact that
the other party to the Corus proceedings (Dŵr Cymru) did not agree to the
witness statement being disclosed is irrelevant for these purposes. It
follows that Albion is entitled to use information contained in Dr
Elliot’s witness statement in the appeal before the Tribunal and
particularly in its application for specific disclosure of the letter of
17 March 2003 referred to in that document.
49. The
letter of 17 March 2003 is requested because, in Albion’s submission, it
bears on the correct measure of the distribution costs of non-potable
water.
50.
Albion says that it needs access to this letter because it concerns
the calculation of the cost of distribution for non-potable water. Albion
refers to the apparent discrepancy between the figures of 7.86 p/m³ (in
the letter of 17 March 2003) and 16p/m³ (in the Decision). We accept
Albion’s submission that the calculations are relevant to the question
whether the First Access Price bears a reasonable relation to the economic
value of the service provided by Dŵr Cymru. In that regard it is relevant
that the Authority itself referred to the New Tariff in the Decision and
specifically noted that “Dŵr Cymru’s approach to the First Access Price
and its approach to the New Tariff are similar” (see paragraph 248 of the
Decision). This document appears to us to be relevant to a consideration
of the similarity of its approaches, which was a factor relied upon by the
Authority in its Decision.
51. As
to the submissions put to us for resisting the application, the fact that
the letter of 17 March 2003 relates to confidential discussions between
the Authority and Dŵr Cymru in a regulatory context and that, as a matter
of policy, such correspondence is not disclosed to other water companies,
is not relevant to the Tribunal’s consideration of whether it ought to
order disclosure of a document in an appeal before it.
52. The
fact that the accounting costs information, on which the New Tariff
calculations are based, is already publicly available is also irrelevant
to the question whether the letter of 17 March 2003 should be disclosed.
That information does not explain the discrepancy between the two figures
referred to above. |
||
|
||
3 See Civil Procedure
Volume 1 (The White Book Service 2007), p 57 and Schedule 1 to the
Interpretation Act 1978: “Person” includes a body of persons corporate or
unincorporated.
13 |
||
|
||
|
||
53. For
the reasons set out above, we order disclosure of the letter of 17 March
2003 since in our judgment it is necessary, relevant and proportionate to
the fair and just disposal of this appeal.
54. We
referred above to the previously expressed concerns of the Tribunal as to
the approach which Dŵr Cymru has taken in this appeal to disclosure of
documents relating to the “cost” of distribution of non potable water (see
in particular paragraph 464 of the main judgment and paragraph 254 of the
further judgment cited above). The position which Dŵr Cymru has taken in
this application for specific disclosure in relation to Dr Elliot’s
witness statement and the letter of 17 March 2003 is but a further example
of this concern. This is particularly so in relation to the present
application because the Authority admits that the letter is of relevance
albeit of limited relevance.
The unredacted Dŵr Cymru documents
55. We
note that Albion has been seeking disclosure of these documents since as
long ago as 13 May 2004. Albion renewed its request for voluntary
disclosure of these documents in 2007 and, quite properly on 11 October
2007, the Authority finally disclosed a redacted copy of document
LCE/01/001 and a redacted copy of the email dated 30 April
2001.
56.
Albion submits that the Authority and Dŵr Cymru, in producing
redacted versions of the unredacted Dŵr Cymru documents, have consistently
failed to provide material that is central to the calculation and
determination of the First Access Price.
57.
Albion submits that the redacted passages of the unredacted Dŵr
Cymru documents are relevant and necessary since they bear on the steps
leading to the First Access Price and Dŵr Cymru’s actions immediately
thereafter. The Authority and Dŵr Cymru resist disclosure of the
unredacted versions on the basis that the information is irrelevant to
these proceedings. United Utilities who is an intervener in these
proceedings has not made any submissions on this disclosure
application.
58. The
title of the document “LCE/01/001” is “Common Carriage Application at
Ashgrove, Deeside”. The document in its redacted form discusses various
matters which are (directly or indirectly) relevant to the access price to
cover the partial treatment and transport of water |
||
|
||
14 |
||
|
||
|
||
through the Ashgrove system.
These matters are plainly relevant to our decision. We are told that the
redacted passages of document LCE/01/001 relate to commercial arrangements
between Dŵr Cymru and United Utilities. However, we note that paragraphs
5.73-5.79 of the Final Report specifically refer to these arrangements.
Unlike the LG main costs, discussed below, these were matters before the
Authority during its further investigation. For example, paragraphs
5.78-5.79 of the Final Report refer to the bulk supply arrangements
between Dŵr Cymru and United Utilities when the Authority determines
whether “connection charges” should be included as a cost underlying the
First Access Price. In our judgment, the redacted information in
LCE/01/001 appears on the information presently available to us to be
relevant and necessary to the issues to be determined. Accordingly, we
reject the submissions of the Authority and Dŵr Cymru in that
regard.
59. The
other Dŵr Cymru document – the email dated 30 April 2001 – relates to the
water undertaker’s strategic thinking in relation to ongoing bulk supply
negotiations with Albion. At present, Albion purchases the water in
question under a bulk supply agreement from Dŵr Cymru at the boundary of
Albion’s inset appointment area at the premises of Shotton Paper. Dŵr
Cymru submits, however, that the redacted material is irrelevant to
Albion’s common carriage proposal in general and to the calculation of the
First Access Price in particular. The email specifically refers to
Albion’s complaint under the 1998 Act dated 10 December 2000. It also sets
out Dŵr Cymru’s reactions to correspondence with Albion, following
notification of the First Access Price. We note that the email touches on
other material issues such as security of supply which have been raised in
paragraphs 5.37-5.72 of the Final Report.
60. We
consider that disclosure of the unredacted Dŵr Cymru documents is both
relevant and necessary. On the information before us the redacted parts of
these documents appear to us to be relevant and necessary to a matter
presently before the Tribunal which is whether Dŵr Cymru “has made use of
the opportunities arising out of its dominant position in such a way as to
reap trading benefits which it would not have reaped if there had been
normal and sufficiently effective competition”, so as to satisfy the test
of abuse as laid down by the European Court of Justice in Case 27/76
United Brands v Commission [1978] ECR 207 at paragraph
249. |
||
|
||
15 |
||
|
||
|
||
61. The
disclosure application is resisted by the Authority and Dŵr Cymru on the
basis that the redacted passages in the unredacted Dŵr Cymru documents are
confidential. In our judgment, when documents are confidential, the claim
that their disclosure is necessary for the fair resolution of proceedings
may well be subjected to careful scrutiny. However, the fact that the
documents of which disclosure is sought are confidential or contain
confidential information is not a bar to an order for their
disclosure.
62. The
unredacted Dŵr Cymru documents as disclosed by the Authority excluded
certain commercially confidential information under Part 9 of the
Enterprise Act 2002. By virtue of section 237(5) of that Act, the
restrictions on disclosure of confidential information which apply to the
Authority do not apply to the Tribunal.
63. The
Tribunal’s duty to have regard to the need to exclude certain confidential
matters from its decisions is set out in Schedule 4, paragraph 1(2) and
(3) of the Enterprise Act 2002, as follows:
“Decisions of the Tribunal
…
(2) In preparing
that document the Tribunal shall have regard to the need for excluding, so
far as practicable—
(a) information the
disclosure of which would in its opinion be contrary to the public
interest;
(b) commercial information
the disclosure of which would or might, in its opinion, significantly harm
the legitimate business interests of the undertaking to which it
relates;
(c) information relating to
the private affairs of an individual the disclosure of which would, or
might, in its opinion, significantly harm his interests.
(3) But the Tribunal
shall also have regard to the extent to which any disclosure mentioned in
sub-paragraph (2) is necessary for the purpose of explaining the reasons
for the decision”.
64.
This provision anticipates that disclosure of confidential material
may be made in the course of proceedings before the Tribunal.
65. For
the reasons set out above we consider that it is relevant, necessary and
proportionate for the fair and just disposal of this appeal that the
unredacted Dŵr Cymru documents should be disclosed. |
||
|
||
16 |
||
|
||
|
||
66. Dŵr
Cymru has a legitimate interest in protecting its business
confidentiality. Having regard to the submissions that have been made, and
in particular the fact that no party objects to the principle of a
confidentiality ring, we consider it appropriate in the first instance to
order disclosure within a confidentiality ring (consisting of certain
named external advisers of Albion, and Dŵr Cymru) of unredacted copies of
document LCE/01/001 and of the email dated 30 April 2001.
The LG main costs
67.
Albion’s case, in essence, is that the Authority did not look at a
potentially important comparator – the costs of laying the LG main – when
assessing the costs reasonably attributable to the Ashgrove system. In
order to develop this criticism of the Authority’s Final Report Albion
seeks access to the accounting evidence relating to the actual
construction costs of the LG main.
68.
Albion is anticipating that disclosure of this evidence may
highlight deficiencies in the evidence and documentation before the
Authority and may also be used by it to explore more generally the
underlying issues in the case.
69.
Although in its letter of 4 April 2007 Dŵr Cymru mentioned the LG
main to the Authority, the Authority did not pursue this as an avenue of
enquiry for the purposes of its Final Report. It was only five days before
the date for submission of the Final Report to the Tribunal that Albion
first raised with the Authority the LG main as a possible cost comparator.
As a matter of administrative procedure, we consider that the course taken
by the Authority in these circumstances to have been
reasonable.
70.
There are undoubtedly areas of factual conflict in this case but
their resolution by way of comparative evidence relating to the LG main,
which is in an area of different topography and has different pipeline
dimensions and lengths, would be very time-consuming, would not be a
proportionate exercise and is not in our judgment necessary for the
Tribunal’s determination of this appeal, having regard in particular to
the other comparative evidence already available. |
||
|
||
17 |
||
|
||
|
||
71. In
the further judgment the Tribunal decided that it would be better if there
were to be a short further investigation “of the costs reasonably
attributable to the service of the transportation and partial treatment of
water by Dŵr Cymru, generally and through the Ashgrove system in
particular”, before a final conclusion was reached on the issue of abuse
(see paragraph 247 of the further judgment). The referral back did not
anticipate detailed investigation of the costs of laying other non-potable
water pipelines. How the Authority went about its further investigation
was, in the first instance, a matter for it. We do not consider that it
would be appropriate or proportionate for the Tribunal to order disclosure
of this accounting evidence which the Authority did not
consider.
72. In
our judgment, therefore, Albion has failed to satisfy us that documents
concerned with the LG main costs are relevant or necessary or
proportionate for the fair and just disposal of the appeal.
V CONCLUSION
73. For
the above reasons we unanimously grant Albion’s application for disclosure
in respect of the letter of 17 March 2003 and the unredacted Dŵr Cymru
documents, but, as regards the LG main costs, the application for
disclosure is refused. |
||
|
||
Marion Simmons
Antony
Lewis
John Pickering |
||
|
||
Charles Dhanowa
Registrar
Date: 17 January 2008
18 |
||
|
||