High Court of Ireland Decisions
You are here:
BAILII >>
Databases >>
High Court of Ireland Decisions >>
Redmond v An Bord Pleanala [2020] IEHC 151 (10 March 2020)
URL: http://www.bailii.org/ie/cases/IEHC/2020/2020IEHC151.html
Cite as:
[2020] IEHC 151
[
New search]
[
Printable PDF version]
[
Help]
Page 1 ⇓
THE HIGH COURT
JUDICIAL REVIEW
[2020] IEHC 151
2019 No. 709 J.R.
IN THE MATTER OF SECTION 50 AND 50A OF THE PLANNING AND DEVELOPMENT ACT
2000 (AS AMENDED)
BETWEEN
MICHAEL REDMOND
APPLICANT
AND
AN BORD PLEANÁLA
RESPONDENT
DURKAN ESTATES CLONSKEAGH LIMITED
DUN LAOGHAIRE RATHDOWN COUNTY COUNCIL
NOTICE PARTIES
JUDGMENT of Mr. Justice Garrett Simons delivered on 10 March 2020
INTRODUCTION…………………………………………………………………………………………………………………………………1
NOMENCLATURE……………………………………………………………………………………………………………………………….6
THE APPLICATION SITE …………………………………………………………………………………………………………………10
“INSTITUTIONAL LANDS” DESIGNATION………………………………………………………………………………………13
INTERPRETATION OF DEVELOPMENT PLAN: LEGAL PRINCIPLES……………………….……………………...16
INTERPRETATION IS A QUESTION OF LAW FOR THE COURT………………………………………………………22
DOES THE DESIGNATION APPLY TO THE APPLICATION SITE?..............................................29
SALE OF THE APPLICATION SITE…………………………………………………………………………………………………..48
MATERIAL CONTRAVENTION OF ZONING OBJECTIVE?........................................................60
MATERIAL CONTRAVENTION OF NON-ZONING OBJECTIVE?................................................73
MISINTERPRETATION IS AN ERROR OF LAW………………………………………………………………………………..94
CHIEF EXECUTIVE’S REPORT…………………………………………………………………………………………………………95
PRE-APPLICATION CONSULTATIONS…………………………………………………………………………………………..132
HABITATS DIRECTIVE: BATS……………………………………………………………………………………………………….149
SUMMARY OF CONCLUSIONS………………………………………………………………………………………………………157
FORM OF ORDER………………………………………………………………………………………………………………………….163
APPENDIX……………………………………………………………………………………………………………………………………………
* References are to paragraph numbers
Page 2 ⇓
INTRODUCTION
1. The within proceedings seek to question the validity of a decision of An Bord Pleanála to
grant planning permission for a large scale residential development (134 units). The
decision to grant planning permission was made on 10 May 2019, and bears the An Bord
Pleanála reference “PL06D.304420”.
2. The impugned decision was made pursuant to the special statutory procedure which
governs applications for “strategic housing development” (as defined). One of the key
features of this procedure is that the application for planning permission is made to An
Bord Pleanála directly, i.e. there is no first-instance application to the local planning
authority.
3. Notwithstanding that the planning authority does not have a formal decision-making
function in respect of such applications, the authority continues to have a significant role
to play. First, it is a statutory consultee and An Bord Pleanála is required to consider the
report and recommendation prepared on behalf of the planning authority by its chief
executive. Secondly, An Bord Pleanála must have regard to the planning authority’s
development plan in determining the application for planning permission. The board is
precluded from granting planning permission if the proposed development would involve a
material contravention of a zoning objective of the development plan or local area plan.
In the case of a non-zoning objective, i.e. an objective other than one in relation to the
zoning of land, the board has jurisdiction to grant planning permission in material
contravention of the objective provided that certain prescribed statutory criteria are
fulfilled.
4. The principal issue which arises for determination in this judgment is whether the lands,
the subject-matter of the planning application, are designated as “institutional lands”
under the development plan. If this designation is held to apply, then a number of
subsidiary issues arise for determination by the court, including (i) whether the
designation represents a zoning objective, and (ii) whether the proposed development
constitutes a material contravention of the development plan objectives applicable to
“institutional lands”.
5. This judgment will also address a number of separate grounds of challenge which have
been advanced by the applicant for judicial review. The legal issues presented by these
other grounds can be disposed of more shortly. The lion’s share of this judgment will be
taken up with the issues identified in the preceding paragraph.
NOMENCLATURE
6. The following shorthand will be used to describe the parties to the proceedings. The
applicant for judicial review, Mr Michael Redmond, will be referred to as “the objector”.
The applicant for planning permission, Durkan Estates Clonskeagh Ltd., will be referred to
as “the developer”. (The use of the term “applicant” to describe either of these parties
will be avoided as it is apt to lead to confusion between the applicant for judicial review,
and the applicant for planning permission). The decision-maker, An Bord Pleanála, will be
Page 3 ⇓
referred to as either “An Bord Pleanála” or “the board”. Dun Laoghaire Rathdown County
Council will be referred to as “the planning authority”.
7. The underlying legislation, the Planning and Development Act 2000, and the Planning and
Development (Housing) Act 2016, will be referred to by the abbreviations “PDA 2000” and
“PD(H)A 2016”.
8. The lands the subject-matter of the planning permission impugned in these proceedings
will be referred to as “the application site”.
9. The development plan imposes certain policies and objectives in the case of what are
described as lands in “institutional use” or “institutional lands”. The relevant provisions of
the 2016–2022 development plan are set out in an appendix to this judgment. I will refer
to lands subject to these policies and objectives as lands which have been “designated” as
“institutional lands”. The term “designated” is employed in contradistinction to the term
“zoned”. This is because, as explained at paragraph 60 et seq., the objectives and
policies do not amount to a zoning objective.
THE APPLICATION SITE
10. The application site is located in Goatstown, some 5 kilometres from Dublin city centre,
and is in the functional area of Dun Laoghaire Rathdown County Council. The general
area in the vicinity of the application site is primarily in residential use. The application
site itself measures some 1.969 hectares. The application site had previously formed part
of an overall landholding of 6.4 hectares which had been in the ownership of the
Congregation of Religious of Jesus and Mary (“the religious congregation”). The
developer purchased the application site from the religious congregation in October 2017.
The precise relationship between the application site and the overall landholding is one of
the central issues in dispute in these proceedings.
11. The religious congregation had previously sold another part of the overall landholding to
the same developer. A residential development known as “The Grove” has been erected
on these lands.
12. The balance of the overall landholding which remains in the ownership of the religious
congregation accommodates (i) a secondary school (Jesus and Mary College); (ii) a
primary school (Our Lady’s Grove Primary School); (iii) a new four-storey convent
building (Errew House); (iv) a hockey pitch; and (v) tennis courts. The hockey pitch had
originally run north-south, and had straddled part of the application site. An Bord
Pleanála issued a (separate) grant of planning permission on 14 March 2019 which
authorised the development of a new all-weather hockey pitch on an east-west alignment.
This new pitch has since been installed, with the result that no part of the new hockey
pitch lies within the application site. Rather, the new hockey pitch is located on lands
within the continued ownership of the congregation.
“INSTITUTIONAL LANDS” DESIGNATION
13. It is evident from the positions adopted by the parties in their respective pleadings and
legal submissions that the principal dispute between them centres on the interpretation of
Page 4 ⇓
the Dun Laoghaire Rathdown Development Plan 2016–2020 (“the 2016–2020
development plan”). More specifically, the parties are divided on the question of whether
the application site is subject to the “institutional lands” designation. If this designation
does apply, then An Bord Pleanála would have been required to have regard to certain
policies and objectives in determining the planning application. In particular, it would
have had to have regard to objectives in respect of (i) the density of the proposed
development (dwellings per hectare); (ii) the provision of open space; (iii) the retention
of trees; and (iv) the retention of sufficient space for possible future school expansion or
redevelopment. Unless certain statutory criteria were met, the board would be precluded
from granting planning permission for the proposed development if it constituted a
material contravention of these policies and objectives.
14. The position adopted by the objector, Mr. Redmond, is that the “institutional lands”
designation does apply. Conversely, An Bord Pleanála and the developer submit that the
designation does not apply, and further submit that, even if it did apply, An Bord Pleanála
had assessed the proposed development by reference to the relevant objectives in any
event.
15. In order to resolve this dispute, it is necessary to consider the relevant provisions of the
2016–2022 development plan (both in terms of the written statement and maps). Before
turning to that task, however, it is necessary first to consider the legal principles which
govern the interpretation of a development plan.
INTERPRETATION OF DEVELOPMENT PLAN: LEGAL PRINCIPLES
16. The approach to be adopted in interpreting a development plan is well established. The
provisions of the plan fall to be interpreted as they would be understood by a reasonably
intelligent person, having no particular expertise in law or town planning. See Tennyson
v. Dun Laoghaire Corporation [1991] 2 I.R. 527 at 535. This is the same legal test which
applies to the interpretation of planning decisions as set out by the Supreme Court in In
Re XJS Investments Ltd [1986] I.R. 750.
17. The parties were all in agreement that this is the correct approach. The parties cited
more recent case law where this approach has been endorsed, including, in particular, the
judgment of the Supreme Court in Lanigan v. Barry [2016] IESC 46; [2016] 1 I.R. 656
(interpretation of planning permission), and the judgments of the High Court in Heather
Hill Management Company clg v. An Bord Pleanála (No. 2) [2019] IEHC 450 and Spencer
18. There was, however, disagreement between the parties as to the extent, if any, to which
it is legitimate for a court to have regard to materials outside of the development plan in
interpreting the plan. The developer submitted that it was legitimate to have regard to
earlier development plans in interpreting the 2016–2022 development plan. In particular,
it was submitted that the documentary record of the statutory procedure leading up to
the making of the 2010–2016 development plan explained the significance of the change
in the location of the symbol, which designates lands in “institutional use”, as between the
2010–2016 plan and its precursor, namely, the 2004–2010 development plan. The
Page 5 ⇓
manager’s report in respect of the process leading up to the making of the 2010–2016
plan indicated that the symbol had been repositioned to “the northeast corner of the
defined site to more accurately reflect the residual bona fide institutional use remaining
on the site”. (See affidavit of Julie Costello, paragraph 31 and exhibit JC10). (As an
aside, it should be noted that, whatever the authority’s position may have been in 2010,
it is evident from the chief executive’s report that the planning authority is now firmly of
the view that the designation applies to the application site).
19. With respect, this submission seeks to attribute far too great a knowledge to the
hypothetical “reasonably intelligent person”. The case law indicates that a development
plan is to be interpreted as it would be by a person who has no particular expertise in law
or town planning. Whereas such a person can be assumed to have read the extant
development plan, it is unrealistic to assume that he or she would have gone further and
sought out copies of the previous development plan and of the documentation leading up
to the making of that plan. This would entail a level of knowledge which is the exclusive
preserve of those with a professional role in town planning, i.e. planning consultants or
lawyers.
20. It would also be inconsistent with effective public participation, as required under national
and EU law, to impose an obligation on a member of the public, who wishes to
understand current planning policy, to have to read not only the extant development
plan—the contents of which often run to hundreds of pages—but also to have to read
previous development plans and the statutory reports associated with the making of
those earlier development plans. This would place an unrealistic burden on members of
the public.
21. The 2016–2022 development plan thus falls to be interpreted without reference to the
2010–2016 development plan.
INTERPRETATION IS A QUESTION OF LAW FOR THE COURT
22. Before turning to consider the provisions of the 2016–2022 development plan in detail, it
is necessary first to say something about the standard of review which the court is
required to apply in interpreting a statutory development plan. The parties all agree that
the general rule is that the interpretation of a plan is a question of law, and, accordingly,
the court is not required to show deference to the views of An Bord Pleanála (or even to
the views of the local planning authority who is the author of the plan).
23. It is important to understand the rationale underlying this principle that the interpretation
of a development plan is a question of law for the court. The rationale is predicated on
the legal effect of a development plan, and, in particular, the manner in which it acts as a
fetter on the discretion of An Bord Pleanála. An Bord Pleanála enjoys a broad discretion
in determining planning applications, and its decision on whether proposed development
is in accordance with proper planning and sustainable development is subject only to the
most limited merits-based review under the principles in O’Keeffe v. An Bord Pleanála
[1993] 1 I.R. 39. The board is, however, required to “have regard to” the provisions of
the relevant development plan. Further, there are statutory restrictions on the board’s
Page 6 ⇓
jurisdiction to grant planning permission for proposed development in material
contravention of the development plan. These statutory restrictions are stricter in the
case of a “strategic housing development” application under the PD(H)A 2016 than they
are in the case of a conventional planning application. The board cannot grant planning
permission under the PD(H)A 2016 where the proposed development, or a part of it,
contravenes materially the development plan in relation to the zoning of the land. This
difference in treatment between a “strategic housing development” application and a
conventional application is, presumably, intended to reflect the fact that an application of
the former type is made directly to An Bord Pleanála without there being any first-
instance application to the planning authority. The enhanced status afforded to the
zoning objectives ensures that the planning authority’s role, as author of the development
plan, in setting planning policy, is respected. As to the role of a local planning authority
in making policy, see, generally, Christian v. Dublin City Council (No. 1) [2012] IEHC 163;
“[…] However, for the reasons already analysed, a development plan contains at
least a significant element of what might legitimately be described as policy
formation. It is, of course, the fact that there are limits on the range of policy
options which can be adopted by a local authority for the purposes of formulating
its development plan. The development plan must conform with the legislation. It
must be designed and set out with ‘an overall strategy for the proper planning and
sustainable development’ of the relevant area (s. 10(1) of the Act of 2000). It
must conform with the overall policy objectives mandated by the legislation (such
as have been described earlier in this judgment). Within those very general
obligations a great deal of discretion is left to the local authority and it does not
seem to me to be unreasonable to describe the breadth of that discretion as
amounting to an express, and constitutionally permissible, conferral of at least a
degree of policy- making discretion on the local authority concerned.”
24. Insofar as non-zoning objectives are concerned, An Bord Pleanála may only grant
planning permission in material contravention of a development plan by reference to the
statutory criteria under section 37(2)(b) of the PDA 2000. (See section 9(6)(c) of the
PD(H)A 2016). These criteria read as follows:
(i) the proposed development is of strategic or national importance;
(ii) there are conflicting objectives in the development plan or the objectives are not
clearly stated, insofar as the proposed development is concerned;
(iii) permission for the proposed development should be granted having regard to
regional spatial and economic strategy for the area, guidelines under section 28,
policy directives under section 29, the statutory obligations of any local authority in
the area, and any relevant policy of the Government, the Minister or any Minister of
the Government;
Page 7 ⇓
(iv) permission for the proposed development should be granted having regard to the
pattern of development, and permissions granted, in the area since the making of
the development plan.
25. It follows from this legislative scheme that the question of whether or not a proposed
strategic housing development involves a material contravention of the development plan
must be a question of law exclusively for the court. Were it otherwise—and were An Bord
Pleanála to be allowed to determine conclusively whether or not a material contravention
is involved—then this would set at naught the statutory restraints on An Bord Pleanála’s
ability to grant planning permission which are imposed by section 9(6) of the PD(H)A
2016. The board would, in effect, be allowed to determine its own jurisdiction.
26. Of course, An Bord Pleanála will, as a matter of daily practice, have to take a view on the
interpretation of development plans as part of its decision-making on individual planning
appeals and applications. This is entirely proper. There is no suggestion that the board
has to pause, and refer the question of interpretation to the High Court. Rather, the point
of the above analysis is that, in the event that a planning decision is challenged by way of
judicial review, then An Bord Pleanála’s view on the interpretation of the plan is subject to
full-blooded review, and not the attenuated form of review under the principles in
O’Keeffe v. An Bord Pleanála [1993] 1 I.R. 39.
27. In some instances, objectives of a development plan will—on their correct interpretation—
be formulated in broad terms, and it will be a matter of planning judgment as to how to
apply those objectives to any given planning application. However, the correct
interpretation of a development plan is always a logically anterior question to the
application of the plan’s objectives in the assessment of any particular development
proposal. This point is illustrated by the judgment of the UK Supreme Court in Tesco
“A provision in the development plan which requires an assessment of whether a
site is ‘suitable’ for a particular purpose calls for judgment in its application. But
the question whether such a provision is concerned with suitability for one purpose
or another is not a question of planning judgment: it is a question of textual
interpretation, which can only be answered by construing the language used in its
context. In the present case, in particular, the question whether the word ‘suitable,
in the policies in question, means ‘suitable for the development proposed by the
applicant’, or ‘suitable for meeting identified deficiencies in retail provision in the
area’, is not a question which can be answered by the exercise of planning
judgment: it is a logically prior question as to the issue to which planning judgment
requires to be directed.”
28. The judgment in Tesco Stores Ltd. has been cited with approval by the High Court in
Navan Co-ownership v. An Bord Pleanála [2016] IEHC 181 and Kelly v. An Bord Pleanála
DOES THE DESIGNATION APPLY TO THE APPLICATION SITE?
Page 8 ⇓
29. The 2016–2022 development plan comprises a written statement, consisting of a series of
chapters dedicated to particular issues, and a number of maps. It is indicated at the
outset of the plan that, in the event of a conflict, the written statement is to prevail over
the maps. See §1.1.4.3. as follows.
“The 14 No. County Development Plan Maps provide a graphic representation of the
proposals contained in the Written Statement and/or Appendices and indicate land
use zoning and control standards together with various other objectives of the
Council. The Maps do not purport to be accurate survey maps from which site
dimensions or other survey data can be determined. Should any potential conflicts
arise between the Written Statement and the County Maps the Written Statement
shall prevail.”
30. As flagged earlier, the principal dispute between the parties centres on whether the
application site is subject to the “institutional lands” designation. The starting point for
the hypothetical “reasonably intelligent person”, in seeking to address this question,
would be to consider the written statement of the development plan in order to identify
the policies and objectives applicable to institutional lands. The relevant policies and
objectives are set out in an appendix to this judgment. The intelligent reader would note
that it is the planning authority’s policy to retain the open character and/or recreational
amenity of these lands wherever possible.
31. The intelligent reader would then turn to Map 1 of the 2016–2022 development plan
which sets out a graphic representation of zoning objectives and other objectives
contained in the written statement. The legend to Map 1 indicates that the symbol “INST”
is employed to designate the objective “To protect and/or provide for Institutional Use in
open lands”. The language employed in the legend differs slightly from the written
statement which generally employs the term “institutional lands”. There is no definition
of “institution”, “institutional use” or “institutional lands” provided for under the 2016–
2020 development plan. Examples of institutional use are cited at §2.1.3.5 as follows:
education, residential or other such uses. A “residential institution” is defined under the
development plan, for the purposes of the use classes, as “A building or part thereof or
land used as a residential institution and includes a monastery, convent, hostel, home for
older persons/nursing home”.
32. The dictionary definition of “institution” includes an organisation founded for inter alia
religious and education purposes.
33. The “INST” symbol appears at a number of locations on Map 1. The size of the symbol is
always the same, i.e. the footprint of the symbol is not intended to delimit the lands
subject to the designation.
34. The application site is not separately identified in Map 1, but rather appears within a
larger overall area of lands. These lands are shown as being surrounded on three sides
by existing housing, and on the fourth by a road. The site coverage of these lands, i.e.
Page 9 ⇓
the proportion of the lands occupied by buildings and structures, is noticeably less than
the surrounding lands in residential use.
35. There are a number of factors which indicate that the intelligent reader of the
development plan would interpret it as applying the “institutional lands” designation to
the entire of the lands in the ownership of the religious congregation as of the date of the
adoption of the 2016–2022 development plan (March 2016) as follows.
36. First, the very description of the objective as per the legend to Map 1 emphasises the
open character of the lands so designated. The stated objective is to protect and/or
provide for institutional use in open lands. This is underscored by the relevant provisions
of the written statement of the development plan, in particular at §2.1.3.5 (Policy RES5:
Institutional Lands) and §8.2.3.4 (xi) (Institutional Lands), which expressly refer to the
“open character” of the lands. It is the stated policy of the planning authority to retain
the open character and/or recreational amenity of institutional lands wherever possible.
It would be entirely inconsistent with these objectives to interpret Map 1 as confining the
designation to the depicted buildings or structures within the immediate vicinity of the
“INST” symbol. To do so would exclude the open lands, which are the very thing to which
the development plan objectives and policies are directed.
37. Secondly, it is evident from the features depicted on Map 1 that—as of March 2016 at
least—the lands to the south-west were still in institutional use. In particular, a hockey
pitch associated with the secondary school (Jesus and Mary College) is depicted on the
map, and straddles part of what is now the application site. This hockey pitch had a
north-south alignment, and approximately one-third of the pitch lay within the application
site. The secondary school has since obtained planning permission, on appeal, for the
construction of a new synthetic all-weather hockey pitch. An Bord Pleanála’s decision to
grant planning permission is dated 14 March 2019. In reaching its decision to grant
planning permission for the new pitch, An Bord Pleanála expressly relied on the
“established use of the site for sports and recreation”. The new pitch has a different
alignment, i.e. east-west, than had the former hockey pitch, with the consequence that
the full of the new pitch lies outside the application site.
38. There had been some suggestion at the hearing before me that the former hockey pitch
may have fallen into disuse in more recent years, and that this is something of which the
intelligent reader of the development plan would have knowledge. This suggestion was
contested by the objector, Mr Redmond. Neither side addressed this issue specifically in
their affidavit evidence. At all events, it is obvious from the approach taken by An Bord
Pleanála in March 2019 to the application for a synthetic all-weather hockey pitch that the
established use of the hockey pitch had not been abandoned. The established use for
sports and recreation is expressly referenced by the board in its decision to grant
planning permission.
39. An Bord Pleanála’s direction records that it had “decided to grant permission generally in
accordance with the Inspector’s recommendation”. The inspector had addressed the
established use of the lands as follows at §7.1.2. of her report of 1 February 2019.
Page 10 ⇓
“The appeal site is within the grounds of an established Educational Institution, i.e.,
Jesus and Mary College and the proposed use is an ancillary use to the existing
secondary school. Furthermore, the proposal would replace the existing hockey
pitch. Therefore, I would consider that the proposed development represents a
replacement of an existing use and having regard to the zoning objective of the
area I would consider that the proposed development would be acceptable in
principle.”
40. It follows that the intelligent reader examining the development plan in March 2016 would
similarly understand that the lands occupied by the hockey pitch were associated with the
secondary school and remained in institutional use.
41. Thirdly, the intelligent reader would be aware that—with the exception of the lands which
were being transferred to the ownership of Durkan Estates Clonskeagh Ltd and have since
been developed as “The Grove”—the balance of the overall site remained in the ownership
of the religious congregation as of March 2016. As counsel for the developer correctly
noted, one of the factors which can be considered in identifying the relevant “planning
unit” is the ownership or occupation of the lands. Counsel referenced the well-known
judgment in Burdle v. Secretary of State for the Environment [1972] 1 W.L.R. 1207
(“Burdle”). This judgment suggests a three point test for identifying the relevant planning
unit as follows.
“First, whenever it is possible to recognise a single main purpose of the occupier’s
use of his land to which secondary activities are incidental or ancillary, the whole
unit of occupation should be considered.
[…]
But, secondly, it may equally be apt to consider the entire unit of occupation even
though the occupier carries on a variety of activities and it is not possible to say
that one is incidental or ancillary to another. This is well settled in the case of a
composite use where the component activities fluctuate in their intensity from time
to time, but the different activities are not confined within separate and physically
distinct areas of land.
Thirdly, however, it may frequently occur that within a single unit of occupation two
or more physically separate and distinct areas are occupied for substantially
different and unrelated purposes. In such a case each area used for a different
main purpose (together with its incidental and ancillary activities) ought to be
considered as a separate planning unit.”
42. The Court of Appeal, per Bridge J., then suggested the following “working rule”.
“It may be a useful working rule to assume that the unit of occupation is the appropriate
planning unit, unless and until some smaller unit can be recognised as the site of
activities which amount in substance to a separate use both physically and functionally.”
Page 11 ⇓
43. Counsel for the developer was careful to emphasise that Burdle is not a case concerned
with the interpretation of a development plan. Rather, it is a case concerning
enforcement proceedings and established use rights. Counsel also submitted that the
crucial date for determining whether lands are in institutional use must be the date of the
relevant application for planning permission. I will return to examine these submissions
in more detail under the next heading, at paragraph 48 below.
44. For present purposes, I am satisfied that the intelligent reader of the 2016–2022
development plan would attach weight to the ownership of the lands in identifying the
extent of the “institutional lands” designation. As of the date of the adoption of the
development plan, what is now the application site had been part of the overall lands in
the ownership of the religious congregation. These lands were being used for religious
and educational uses associated with the congregation.
45. Finally, it is necessary to address the principal argument relied upon by An Bord Pleanála
and the developer, which is to the effect that the precise location of the “INST” symbol
within the overall landholding would be regarded as significant by the intelligent reader.
More specifically, it was submitted that the location of the symbol in the north-east corner
of the overall landholding would be understood as drawing a clear demarcation between
the northern uses and the southern uses. The “INST” symbol was described as being
tucked on the north-eastern corner of the site where all of the school-related uses and
buildings are said to be. The south-western part of the site was described as being
unused at the time, and as not available for public access or recreation. The location of
the “INST” symbol was said to reflect the rationalisation of the institutional uses to the
north of the overall landholding.
46. With respect, there are a number of flaws in this argument, and I have concluded that it
does not represent the correct interpretation of the development plan for the following
reasons. (To avoid unnecessary duplication with the discussion above, the reasons are
stated in short form where there is an overlap with the earlier discussion. The reasons
which follow should be read in conjunction with that earlier discussion.)
(1). The contended for division of the overall landholding between institutional uses to
the north-east and non-institutional uses to the south-west ignores the fact that the
former hockey pitch continued to have an established institutional use, i.e. it had
an established use for sports which was ancillary to the secondary school. This
established use had been expressly recognised by An Bord Pleanála as recently as
March 2019 in its decision in respect of the new all-weather hockey pitch.
(2). The “open lands” to the south-west remained in the ownership of the religious
congregation as of March 2016. The written statement of the development plan
expressly refers to the “open character” of the lands. It would be illogical to
exclude open lands, which are the very thing to which the objectives and policies
are directed, from the designation.
Page 12 ⇓
(3). There are “INST” symbols dotted throughout Map 1. It would be immediately
apparent to the intelligent reader of the development plan that the precise location
of these “INST” symbols, relative to the particular open lands and structures to
which each individual symbol refers, does not follow any coherent pattern. There
are, for example, three “INST” symbols on lands to the north of the religious
congregation’s landholding. In the case of “Saint Killian’s Deutsche Schule”, the
symbol appears to have been placed in the vicinity of a playing field depicted on
Map 1, rather than placed on any of the depicted school buildings. For the lands to
the right of the German School, the symbol appears in the middle of the buildings,
but for the lands on the right, the symbol is away from the buildings. In the case
of the religious congregation’s own landholding, the symbol appears to be placed on
top of the depiction of the primary school (and not on both the primary and
secondary school). It can scarcely be suggested that the designation was confined
to the primary school.
Given the manner in which the placement of the “INST” symbol varies throughout
the map, the intelligent reader would assume that the precise location of the
symbol within an overall landholding was not intended to be determinative.
(4). The “INST” symbols are all of uniform size, and it appears from the scale on Map 1
that the symbol would only cover a footprint of roughly 50 m x 25 m. It is obvious,
therefore, that the designation cannot be confined to the lands immediately within
the footprint of the symbol.
47. In summary, therefore, I have concluded that the application site (which it will be recalled
had accommodated part of the secondary school’s hockey pitch) was subject to the
“institutional lands” designation as of the date of the adoption of the development plan in
March 2016. It is next necessary to consider whether the subsequent sale of the
application site altered the planning status of the site.
SALE OF THE APPLICATION SITE
48. As flagged under the previous heading, counsel for the developer placed much emphasis
on the transfer of ownership of the application site from the religious congregation to the
developer in 2017. The developer purchased some 2.34 hectares from the congregation.
Counsel for the developer confirmed that the sale was completed in October 2017 (Day 3
transcript, page 4).
49. The lands in sale included approximately one third of the north-south hockey pitch; and
lands which had been occupied by the former primary school and the former convent
building. The former primary school buildings were demolished after the new primary
school had been completed in August 2012. The new primary school is located to the
north-east. Planning permission for a new all-weather hockey pitch had been granted in
March 2019, and the new pitch is now located on the north-west part of the overall
landholding.
Page 13 ⇓
50. It is argued on behalf of the developer that the legal effect of this transfer of ownership in
October 2017 is that the lands in sale were no longer available to the institutional use.
51. The gravamen of the argument is that the extent of lands subject to the “institutional
lands” designation should be determined by reference to the use of the lands as of the
date that an application for planning permission for residential development is lodged,
and not the use of the lands as of the date the 2016–2022 development plan was adopted
(March 2016). The developer lodged the planning application, which culminated in the
planning permission impugned in these proceedings, on 10 May 2019. As of that date,
the application site was already in the ownership of the developer. The legal consequence
of this, it is said, is that the application site was no longer available to the institutional
use, and the designation no longer applied. It was further submitted that whereas the
interpretation of the development plan does not change, the practical extent of the
“institutional lands” designation on the ground did change as a result of the transfer of
ownership. (Day 3 transcript, page 20).
52. Before turning to examine the developer’s argument in detail, it should be noted that the
position adopted by An Bord Pleanála was more nuanced. The board’s position before the
High Court concentrated on what was said to have been the rationalisation of the
institutional uses on the north-eastern part of the overall landholding, rather than on the
change in ownership of the lands. The implication was that certain parcels of land had
ceased to be put to institutional use, and it was for this reason that the designation no
longer applied. Reference was made, in particular, to the relocation of the primary school
to the north-eastern part of the overall landholding, and the (alleged) disuse of the
hockey pitch. Counsel explained that An Bord Pleanála was not saying that one can
defeat a development plan by simply changing the ownership of lands. For example, it
was not being suggested that if the religious congregation had sold off the primary school
building that it would then cease to be in institutional use. (Day 2 transcript, pages 50 to
53).
53. Returning to the developer’s argument, I have concluded that the sale of the lands did not
have the radical effect in planning terms contended for by the developer. The rationale
for this conclusion is as follows.
54. The relevant policies and objectives of the development plan are intended to inform the
determination of planning applications which seek permission to authorise a material
change in the use of lands which have an established use as “institutional lands”. The
development plan seeks to balance the objective of maintaining lands in institutional use,
against the practical reality that, in some instances, there may no longer be a demand for
institutional use. It is expressly stated that where no demand for an alternative
institutional use is evident or foreseen, the planning authority may permit alternative
uses subject to the zoning objectives of the area and the open character of the lands
being retained. On the facts of the present case, the relevant zoning objectives would
allow for residential development.
Page 14 ⇓
55. On the developer’s argument, the elaborate provision made under the development plan
for regulating a change from an established institutional use to residential use would be
set at naught. The development plan objectives could be by-passed by the simple
expedient of a transfer of ownership. Lands which were subject to institutional use at the
time the development plan was made, and for which planning permission could only be
obtained by reference to the relevant development plan objectives, would be released
from these requirements by the stroke of a pen on a contract for sale. On this
interpretation, the only effect of the development plan would be to regulate the
development of the lands for so long as they remained in the ownership of the religious
congregation. The restriction would be peculiar to the congregation and would not serve
any wider planning purpose.
56. With respect, such an interpretation would make an absurdity of the development plan.
Development objectives are not intended to be personal or peculiar to individual
landowners. Rather, planning permission enures for the benefit of the land. The
developer’s argument ignores the fact that, as of the date of the adoption of the
development plan, the lands had an established institutional use. This established use
and designation is not lost by dint of a transfer of ownership. Rather, it remains until
such time as planning permission is granted for an alternative use, such as, for example,
residential use. The relevant development plan policies are precisely intended to regulate
the circumstances in which such a change in use might be authorised. It is illogical to say
that those policies did not bite on the planning application in the present case, an
application which sought planning permission to do the very thing which the development
objectives are designed to regulate, i.e. to change the authorised use from institutional
use to residential use.
57. Put otherwise, the development plan contains policies which govern the release of
institutional lands for residential development. Yet on the developer’s argument, these
policies simply do not apply to it. For the reasons set out above, this is an incorrect
interpretation of the development plan.
58. Finally, it should be reiterated that the fact that the application site is subject to the
“institutional lands” designation does not preclude the grant of planning permission for
residential development, for the following reasons. First, even on their own terms, the
development plan policies and objectives envisage that residential use may be permitted
in certain circumstances. Secondly, An Bord Pleanála is authorised to grant planning
permission in material contravention of the development plan. Thirdly, the provisions of
the development plan can be overridden by Ministerial guidelines issued under section 28
of the PDA 2000 (as amended). The Minister can include “specific planning policy
requirements” in guidelines. Where such specific planning policy requirements differ from
the provisions of the development plan, then those requirements shall, to the extent that
they so differ, apply instead of the provisions of the development plan. (See section 9(3)
of the PD(H)A 2016). (No reliance has been placed on any specific planning policy
requirements to justify a material contravention of the development plan on the facts of
the present case).
Page 15 ⇓
59. It also remains open to the new owners of the application site, i.e. the developer, to apply
to have the status of the lands changed as part of the next development plan cycle.
MATERIAL CONTRAVENTION OF ZONING OBJECTIVE?
60. For the reasons set out above, I have concluded that the application site is subject to the
development plan policies and objectives applicable to institutional lands. The next
question to be considered is whether the decision to grant planning permission involved a
material contravention of a zoning objective of the development plan.
61. The significance of the distinction between zoning objectives and non-zoning objectives is
that An Bord Pleanála is precluded from granting planning permission for strategic
housing development under the PD(H)A 2016 if the proposed development would
constitute a material contravention of the development plan or local area plan in relation
to the zoning of the land (section 9(6)(b)).
62. Map 1 of the 2016–2022 development plan indicates that the application site is subject to
the zoning objective “Objective A To protect and or improve residential amenity”.
63. There was some debate at the hearing before me as to whether the label which a
development plan attaches to a particular objective is conclusive on the question of
whether the objective is a zoning objective or not. Put shortly, does the fact that the
development plan describes a particular policy as a “zoning objective” make it such.
Counsel for the developer suggested that what a development plan labels as a “zoning
objective” may, in truth, entail a combination of zoning and non-zoning objectives.
Counsel cited, by way of example, a development plan which purported to zone an area
for “low density residential development”, and suggested that the policy in respect of
density does not form part of a zoning objective within the meaning of section 10 of the
PDA 2000.
64. For the reasons which follow, I have determined that whereas the label “zoning objective”
as employed under a development plan will usually coincide with the legal concept of a
zoning objective, the label cannot be conclusive. The concept of a zoning objective is a
term of art under the planning legislation. The concept is introduced under section
10(2)(a) of the PDA 2000 as follows.
“(2) Without prejudice to the generality of subsection (1), a development plan shall
include objectives for—
(a) the zoning of land for the use solely or primarily of particular areas for
particular purposes (whether residential, commercial, industrial, agricultural,
recreational, as open space or otherwise, or a mixture of those uses), where
and to such extent as the proper planning and sustainable development of
the area, in the opinion of the planning authority, requires the uses to be
indicated;”
65. A zoning objective enjoys an enhanced status over that of other policies and objectives
under a development plan. This is most immediately apparent from the provisions of
Page 16 ⇓
section 9(6)(b) of the PD(H)A 2016 discussed above. A zoning objective also has a
particular significance in the context of statutory compensation under Part XII of the PDA
2000. The general position under Part XII is that a decision to refuse planning permission
will attract the payment of statutory compensation if that decision has the effect of
reducing the value of an interest in the affected lands. This entitlement to compensation
is, however, subject to a large number of exceptions. Relevantly, compensation will not
be payable where planning permission has been refused for the following reason.
(Schedule 5 of the PDA 2000, paragraph 20).
“20. The development would contravene materially a development objective indicated in
the development plan for the zoning of land for the use solely or primarily of
particular areas for particular purposes (whether residential, commercial, industrial,
agricultural, recreational, as open space or otherwise or a mixture of such uses).”
66. (This is subject to certain safeguards which address the contingency of a change in zoning
objective having been made during the currency of the development plan).
67. The question of whether a particular development represents a material contravention of
a zoning objective thus has a special importance both to landowners and to the local
planning authority (as the entity liable to pay statutory compensation). It would be
unsatisfactory were the label that the planning authority attached to an objective in the
development plan to be conclusive of whether the objective was a zoning objective. Put
otherwise, the fact that a development plan mistakenly describes a particular policy as a
“zoning objective” cannot defeat a claim for compensation. It is clear from the case law
that the courts will consider the substance of the relevant development plan policy or
objective in order to determine whether or not it operates to exclude compensation. See,
for example, Ebonwood Ltd v. Meath County Council [2004] 3 I.R. 34.
68. Returning to the facts of the present case, the position is clear-cut. The zoning objective
applicable to the lands is “Objective A To protect and/or improve residential amenity”.
The institutional lands designation does not amount to a zoning objective. First, the
designation does not purport to override the residential zoning objective. Rather, the
policies and objectives triggered by the designation expressly recognise that residential
development may in principle be permissible, but seek to regulate the precise
circumstances in which residential development might be authorised and the conditions,
for example, in respect of open space, which might be attached to a grant.
69. Secondly, the limited extent of the lands subject to the designation suggests that the
designation is more akin to the reservation of land for a particular purpose, i.e. a form of
spot zoning, than to a general zoning objective. (cf. Monastra Developments Ltd v.
Dublin County Council [1992] 1 I.R. 468).
70. Finally, it is necessary to address an argument made by the objector by reference to the
treatment of institutional lands under the development plan of a different planning
authority, namely Dublin City Council. The original version of the Dublin City
Development Plan 2011–2017 had purported to regulate the development of institutional
Page 17 ⇓
lands by way of a zoning objective, namely “Z15 (To protect and provide for institutional
and community uses)”. A challenge to the validity of this zoning objective was taken on
behalf of the Sisters of Charity. The challenge was ultimately resolved on the narrow
grounds that adequate reasons for the impugned objective had not been stated. See
was remitted to the planning authority for reconsideration in the light of the findings of
the High Court, and a different form of objective was ultimately adopted.
71. Mr Redmond seeks to rely on the fact that Dublin City Council had sought to implement
its policies by way of a zoning objective in support of his argument that the policies and
objectives under the Dun Laoghaire Rathdown development plan 2016–2022 should be
characterised as a zoning objective. With respect, no useful analogy can be drawn
between the two development plans. The nature of the policies and objectives are
entirely different. Crucially, under the impugned version of the Dublin City Council
development plan, the relevant objective had excluded residential development as a use
which was either permissible or open for consideration. By contrast, on the facts of the
present case, the application site is subject to a residential zoning, and there is no
inconsistency between that zoning objective and the additional policies and objectives
which apply to institutional lands. The policies and objectives recognise that institutional
lands can be developed for residential use, but seek to regulate how and when this is
done.
72. In summary, a decision to grant planning permission for residential development on lands
subject to the “institutional lands” designation would not involve a material contravention
of a zoning objective under the 2016–2022 development plan. Consequently, the
impugned decision to grant planning permission does not fall foul of the prohibition under
section 9(6)(b) of the PD(H)A 2016.
MATERIAL CONTRAVENTION OF NON-ZONING OBJECTIVE?
73. The consequence of the finding that the application site is subject to the institutional
lands designation is that the planning application was subject to certain policies and
objectives under the 2016–2022 development plan, as set out at §2.1.3.5; §8.2.3.4 (xi)
and §8.2.8.2 (i). These sections of the development plan have been reproduced in full in
an appendix to this judgment.
74. The test for determining whether a contravention is material is that prescribed by the
High Court (Barron J.) in Roughan v. Clare County Council, unreported, High Court,
Barron J., 18 December 1996.
“It has been submitted on behalf of the Applicants that what is or is not a material
development has to be considered in the light of the substance of the proposed
development; whether or not any change of use would be significant; the location
of the proposed development; the planning history of the site or area; and the
objectives of the development plan. I accept that all these matters must be taken
into account when considering whether or not any proposed contravention of the
development plan is material. What is material depends upon the grounds upon
Page 18 ⇓
which the proposed development is being, or might reasonably be expected to be,
opposed by local interests. If there are no real or substantial grounds in the
context of planning law for opposing the development, then it is unlikely to be a
material contravention.”
75. This test has been very recently approved of by the High Court (Baker J.) in Byrnes v.
76. For the reasons which follow, I have concluded that the proposed development represents
a material contravention of the development plan policies and objectives in respect of
housing density and minimum open space. It is sufficient for the disposition of these
judicial review proceedings to find that these two policies and objectives have been
breached. These are fundamental provisions of the development plan, and the extent of
the contravention of same is “material” having regard to the principles set out in Roughan
(above).
77. The position in respect of other of the policies and objectives of the development plan is
more nuanced in that the application of same entails the exercise of subjective planning
expertise.
(i). Housing Density
78. The proposed development involves a material contravention of the relevant development
plan policy in respect of housing density. Policy RES 5, which is set out at §2.1.3.5 of the
development plan, addresses the housing density applicable to institutional lands as
follows.
“In the development of such lands, average net densities should be in the region of
35 - 50 units p/ha. In certain instances higher densities will be allowed where it is
demonstrated that they can contribute towards the objective of retaining the open
character and/or recreational amenities of the lands.”
79. The proposed development has a housing density of approx. 67 units per hectare. This
density is well in excess of 35 – 50 units per hectare. It is, of course, the case that Policy
RES 5 allows for higher densities in certain circumstances, i.e. where it is demonstrated
that the higher densities can contribute towards the objective of retaining the open
character and/or recreational amenities of the institutional lands. This reflects the
rationale underlying the 2009 Ministerial Guidelines on Sustainable Residential
Development in Urban Areas (cited by the objector), wherein it is indicated at §5.10 that
the objective of retaining the open character of institutional lands might be achieved by
concentrating increased densities in selected parts of the overall lands. A figure of 70
units per hectare is instanced in the guidelines.
80. There is no suggestion in the present case that An Bord Pleanála’s decision to authorise a
density of c.67 units per hectare had been informed by the objective of retaining the open
character and/or recreational amenities of the lands. Rather, the approach taken by the
Page 19 ⇓
inspector, and adopted by the board, had been to treat the application site as being
subject to a different policy, namely, Policy RES 3, which provides that, as a general rule,
the minimum default density for new residential developments shall be 35 units per
hectare. A higher minimum density of 50 units per hectare will be encouraged where a
proposed development is located within circa 1 kilometre pedestrian catchment of a rail
station, Luas line, BRT, Priority 1 Quality Bus Corridor and/or 500 metres of a Bus Priority
Route. The inspector accepted that none of those criteria were fulfilled by the application
site. The inspector addressed RES 3 as follows at §12.2.4 and §12.2.5 of her report.
“Policy RES 3 of the County Development Plan 2016-2022 requires a minimum
default density of 35 units per hectare for new residential development in areas
outside of e.g. a 1km pedestrian catchment of a Luas line, 1km from a Town or
District Centre etc. Densities of 50 units per hectare are required within these
catchments. The subject site is around a 1.4km walk to the nearest Luas stop and
town/district centre. As such, the required minimum default density of 35 units per
hectares applies.
Density at 67 units per hectare (132 no. units on a 1.969 hectare site) is
considered appropriate for this location and in compliance with relevant section 28
ministerial guidelines. The proposal to increase the density is considered
appropriate given the location of the site and the proposal is not considered to
represent overdevelopment of the site. The 3 no. proposed five-storey apartment
blocks have 109 no. apartments in total. Block A, the south western block, has 38
no. units; Block B the south eastern unit, has 38 no. units and Block C, the north
western block, has 33 no. units. There are 4 no. apartment units in Block D
comprising two ground floor apartments with 2 no. duplex apartments above. Unit
mix is good with 18 no. 1-bed units, 83 no. 2-bed units and 12 no. 3-bed units
proposed. This would lead to a good population mix within the scheme, catering to
persons at various stages of the lifecycle, in accordance with Specific Planning
Policy Requirements (SPPRs) in the Sustainable Urban Housing: Design Standards
for New Apartments’ Guidelines 2018. The proposal for higher density at this
location accords with Ministerial Guidelines.
The Urban Development and Building Heights Guidelines for Planning Authorities
(2018) relate to building heights for apartment buildings. Reusing brownfield land
and building up urban infill sites is required to meet the needs of a growing
population without growing urban areas outwards and ‘increased building height is
a significant component in making optimal use of the capacity of sites in urban
areas…’ Section 3.1 states that ‘it is Government policy that building heights must
be generally increased in appropriate urban locations. There is therefore a
presumption in favour of increased heights in … urban locations with good public
transport accessibility’. The site is proximate to public transport, with bus routes
on Goatstown Road and the NTA report is supportive of the proposed
development.”
Page 20 ⇓
81. As appears, the justification for the higher density of 67 units per hectare seems to have
been informed by factors such as that the site was proximate to the bus routes on the
Goatstown Road. (These are not Priority 1 Quality Bus Corridors). It also seems that the
inspector had accepted the submission made by the developer that the application site
should be characterised as an “intermediate urban location” under the statutory
guidelines, Sustainable Urban Development: Design Standards for New Apartment (March
2018). It should be noted that whereas those guidelines do contain certain “specific
planning policy requirements” or “SPPRs”, same do not relate to housing density.
82. In summary, therefore, the board erred in finding that the proposed development was
subject to the housing density set out at RES 3. Rather, the housing density to be applied
was that provided for under RES 5. The planning permission purports to authorise a
density of c.67 units per hectare. This density exceeds that generally provided for under
RES 5, i.e. 35 units per hectare, and does not meet the criteria for higher density under
RES 5 because the permitted density does not contribute towards the objective of
retaining the open character and/or recreational amenities of the institutional lands.
83. Counsel for An Bord Pleanála made the point at the hearing before me that the argument
in relation to RES 5 was one advanced by the objector alone. More specifically, the
planning authority had not recommended the refusal of planning permission on the basis
that the density breached RES 5.
84. This submission is correct insofar as it goes. However, in circumstances where the
interpretation of a development plan, and, in particular, the determination of whether or
not a proposed development would involve a material contravention of the development
plan, is a question of law for the court, then the views of neither the planning authority
nor An Bord Pleanála can be decisive. Put otherwise, the fact that the planning authority
does not appear to have appreciated that the development would involve a material
contravention of RES 5 does not preclude the court from reaching a contrary view in these
judicial review proceedings. The argument that the proposed development involved a
breach of RES 5 had been expressly raised by the objector in his submission to An Bord
Pleanála, and, again, at the hearing before me. For the reasons set out above, I am
satisfied that the objector’s argument is well founded, and that there is, indeed, a
material contravention of RES 5.
(ii). Minimum open space provision
85. The proposed development also involves a material contravention of the relevant
development plan policy in respect of open space provision. The development plan
requires a minimum open space provision of 25% of either (i) the total site area, or (ii) a
population based provision, whichever is the greater. This open space provision must be
sufficient to maintain the open character of the site.
86. The relevant parts of the policy, as set out at §8.2.3.4 (xi), read as follows.
Page 21 ⇓
“There are still a number of large institutions in the established suburbs of the
County which may be subject to redevelopment pressures in the coming years.
The principal aims of any eventual redevelopment of these lands will be to achieve
a sustainable amount of development while ensuring the essential setting of the
lands and the integrity of the main buildings are retained. In order to promote a
high standard of development a comprehensive masterplan should accompany a
planning application for institutional sites.* Such a masterplan must adequately
take account of the built heritage and natural assets of a site and established
recreational use patterns. Public access to all or some of the lands may be
required. Every planning application lodged on institutional lands shall clearly
demonstrate how they conform with the agreed masterplan for the overall site.*
Should any proposed development deviate from the agreed masterplan then a
revised masterplan shall be agreed with the Planning Authority.
A minimum open space provision of 25% of the total site area* (or a population
based provision in accordance with Section 8.2.8.2 whichever is the greater) will be
required on Institutional Lands. This provision must be sufficient to maintain the
open character of the site - with development proposals built around existing
features and layout, particularly by reference to retention of trees, boundary walls
and other features as considered necessary by the Council.”
*Emphasis (italics) added.
87. An Bord Pleanála and the developer contend that the proposed development achieves this
open space provision. (The figure is calculated by reference to the population
equivalent). This contention is, however, predicated on interpreting the phrase “the total
site area” as referring only to the application site, i.e. the lands within the red line of the
planning application, and as not referring to the overall institutional lands. With respect,
this interpretation is incorrect. The precise purpose of the objective under §8.2.3.4 (xi) is
to ensure that the open character of the institutional lands is maintained. This purpose
would be defeated if the minimum open space requirement were to be confined to the
part of the institutional lands to be developed.
88. The position is correctly stated by the planning authority at page 17 of the chief
executive’s report as follows.
“The second requirement for ‘INST’ sites is that 25% of the site area or a
population-based equivalent, whichever is higher, of public open space be provided
‘sufficient to maintain the open character of the site’. The applicant asserts that
28.9% of the ‘red line’ site is provided as public open space. However, it is the
planning authority’s assertion that this 25% requirement should apply to the
entirety of the campus, rather than in a piecemeal fashion. The intention of the
policy is clearly to retain the ‘open character’ of the site, and this can only be done
by way of a comprehensive approach. Heretofore, the planning permissions on site
have developed the campus to a relatively high intensity, while the western and
south-western portions of the campus have remained effectively greenfield,
Page 22 ⇓
preserving the open nature of the campus, and maintaining the aggregate open
space at above 25%. It is only the subject application that has the potential to
drop the open space across the campus to below the 25% mark. As such, it is at
this point that the matter must be given serious consideration.
There has been no assessment of the public open space provision across the
campus provided by the applicant, but it is evident from a cursory consideration of
the proposed layout that a level of 25% would not be achieved. As such, the
planning authority considers that the proposed development is contrary to the
policies of the CDP, and should be refused on this basis.”
89. The second of the three reasons for refusal recommended by the planning authority reads
as follows.
“The proposed development, by virtue of reducing the provided and potential public
open space across Our Lady’s Grove campus to a level below 25%, and by virtue of
the removal of the vast majority of trees from within the subject-site, would be
contrary to Section 8.2.3.4 (xi) of the Dun Laoghaire-Rathdown-County
Development Plan 2016–2022.”
90. In circumstances where I have concluded that there has been a material contravention of
the 25% open space requirement, it is unnecessary to go further and consider whether
there is an additional material contravention by virtue of the removal of trees. The first
finding on its own has the consequence that the planning permission is invalid.
91. Finally, for the sake of completeness, it is open to the court to make a finding of material
contravention notwithstanding that the planning authority itself merely refers to the
proposed development being “contrary” to §8.2.3.4 (xi). The question of whether or not
there is a material contravention is, ultimately, a question of law for the court.
(iii). Future provision of additional educational facilities
92. A further consequence of An Bord Pleanála’s error in failing to recognise that the
application site was subject to the “institutional lands” designation is that the board did
not properly take into account the possible need for the provision of additional school
facilities. This was a matter which required to be taken into account under RES 5. See
§2.1.3.5 of the development plan as follows.
“In cases of rationalisation of an existing institutional use, as opposed to the
complete cessation of that use, the possible need for the future provision of
additional facilities related to the residual retained institutional use retained on site
may require to be taken into account. (This particularly applies to schools where a
portion of the site has been disposed of but a school use remains on the residual
part of the site.)”
93. There is nothing on the face of An Bord Pleanála’s decision to indicate that it took this
matter into account. Indeed, there is no reference at all to the existing schools in the
Page 23 ⇓
board’s formal decision. For the reasons discussed at paragraph 124 et seq. below, the
board is not entitled to call in aid the inspector’s report in this regard.
MISINTERPRETATION IS AN ERROR OF LAW
94. The misinterpretation of the development plan is an error of law which goes to
jurisdiction. An Bord Pleanála is under an express statutory obligation to have regard to
the development plan in determining an application for planning permission under the
PD(H)A 2016 (see section 9(2)(a)). It is a necessary corollary of this obligation that the
board must correctly interpret the development plan. A decision-maker cannot be said to
have properly had regard to objectives or policies which it has misunderstood.
CHIEF EXECUTIVE’S REPORT
95. It is alleged that An Bord Pleanála failed to consider the recommendations made in the
statutory report from the planning authority, and that this represents a breach of the
requirements of section 9(1)(a) of the PD(H)A 2016. To put this allegation in context, it
is necessary to rehearse the relevant legislative provisions in respect of the planning
authority’s report.
96. Section 8 of the PD(H)A 2016 requires the chief executive of a planning authority, in
whose area a proposed strategic housing development would be situated, to prepare a
report (“the chief executive’s report”). The report must set out, inter alia, the chief
executive’s views on the effects of the proposed development on the proper planning and
sustainable development of the area of the planning authority and on the environment.
97. There are a number of specific matters which must be addressed in the chief executive’s
report as follows (section 8(5)(b)).
“(b) In the report referred to in paragraph (a) the planning authority shall—
(i) set out the authority’s opinion as to whether the proposed strategic housing
development would be consistent with the relevant objectives of the
development plan or local area plan, as the case may be,
(ii) include a statement as to whether the authority recommends to the Board
that permission should be granted or refused, together with the reasons for
its recommendation, and
(iii) specify in the report—
(I) where the authority recommends that permission be granted, the
planning conditions (if any), and the reasons and grounds for them,
that it would recommend in the event that the Board decides to grant
permission, or
(II) if appropriate in the circumstances, where the authority recommends
that permission be refused, the planning conditions, and the reasons
and grounds for them, that it would recommend in the event that the
Board decides to grant permission.”
98. As appears, the planning authority is obliged to state whether it recommends that
permission should be granted or refused, together with the reasons for its
Page 24 ⇓
recommendation. In circumstances where the planning authority recommends that
permission be refused, the authority may nevertheless go on to specify the planning
conditions that it would recommend in the event that the board decides to grant
permission. Where the planning authority does specify conditions, then it must also
specify the reasons and grounds for those conditions.
99. On the facts of the present case, the chief executive’s report had recommended that
planning permission be refused on three grounds. (These are set out in an appendix to
this judgment). The report then specifies some twenty-five planning conditions that the
planning authority would recommend in the event that the board decided to grant
permission. The third of these conditions assumes a particular significance given the
manner in which the application was addressed by the inspector. The recommended
condition reads as follows.
“3. The area in the northeast of the campus identified as ‘Option Site’ shall be used for
education purposes only. The area of public open space within the subject site shall
be made available for use by all users of the wider Our Lady’s Grove campus,
including the schools.
Reason: in the interests of providing for the existing and future needs of the
educational uses on the campus.”
100. This condition had been replicated by the inspector in her report, but subsequently
omitted by An Bord Pleanála from its decision. I will return to consider this condition at
paragraph 124 below.
101. The objector’s complaint is that the recommendations in the chief executive’s report were
not considered in any meaningful way by An Bord Pleanála.
102. In practical terms, the only basis on which a member of the public, the planning authority
and, ultimately, the court, can assess whether An Bord Pleanála did properly consider the
chief executive’s report is by reference to the reasons and considerations stated for the
board’s decision. Whereas An Bord Pleanála is not, of course, in any sense bound by the
recommendations in the chief executive’s report, it should be evident that the board has
considered the recommendations. Were it otherwise, the High Court would be unable to
exercise its supervisory jurisdiction to ensure compliance with section 9(1)(a)(i) of the
PD(H)A 2016.
103. On the facts of the present case, there is no express reference in the formal decision of
An Bord Pleanála to the chief executive’s report at all. It is, however, clear from the
inspector’s report that same was considered by her, and, in particular, reference is made
in the inspector’s report both to the recommended reasons for refusal, and to the
recommended conditions as per the chief executive’s report.
104. There are, in effect, two strands to the objector’s arguments in respect of this ground of
challenge. First, it is submitted that An Bord Pleanála should have addressed the chief
Page 25 ⇓
executive’s report in its formal decision. Secondly, it is submitted that even if the board
is to be taken as having adopted the inspector’s report, that report does not engage in
any meaningful way with the chief executive’s recommendations. I address each of these
arguments in turn under separate headings below.
(i). An Bord Pleanála and the inspector’s report
105. The first issue to be addressed is whether the analysis in the inspector’s report can be
imputed to An Bord Pleanála. This issue falls to be resolved by reference to the legal
principles set out by the Supreme Court in Connelly v. An Bord Pleanála [2018] IESC 31;
reasons for a decision may be derived in a variety of ways, either from a range of
documents or from the context of the decision, or in some other fashion. This is subject
always to the requirement that the reasons must actually be ascertainable and capable of
being determined. In the specific context of planning decisions, the Supreme Court
accepted that in assessing the adequacy of reasons, it was appropriate to have regard not
only to An Bord Pleanála’s formal decision, but also to the report prepared in respect of
the planning appeal by an inspector employed by An Bord Pleanála. The inspector’s
report is made available to the public at the same time as the board’s decision is notified.
The Supreme Court further accepted that it might also be appropriate to have regard to
the documentation accompanying the planning appeal, including documentation
submitted by the applicant for planning permission, i.e. the proposed developer.
106. The Supreme Court indicated that it would be preferable in all cases if An Bord Pleanála
made expressly clear whether it accepts all of the findings of its inspector or, if not so
doing, where and in what respect it differs. Failure to do so is not, however, necessarily
fatal if in the circumstances it is possible to reach a significantly clear inference as to what
the board thought in that regard.
107. Where the board differs from its inspector, then there is clearly an obligation for the
board to set out the reasons for coming to that conclusion in sufficient detail to enable a
person to know why the board differed from the inspector, and also to assess whether
there was any basis for suggesting that the board’s decision is thereby not sustainable.
108. I turn now to apply these principles to the facts of the present case. The board’s formal
decision does not expressly adopt the inspector’s report, nor does it expressly accept the
report’s findings. As stated by Clarke C.J. in Connelly, it would be preferable in all cases
if the board made expressly clear whether it accepts all of the findings of an inspector.
109. The board direction, which is the precursor to the board’s formal decision and is published
on the board’s website, does record that the board “decided to grant permission generally
in accordance with the Inspector’s recommendation”. The content of the board’s formal
decision is broadly similar to that of the inspector’s recommended form of decision. One
distinction between the two documents is that the formal decision omits any express
finding to the effect that the proposed development is consistent with the development
plan. The inspector’s recommended form of decision had expressly stated that the
Page 26 ⇓
nature, scale and design of the proposed development is consistent with the provisions of
the 2016–2022 development plan.
110. A second distinction is that the board’s formal decision also omits a condition stipulating
that an area in the north-east of the overall landholding was to be used for education
purposes only. The text of this recommended condition is set out at paragraph 124
below.
111. It seems reasonable to infer that—with the exception of the treatment of the future
expansion of the existing school sites—the board accepted the findings in the inspector’s
report. In particular, I am satisfied that the board agreed with the inspector’s (mistaken)
finding at §12.1.8 of her report that the application site is not subject to the institutional
lands designation. (This finding appears to have been predicated on (i) the location of the
“INST” symbol to the north-east of the lands, and (ii) the fact that the application site is
now in private ownership).
112. It is correct to say, as the objector does, that An Bord Pleanála’s formal decision does not
contain an express finding to the effect that the lands were not subject to the
“institutional lands” designation. It would have been preferable if the formal decision had
set out an express finding on this issue, and on the related issue of the appropriate
housing density. It is also, perhaps, unfortunate that the inspector’s discussion at
§12.1.9 segues from a finding that there is no material contravention to a suggestion that
a material contravention would be justified in any event. It would have been preferable if
there had been an unequivocal statement by the inspector that she was finding that the
application site was not subject to the “institutional lands” designation, and that her
subsequent observations, i.e. that a material contravention would be justified, were made
in the alternative only.
(ii). Does inspector’s report contain a proper consideration of chief executive’s report
113. Having ruled that the inspector’s findings can be imputed to An Bord Pleanála—with the
exception of her findings on the issue of the future expansion of the existing schools—it is
next necessary to consider whether the inspector’s report demonstrates that the chief
executive’s report has been properly considered as required under section 9(1)(a) of the
PD(H)A 2016.
114. Counsel on behalf of An Bord Pleanála and the developer both made much of the fact that
there is no express requirement under the PD(H)A 2016 to state the reasons for not
following the recommendations in the chief executive’s report. This was contrasted with
the requirement, in the case of a conventional planning application, to state reasons for
not accepting the recommendation of the board’s inspector. See section 34(10)(b) of the
PDA 2000 as follows.
“(b) Where a decision by a planning authority under this section or by the Board under
section 37 to grant or to refuse permission is different, in relation to the granting or
refusal of permission, from the recommendation in—
Page 27 ⇓
(i) the reports on a planning application to the chief executive (or such other
person delegated to make the decision) in the case of a planning authority, or
(ii) a report of a person assigned to report on an appeal on behalf of the Board,
a statement under paragraph (a) shall indicate the main reasons for not accepting
the recommendation in the report or reports to grant or refuse permission.”
115. This submission is correct insofar as it goes. It would, however, be a mistake to read too
much into the absence of an express provision requiring An Bord Pleanála to indicate the
main reasons for not accepting the recommendations in the chief executive’s report.
First, there is an important distinction between the respective reports of the board’s
inspector and the chief executive. The former is an internal report which is prepared by
an employee or agent of An Bord Pleanála. The latter is prepared by a separate
competent authority, namely the local planning authority. The report contains not only
the views of the chief executive, but also those of the “relevant elected members” as
defined. Article 28A of the Constitution of Ireland expressly recognises the role of local
government in providing a forum for the democratic representation of local communities,
in exercising and performing at local level powers and functions conferred by law and in
promoting by its initiatives the interests of such communities. See, generally, Christian v.
“It seems to me that the provisions of Article 28A of the Constitution, and the more
detailed measures cited from the Local Government Act 2001, provide a
constitutional and legal acknowledgement of the importance of the role of local
representative democracy in our constitutional model. It remains, of course, the
case that local authorities have no inherent jurisdiction. The power of local
government authorities to make decisions affecting the rights and obligations of
parties must be found in statute. However, it does seem to me that it is open to the
Oireachtas, in the light of the provisions of Article 28A, to confer a wide degree of
policy discretion on local authorities. That is not, however, to say that local
authorities are entirely at large. They operate within the parameters of an enabling
statute even though that statute may, in its terms, confer a broad policy discretion
on the local authority concerned. Against those broad observations on the status of
local authority decision making it is next necessary to turn to the case law in
relation to development plans.”
116. The obligation for An Bord Pleanála to engage with the recommendation set out in the
chief executive’s report is more obvious than the obligation to engage with an internal
report such as that prepared by a board inspector. This may explain why the Oireachtas
considered it necessary to impose the express statutory obligation to do so in the case of
the latter (section 34(10)(b) of the PDA 2000).
117. Secondly, and in any event, there is an implied obligation upon a decision-maker to
address submissions which are properly made to it. The nature of this obligation has
been stated as follows by the Supreme Court in Balz v. An Bord Pleanála [2019] IESC 90,
[57].
Page 28 ⇓
“[…] It is a basic element of any decision-making affecting the public that relevant
submissions should be addressed and an explanation given why they are not
accepted, if indeed that is the case. This is fundamental not just to the law, but
also to the trust which members of the public are required to have in decision
making institutions if the individuals concerned, and the public more generally, are
to be expected to accept decisions with which, in some cases, they may profoundly
disagree, and with whose consequences they may have to live.”
118. The above statement was made in the context of submissions made by members of the
public in respect of an application for planning permission. It follows that the same
obligation must apply a fortiori to a statutory consultee, such as the local planning
authority, which is required to submit a formal report in prescribed form to An Bord
Pleanála.
119. Put otherwise, the recommendations in the chief executive’s report cannot have a lesser
status than submissions made by a member of the public. Thus, notwithstanding that
there is no express statutory provision imposing an obligation to do so, the board is
required to address the recommendations set out in the chief executive’s report. This
does not entail an obligation to produce a discursive judgment nor a point-by-point
refutation of the statutory report. It must, however, be clear to a person reading An Bord
Pleanála’s decision, in conjunction with the inspector’s report, as to why the planning
authority’s recommendation to refuse planning permission was not accepted.
120. This obligation is consistent with the purpose which a duty to state reasons serves, as
identified by the Supreme Court in Connelly (cited earlier). Clarke C.J. formulated the
legal requirements against which the adequacy of reasons may be tested as follows.
First, any person affected by a decision is entitled to know in general terms why the
decision was made. This requirement derives from the obligation to be fair to individuals
affected by binding decisions, and also contributes to transparency. Second, a person is
entitled to have enough information to consider whether they can or should seek to avail
of any appeal or to apply for judicial review of a decision. The reasons provided must
also be such as to allow a court hearing an appeal or reviewing a decision to engage
properly in such an appeal or review.
121. I turn now to apply these legal principles to the facts of the present case.
122. It is evident from the inspector’s report that the inspector gave careful consideration to
the chief executive’s report. The reasons for the recommendation to refuse planning
permission are set out in full. The inspector addresses the reasons and explains why she
does not accept the recommendation, as follows.
123. The gist of the first recommended reason for refusal had been that the proposed
residential development would adversely affect the ability of the two existing schools to
expand. This is addressed at §12.1.7 and §12.1.8 of the inspector’s report.
Page 29 ⇓
“Policy SIC8 relates to both the provisions of new schools and the expansion of
existing schools. The Department of Education has no objection to the reduction in
the size of the existing school’s campus. Should the subject planning application be
successful, it is the applicant’s intention to transfer the ‘Option Site’ (an area to the
north of the Primary School) to the DoES for the sole use of the primary school for
educational use.* The development of the subject site, which are privately owned
lands, does not preclude the extension of the existing schools within their sites. It
is noted that the sale of the subject lands included the provision of a new all-
weather hockey pitch, which will enhance the Secondary Schools facilities. Planning
permission has been granted for this synthetic all-weather pitch on foot of Reg. Ref.
ABP-302898-18. It is submitted that the DoES did not seek to purchase the lands
when they were placed on the open market by the RJM in 2017.
The Development Plan does not indicate that the subject lands have been identified
(and reserved) for educational development. The legal opinion from Eamon Galligan
SC enclosed with the application is highlighted. Policy SIC8 makes it clear that
potential school sites are to be identified in the Development Plan. Regard being
had to the position of the planning authority that ‘INST’ Objective does apply to the
subject site and overall lands, I am of the opinion that it is clearly placed on the
school lands to the north of the subject lands. The lands the subject of this
application are zoned objective ‘A’, are in private ownership and the ‘INST’ local
Objective only refers to general institutional purposes and does not amount to the
identification of the relevant lands specifically for school or educational purposes.”
*Emphasis (italics) added.
124. As appears, one of the factors which informed the inspector’s findings was that the
applicant for planning permission, i.e. the developer, intended to transfer an area to the
north of the existing primary school to the Department of Education and Skill for
educational use (in the event that planning permission was granted). Crucially, the
inspector recommended a planning condition to address this contingency as follows. (This
replicates a condition recommended as part of the chief executive’s report).
“3. The area in the northeast of the campus identified as ‘Option Site’ shall be used for
education purposes only. The area of public open space within the subject site shall
be made available for use by all users of the wider Our Lady’s Grove campus,
including the schools.
Reason: In the interests of providing for the existing and future needs of the
educational uses on the campus.”
125. An Bord Pleanála omitted this recommended condition from its decision to grant planning
permission. This difference in approach between the board and the inspector creates an
inescapable difficulty for the board in attempting to rely on the inspector’s reasoning on
this issue. At least part of the inspector’s explanation for not accepting the
recommendation in the chief executive’s report to refuse planning permission had been
Page 30 ⇓
that the area to the north-east would be reserved for educational use. This was to be
achieved by way of the recommended condition. An Bord Pleanála chose to omit this
condition. (This appears to be the only substantive difference between the conditions
imposed by the board, and those recommended by the inspector). The board has,
however, failed to explain in its decision what approach it took to the question of the
possible future expansion of the existing schools. Indeed, it is a remarkable feature of
the board’s formal decision that it makes no reference at all to the existing schools nor to
the implications for same of the proposed residential development. This is so
notwithstanding that this was one of the principal objections raised by the planning
authority in the chief executive’s report: the planning authority went so far as to
characterise it as a material contravention of the development plan.
126. Counsel for An Bord Pleanála sought to offer a (belated) explanation for the omission of
the condition by suggesting that the recommended condition would be ultra vires having
regard to the judgment of the Supreme Court in Ashbourne Holdings Ltd. v. An Bord
Pleanála [2003] 2 IR 114 (even allowing for the subsequent amendments to the power
to attach conditions introduced by the Planning and Development (Strategic
Infrastructure) Act 2006). The submission does not provide any insight as to what
approach the board actually took to the possible future expansion of the existing schools.
Even if, as suggested by counsel, An Bord Pleanála may have thought that a condition
requiring the reservation of land for school expansion would be ultra vires, the board was
still required to address the planning authority’s recommended reason for refusal, and to
provide an explanation as to why it was not accepted. We simply do not know, for
example, whether the board considered the land would be provided to the Department of
Education and Skills even in the absence of a condition, or, alternatively, whether the
board considered that the future expansion of the schools might be met in some other
way. Perhaps the board took the view that it was not possible to give effect to the
development plan policy.
127. The one thing which is certain, however, is that the board cannot rely on the inspector’s
reasoning on this issue. The inspector’s finding is predicated on the putting in place of a
legal mechanism, i.e. the proposed planning condition, to ensure that the area in the
north-east be used for educational purposes only. This plank of the reasoning fell away
once the recommended condition was omitted.
128. Finally, for the sake of completeness, it should be noted that, in a number of recent
judgments, reliance has been placed on the fact that the board imposed planning
conditions in substantially the same terms as those recommended by the inspector, as
supporting the inference that the board had accepted the inspector’s report. (See, for
example, Buckley v. An Bord Pleanála [2015] IEHC 572, [117] and Sliabh Luachra Against
Ballydesmond Windfarm Committee v. An Bord Pleanála [2019] IEHC 888, [114]). It
seems to follow as a corollary that where the board has omitted a recommended
condition, which addresses a matter of significance, that the board must have differed
from its inspector on this aspect of his or her report. (This is to be contrasted with a
Page 31 ⇓
scenario where the board merely makes minor revisions to the recommended conditions
or amalgamates two or more of the recommended conditions).
129. The position in respect of the second and third reasons for refusal recommended in the
chief executive’s report is different. The second and third reasons are concerned with the
provision of public open space and the retention of trees. The explanation for the
difference in approach between the chief executive’s report and the inspector’s report is
explicable by reference to a disagreement on the question of whether the application site
was subject to the “institutional lands” designation. The chief executive’s report proceeds
on the basis that the designation does apply, and hence assesses the planning application
by reference to the policies and objectives at §8.2.3.4 (xi) of the development plan. By
contrast, the inspector had concluded—mistakenly—that the designation did not apply.
The error, which was replicated by An Bord Pleanála, means that the decision is invalid for
the reasons set out under the previous headings above. However, insofar as the specific
ground of challenge now under discussion, namely the alleged failure to properly consider
the chief executive’s report, is concerned, it is clear that the inspector did engage with
these issues.
130. In summary, therefore, the inspector’s report does consider and engage with the reasons
for refusal recommended in the chief executive’s report as required under section 9(1)(a)
of the PD(H)A 2016. This engagement does, however, disclose an error of law in respect
of the interpretation of the development plan. Save with the exception of the issues
concerning the implications of the proposed residential development for the possible
future expansion of the existing schools, the inspector’s approach can be imputed to An
Bord Pleanála.
131. There has been a breach of section 9(1)(a) insofar as the board has failed to explain in its
decision what approach it took to the question of the possible future expansion of the
existing schools and as to why it disagreed with the first of the recommended reasons for
refusal.
PRE-APPLICATION CONSULTATIONS
132. The objector makes a number of complaints in respect of procedural steps which occurred
prior to the making of the application for planning permission. In order to put these
complaints in context, it is necessary first to rehearse what might be described as the
“pre-application procedure”.
133. One of the unusual features of the PD(H)A 2016 is that it imposes a mandatory
requirement for consultation between (i) the prospective applicant for planning
permission; (ii) An Bord Pleanála; and (iii) the local planning authority, prior to the
making of an application for planning permission. In brief, the objective of this pre-
application consultation is to allow An Bord Pleanála to form an opinion as to whether or
not the documents submitted by the prospective applicant constitute a “reasonable basis”
for an application. If the board’s opinion is that the documents as submitted require
further consideration and amendment, then the board sets out, in a notice, its advice as
to the issues that need to be addressed in the documents. There is no provision for the
Page 32 ⇓
submission of further information once the planning application has been made, and
hence the importance of ensuring that all relevant issues have been addressed in
advance.
134. The PD(H)A 2016 obliges a prospective applicant to consult with the local planning
authority prior to its pre-application consultation with An Bord Pleanála. Thereafter, the
planning authority concerned must submit copies of all records of the consultation(s) held
with the prospective applicant to the board. As explained presently, the complaint made
in this case involves an allegation that this part of the procedure has not been complied
with in full.
135. A similar two-stage process, involving a pre-application consultation in advance of the
making of the planning application, is to be found in the context of the “strategic
infrastructure development” or “SID” procedure under the PDA 2000 (as inserted by the
Planning and Development (Strategic Infrastructure) Act 2006).
136. The question of whether such pre-application consultations might undermine public
participation in the formal planning process has been considered by the Supreme Court in
Callaghan v. An Bord Pleanála [2018] IESC 39; [2018] 2 I.L.R.M. 373. The Supreme
Court, per Clarke C.J., emphasised that An Bord Pleanála cannot be bound or influenced
by the pre-application consultation.
“It seems to me to clearly follow that, unless the relevant legislation contains clear
provision to the contrary, the proper interpretation of legislation involving a two
stage process must be that any matters determined at an earlier or preliminary
stage where an interested party is not entitled to be heard must remain open for
full re-consideration at the stage when a final decision potentially affecting the
rights or obligations of any individual is to be made. It follows in turn that the
default position in this case must be that the Board cannot be bound or influenced
by its earlier decision to go down the SID route when considering the strategic
importance of the proposed development in the context of making a final decision
as to whether to grant permission.”
137. The same logic applies, by analogy, to the two-stage process provided for in the case of
strategic housing development under the PD(H)A 2016.
138. The Oireachtas has been careful to ensure that the pre-application consultation process—
which it will be recalled does not involve public participation—does not give rise to any
reasonable apprehension of prejudgment or predetermination on the part of the board in
respect of the subsequent planning application. The PD(H)A 2016 expressly precludes
any reliance being placed on the pre-application stage in the determination of the
subsequent planning application. Section 6(9) reads as follows.
(9) Neither—
(a) the holding of a consultation under this section, nor
Page 33 ⇓
(b) the forming of an opinion under this section,
shall prejudice the performance by the Board, or the planning authority or
authorities in whose area or areas the proposed strategic housing development
would be situated, of any other of their respective functions under the Planning and
Development Acts 2000 to 2016, or any other enactment and cannot be relied upon
in the formal planning process or in legal proceedings.
139. An almost identical statutory prohibition on the placing of reliance upon pre-application
consultations in the formal planning process is to be found in the case of strategic
infrastructure development (section 37C of the PDA 2000), and in the case of pre-
application consultations with a planning authority (section 247 of the PDA 2000). The
practical implications of these types of prohibition have been explained as follows by the
High Court (Haughton J.) in O’Flynn Capital Partners v. Dun Laoghaire Rathdown County
“It follows that, in general, reports and recommendations from planning or other
local authority officials prepared in the course of the formal planning process in
response to a planning application should not rely upon advice given or received at
any statutory pre-planning consultation, and in turn should not be relied upon by
the decision maker(s) when considering or determining the application.
There will be some circumstances in which it may be permissible for reference to be
made to pre-planning consultations. For instance, it is difficult to see how an
applicant could realistically object to a simple listing in a planner’s report of the
pre-planning consultations. It may be that documentation furnished at such a
meeting, if furnished with the intention that it would used in a planning application,
would not be covered by the s. 247(3) prohibition. It must also be open to an
applicant for judicial review who asserts that there was improper reliance by a
planning authority on the content of pre-planning consultations in ‘the formal
planning process’ to refer to sufficient material to support a case for breach of s.
247(3). There may be other exceptional circumstances in which evidence from a
pre-planning consultation may be admissible, for example, where an egregious
comment at such a meeting gives rise to an allegation of actual bias.”
140. This completes the summary of the relevant statutory context. I now turn to the specific
complaints made by the objector. It seems that three pre-application consultations were
held by the planning authority in respect of different development proposals during the
period 2016 to 2018. The relevant chronology is as follows.
20 October 2016
Pre-application consultation re: proposed 72 unit
residential development.
19 July 2017
Pre-application consultation re: proposed 124 unit
residential development.
Page 34 ⇓
14 June 2018
Pre-application consultation re: proposed 132 unit
residential development.
141. The minutes in respect of the second and third of these meetings had been submitted by
the planning authority to An Bord Pleanála in advance of the pre-application consultation
between the prospective applicant; An Bord Pleanála; and the planning authority in
January 2019.
142. The objector’s complaint is that the minutes in respect of the first meeting, on 20 October
2016, had not been forwarded to An Bord Pleanála. With respect, this complaint is not
well-founded. The meeting predated the coming into force and effect of the relevant
provisions of the PD(H)A 2016 on 3 July 2017. Consequently, the meeting could not, by
definition, be one which had been held in discharge of the obligation under section 6 of
the PD(H)A 2016. It follows that the minutes of that meeting did not require to be
submitted to An Bord Pleanála in accordance with section 6(4). Moreover, the nature and
extent of the development proposed at that time was very different from that the subject
of the application ultimately made in May 2019.
143. It should also be reiterated that the minutes in respect of pre-application meetings with
the planning authority are only admissible as part of the pre-application consultation
process mandated under section 6 of the PD(H)A 2016. Same cannot be relied upon for
the purposes of the formal planning process thereafter, i.e. in the determination of the
planning application (section 6(9)). The objector cannot therefore have suffered any
prejudice as a result of the alleged failure to submit the minutes of the 20 October 2016
meeting to An Bord Pleanála.
144. The objector makes a related complaint in respect of the timing of the pre-application
consultation in respect of the strategic housing development viz-a-viz his third-party
appeal against the first-instance decision of the planning authority to grant planning
permission for the all-weather hockey pitch. The sequence of events is as follows. The
pre-application consultation took place on 16 January 2019. As of that date, the
objector’s appeal in relation to the hockey pitch was pending before An Bord Pleanála.
The appeal in respect of the hockey pitch was determined on 14 March 2019. The
application for the strategic housing development was submitted on 10 May 2019.
145. The record of the meeting on 16 January 2019 indicates that the following comment was
made on behalf of the board officials.
“If there is an appeal on the hockey pitch an application for this site which includes
part of the hockey pitch which is to be re-positioned could be deemed premature”.
146. The objector appears to argue that it was prejudicial to him for An Bord Pleanála to be
considering—even if only in the context of pre-application consultations—the possibility of
residential development being carried out on lands which were then occupied by the
(former) hockey pitch. The implication of this argument seems to be that the decision as
to whether to grant or refuse planning permission for a new hockey pitch on an east-west
Page 35 ⇓
alignment might be influenced by considerations related to the proposed residential
development discussed at the pre-application consultation. It is submitted that the board
should have postponed any pre-application consultation until the appeal in respect of the
hockey pitch had been determined.
147. With respect, any concerns in this regard are not well founded. For the reasons set out
by the Supreme Court in its judgment in Callaghan v. An Bord Pleanála (cited earlier), An
Bord Pleanála cannot be bound or influenced by a pre-application consultation. This holds
true not only for the planning application made consequent upon the pre-application
consultation, but also for any related planning applications or appeals.
148. There is no reasonable basis for suggesting that simply because An Bord Pleanála had
discussed with the developer the possibility of a strategic housing development
application, that the board would do other than determine the hockey pitch appeal on its
own merits. The objector has exhibited the decision and the inspector’s report in respect
of the hockey pitch appeal. There is nothing in any of the materials before the High Court
to suggest that the board’s decision to grant planning permission for the new hockey pitch
in March 2019 was in any way influenced by the pre-application consultation held in
respect of a different planning application in January 2019.
HABITATS DIRECTIVE: BATS
149. The application for planning permission was accompanied by an ecological impact
assessment report (“the ecological report”). The ecological report indicates that there is
some bat activity within the application site. No bat roosts were identified within the
application site, but taking a precautionary approach, the site was treated as having the
potential for bat roosts. The ecological report valued the site as having a local ecological
importance (higher value) for bats. The ecological report then set out a series of
mitigation measures.
150. The inspector’s report addresses these issues at §12.6. The inspector recommended that
conditions should be attached to the planning permission requiring (i) that the developer
implement the mitigation measures in the ecological impact assessment report; and (ii)
that a suitably qualified ecologist be appointed by the developer to oversee the site set-up
and construction of the proposed development.
151. These recommendations were accepted by An Bord Pleanála, and the grant of planning
permission includes the following two conditions.
“10. All mitigation and monitoring measures outlined in the plans and particulars,
including the Ecological Impact Assessment report submitted with this application
shall be carried out in full, except where otherwise required by conditions attached
to this permission.
Reason: In the interest of protecting the environment and in the interest of public
health.
Page 36 ⇓
11. A suitably qualified ecologist shall be appointed by the developer to oversee the site
set-up and construction of the proposed development and the ecologist shall be
present on site during construction works. The ecologist shall ensure the
implementation of all proposals contained in the Schedule of Ecological proposals.
Prior to commencement of development, the name and contact details of said
person shall be submitted to the planning authority. Upon completion of works, an
audit report of the site works shall be prepared by the appointed ecologist and
submitted to the planning authority to be kept on record.
Reason: In the interest of nature conservation.”
152. The objector complains that the decision to grant planning permission is contrary to
article 12 of the EU Habitats Directive (Directive 92/43/EC). It is suggested that the
carrying out of the proposed development may result in the “deliberate disturbance” of
protected bats species and the “deterioration or destruction” of their breeding sites or
resting places. It is alleged that a condition should have been attached to the planning
permission requiring the developer to obtain a “derogation licence” under regulation 54 of
the EC (Birds and Natural Habitats) Regulations 2011 (S.I. No. 477 of 2011) (which
implements article 12 of the Habitats Directive).
153. With respect, the objector’s argument appears to be predicated on a misconception as to
the interaction between the planning legislation and the Birds and Natural Habitats
Regulations. The existence of a grant of planning permission does not obviate the
requirement to comply with other statutory codes. This is confirmed by section 10(6) of
the PD(H)A 2016.
“(6) A person shall not be entitled solely by reason of a permission under section 9 to
carry out any development.”
154. The grant of planning permission merely confirms that the statutory requirements under
the planning legislation have been complied with. Accordingly, the fact that An Bord
Pleanála has granted permission does not obviate the need for the developer to apply for
a “derogation licence” in circumstances where required. Had An Bord Pleanála included a
condition stating that a “derogation licence” must be applied for where required, the
condition would merely be replicating a legal obligation that subsists in any event.
155. On the facts of the present case, there is nothing in the materials before An Bord Pleanála
which indicates that there is a likelihood that the carrying out of the proposed
development will result in any of the type of activities which would necessitate a
“derogation licence”.
156. The mitigation measures identified in the ecological impact assessment report require that
potential bat roost trees are inspected by an experienced ecologist for the presence of
bats prior to felling and are section-felled using controlled rigging under the supervision of
an experienced ecologist. In the event that bats are present, then the relevant works will
have to cease and it would be necessary to apply for a “derogation licence” at that stage.
Page 37 ⇓
SUMMARY OF CONCLUSIONS
157. An Bord Pleanála erred in law in its interpretation of the development plan. On its proper
interpretation, the “institutional lands” designation applied to the lands the subject-matter
of the planning application, i.e. the application site. The entire of the lands, including
what is now the application site, had been in the ownership and occupation of the
religious congregation as of the date of the adoption of the 2016–2022 development plan
(March 2016). The application site accommodated part of the hockey pitch associated
with the secondary school, and open lands in institutional use. As recognised by An Bord
Pleanála in its decision of March 2019 to grant planning permission for a new all-weather
hockey pitch, the former hockey pitch continued to have an established use for sports and
recreation, and this use was ancillary to an institutional use.
158. The relevant policies and objectives of the development plan are intended to inform the
determination of planning applications which seek permission to authorise a material
change in the use of lands which have an established use as “institutional lands”. These
policies and objectives cannot be by-passed by the simple expedient of the sale of the
lands. The application site remained subject to the “institutional lands” designation
notwithstanding the transfer of the ownership of the lands from the religious congregation
to the developer in October 2017.
159. The proposed development involves a material contravention of the development plan
policies and objectives applicable to institutional lands in respect of (i) housing density
and (ii) public open space. The decision to grant planning permission is invalid in
circumstances where An Bord Pleanála did not seek to invoke its statutory power to grant
planning permission in material contravention of the development plan (section 9(6)(c) of
the PD(H)A 2016).
160. The inspector’s report does consider and engage with the reasons for refusal
recommended in the chief executive’s report, as required under section 9(1)(a) of the
PD(H)A 2016. This engagement does, however, disclose an error of law in respect of the
interpretation of the development plan. Save with the exception of the issues concerning
the implications of the proposed residential development for the possible future expansion
of the existing schools, the inspector’s approach can be imputed to An Bord Pleanála.
161. There has been a breach of section 9(1)(a) insofar as the board has failed to explain in its
decision what approach it took to the question of the possible future expansion of the
existing schools and as to why it disagreed with the first of the recommended reasons for
refusal set out in the chief executive’s report.
162. The grounds of challenge in respect of pre-application consultations and the Habitats
Directive have not been made out.
FORM OF ORDER
163. The decision to grant planning permission is invalid and an order of certiorari will be made
setting aside An Bord Pleanála’s decision of 15 August 2019.
Page 38 ⇓
164. If any party intends to apply for leave to appeal to the Court of Appeal pursuant to
section 50A(7) of the PDA 2000, then the draft points of law in respect of which leave is
sought must be filed in the Central Office and circulated to the other parties within
twenty-eight days of the date of this judgment.
165. The proceedings will be adjourned to a date convenient to the parties to address the issue
of costs and any application to remit the matter to An Bord Pleanála pursuant to Order
84, rule 27 of the Rules of the Superior Courts. A date will also be fixed for the hearing of
any application for leave to appeal.
Appearances
Michael Redmond, the applicant for judicial review, represented himself
Nuala Butler, SC and Fintan Valentine for An Bord Pleanála instructed by Fieldfisher
Solicitors
Eamon Galligan, SC and Suzanne Murray for the notice party developer instructed by
Cannon Solicitors
Isabelle Aylmer for the planning authority
APPENDIX
Policies and objective of the 2016–2022 development plan applicable to institutional
lands
2.1.3.5 Policy RES5: Institutional Lands
Where distinct parcels of land are in institutional use (such as education, residential or
other such uses) and are proposed for redevelopment, it is Council policy to retain the
open character and/or recreational amenity of these lands wherever possible, subject to
the context of the quantity of provision of existing open space in the general environs.
It is recognised that many institutions in Dún Laoghaire-Rathdown are undergoing change
for various reasons. Protecting and facilitating the open and landscaped ‘parkland’
settings and the activities of these institutions is encouraged. Where a well established
institution plans to close, rationalise or relocate, the Council will endeavour to reserve the
use of the lands for other institutional uses, especially if the site has an open and
landscaped setting and recreational amenities are provided. Where no demand for an
alternative institutional use is evident or foreseen, the Council may permit alternative
uses subject to the zoning objectives of the area and the open character of the lands
being retained.
A minimum open space provision of 25% of the total site area (or a population based
provision in accordance with Section 8.2.8.2 whichever is the greater) will be required on
Institutional Lands. This provision must be sufficient to maintain the open character of
the site with development proposals structured around existing features and layout,
particularly by reference to retention of trees, boundary walls and other features as
considered necessary by the Council (Refer also to Section 8.2.3.4(xi) and 8.2.8).
Page 39 ⇓
In the development of such lands, average net densities should be in the region of 35 -
50 units p/ha. In certain instances higher densities will be allowed where it is
demonstrated that they can contribute towards the objective of retaining the open
character and/or recreational amenities of the lands.
In cases of rationalisation of an existing institutional use, as opposed to the complete
cessation of that use, the possible need for the future provision of additional facilities
related to the residual retained institutional use retained on site may require to be taken
into account. (This particularly applies to schools where a portion of the site has been
disposed of but a school use remains on the residual part of the site.)
8.2.3.4 Additional Accommodation in Existing Built-up Areas
(xi) Institutional Lands
Where no demand for an alternative institutional use is evident or foreseen, the Council
may permit alternative uses subject to the area’s zoning objectives and the open
character of the lands being retained.
There are still a number of large institutions in the established suburbs of the County
which may be subject to redevelopment pressures in the coming years. The principal
aims of any eventual redevelopment of these lands will be to achieve a sustainable
amount of development while ensuring the essential setting of the lands and the integrity
of the main buildings are retained. In order to promote a high standard of development a
comprehensive masterplan should accompany a planning application for institutional sites.
Such a masterplan must adequately take account of the built heritage and natural assets
of a site and established recreational use patterns. Public access to all or some of the
lands may be required. Every planning application lodged on institutional lands shall
clearly demonstrate how they conform with the agreed masterplan for the overall site.
Should any proposed development deviate from the agreed masterplan then a revised
masterplan shall be agreed with the Planning Authority.
A minimum open space provision of 25% of the total site area (or a population based
provision in accordance with Section 8.2.8.2 whichever is the greater) will be required on
Institutional Lands. This provision must be sufficient to maintain the open character of
the site - with development proposals built around existing features and layout,
particularly by reference to retention of trees, boundary walls and other features as
considered necessary by the Council.
In addition to the provision of adequate open space, on Institutional Lands where existing
school uses will be retained, any proposed residential development shall have regard to
the future needs of the school and allow sufficient space to be retained adjacent to the
school for possible future school expansion/ redevelopment.
8.2.8.2 Public/Communal Open Space – Quantity
Page 40 ⇓
To provide existing and future communities with adequate active recreational and passive
leisure opportunities the Council will employ a flexible approach to the delivery of public
open space/communal open space and more intensive recreational/amenity/community
facilities.
The overarching hierarchy of public open spaces across the County is set out in Policy
OSR3 in Section 4.2.2.2. The hierarchy of existing parks and open spaces within the
County have also been mapped to differentiate this hierarchical classification (Refer also
to Appendix 14).
The Planning Authority will require public6 and/or communal open space to be provided
within new residential and large scale commercial developments. This should preferably
be located at specific sites or locations that would facilitate the assembly of areas of
satisfactory size or usability or would enhance established on-site features.
Applicants for all new developments are encouraged to engage with the Planning
Authority at pre-planning stage to discuss the Open Space requirements for a specific
site.
(i) Residential / Housing Developments Open Space:
For all developments with a residential component – 5+ units - the requirement of 15
sq.m- 20 sq.m. of Open Space per person shall apply based on the number of
residential/housing units. For calculation purposes, open space requirements shall be
based on a presumed occupancy rate of 3.5 persons in the case of dwellings with three or
more bedrooms and 1.5 persons in the case of dwellings with two or fewer bedrooms. A
lower quantity of open space (below 20 sq.m per person) will only be considered
acceptable in instances where exceptionally high quality open space is provided on site
and such schemes may be subject to financial contributions as set out under Section
8.2.8.2 (iii) below.
The Planning Authority shall require an absolute default minimum of 10% of the overall
site area for all residential developments to be reserved for use as Public Open and/or
Communal Space irrespective of the occupancy parameters set out in the previous
paragraph.
It is Council Policy to retain the open space context of Institutional Lands which
incorporate significant established recreational or amenity uses, as far as is practicable. In
the event of permission for development being granted on these lands, open space
provision in excess of the normal standards will be required to maintain the open
character of such parts of the land as are considered necessary by the Council. For this
purpose a minimum open space provision of 25% of the total site area - or a population-
based provision in accordance with the above occupancy criteria – will be required,
whichever is the greater. There may also be a requirement to provide open space in
excess of the 25% if an established school use is to be retained on site in order to
facilitate the future needs of the school (refer also to Section 8.2.3.4(xi)).
Page 41 ⇓
Chief Executive’s report: recommended reasons for refusal
1. The proposed development, by virtue of its bringing about a scenario whereby lands that
were previously available to the two schools on the overall Our Lady’s Grove campus
would be made permanently unavailable to those schools, would result in a situation
whereby the existing schools on site would be operating on sites that would be smaller
than those recommended under Technical Guidance Documents TGD–025 and TGD–027
as produced by the Department of Education and Skills. As such, the proposed
development would be contrary to the ‘Code of Practice on the Provision of Schools and
the Planning System’, prepared jointly by the Department of Environment, Heritage, and
Local Government and the Department of Education and Science in 2008, and by
extension would be contrary to Section 8.2.12.4 of the Dun Laoghaire Rathdown County
Development Plan 2016–2022, which references this Code of Practice. Furthermore, and
by extension, the proposed development would result in a scenario whereby the campus
would be unavailable to address the identified demand for school places in the area by
way of expansion. As such, the proposed development would be contrary to Policy SIC8,
and Section 8.2.12.4 of the County Development Plan, and indeed the zoning objective to
‘protect and-or improve residential amenity’ of which the provision of community
facilities, including schools, forms part. As such the proposed development would
materially contravene the County Development Plan and would be contrary to the proper
planning and sustainable development of the area.
2. The proposed development, by virtue of reducing the provided and potential public open
space across the Our Lady’s Grove campus to a level below 25%, and by virtue of the
removal of the vast majority of trees from within the subject-site, would be contrary to
Section 8.2.3.4 (xi) of the Dun Laoghaire-Rathdown County Development Plan 2016–
2022.
3. The proposed development would be deficient in terms of the quantity and quality of
public open space available to the residents of the scheme, as required under Section
8.2.8.2 of the Dun Laoghaire Rathdown County Development Plan 2016–2022.”
Result: No result given