High Court of Ireland Decisions
You are here:
BAILII >>
Databases >>
High Court of Ireland Decisions >>
Krikke v Barrannafaddock Sustainability Electricity Ltd [2019] IEHC 825 (06 December 2019)
URL: http://www.bailii.org/ie/cases/IEHC/2019/2019IEHC825.html
Cite as:
[2019] IEHC 825
[
New search]
[
Printable PDF version]
[
Help]
Page 1 ⇓
THE HIGH COURT
[2019] IEHC 825
2019/55/MCA
IN THE MATTER OF SECTION 160 OF THE PLANNING AND DEVELOPMENT ACT
AND IN THE MATTER OF AN APPLICATION
BETWEEN
RONALD KRIKKE
PIA UMANS
SEAN HARRIS
CATHERINE HARRIS
PATRICK KENNEALLY
CAROLINE KENNELLY
KENNETH GEARY
APPLICANTS
AND
BARRANAFADDOCK SUSTAINABILITY ELECTRICITY LIMITED
RESPONDENT
JUDGMENT of Mr Justice Garrett Simons delivered on 6 December 2019
INTRODUCTION
1. This matter comes before the High Court by way of an application pursuant to Section
160 of the Planning and Development Act 2000 (“the PDA 2000”). Section 160 is
intended to provide a summary procedure whereby breaches of the planning legislation
can be brought before the court expeditiously. The procedure is colloquially described as
an application for a “planning injunction”. The procedure is available to “any person”, and
benefits from special costs rules under Part 2 of the Environment (Miscellaneous
Provisions) Act 2011.
2. The principal legal issues which fall for determination in the present case all concern the
interaction between the respective competences of local planning authorities, An Bord
Pleanála and the courts. In particular, an issue arises as to the weight, if any, which
must be given to a Section 5 declaration in subsequent enforcement proceedings. An
issue also arises as to the legal status of a decision made by the local planning authority
purporting to agree points of detail pursuant to a planning condition.
3. The facts of the case are straightforward. The respondent is the operator of a wind farm
(hereinafter “the Developer”). The wind farm is located in the townland of Ballyduff,
County Waterford. The relevant planning permission had authorised the erection of wind
turbines of a particular scale and dimensions. In the event, wind turbines of a different
scale and dimensions have been erected instead. The principal distinction between the
“as permitted” and the “as built” turbines is that the rotor blade diameter has increased
from 90 metres to 103 metres. This deviation is said, by the Developer, to have been
compensated for by a reduction in hub height, which has the consequence that the overall
tip height has remained at the permitted level of 125 metres.
4. An Bord Pleanála has since made a declaration pursuant to Section 5 of the PDA 2000 to
the effect that the alterations to the turbines, including the length of the rotor blades, do
not come within the scope of the planning permission. The Applicants contend that the
Developer is precluded by the existence of this Section 5 declaration from reagitating
before this court an argument that the “as built” turbines are authorised by the planning
Page 2 ⇓
permission. In response, the Developer seeks to rely on an earlier decision, namely the
decision of the planning authority to “agree” points of details in respect of the wind
turbines. This earlier decision was made pursuant to a condition of the planning
permission which left over points of detail, including the design, height and colour of the
turbines, for agreement with the planning authority. It is said that neither the Applicants
nor this court is entitled to look behind this decision in circumstances where same has not
been challenged in judicial review proceedings.
5. The Developer has advanced a number of other arguments for saying that there has been
no “unauthorised development”, and contends, in the alternative, that relief should be
refused as a matter of discretion.
6. The Developer, whilst maintaining the formal position that the change in turbine type is
authorised by the planning permission, has, nevertheless, made two attempts to obtain
development consent retrospectively in respect of the “as built” turbines. First, the
Developer made an application for leave to apply for “substitute consent” under Part XA of
the PDA 2000. The application for leave was refused by An Bord Pleanála by decision
dated 13 August 2019. This decision is now the subject of judicial review proceedings
before the High Court. These judicial review proceedings have been taken by all of the
Applicants herein. The parties informed the court last week (28 November 2019) that the
judicial review proceedings are not being opposed by An Bord Pleanála, but that there is
likely to be a dispute as to whether the matter should be remitted to the Board. This
matter is listed for hearing in the Commercial List this morning (6 December 2019).
7. Secondly, the Developer had made an application for retention planning permission to the
local planning authority pursuant to Section 34(12) of the PDA 2000. This application had
been submitted to Waterford City and County Council on 4 October 2019. This application
has since been withdrawn in early November 2019.
STRUCTURE OF THIS JUDGMENT
8. This judgment is structured as follows. The factual background to the dispute will be set
out in more detail under the next heading below. This chronology will include more
recent events, such as the decision on the part of An Bord Pleanála to refuse leave to
apply for substitute consent.
9. The legal issues will then be addressed in the following sequence. First, the legal status
of the Section 5 declaration will be considered. This will be the lengthiest part of the
judgment. This is because there is a significant body of case law in relation to Section 5,
and it is necessary to examine same in some detail. Secondly, the court will consider de
novo the question of whether the change in turbine type represents unauthorised
development. This exercise is carried out on a de bene esse basis. Thirdly, the legal
status of the planning authority’s purported agreement to the compliance submission will
be considered. Fourthly, the factors which are relevant to the exercise of the court’s
discretion will be addressed. Finally, the principal conclusions of the court will be
summarised at the end of this judgment.
Page 3 ⇓
FACTUAL BACKGROUND
THE PLANNING PERMISSIONS
10. An Bord Pleanála granted planning permission on 22 November 2005 for the development
of a wind farm. (Reg. Ref. 04/1559) (“the 2005 planning permission”). The planning
application had initially sought permission for the erection of twelve wind turbines. It
seems, however, that revised plans and particulars were subsequently submitted, and
one of the proposed turbines was omitted and the scale and dimensions of three of the
turbines were reduced.
11. The development is of a type which is subject to the requirements of the Environmental
Impact Assessment Directive (2011/92/EU) (“the EIA Directive”). This is because the
proposed development exceeded the threshold for a mandatory environmental impact
assessment (“EIA”) under Schedule 5 of the Planning and Development Regulations 2001.
As such, the planning application had to be accompanied by an environmental impact
statement (“EIS”), and An Bord Pleanála was required to carry out an EIA as part of its
decision-making.
12. The planning permission, as granted by An Bord Pleanála, allowed for the erection of
eleven wind turbines and other associated development. More specifically, the planning
permission authorised the erection of eight wind turbines with a hub height of 80 metres
and a blade length of 40 metres (equivalent to a rotor diameter of 80 metres), and a
further three wind turbines with a hub height of 60 metres and a blade length of 40
metres (equivalent to a rotor diameter of 80 metres). The two sets of wind turbines
would have had an overall tip height of 120 metres and 100 metres, respectively.
13. The following two conditions of the 2005 planning permission are relevant to the issues
which arise in these proceedings.
1. The development shall be carried out in accordance with the plans and particulars
lodged with the application, as amended by the revised information received by the
planning authority on the 3rd day of February, 2005, the 22nd day of February,
2005 and the 27th day of May, 2005, except as may otherwise be required in order
to comply with the following conditions. For the avoidance of doubt, this
permission relates only to 11 number turbines only with the layout of the turbines
as that received on 27th day of May, 2005.
Reason: In the interest of clarity.
3. Prior to commencement of development, details of the proposed turbines and
associated structures, including design, height and colour shall be submitted to and
agreed in writing with the planning authority. The wind turbines shall be geared to
ensure that the blades rotate in the same direction. In default of agreement, the
matter shall be referred to An Bord Pleanála for determination.
Reason: In the interest of visual amenity.
Page 4 ⇓
14. The first condition had the legal effect of confining the permitted development to that as
set out in the revised information received by the planning authority, i.e. the scale and
dimensions of three of the turbines had been reduced. The third condition has since been
replicated in a subsequent decision of the planning authority (2011) which authorised
certain modifications in respect of the proposed development.
15. The next event of relevance is that the “appropriate period” of the 2005 planning
permission, i.e. the time period within which development works could be lawfully carried
out, had been extended on 29 November 2010 for a further period of five years. (22
November 2015). But for this extension, the planning permission would have withered in
2010.
16. The Developer subsequently submitted an application in 2011 for permission for a
“modification” to the permitted wind farm development. The hub height of the three
smaller turbines was to be increased to 80 metres; and the blade length of all eleven
turbines was to be increased to 45 metres (equivalent to a rotor diameter of 90 metres).
All eleven turbines would, therefore, have an overall tip height of 125 metres.
17. The application had been made, at first instance, to the local planning authority,
Waterford County Council. (Reg. Ref. PD 11/400). The planning authority made a
decision on 23 November 2011 to grant planning permission (“the 2011 planning
permission”).
18. Condition No. 1 of the 2011 planning permission provides as follows.
“1. The proposed development shall be carried out in accordance with plans and
particulars lodged with the Planning Authority on 30 September 2011 save where
amended by the conditions herein.
Reason: to clarify the scope of the permission in the interests of development
control.”
19. As explained under the next heading below, Condition No. 3 of the 2011 planning
permission required points of detail to be agreed subsequently with the planning
authority.
20. It does not appear from the face of the planning authority’s decision of 23 November
2011 that an EIA had been carried out by the planning authority.
21. For the sake of completeness, it should be noted that a further application for planning
permission was made in 2013. This related to what has been described as “Phase 2” of
the wind farm. The decision of the planning authority at first instance was to grant
planning permission for an extension to the permitted wind farm, comprising three
(additional) turbines with a tip height of up to 130.5 metres and associated access tracks
and site works. An environmental impact statement (“EIS”) had been submitted with this
application. Thereafter, there was an attempt made by third parties to appeal the
Page 5 ⇓
planning authority’s decision to An Bord Pleanála. The appeal was, however, dismissed as
invalid.
22. Condition No. 7 of the 2013 planning permission stipulates that the maximum blade tip
height of the (three) proposed wind turbines shall be 130.5 metres. No complaint is
made in these proceedings in respect of this second phase of the wind farm.
23. The wind farm, as constructed, consists of twelve turbines. Nine of these turbines have
been constructed pursuant to the earlier planning permissions. (Two permitted turbines
have been omitted). The balance of three turbines has been constructed pursuant to the
2013 planning permission. These Section 160 proceedings are concerned only with the
first nine turbines.
COMPLIANCE SUBMISSION: 13 DECEMBER 2013
24. Condition No. 3 of the 2011 planning permission provides as follows.
“3. Prior to commencement of development, details of the proposed turbines and
associated structures, including design, height and colour shall be submitted to and
agreed in writing with the planning authority. The wind turbines shall be geared to
ensure that the blades rotate in the same direction.
Reason: In the interest of visual amenity.”
25. Given the importance which they have since assumed as an issue in these proceedings, it
is necessary to set out in some detail the events in relation to the compliance submission
made pursuant to this condition.
26. The consultants acting on behalf of the Developer, Fehily Timoney & Company, made a
compliance submission to Waterford County Counsel under cover of letter dated 6
November 2013. This compliance submission sought the agreement of the planning
authority in relation to points of detail under a number of the conditions of the 2011
planning permission. Relevantly, the compliance submission addressed Condition No. 3 of
the planning permission as follows.
“4.1. Condition Wording
Prior to commencement of development, details of the proposed turbines and
associated structures, including design, height and colour shall be submitted to and
agreed in writing with the planning authority. The wind turbines shall be geared to
ensure that the blades rotate in the same direction.
Reason: In the interest of visual amenity.
4.2. Developers Compliance Proposal
The preferred model being considered for installation at Barranafaddock Wind Farm
is the GE 2.x Series wind turbine.
Page 6 ⇓
Design
Technical details of the selected turbine model are included in Appendix B of this
report. The document summarizes the technical description and specification of the
GE 2.x Series wind turbines and includes a number of available turbine variants.
The 2.x Series are three-bladed, upwind, horizontal-axis wind turbines with the
turbine rotor and nacelle mounted on the top of a tubular tower.
Height
The preferred turbine is installed on a tapered tubular tower of hub height 73.5m
with a maximum tip height of 125m. Schematic details of the GE turbine
arrangement proposed are included in Appendix B.
Colour
The wind turbines will be finished in a light grey colour.
At this stage the developer requests that the Planning Authority confirm that the
proposed turbine is considered appropriate.
The turbines will be geared to ensure that the blades rotate in the same direction.”
27. As appears from the foregoing, the compliance submission does not expressly state that
the planning authority’s agreement was being sought in respect of an increase in rotor
diameter from 90 metres to 103 metres.
28. The above text from the compliance submission does, of course, refer to Appendix B.
One of the documents included in Appendix B is a drawing labelled “LE13-731-04-0 10
(Rev. A)”. This drawing had been submitted in A3 format. This drawing shows a
schematic of a wind turbine, and indicates, albeit in very small font, that the rotor
diameter is 103 metres.
29. The compliance submission also included a document prepared by GE Energy entitled
“Technical Documentation Wind Turbine Generator Systems 2.x Series”. Page 14 of this
latter document sets out, in tabular form, Technical Data for the 2.x Series. The rotor
diameter for the various models of the turbines is indicated as ranging between 100
metres and 103 metres.
30. The response of Waterford County Council to the compliance submission was to issue a
letter to the Developer, care of Fehily Timoney & Co., on 13 December 2013 (“the
decision-letter”). The decision-letter is less than three pages in length. In effect, the
decision-letter merely lists off various conditions of the 2011 planning permission, with a
brief observation below each.
31. Insofar as Condition No. 3 is concerned, the decision-letter states as follows.
“Condition 3
Noted and agreed.”
Page 7 ⇓
32. There is no analysis in the decision-letter of the compliance submission. Nor is there any
express acknowledgement that the planning authority were agreeing to an increase in
rotor diameter from 90 metres to 103 metres.
SECTION 5 REFERENCE
33. Waterford City and County Council made a reference to An Bord Pleanála pursuant to the
provisions of Section 5 of the PDA 2000 on 24 May 2018. (Ref. ABP-301738-18).
34. The question referred was as follows.
“Whether the deviation from the permitted blade length of 45 metres (90 metres in
diameter) to the constructed blade length of 51.5 metres (103 metres in diameter)
in relation to permission granted under planning register reference number PD
11/400 for modifications to a windfarm at Barranafaddock Wind Farm, County
Waterford is or is not development or is or is not exempted development?”
35. The Developer made a detailed submission on the Section 5 reference through its
consultants, Fehily Timoney & Company, on 29 June 2018. It is apparent from this
submission that the Developer was fully aware that an earlier Section 5 Declaration issued
by An Bord Pleanála in respect of the Kilvinane Wind Farm was potentially relevant. The
Developer also sought to rely on the planning authority’s decision-letter of 13 December
2013.
36. The submission on behalf of the Developer summarised its conclusions as follows.
“7.0 Conclusion
In summary, the deviation of the rotor diameter from 90m to 103m can be
considered immaterial in planning terms because:
1. The nature and scale of the windfarm development is such that the increase
in rotor diameter is not a material alteration.
2. There has been no alteration to the turbine locations and the increase in rotor
diameter of 14% is significantly less than the 40% alteration which was
found to be material in Bailey v. Kilvinane.
3. On the basis of the comparative environmental analysis, it can be concluded
that there are no significant changes to the environmental impacts arising
from the change in rotor diameter.
4. Waterford County Council, in approving the detailed design of the turbines in
2013, did not consider the increase in rotor diameter to be material in
planning terms.”
37. The reference above to a “comparative environmental analysis” is to a separate document
which had been included as part of the submission to An Bord Pleanála. This is a detailed
six-page analysis which compares the environmental impact of the “as permitted” and “as
built” wind turbines. The comparative environmental analysis concludes by stating that
“there are no significant changes relating to the environmental impacts, based on the
Page 8 ⇓
methodologies employed in the September 2011 Environmental Report submitted as a
part of the planning application for the permitted development”.
38. As is standard practice, An Bord Pleanála assigned an inspector to prepare a report and
recommendation in relation to the Section 5 reference.
39. It is evident from the inspector’s report that the Developer had made a similar
jurisdictional objection to that which it seeks to agitate in these proceedings. More
specifically, as appears from the following passage at page 5 of the inspector’s report, the
Developer had sought to rely on the decision-letter of 13 December 2013 as authorising
the alterations in the scale and dimensions of the wind turbines.
“The owner / occupier has submitted a response to the PA referral request which
provides for a summary of the planning history associated with the wind farm
development. The submission also note that Waterford City & County Council
issued a compliance response in December, 2013 indicating that the turbine
erected on the site was noted and agreed. The response questions the
appropriateness of the Section 5 Referral with regard to the particular question
raised by WCCC in the context of the planning compliance agreed. It is further
considered that the statement under the heading ‘Reason for Referral’ may give the
incorrect impression that WCCC was not aware of the change in blade length before
2016. […]”
40. This summary in the inspector’s report reflects the points made, in particular, at §5.2.1 of
Fehily Timoney & Company’s submission.
41. The inspector indicated (at pages 10 and 11 of her report) that she would have “no
objections in principle” to the alterations given that the overall tip height of the wind
turbines continued to comply with the specific condition of the planning permission. (It
will be recalled that the increase in the length of the rotor blades had been off-set by a
reduction in the hub height). The inspector went on to say, however, that An Bord
Pleanála itself had adopted a different approach in relation to the Kilvinane Wind Farm.
As discussed presently, the Kilvinane Wind Farm is the subject of a judgment of the Court
of Appeal. An order had been made under Section 160 restraining the operation of a wind
farm, the turbines of which did not comply with the scale and dimensions permitted.
42. The approach which An Bord Pleanála had taken in relation to the Kilvinane Wind Farm
had been summarised as follows in the inspector’s report.
“The Board will note a similar Section 5 request in relation to the Kilvinane Wind
Farm, PL88.RL2891 refers, whereby the developer of that windfarm received
confirmation from the PA that a number of changes made, including a reduction in
turbine hub heights, increased rotor blade lengths, reduction in the number of
turbines installed and a change of location of turbines within 20m of the permitted
locations, were not material and complied with the permission granted. The Board,
following a Section 5 request from a third party, concluded that –
Page 9 ⇓
(a) the erection of the turbines comes within the scope of the definition of
development contained in Section 3 of the Planning and Development Act
2000,
(b) the relocation of and alterations to turbines, including the modification to the
overall height of the turbines and the length of the rotor arms/blades do not
come within the scope of the permission granted,
(c) there is no provision for exemption for the said relocation and alterations to
turbines provided for in either Section 4, as amended, of the said Act or
Article 6 of the Planning and Development Regulations 2001, and
(d) therefore, the construction of the wind turbines as currently erected on site
including alterations and modifications to the turbines height and rotor
arms/blades is development and is not exempted development.”
43. The inspector’s own conclusion was then set out as follows.
“8.9. Is or is not exempted development
While I would have no objections in principle to the alterations to the blade length
as constructed, given that the hub heights have been reduced and the overall tip
height has complied with the specific condition of planning permission, in light of
the determination in relation to PL88.RL2891, a precedent might be considered as
having been set. In this regard, I refer to the Boards consideration of the physical
alterations to turbines - in particular the alterations to blade length and the overall
height of the turbines - did not come within the scope of the relevant planning
permission, it is possible to conclude in this case that the reduction in the hub
height and the increased length of the rotor length, notwithstanding the fact that
the permitted tip height of 125m has been maintained, do not come within the
scope of the planning permission granted. In addition, the Board will note that
there is no provision for exemption for the alterations to turbines provided for in
either Section 4 of the Planning & Development Act 2000, as amended or Article 6
of the Planning & Development Regulations, 2001, as amended. As such, the
development is not exempted development.”
44. An Bord Pleanála ultimately accepted the inspector’s recommendation. The Board made a
declaration on 4 December 2018.
45. The operative part of the Board Order reads as follows.
“AND WHEREAS An Bord Pleanála has concluded that -
(a) the erection of the turbines comes within the scope of the definition of
development contained in Section 3 of the Planning and Development Act
2000,
(b) the alterations to turbines, including the length of the rotor arms/blades, do
not come within the scope of the permission granted,
Page 10 ⇓
(c) there is no provision for exemption for the said alterations to turbines in
either Section 4, as amended, of the said Act or Article 6 of the Planning and
Development Regulations 2001, and
(d) therefore, the construction of the wind turbines as currently erected on site
including the alterations to the rotor arms/blades is development and is not
exempted development.
NOW THEREFORE An Bord Pleanála, in exercise of the powers conferred on it by
section 5 (4) of the 2000 Act, hereby decides that the deviation from the permitted
blade length of 45 metres (90 metres in diameter) to the constructed blade length
of 51.5 metres (103 metres in diameter) in relation to permission granted under
planning register reference number PD11/400 for modifications to a windfarm at
Barranafaddock Wind Farm, County Waterford is development and is not exempted
development.”
46. The Developer took no steps to challenge the validity of An Bord Pleanála’s determination
by way of judicial review proceedings.
ENFORCEMENT NOTICE
47. Following on from An Bord Pleanála’s declaration, the planning authority issued a warning
letter dated 20 December 2018. An enforcement notice was subsequently issued in
respect of the wind farm development. This enforcement notice is dated 22 March 2019.
The Developer then instituted judicial review proceedings in May 2019 seeking to
challenge the validity of the enforcement notice. It seems that the operation of the
enforcement notice has been stayed pending the outcome of these judicial review
proceedings.
APPLICATIONS FOR RETROSPECTIVE DEVELOPMENT CONSENT
48. The Developer maintains the position that the change in the scale and dimensions of the
wind turbines is authorised by the 2011 planning permission. Without prejudice to this
position, the Developer had submitted an application to An Bord Pleanála for leave to
apply for substitute consent on 29 January 2019.
49. It may be of assistance to the reader to pause briefly here, and to explain the concept of
“substitute consent”. The planning legislation had to be amended following a judgment of
the Court of Justice of the European Union (“CJEU”), Case C-215/06, Commission v.
Ireland, which had held that the blanket provision made for retention planning permission
under the pre-2010 version of the PDA 2000 was inconsistent with the EIA Directive. The
option of making an application for retention planning permission is no longer available in
respect of an EIA development project which has been carried out in breach of either the
requirement for a screening determination or for a full EIA.
50. The planning status of such an EIA development project may only be regularised by an
application for substitute consent under Part XA of the PDA 2000. There is no automatic
right to apply for substitute consent. Rather, a developer will, generally, be required to
apply first for leave to make the application. Such an application for leave is made to An
Page 11 ⇓
Bord Pleanála. (There are special rules in relation to quarrying activity, but these are not
relevant to this case).
51. On the facts of the present case, the Developer had made a leave-application to An Bord
Pleanála on 29 January 2019, that is, shortly after An Bord Pleanála had issued its Section
5 declaration. An Bord Pleanála subsequently made a decision refusing leave to apply on
13 August 2019. The approach adopted by An Bord Pleanála appears to have been that it
was not necessary to obtain substitute consent. The validity of An Bord Pleanála’s
decision has been challenged in two separate sets of judicial review proceedings which
have been entered into the Commercial List of the High Court. The first of these
proceedings has been taken by the Applicants herein; the second by Mr Peter Sweetman.
52. The parties informed me last week (28 November 2019) that An Bord Pleanála does not
intend to oppose those judicial review proceedings. The Board is conceding the judicial
review proceedings on the very narrow ground that the Board’s records of the decision-
making process are inadequate. The Board has been careful to note in correspondence
that its approach does not involve any concession by the Board of any of the additional
grounds of judicial review relied upon by the Applicants.
53. The parties to the judicial review proceedings are in disagreement as to the precise basis
on which the Board’s decision is to be set aside, and, as to whether the application for
leave to apply for substitute consent should be remitted to An Bord Pleanála for
reconsideration. These matters are to be the subject of a separate hearing before the
Commercial List of the High Court this morning.
54. The Developer had also made an application for retention planning permission to
Waterford City and County Council. That application had been made on 4 October 2019,
but has now been withdrawn.
55. I will return to consider the relevance of these applications, towards the end of this
judgment, when I come to address the factors informing the exercise of the court’s
discretion in Section 160 proceedings.
SUPPLEMENTARY LEGAL SUBMISSIONS
56. By order dated 28 November 2019, the parties were given liberty to file supplemental
written legal submissions addressing the implications for the within proceedings, if any, of
the very recent judgment of the CJEU in Case-261/18, Commission v. Ireland
(Derrybrien) and Mone v. An Bord Pleanála [2010] IEHC 395. The submissions were
received by the court on 5 December 2019.
DETAILED DISCUSSION OF LEGAL ISSUES
STATUS OF SECTION 5 DECLARATION
57. The first legal issue to be addressed in this judgment is whether the finding by An Bord
Pleanála, i.e. that the increase in the length of the rotor blades does not come within the
scope of the planning permission granted, is binding on the parties. Put otherwise, does
the Section 5 declaration give rise to a form of issue estoppel which precludes the
Developer from reagitating, before this court, the argument which it had lost before An
Page 12 ⇓
Bord Pleanála to the effect that the deviations are within the scope of the planning
permission.
58. Leading counsel for the Applicants, Mr John Rogers, SC, submits that the Section 5
reference is binding. Counsel cites, in particular, the judgment in Cleary Compost and
Shredding Ltd v. An Bord Pleanála (No. 1) [2017] IEHC 458, [104] to [118]. That
judgment, in turn, relies on the Court of Appeal judgment in Killross Properties Ltd.
59. In the Applicants’ written legal submissions, it is stated that An Bord Pleanála has
concluded that the alteration was not only “development”, but also that it was not an
“exempted development”, and that it was carried out in breach of a permission and the
conditions thereof. It is further submitted that the Board’s finding “removed any room for
argument” on the part of the Developer with regard to the status of the development.
60. Leading counsel on behalf of the Developer, Mr Declan McGrath, SC, has sought to argue
that An Bord Pleanála does not have jurisdiction under Section 5 of the PDA 2000 to make
a finding that “unauthorised development” has been carried out. It is further submitted
that for the Board to have found that the “as constructed” wind turbines had not been
carried out in accordance with the planning permission would, by necessary implication,
involve an (impermissible) finding that the Developer had carried out “unauthorised
development”. Counsel cites, in particular, Roadstone Provinces Ltd. v. An Bord Pleanála
County Council v. Murray [2017] IESC 25; [2018] 1 I.R. 189; [2017] 2 I.L.R.M. 297. It is
sought to distinguish the judgment in Killross Properties on two bases: (i) the Section 5
declaration in that case was to the effect that the development was not “exempted
development” which is a finding within the Section 5 jurisdiction; and (ii) it was the
applicant, not the respondent, who was held to be bound by the Section 5 declaration. It
is submitted that a respondent, faced with proceedings which place reliance on a public
law measure, may be justified in challenging the validity of the measure concerned even
though that party might be, strictly speaking, out of time in maintaining a direct challenge
to the relevant measure (Shell E & P Ireland Ltd. v. McGrath [2013] IESC 1, [2013] 1 I.R.
247, [49]).
61. It is further submitted that the court should lean against an interpretation of the Section
5 declaration which would involve attributing to the Board a finding that the development
was in breach of planning permission. (Such a finding would, on the Developer’s
argument, be ultra vires). The court should instead interpret the Section 5 declaration as
saying no more than that the erection of wind turbines constitutes “development” and is
not “exempted development”.
62. The Developer submits that the operative part of the Section 5 declaration is confined to
the very last paragraph thereof, i.e. the paragraph commencing with the words “NOW
THEREFORE An Bord Pleanála …”. (The Board’s declaration has been set out in full at
paragraph 45 above). This narrow interpretation of the declaration would, it is submitted,
“square the circle” by rendering the Board’s declaration in a manner which holds it intra
Page 13 ⇓
vires. The decision would otherwise be unlawful and invalid. This is because, on the
Developer’s argument, An Bord Pleanála had no jurisdiction to decide what falls within or
outwith a planning permission.
ANALYSIS OF THE ARGUMENTS ON SECTION 5
63. It is proposed to structure this discussion as follows. First, the interaction between a
Section 5 declaration and enforcement proceedings will be considered. Secondly, the
Developer’s argument that the Section 5 reference procedure does not properly apply to
the interpretation of a planning permission will then be addressed.
(1). Section 5 declaration and enforcement proceedings
64. The planning legislation has, from the very outset, put in place a procedure whereby the
question of whether a particular act constituted “development” or “exempted
development” could be determined. This initially took the form of a reference to An Bord
Pleanála, with an appeal thereafter to the High Court. This was provided for under
Section 5 of the Local Government (Planning & Development) Act 1963.
65. Since the enactment of the PDA 2000, the reference is now normally made in the first
instance to the local planning authority, with a right of review thereafter to An Bord
Pleanála, and a right of judicial review to the High Court. The planning authority can
itself make a reference directly to An Bord Pleanála, and this is what occurred on the facts
of the present case.
66. The Section 5 procedure is unusual in that it confers a jurisdiction upon a public authority
to determine issues which, in many instances, will necessitate an adjudication on
questions of law. The constitutional validity of conferring such a jurisdiction upon An Bord
Pleanála under the Local Government (Planning & Development) Act 1963 had been
upheld by the High Court (Kenny J.) in Central Dublin Development Association v.
Attorney General (1969) 109 I.L.T.R. 69.
67. The more modern case law is characterised by an enthusiasm for the revised form of
procedure now provided for under Section 5 of the PDA 2000. As elaborated upon below,
the case law over the last fifteen years or so has confirmed (i) that Section 5 of the PDA
2000 has largely ousted the High Court’s jurisdiction to grant declaratory relief in respect
of planning matters; (ii) that an unchallenged declaration may be relied upon in
enforcement proceedings; and (iii) that An Bord Pleanála is an expert decision-maker,
whose decisions attract curial deference.
68. This modern case law commences with the judgment of the Supreme Court in Grianán an
Aileach Interpretative Centre Ltd. v Donegal County Council [2004] IESC 41; [2004] 2
I.R. 625 (“Grianán an Aileach”). The judgment addresses the question of whether the
court’s inherent jurisdiction to grant declarations as to the planning status of lands is
consistent with the Section 5 procedure. The Supreme Court considered that the
continued existence on the part of the High Court of a general jurisdiction to adjudicate
upon the proper construction of a planning permission would create a danger of
Page 14 ⇓
“overlapping and unworkable jurisdictions”. The making of a declaration by the High
Court might have the result that neither An Bord Pleanála nor the local planning authority
would thereafter be in a position whereby it could exercise its statutory jurisdiction under
Section 5 without finding itself in conflict with the earlier determination by the High Court.
69. The solution adopted by the Supreme Court to this conundrum was, in effect, to find that
the existence of the Section 5 reference procedure ousted the High Court’s jurisdiction to
grant (freestanding) declarations in respect of planning matters.
70. The judgment recognises, of course, that the High Court continues to have original
jurisdiction to determine planning issues when adjudicating upon enforcement
proceedings under Section 160 of the PDA 2000. The Supreme Court held that if
enforcement proceedings are brought in the High Court, then that court may
“undoubtedly find itself having to determine whether there has been a material change of
use or whether a development is sanctioned by an existing planning permission”.
71. At a later point in the judgment, Keane C.J. stated as follows at paragraph [36].
“Some responsibility may be attributed to the defendant for the difficulties that
have arisen in determining to what uses the premises may be put without a further
planning permission: they might well have been avoided by the use of more precise
language when the permission was being granted. I am satisfied, however, that
the High Court cannot resolve these difficulties by acting, in effect, as a form of
planning tribunal. As I have already indicated, if enforcement proceedings were
brought in the High Court, that court might find itself having to determine whether
particular operations constituted a ‘development’ which required permission and the
same issue could arise in other circumstances, e.g., where a commercial or
conveyancing document containing a particular term dealing with compliance with
planning requirements was the subject of litigation. But in every such case,
however it came before the court, the court would resolve the issue by determining
whether or not there had been or would be a development within the meaning of
the planning code. The only circumstance in which the court could find itself
making a declaration of the kind ultimately granted in this case would be where it
had been drawn into a role analogous to that of a planning authority granting a
permission. That is difficult to reconcile with the law as stated thus by Finlay C.J. in
O’Keeffe v. An Bord Pleanála [1993] 1 I.R. 39 […]”.
72. This aspect of the judgment is entirely consistent with the approach adopted in Cork
Corporation v. O’Connell [1982] I.L.R.M. 505. There, the Supreme Court held that the
existence of a pending reference under the precursor of what is now Section 5 of the PDA
2000, i.e. Section 5 of the Local Government (Planning & Development) Act 1963, did not
oust the High Court’s jurisdiction to entertain enforcement proceedings.
73. The judgment in Grianán an Aileach left open the separate question as to what should
happen where An Bord Pleanála had already issued a Section 5 declaration in advance of
the hearing of enforcement proceedings. This question has since been addressed in a
Page 15 ⇓
series of High Court judgments. There is now a consistent line of case law which indicates
that a Section 5 declaration, which has not been challenged in judicial review
proceedings, is binding and conclusive in enforcement proceedings involving the same
parties as to the reference. In particular, a declaration to the effect that an act is
“development” or is “exempted development” cannot normally be revisited in subsequent
enforcement proceedings between the same parties or their privies. See Wicklow County
development); and McCoy v. Shillelagh Quarries Ltd [2015] IEHC 838 (quarrying activity
had intensified to such an extent as to amount to a material change of use).
74. There is an exception to this approach where it would be unfair to treat a party as bound
by a Section 5 declaration. In Wicklow County Council v. Fortune (No. 3) [2013] IEHC 397,
the High Court (Hogan J.) declined to treat a respondent to enforcement proceedings
as bound by a Section 5 reference which had been made without a proper statement of
reasons. The High Court held that it would be “quite unfair” to shut out a respondent
from arguing that a structure was “exempted development” on the basis of a Section 5
declaration which, on its face, plainly failed to meet the requirements of administrative
fairness specified in Mallak v. Minister for Justice and Equality [2012] IESC 59; [2012] 3
I.R. 297, notwithstanding that the determination had never been challenged at the
relevant time by way of judicial review.
75. The correctness of this line of case law has since been upheld by the Court of Appeal in
(“Killross Properties”). On the facts, An Bord Pleanála had issued a series of Section 5
declarations to the effect that works, consisting of the erection of a temporary electricity
transmission line by a statutory undertaker, were “exempted development”. Killross
Properties Ltd., who had made the Section 5 references, had sought to challenge An Bord
Pleanála’s declarations in judicial review proceedings, but those proceedings were
dismissed by the High Court (Hedigan J.) in August 2014 . Notwithstanding this
procedural history, Killross Properties Ltd. then pursued an application under Section 160
of the PDA 2000.
76. The Court of Appeal, per Hogan J., held that the High Court was not entitled to “go
behind” the Section 5 declarations.
“[…] the High Court cannot go behind an otherwise valid s. 5 determination to the
effect that the development in question represent exempted development in the
course of a s.160 application. The effect of such a determination is that planning
permission is not required, so that by definition the development cannot be
unauthorised. It follows that the High Court cannot grant the relief claimed in the
s. 160 proceedings.
77. The rationale for this approach is explained as follows, at paragraphs [29] to [31] of the
Court of Appeal’s judgment.
Page 16 ⇓
“First, it can be said that as the planning authorities (or, An Bord Pleanála, as the
case may be) determined that the works in question represent exempted
development, it necessarily follows that no planning permission is required. The
logical corollary of this conclusion is that the development in question cannot by
definition be “unauthorised” within the meaning of s. 160 if no planning permission
is required so that consequently any such s. 160 application is bound to fail.
Second, it could equally be said that the s. 160 application represents a collateral
attack on the decision of the planning authority, since it effectively invites the court
to revisit the merits of the issue which had already been determined in the course
of the s. 5 determination. This is further reinforced so far as the present
proceedings are concerned, since Killross elected to challenge the validity of three
of the s. 5 determinations in judicial review proceedings and failed in that
endeavour.
Third (and related to it the second argument), it could be said that the s. 160
proceedings represent an attempt indirectly to challenge the validity of the s. 5
determinations otherwise than by means of the judicial review requirement
specified by s. 50 of the 2000 Act.”
78. The practical effect of these various judgments is that the existence of an (unchallenged)
Section 5 declaration gives rise to a form of issue estoppel whereby the parties are bound
by the declaration. In circumstances where the Section 5 declaration is to the effect that
a particular act constitutes “development”, then the moving party in an application for
injunctive relief under Section 160 of the PDA 2000 can rely upon that declaration in
support of their application. This is subject to an exception where it would be unfair.
79. The current legal position is, therefore, that enormous significance now attaches to a
Section 5 declaration. The existence of an (unchallenged) declaration will, in certain
circumstances, be dispositive of many of the issues which arise in enforcement
proceedings. The precise implications of all of this have not yet been fully teased out. In
particular, questions remain as to whether, for example, An Bord Pleanála would be
precluded from entertaining a reference by virtue of the existence of an earlier un-
appealed declaration made by a local planning authority pursuant to a separate reference.
Questions also remain as to whether a Section 5 declaration constitutes a “development
consent” for the purpose of the EIA Directive.
80. The Developer in the present case seeks to argue that a distinction should be drawn
between (i) a finding that a particular act is “development” or “exempted development”,
and (ii) a finding that it is “unauthorised development”. It is contended that An Bord
Pleanála does not have jurisdiction to make a finding of the latter type. Much reliance is
placed in this regard on the following passage from the judgment of the High Court
(Finlay Geoghegan J.) in Roadstone Provinces Ltd. v. An Bord Pleanála [2008] IEHC 210
(“Roadstone Provinces”).
Page 17 ⇓
“[An Bord Pleanála] has no jurisdiction on a reference under s.5 (4) of the Act to
determine what is or is not ‘unauthorised development’. It may only determine
what is or is not ‘development’. Hence, a planning authority, such as the notice
party, cannot refer a question under s.5 (4) as to whether the works or proposed
works or use constitutes unauthorised works or use and hence unauthorised
development. Determination of what is or is not ‘unauthorised development’ will
most likely be determined by the courts where a dispute arises on an application
under s. 160 of the Act.”
81. It should be noted, however, that this statement was made in the context of a pre-1964
quarry, and appears to have been informed, in part at least, by the highly technical
definition of “unauthorised development”. To elaborate: the planning legislation does not
apply retrospectively to “development” which had commenced prior to the coming into
force and effect of the Local Government (Planning & Development) Act 1963 on 1
October 1964. Such pre-1964 development is not, however, treated as “exempted
development”, but rather enjoys a sui generis status. This is achieved by confining the
definitions of “unauthorised works” and “unauthorised use” to development which
commenced on or after 1 October 1964. The Supreme Court in Waterford County Council
v. John A. Wood Ltd. [1999] 1 IR 556 has since formulated a test which defines the
extent of quarrying activity which can be carried out and completed in reliance on the
commencement of works prior to 1 October 1964.
82. Returning to the facts of Roadstone Provinces, it appears that the point being made in the
passage cited above is that An Bord Pleanála does not have jurisdiction to determine
whether a particular development constitutes the lawful continuation of pre-1964
development. Put shortly, An Bord Pleanála does not have jurisdiction to apply the legal
test in John A. Wood Ltd. This is apparent from the very next passage of the judgment in
Roadstone Provinces, at paragraph [22].
“The reason for which I have drawn attention to the fact that the respondent was
considering whether or not there was or is a development by reason of a material
change in the use of the applicant’s lands, as distinct from the carrying out of any
works, is because of the reliance placed by both parties, for different purposes, on
the decision of the Supreme Court in Waterford County Council v. John A. Wood
Ltd. [1999] 1 IR 556. That is a decision on a case stated from the High Court
(determining an appeal from the Circuit Court) on proceedings under s. 27 of the
Local Government (Planning and Development) Act, seeking an order restraining
the respondent therein from carrying on quarrying operations on certain lands.
Section 27 of the Act of 1976 is similar to s. 160 of the Act of 2000. The question
put by the High Court to the Supreme Court in the case stated was whether the
quarrying operations being carried out by the respondent ‘is development requiring
planning permission?’. The resolution of that question depended upon whether or
not the quarrying operations then carried on were or were not ‘development
commenced before the appointed day’ and therefore were or were not excluded
from a requirement to apply for planning permission under s. 24 (1) of the Act of
Page 18 ⇓
1963. That issue was resolved by the Supreme Court by considering whether or
not the works then being carried out by the respondent at its quarrying operations
were works which commenced prior to the appointed day. The Supreme Court did
this by considering what might have been reasonably contemplated or anticipated
as the continuation of works commenced before the appointed day. In the context
of the definitions in the Act of 2000, it was a determination as to whether the works
were or were not ‘unauthorised works’. That is not a question which the
respondent has jurisdiction to determination on the instant reference under s.5 (4)
of the Act of 2000.* The Supreme Court, in Waterford County Council v. John A.
Wood Ltd., was not considering whether or not there had been a material change in
use of the lands. On the facts, the only objection appears to have been based upon
the carrying out of works without planning permission.”
*Emphasis (italics) added.
83. It would appear, therefore, that the judgment in Roadstone Provinces, strictly speaking,
had been concerned with the narrow question of pre-1964 user, and does not necessarily
articulate a more general proposition as to the limitations of the Section 5 jurisdiction.
Certainly, this seems to have been the interpretation of the judgment taken by the High
Court (Baker J.) in Cleary Compost and Shredding Ltd v. An Bord Pleanála (No. 1
[2017] IEHC 458. Having cited the passage from Roadstone Provinces set out at paragraph 80
above, Baker J. stated as follows.
“This dicta of Finlay Geoghegan J. is regularly quoted as authority for the
proposition that the jurisdiction under s. 5(4) of the Act is one which is confined to
determining whether works or use is development.
Finlay Geoghegan J. was considering the import of a s. 5 declaration where what
was challenged was the decision of the respondent that the expansion southward of
a quarry was development and not exempted development. The decision was
quashed by certiorari as there was pre-1964 use and no determination had been
made whether there was an identified factual difference between that use and
current use. The judgment does not go so far as to say that the consequence of a
s. 5 declaration can never be understood to mean that a development is not one
authorised by planning permission. The judgment of Finlay Geoghegan J. is
authority for the proposition that development which does not have the benefit of a
planning permission is not always in legal terms a development which is
‘unauthorised’, and the jurisdictional limit of s. 5 is to determine whether there is
development, after which there arises the second question whether permission is
required or exists.
[…]
A development is not unauthorised merely on account of the fact that an activity or
works are found to be development. The development may, as in the case of a
quarry, the context in which Roadstone Provinces Limited v. An Bord Pleanála was
Page 19 ⇓
decided, be exempt from the requirement to obtain planning permission if it is a
continuation of pre-1964 user. In such cases the development is not unauthorised
although it is development. A development may also be found to have occurred but
to be exempt.
However, it must be the case that, absent an argument that there is relevant pre-
1964 use, if works or activity are declared in the s. 5 process to amount to
development and if a determination is made that it is not exempt, then the
inevitable conclusion is that the development does not have the benefit of planning
permission, is not authorised in planning terms, and is ‘unauthorised’.”
84. The judgment in Cleary Compost goes on to make the separate point at paragraph [90]
that an earlier Section 5 declaration will not preclude a subsequent declaration to different
effect being made if there has been a change in circumstances between the dates of the
two declarations.
85. The nature of the Section 5 jurisdiction has also been considered by the Court of Appeal
in Killross Properties. The Court of Appeal put the matter as follows (in a passage
subsequently cited with approval in Cleary Compost).
“Yet if An Bord Pleanála (or, as the case may be, a planning authority) rules that a
particular development is not exempted development, the logical corollary of that
decision is that planning permission is required. In practice, there is often only a
very slender line between ruling that a development is not exempted development
since this will generally – perhaps, even, invariably – imply that the development is
unauthorised on the one hand and a finding that a particular development is
unauthorised on the other. Conversely, where (as here) An Bord Pleanála (or the
planning authority) rules that the development is exempt, this necessarily implies
that the development is lawful from a planning perspective since, by definition, it
has been determined that no planning permission is required.”
86. In two recent judgments, the Supreme Court has expressed some caution as to the
reliance on Section 5 declarations in criminal proceedings and enforcement proceedings,
respectively. Both judgments were delivered in May 2017. The first in time is the
judgment in Cronin (Readymix Ltd.) v. An Bord Pleanála [2017] IESC 36; [2017] 2 I.R.
658. In addressing the question of whether the planning legislation falls to be interpreted
as penal legislation, the Supreme Court, per O’Malley J., stated as follows at paragraph
[43] of the judgment.
“It follows that the primary role in determining whether a development is exempted
or not is given to (depending on the circumstances) either the planning authority or
the Board. A decision by one of those bodies is an authoritative ruling on the issue,
subject to the potential for judicial review. However, it plainly does not, and could
not, result in a determination of guilt or innocence of a criminal offence. There was
no suggestion to the contrary at any stage of these proceedings. In my view,
therefore, it is entirely inappropriate to read the provisions of s.4 as if they related
Page 20 ⇓
to ‘the imposition of a penal or other sanction’. What they are concerned with is the
exemption of categories of development from the general requirement to obtain
permission.”
87. The second judgment is that in Meath County Council v. Murray [2017] IESC 25; [2018] 1
I.R. 189; [2017] 2 I.L.R.M. 297. McKechnie J., delivering the judgment of the court,
reserved his position in relation to the status of a Section 5 declaration in the context of
enforcement proceedings. See paragraphs [55] and [56] of the reported judgment as
follows.
“By engaging the enforcement mechanism of, say, s. 160, there is no question of
the Council making any planning determination that the structure is unauthorised:
even that power is not conferred on either a planning authority or An Bord Pleanála
by s. 5 of the 2000 Act (Roadstone Provinces Limited v. An Bord Pleanála
[2008] IEHC 210, (Unreported, High Court, Finlay Geoghegan J., 4 July 2008)), nor is the
situation in any way analogous to that arising in Grianán an Aileach Centre v.
seems to bear no real relationship to the other cases quoted, including Heatons
Limited v. Offaly County Council [2013] IEHC 261, (Unreported, High Court, Hogan
J., 4 June 2013) and State (Fitzgerald) v. An Bord Pleanála [1985] I.L.R.M. 117.
A further word about s. 5 of the 2000 Act: the power given to both planning bodies
under that section relates to what is a ‘development’ or what is an ‘exempted
development’. Even though a decision on either issue may have significant
consequential effect, it is not an end in itself. Without more, and simply on that
basis, a s. 160 order could not be made: one must go further and establish the
“unauthorised” nature of the underlying development. Thankfully, the difficult
question of the courts’ review power where a declaration one way or the other has
been made on a s. 5 reference does not arise on this appeal (see the judgment of
the Court of Appeal (per Hogan J.) in Bailey v. Kilvinane Wind Farm Ltd.
[2016] IECA 92, (Unreported, Court of Appeal, 16 March 2016), which judgment is under
appeal to this court).”
88. It should be noted that the appeal in Bailey v. Kilvinane Wind Farm Ltd. (referenced in the
above passage from Meath County Council v. Murray) subsequently became moot in
circumstances where the developer in that case obtained a grant of substitute consent.
The Supreme Court did not, therefore, have to rule on this issue in the context of that
appeal.
(2). Section 5 jurisdiction to interpret planning permission
89. The case law confirms that An Bord Pleanála does have jurisdiction to interpret a planning
permission in the context of a Section 5 reference. The question first arose for
case decided under the previous version of the planning legislation. The equivalent
Page 21 ⇓
provision to what is now Section 5 of the PDA 2000 was to be found in the coincidentally
numbered Section 5 of the Local Government (Planning & Development) Act 1963.
90. The judgment in Palmerlane Ltd. arose out of a dispute as to whether the use of a
convenience store for the sale of hot food for consumption off the premises represented
“development”. The operator of the convenience store had sought to refer the matter to
An Bord Pleanála. An Bord Pleanála had refused to entertain the reference, stating that it
did not have power to decide whether or not a particular development had been carried
out in accordance with a particular permission. An Bord Pleanála considered that as the
sale of hot food had been part of the user of the premises from the outset, there simply
was no change in use, the materiality of which it could assess. The board’s decision to
decline jurisdiction was then challenged in judicial review proceedings. Having noted that
An Bord Pleanála would have been prepared to entertain the reference had the use for the
sale of hot food been introduced subsequent to the opening of the store, the High Court
(McGuinness J.) took the pragmatic view that the board’s jurisdiction should not turn on
such nice distinctions.
“The decision of An Bord Pleanála in the instant case also, in my view, creates the
somewhat anomalous and unreasonable situation that if the Applicant were to
select another of its ‘Spar’ shops, where the position was that the premises had
been in use as a retail shop under an earlier planning permission and the company
had subsequently embarked on the limited sale of hot food for consumption off the
premises, the Applicant could presumably successfully have sought a determination
of a reference pursuant to Section 5 of the 1963 Act. I appreciate that each
determination under Section 5 deals only with the particular case on its own facts.
However, in a situation where a very large number of convenience stores operate in
the same way as the shop in question in the instant case, it seems to me to be in
accordance with reason and common sense that questions such as this should be
determined on a consistent basis by those with expertise in the planning area,
namely An Bord Pleanála.”
91. This pragmatic approach on the part of the High Court was elevated to a more general
statement of principle by the judgment of the Supreme Court in Grianán an Aileach. As
discussed under the previous heading above, the central issue in the appeal had been
whether the High Court continued to enjoy a parallel jurisdiction to grant declarations as
to the interpretation of planning permissions notwithstanding the existence of Section 5 of
the PDA 2000. In the course of its adjudication on the central issue, the Supreme Court
had cause to consider the nature and extent of the Section 5 jurisdiction. The Supreme
Court, per Keane C.J., concluded that a question as to whether proposed uses constitute
“development” which is not authorised by planning permission is one which may be
determined under Section 5 of the PDA 2000.
“In the present case, the issue that has arisen between the plaintiff and the
defendant is as to whether the proposed uses are authorised by the planning
permission. I am satisfied, however, that, although the issue has arisen in that
Page 22 ⇓
particular form, it necessarily requires the tribunal which determines it to come to a
conclusion as to whether what is being proposed would constitute a material
change in the use of the premises. If it would not, then the question as to whether
the particular uses were authorised by the permission simply would not arise. In
the present case, the defendant at all times has been contending, in effect, that the
proposed uses would constitute a material change in use which is not authorised by
the present planning permission. Equally, for its part, the plaintiff has been
contending that the uses are authorised by the existing planning permission but has
not contended that, if that were not the case, it would in any event be entitled to
carry them out as not constituting a material change of use. It would seem to
follow that the question as to whether planning permission is required in this case
necessarily involves the determination of the question as to whether the proposed
uses would constitute a ‘development’, i.e. a question which the planning authority
and An Bord Pleanála are empowered to determine under s. 5 of the Act of 2000.”
92. Keane C.J. at a later point in his judgment stated as follows (at pages 636/37 of the
reported judgment).
“The reasoning adopted in both McMahon v. Dublin Corporation and Palmerlane v.
An Bord Pleanála which, I am satisfied, is correct in law would indicate that, in such
circumstances, a question as to whether the proposed uses constitute a
‘development’ which is not authorised by the planning permission is one which may
be determined under the Act of 2000 either by the planning authority or An Bord
Pleanála. In the present case the question is as to whether the various proposed
uses, which the defendant contends, would involve the regular use of the premises
for events associated with a concert/entertainment venue rather than a visitors’
centre, are in a planning context materially different uses from use as a visitors’
centre and the uses indicated on the lodged plan, in which case they would not be
authorised by the planning permission.”
93. There is no principled distinction between (i) a finding that a particular act of
development is or is not “exempted development”, and (ii) a finding that a particular act
of development does not come within the scope of a planning permission. In each
instance, An Bord Pleanála is required to assess the difference between two forms of
“development”, and to reach a determination as to whether the difference between the
two is material or immaterial. In the case of the user of lands, the exercise is to
determine whether there has been a material change of use. In the case of permitted
works under a planning permission, the exercise is to determine whether the difference is
an immaterial deviation.
94. An Bord Pleanála is the expert body entrusted under the planning legislation with this
task. For the court to carry out the same exercise subsequently gives rise to the very
mischief which the judgment in Grianán an Aileach is intended to avoid.
SUMMARY OF LEGAL PRINCIPLES RE: SECTION 5
95. The current state of the case law can be summarised as follows.
Page 23 ⇓
(i). The fact that both the High Court and An Bord Pleanála have jurisdiction, in certain
circumstances, to determine whether a particular act is “development” or
“exempted development” presents a potential risk of overlapping and unworkable
jurisdictions.
(ii). In order to reduce this risk, the Supreme Court has held that the High Court’s
inherent jurisdiction to make declarations as to the planning status of lands is
ousted. More specifically, the High Court’s jurisdiction to adjudicate upon the
proper construction of a planning permission is largely confined to enforcement
proceedings. (It might also arise in the context of contractual or conveyancing
disputes). The Supreme Court has not yet had to address the specific question of
whether the High Court, in hearing enforcement proceedings, is bound by an earlier
(unchallenged) Section 5 declaration.
(iii). The Court of Appeal has held that an (unchallenged) Section 5 declaration to the
effect that certain works are “exempted development” is binding on the parties in
subsequent enforcement proceedings. The Court of Appeal has not yet had to
address the question of the legal status of a Section 5 declaration to the effect that
certain works are not “exempted development” or to the effect that certain works
do not come within the scope of an existing planning permission. Put otherwise,
the Court of Appeal has not yet ruled on whether a declaration which is adverse to
a respondent is binding.
(iv). The High Court, in at least three judgments, has held that Section 5 declarations to
the effect that planning permission is required for certain acts are, in principle,
binding on the parties in enforcement proceedings.
(v). Certain judgments have expressed reservations as to the jurisdiction of An Bord
Pleanála to make declarations to the effect that a particular act is “unauthorised
development”.
(vi). The principal ground for finding that a Section 5 declaration is binding is in order to
reduce the risk of overlapping and unworkable jurisdictions. This would appear to
involve a form of issue estoppel. A secondary ground for the finding is that it might
offend against Section 50 of the PDA 2000 to allow a party to make a collateral
challenge to a Section 5 declaration in the context of subsequent enforcement
proceedings.
(vii). The Section 5 jurisdiction extends to questions of interpretation of planning
permission.
(viii). Whereas a Section 5 declaration may be dispositive of many of the issues in
enforcement proceedings, there remain a number of matters which fall outwith the
Section 5 jurisdiction. In particular, An Bord Pleanála has no function in
determining whether the development being enforced against has the benefit of the
“seven-year rule”, i.e. whether the proceedings are statute barred by reference to
Page 24 ⇓
the seven-year limitation period provided for under Part VIII of the PDA 2000. It
also follows by analogy with the judgment in Cleary Compost that an earlier Section
5 declaration will not be binding if there has been a change in circumstances in the
interim.
FINDINGS OF THE COURT ON SECTION 5 REFERENCE
96. The current state of the authorities, therefore, appears to be that, at the very least, a
Section 5 declaration must be given significant weight in subsequent enforcement
proceedings. The principal rationale underlying this case law is the desirability of avoiding
overlapping and inconsistent decision-making.
97. Applying these principles to the facts of the present case, I have concluded that the
Section 5 declaration precludes the Developer from reagitating the argument that the “as
built” wind turbines are authorised by the 2011 planning permission. The Developer had
a full opportunity of making its case in this regard to An Bord Pleanála. In particular, the
Developer had made submissions before the Board to the effect, first, that the decision-
letter of 13 December 2013 authorised the change in scale and dimensions; and,
secondly, that the circumstances were distinguishable from those of the Kilvinane Wind
Farm. Those submissions were, ultimately, rejected by An Bord Pleanála.
98. To allow the Developer to rerun the same arguments before this court would give rise to
precisely the type of overlapping and unworkable jurisdictions which the judgments
discussed above are intended to avoid. Were this court to embark upon a de novo
consideration of these matters, and to come to a contrary conclusion to that of An Bord
Pleanála, this would bring about the very mischief which the case law is intended to
avoid.
99. Of course, different considerations would apply where a party had not been afforded fair
procedures before An Bord Pleanála or where the declaration is bad on its face, e.g. the
decision is not fully reasoned. See, for example, Wicklow County Council v. Fortune (No.
3) [2013] IEHC 397 (discussed at paragraph 74 above). A Section 5 declaration would
not be binding in such circumstances. No such contingencies arise, however, on the facts
of the present case.
100. In reaching this conclusion as to the status of the Section 5 declaration, I have given
careful consideration to the legal submissions—both written and oral—advanced on behalf
of the Developer. It will be recalled that one of the arguments advanced is to the effect
that the court should apply a “double construction” rule to the Section 5 declaration, i.e. if
the declaration is open to two constructions, then it should be interpreted in the manner
which holds it intra vires. More specifically, it had been argued that the declaration
should be interpreted as confined to a finding that the erection of the wind turbines is
“development” and not “exempted development”. (See paragraph 62 above).
101. With respect, the narrow interpretation which the court is invited to give to the Section 5
declaration is entirely artificial. It would require the court to disregard large portions of
the text of the declaration, and also to disregard the underlying inspector’s report. Such
Page 25 ⇓
an artificial approach would be contrary to the well-established principles governing the
interpretation of planning decisions. (See In re XJS Investments Ltd. [1986] IR 750).
The rationale for a decision of An Bord Pleanála is to be found by reading the Board’s
decision in conjunction with the underlying inspector’s report (save in cases where the
Board had disagreed with the inspector’s recommendation). See Connelly v. An Bord
102. On the facts of the present case, it is obvious the Board followed its inspector’s
recommendation, and had adopted the same approach as it had in respect of the
Kilvinane Wind Farm. This entailed making an express finding, at sub-paragraph (b) of
the Section 5 declaration, to the effect that the alterations to the turbines, including the
length of the rotor arms/blades, do not come within the scope of the planning permission
granted. Put otherwise, An Bord Pleanála expressly addressed the interpretation of the
planning permission and resolved this issue against the Developer.
103. Notwithstanding the fact that the Developer did not seek to challenge An Bord Pleanála’s
declaration at the time, the Developer now maintains the position in these enforcement
proceedings that the Section 5 jurisdiction does not allow An Bord Pleanála (i) to
determine whether particular works come within the scope of a planning permission, nor
(ii) to make a finding of “unauthorised development”. This position is untenable. As
discussed in detail under the previous headings, the case law establishes that the Section
5 jurisdiction is not as narrow as the Developer contends.
104. Similarly, the attempt on the part of the Developer to distinguish the facts of the present
case from those of Killross Properties is not well-founded. Whereas it is correct to say
that Killross Properties was concerned with a declaration to the effect that certain works
were “exempted development”, and that this declaration was, therefore, adverse to the
case which the applicant, as opposed to the respondent, was making in those
proceedings, these points of distinction do not affect the underlying rationale. The
underlying rationale of the judgment is to avoid unworkable and overlapping jurisdictions.
This mischief arises equally in the case of a Section 5 declaration which is adverse to a
respondent as in the case of a declaration which is adverse to the applicant. In each
instance, An Bord Pleanála will have made findings on issues which are relevant to the
subsequent enforcement proceedings. For the court hearing the enforcement proceedings
to embark on a de novo consideration of these issues would involve the court re-opening
the very issues which had been determined by An Bord Pleanála. This would be contrary
to the general principle stated in Grianán an Aileach to the effect that the Oireachtas may
confer on statutory bodies, expressly or by implication, an exclusive jurisdiction to
determine specific issues. Section 5 of the PDA 2000 has conferred just such a
jurisdiction on An Bord Pleanála.
105. It might, perhaps, be said that the legal status now attaching to a Section 5 declaration is
more significant than a literal interpretation of the section might at first suggest. The
case law from the last fifteen years is, however, clear. Section 5 has been given a
purposive interpretation, which is intended to reflect the fact that An Bord Pleanála has
Page 26 ⇓
been entrusted with specific competences under the PDA 2000. More generally, this
interpretation is also consistent with the principle of finality in litigation and that parties
are estopped from re-agitating issues which have been decided against them. This is
subject to the exceptions discussed under the next paragraph.
106. The High Court will retain original jurisdiction to determine planning issues in enforcement
proceedings where there is no Section 5 determination in existence. It will also have
jurisdiction where, as in Wicklow County Council v. Fortune (No. 3), the Section 5
declaration is bad on its face or had been reached in breach of fair procedures. The High
Court will also retain original jurisdiction where an issue arising in enforcement
proceedings has not been specifically addressed by An Bord Pleanála or where there has
been a change in circumstances in the interim. None of these contingencies arise on the
facts of the present case. The precise same issues which the Developer seeks to agitate
in this court had been raised before An Bord Pleanála and were determined against the
Developer. If the Developer had wished to challenge that determination, then the remedy
was to make an application for judicial review. The Developer did not do so.
107. Accordingly, I am satisfied that the Section 5 declaration made by An Bord Pleanála in
this case should be treated as binding on the Developer, and as conclusive of the question
of whether or not the “as built” wind turbines come within the scope of the 2011 planning
permission. The declaration is not, of course, determinative of the outcome of the
enforcement proceedings. The Applicants would still have to prove to the satisfaction of
the court that works had been carried out by the Developer, and that proceedings were
instituted within the relevant seven-year limitation period. It remains open to the
Developer to resist the proceedings on the basis of the court’s discretion.
DE NOVO ASSESSMENT
108. For the reasons set out under the previous heading, I have found that the Section 5
declaration is binding on the Developer. The Developer cannot, therefore, seek to defend
the enforcement proceedings before this court on the basis of an argument that the “as
built” turbines come within the scope of the planning permission.
109. Lest I be incorrect in this finding, however, I propose to address the question of
compliance with the planning permission de novo. Put otherwise, I propose to embark
upon my own assessment of whether the “as built” turbines come within the scope of the
planning permission. This exercise is being carried out de bene esse, and without
prejudice to my finding as to the binding effect of the Section 5 declaration. The exercise
is only being undertaken on account of the urgency of the proceedings. There is a risk
that if this judgment were to be decided on the narrow basis that the Section 5
determination is binding, then this might result in unnecessary delay in the event of an
appeal. More specifically, if the finding on the narrow issue were to be overturned on
appeal, and this court had not addressed separately the question of compliance with the
planning permission, then it would become necessary to remit the matter to the High
Court for rehearing (with all the attendant delay and cost). It seems preferable that this
judgment should, insofar as reasonably practicable, address all issues and contingencies.
Page 27 ⇓
110. The Developer’s argument can be summarised as follows. A planning permission provides
for some flexibility, and “immaterial deviations” from the permitted development are
implicitly authorised by the permission. The court should, therefore, engage in the
process of examining whether the environmental impact of the deviations between the
“as permitted” and “as built” wind turbines are material. The Developer has filed detailed
affidavit evidence which, it is said, indicates that there is no material difference between
the two.
111. The court is, in effect, being invited to engage in a form of screening exercise analogous
to that required under the EIA Directive. With respect, this is not what the planning
legislation requires. The term “works” is broadly defined under the PDA 2000, and, in
contrast to the term “use”, is not subject to a “materiality” test.
“‘works” includes any act or operation of construction, excavation, demolition,
extension, alteration, repair or renewal and, in relation to a protected structure or
proposed protected structure, includes any act or operation involving the
application or removal of plaster, paint, wallpaper, tiles or other material to or from
the surfaces of the interior or exterior of a structure.”
112. The legal consequence of this is that even very minor “works” are, in principle, subject to
a requirement to obtain planning permission. The broad definition of development
“works” is counterbalanced by the putting in place of legislative measures which exempt
prescribed classes of development from the requirement to obtain planning permission.
Some of these exemptions are provided for under Section 4(1) of the PDA 2000, but most
are to be found in Regulations made by the Minister for Housing, Planning and Local
Government (“the Minister”) pursuant to Section 4(2) of the PDA 2000. This section
reads as follows.
“(2)(a) The Minister may by regulations provide for any class of development to be
exempted development for the purposes of this Act where he or she is of the
opinion that—
(i) by reason of the size, nature or limited effect on its surroundings, of
development belonging to that class, the carrying out of such development
would not offend against principles of proper planning and sustainable
development, or
(ii) the development is authorised, or is required to be authorised, by or under
any enactment (whether the authorisation takes the form of the grant of a
licence, consent, approval or any other type of authorisation) where the
enactment concerned requires there to be consultation (howsoever
described) with members of the public in relation to the proposed
development prior to the granting of the authorisation (howsoever
described).”
Page 28 ⇓
113. The position under the planning legislation is, therefore, that planning permission is
required for even minor development “works”, the definition of which includes relevantly
an “extension”, unless the works fall within a class of “exempted development”.
114. The decision as to whether to exempt particular classes of development “works” from the
requirement to obtain planning permission resides principally with the Minister. As
appears from Section 4(2), the Minister is required to consider whether or not the
carrying out of such development would “offend against principles of proper planning and
sustainable development”.
115. The courts do not have an equivalent jurisdiction to waive the requirement to obtain
planning permission for minor development “works”. The only role which a court has in
assessing the materiality of development “works” is where a developer seeks to argue
that a departure from the terms of a planning permission represents an “immaterial
deviation”. The principles governing this assessment have been set out, with
characteristic clarity, by Fennelly J. in Kenny v. Provost, Fellows & Scholars of the
University of Dublin, Trinity College [2009] IESC 19 (“Kenny”) at paragraphs [18] to [20]
of the judgment as follows.
“There will inevitably be small departures from some or even many of the plans and
drawings in every development. There can be discrepancies between and within
plans, drawings, specifications and measurements; there can be ambiguities and
gaps. It seems improbable that any development is ever carried into effect in exact
and literal compliance with the terms of the plans and drawings lodged. If there
are material departures from the terms of a permission, there are enforcement
procedures.
However, planning laws are not intended to make life impossible for developers, for
those executing works such as architects, engineers or contractors or for the
planning authorities in supervising them. Nor are they there to encourage fine-
tooth combing or nit-picking scrutiny of the works. I will mention later one or two
examples of this type of exercise in the present case. The exchange of affidavits
amounts to some 300 pages.
While the planning authority or An Bórd Pleanála on appeal grants the permission,
it is a common feature of permissions, especially for large developments, that
additional detail is necessary in order to carry the development into effect and such
detail, often in the form of further plans, drawings, specifications or other
explanations, will require approval by the planning authority prior to
commencement of the development. There is an obvious practical necessity for a
procedure whereby matters of detail can be agreed between the planning authority
and the developer. This ensures supervision but allows a degree of flexibility within
the scope of the permitted development.”
116. The planning permission in Kenny had included a number of conditions, of the type
flagged in the last paragraph above, i.e. conditions which left over points of detail to be
Page 29 ⇓
agreed between the developer and the planning authority. The planning authority had
relied on the conditions to authorise certain departures from the strict terms of the
planning permission. As discussed under the next heading below, the Developer in the
present case seeks to rely on the existence of such a condition in the 2011 planning
permission as authorising the increase in rotor diameter.
117. Staying for the moment with immaterial deviations, the case law indicates that the
flexibility allowed under a planning permission is very limited. Thus, for example, the
High Court in Cork County Council v. Cliftonhall Ltd. [2001] IEHC 85 held, with some
reluctance, that an exceedance of the ridge height of one block of apartments of between
0.5 metres and 1.3 metres was immaterial in the context of an overall residential
development of six blocks. The court calculated that the deviation between the “as
permitted” and “as built” height was in the order of some 7 per cent.
118. In O’Connell v. Dungarvan Energy Ltd., unreported, High Court, Finnegan J., 27 February
2000, it was held that the relevant planning permission implicitly authorised the erection
of a steel structure to replace an existing structure. Crucially, the replacement structure
was of the same dimensions as the existing structure, and would, in any event, have been
“exempted development”.
“It was therefore necessary, if the development should proceed, that a stronger
steel structure capable of supporting the cladding be provided. This replacement
steel structure as to its external dimensions will correspond both as to height and
floor area with that which is being demolished. The external appearance of the
building will be in accordance with the planning permission condition 3 thereof. In
these circumstances the course of conduct which the Respondent has undertaken is
in direct consequence of the imposition of the said condition 8 in the Integrated
Pollution Control Licence. It is therefore within the category of unforeseen
variations mentioned by Denning M R and as such authorised by the planning
permission. It is also immaterial having regard to what I have said as to its floor
area, height and the fact that its external appearance will be determined in
accordance with condition 3 of the planning permission and so unaffected by the
variation. In short the variation in the development is within the terms of the
planning permission. It is also exempted development pursuant to the Local
Government (Planning and Development) Regulations 1995 Article 9 A as inserted
by the Local Government (Planning and Development) Regulations 1995.”
119. The judgment most directly on point is that of the Court of Appeal in Bailey v. Kilvinane
Wind Farm [2016] IECA 92. The Court of Appeal held at paragraph [87] that an increase
in rotor diameter of 23 metres was a material deviation.
“The same reasoning also applies in the context of the diameter size of the
turbines. As constructed the two turbines, T3 and T4, each have a rotor diameter
of 90m, which is 23m. larger than that sanctioned by the 2002 planning
permission, thus very significantly extending the sweep of the rotor circumference.
The sweep of the rotor diameters thus rises from 57π (57 x3.1416 = 179m.) to 90π
Page 30 ⇓
(57 x 3.1416 = 283m.). It is impossible to say that such a large and appreciable
increase in the diameter size of the rotors beyond that sanctioned by the planning
permission is not material. The potential impact in terms of sightlines (and other
visual impacts), noise, shadow flicker and the overall footprint of these larger
turbines on third parties is simply too great.”
120. The increase in rotor diameter in the present case is 13 metres. I am satisfied, for
reasons similar to those set out in the judgment in Kilvinane Wind Farm that this is a
material deviation.
121. The materiality of the deviation has to be assessed by reference to the description of the
permitted development as per the grant of planning permission. The description
expressly refers to a rotor diameter of 90 metres. Indeed, the precise purpose of the
application had been to allow for an increase of 10 metres from that permitted under the
2005 planning permission.
122. There is a further reason that the Developer cannot rely on the concept of “immaterial
deviations”. The case law indicates that the rationale for allowing some flexibility in
planning permissions is to address unexpected contingencies during the course of the
carrying out of the development. On the facts of the present case, the decision to change
turbine types was a deliberate decision made in advance of the carrying out of the works.
This was not an unexpected event such as might benefit from the concept of “immaterial
deviations”. The materials put before the Board in the context of the Section 5 reference
indicate that this decision was informed by considerations other than visual amenity.
“The reason for this selection is to facilitate the use of the best available technology
at the wind farm, ensuring that the wind farm can harness the local wind capacity
to its full potential, thus ensuring that the viability of the development is not
compromised.”
123. The court is not tasked nor properly qualified to determine whether or not planning
permission should be granted. For this reason, the arguments made by the Developer
which touch upon the merits of the proposed development, and invite the court to engage
in a detailed “compare and contrast” exercise as between the environmental impacts of
the “as permitted” and “as built” turbines is inappropriate. This is not the function of the
court. It is no answer to a complaint that a person has carried out development without
the requisite planning permission to say that it is highly likely that had a planning
application been made same would be granted. A developer cannot short-circuit the
process in this way. This is especially so in the context of an EIA development project
such as that in issue in the present proceedings.
124. The correct legal analysis is that the court is merely deciding whether or not the
Developer is required to make a planning application. The court is not making any
adjudication as to whether planning permission will be granted, or whether the planning
application is subject to environmental impact assessment for the purposes of the EIA
Directive. These are all matters for the expert decision-makers who have been entrusted
Page 31 ⇓
with these functions under the planning legislation. The case law is all in one direction,
and it is to the effect that matters of planning judgment are best left to the local planning
authorities and An Bord Pleanála.
COMPLIANCE SUBMISSION
125. The Developer contends that the change in wind turbine type has been authorised by dint
of the planning authority having “agreed” to the compliance submission by its letter dated
13 December 2013. In circumstances where no application for judicial review has been
made seeking to question the validity of this decision-letter, it is said to be immune from
challenge. The decision-letter is said to be binding on the court and cannot be impugned
in these enforcement proceedings. Counsel relies in this regard on Section 50 of the PDA
2000, and the judgment of the Supreme Court in Kenny v. Provost, Fellows & Scholars of
126. I have concluded that the decision-letter of 13 December 2013 cannot be relied upon as
authorising the alterations to the rotor diameter of the wind turbines for the following two
reasons.
127. First, as a matter of interpretation, the decision-letter cannot be read as “agreeing” to an
increase in rotor diameter in circumstances where the Developer did not expressly
request agreement to this increase. Planning documents are to be interpreted in their
ordinary meaning as they would be understood by members of the public, without legal
training, as well as by developers and their agents, unless such documents, read as a
whole, necessarily indicate some other meaning. (See In re XJS Investments Ltd.
[1986] IR 750).
128. The decision-letter is headed up as follows.
“Re: PD 11/400 – permission for a modification to the permitted Barranafaddock
Wind Farm (Planning Ref. 04/1559 & An Bord Pleanála reference number PL
24.213290 in the townlands of […] Co. Waterford. The modifications include a
proposed increase in turbine hub height (to 80m) of three of the permitted 11
turbines, and an increase in rotor diameter of all turbines to 90m (from 80m) and
the micro-siting of ten of the permitted turbines. As a result of this modification
there will also be associated minor revisions to the supporting civil infrastructure
design including the provision of a borrow pit and the modification and relocation of
the permitted substation.”
129. As appears, the description of the development expressly refers to a rotor diameter of 90
metres. A person reading the decision-letter would naturally assume that this is all that is
permitted. There is no other reference to rotor diameter in the decision-letter, and there
is literally nothing which indicates that an increase in rotor diameter to 103 metres has
been agreed to.
130. It is no answer to this to suggest that the heading of the decision-letter might have been
intended merely to reflect the description of the permitted development as per the 2011
Page 32 ⇓
planning permission. There is nothing in the decision-letter which indicates that the
heading is intended to refer to anything other than the form of development as agreed by
the planning authority. Moreover, the very fact that the planning permission only permits
a rotor diameter of 90 metres emphasises that the planning authority could not use the
occasion of agreeing points of detail to rewrite the planning permission. See Treacy v. An
Bord Pleanála [2010] IEHC 13, [78]. The High Court (MacMenamin J.) emphasised that
Section 34(5) of the PDA 2000 cannot be read in such a manner as to allow a matter of
detail turn the framework or substance of the grant of planning permission on its head.
Any matter of detail must perforce fall within the four walls of the parent grant of
permission. It cannot denature it.
131. Returning to the facts of the present case, the planning authority would not have had
jurisdiction under Condition No. 3 of the planning permission to authorise an increase in
the rotor diameter beyond the 90 metres prescribed under the planning permission. This
is especially so in circumstances where the condition singles out “height” as the only
aspect of the scale or dimensions of the wind turbines which might be subject to
agreement. Even then, the planning authority would only have had jurisdiction to agree a
height equal to or less than the maximum height of 125 metres permitted under the 2011
planning permission. The reason stated for the imposition of the condition was “in the
interests of visual amenity”, and it thus allowed for the possibility of a reduction in the
permitted height.
132. The hypothetical intelligent person reading the decision-letter must be taken as being
aware of the content of the compliance submission of 6 November 2013, and as having
read the decision-letter in conjunction with same. As appears from the extract from the
compliance submission set out at paragraph 26 above, the Developer did not expressly
seek the agreement of the planning authority to an increase in rotor diameter.
133. It is not enough, as has been contended for by counsel on behalf of the Developer, that
the proposed alteration is capable of being deduced by either (i) carrying out the
mathematical exercise of subtracting the figure stated for the hub height from that stated
for the maximum tip height of the turbines, and then multiplying the resulting figure by
two, or (ii) by a careful examination of the fine print of the A3 Schematic GE Turbine
which had been included in Appendix B of the compliance submission.
134. Had the Developer wished to obtain the planning authority’s agreement to an increase in
rotor diameter, then this should have been stated in express terms in the body of the
compliance submission. Neither a planning authority nor a member of the public should
be expected to wade through extensive documentation in order to attempt to ascertain
what precisely it is that a developer is seeking agreement to. Public participation lies at
the heart of the planning process. This is especially so in the context of development,
such as the present case, which consists of a project subject to the public participation
requirements of the EIA directive.
135. The second reason for saying that the decision-letter cannot be relied upon as authorising
the increase in rotor diameter is, perhaps, more fundamental. It is a requirement of the
Page 33 ⇓
EIA Directive that any “change” or “extension” of projects already authorised, executed or
in the process of being executed, which may have significant adverse effects on the
environment, must itself be subject to assessment. It is necessary, therefore, that a form
of screening exercise be carried out before a decision to authorise a change or extension
can lawfully be made.
136. On the Developer’s case, the decision-letter is said to have authorised a change to a
permitted EIA development project. This involved an increase in the rotor diameter from
90 metres to 103 metres. (It will also be recalled that the original 2005 planning
permission had only allowed for a rotor diameter of 80 metres). This “change” or
“extension” should have been screened in order to determine whether it is likely to have
adverse effects. There is simply no evidence that Waterford County Council carried out
such an exercise prior to the issuance of the decision-letter. Rather, the decision-letter
baldly states: “Condition 3 Noted and agreed”. Such an unreasoned decision cannot have
had the legal effect of authorising the change contended for.
137. In this regard, a loose analogy can be drawn with the facts of Bailey v Kilvinane Windfarm
Ltd. [2016] IECA 92. The developer in that case had sought to rely on written
representations made by an official of the local planning authority to the effect that an
extension of the blade length of proposed wind turbines were acceptable to the planning
authority. (In contrast to the present case, the written representations had not been
made pursuant to Section 34(5) of the PDA 2000).
138. The Court of Appeal considered that it was not reasonable for the developer in that case
to have relied upon these written representations. Whereas this finding was informed, in
part, by the fact that the written representations were informal, the court also attached
some weight to the fact that no assessment of the impact of the changes had been
carried out by either the developer or the planning authority. See paragraphs [100] and
[101] of the judgment.
“It is inherent in the doctrine of good faith as a general principle of law that any
party seeking to avail of that principle should show appropriate regard for the rights
of third parties who might reasonably be affected by their actions. There is nothing
at all to suggest that either the developer or, for that matter, the Council official in
question gave any consideration to this issue. In such circumstances no sensible
developer could reasonably suppose that a planning authority could informally
sanction such deviations from location and rotor diameter without a formal
assessment of the potential planning and environmental impact of these changes
and especially their potential effects on third parties.
It is obvious that any thing other than trifling changes in terms of the location of
the turbines and the size of the diameter of the rotor blades could have major
implications for local residents in terms of visual impact, sight lines, noise and
shadow flicker. Viewed objectively, therefore, one could not say that any
conclusion that the development had been constructed in accordance with the
terms of the planning permission or that these admitted deviations were not
Page 34 ⇓
material was one which, adopting the language of O’Sullivan J. in Altara
Developments, a developer could reasonably hold. This was especially so when no
consideration whatever was given to the rights of the neighbours who lived in the
immediate vicinity of the wind farm as to the potential effects of these changes.”
139. Counsel on behalf of the Developer has argued that, in circumstances where it was not
challenged at the time, the decision-letter of 13 December 2013 is immune from judicial
review. It is said, therefore, that it does not matter whether the decision-letter is lawful
or not, it cannot be questioned in these enforcement proceedings.
140. With respect, this argument overstates the effect of Section 50 of the PDA 2000. Reliance
on that section is not available in circumstances where a decision is bad on its face and/or
exhibits an error of law. See, for example, Mone v. An Bord Pleanála [2010] IEHC 395,
[83] and [84].
“It would seem to me that as a matter of common sense, where a grant as in this
case has been issued without the relevant statutory basis, it can have no force.
The fact that the erroneous grant was not challenged could in no way confer it with
retroactive validity; such is wholly outside of the legislative scheme which entirely
governs this area of law. The 1998 grant was therefore wholly illusory; it was a
grant in name only, having no possible basis in either law or fact. No future actions
could change this. The council had no power or jurisdiction to make the grant. It
must therefore follow that any subsequent decision which places reliance upon this
must be similarly flawed, being based on no legitimate legal or factual basis. The
Board’s decision that the development was based on a valid planning permission, as
well as being erroneous, was a decision it had no power to make; it was not
possible as a matter of law for the Board to retroactively confer validity on the 1998
grant.
The argument of the Board by reference to s.50 of the Act of 2000 is misconceived.
That section (subject to the court's power to extend time, which here is not
relevant) is a time limit restriction operating not as a matter of defence but of
jurisdiction. It regulates the challenge to a decision, nothing more. It leaves
unaltered the legal status of the decision. It has no influence on the lawfulness or
effect of the decision. It gives it no badge of either approval or disapproval. It
prevents challenge. Notwithstanding these views the practical effect of this section
is that in almost all cases once the time period has expired, no further
consideration will be required or needed. But exceptionally, as here, where a
subsequent decision depends on conferring the status of legality on a legal nullity,
that decision will not be allowed to stand.”
141. A similar approach had been taken by the High Court, in the specific context of a Section
5 declaration, in Wicklow County Council v. Fortune (No. 3) [2013] IEHC 397. Hogan J.
declined to rely on a Section 5 determination issued by a planning authority in
circumstances where the court considered that the reasons given for the determination
were “not altogether satisfactory”. This was so notwithstanding that the actual validity of
Page 35 ⇓
the Section 5 determination had not been under challenge in the proceedings. (The
proceedings in Fortune (No. 3) were enforcement proceedings under Section 160 of the
PDA 2000).
142. The argument for saying that the court is entitled to disregard a planning decision which
is bad on its face is even stronger in the context of EIA projects. The very recent
judgment of the CJEU in Case C-261/18, Commission v. Ireland (Derrybrien) has
emphasised that a Member State cannot deem a development project, which has been
carried out in breach of the requirements of the EIA Directives, to be authorised simply
because the domestic time-limits for legal challenges to the relevant development consent
have expired.
“80 Similarly, Directive 85/337 precludes projects in respect of which the consent can
no longer be subject to challenge before the courts, because the time limit for
bringing proceedings laid down in national legislation has expired, from being
purely and simply deemed to be lawfully authorised as regards the obligation to
assess their effects on the environment (judgment of 17 November 2016, Stadt
[…]
94 In any event, Ireland simply states that, after the expiry of the period of 2 months,
or 8 weeks set by the PDAA, respectively, the consents at issue could no longer be
the subject of a direct application to a court and cannot be called in question by the
national authorities.
95 By its argument, Ireland fails to have regard, however, to the case-law of the Court
referred to in paragraph 80 above, according to which projects in respect of which
the consent can no longer be subject to challenge before the courts, because the
time limit for bringing proceedings laid down in national legislation has expired,
cannot be purely and simply deemed to be lawfully authorised as regards the
obligation to assess their effects on the environment.
96 It must further be noted that while it is not precluded that an assessment carried
out after the plant concerned has been constructed and has entered into operation,
in order to remedy the failure to carry out an environmental impact assessment of
that plant before the consents were granted, may result in those consents being
withdrawn or amended, this is without prejudice to any right of an economic
operator, which has acted in accordance with a Member State’s legislation that has
proven contrary to EU law, to bring against that State, pursuant to national rules, a
claim for compensation for the damage sustained as a result of the State’s actions
or omissions.”
143. Mr McGrath, SC, on behalf of the Developer, submitted that the within proceedings did
not give rise to any issue of EU law. The facts of the present case were said to be entirely
distinguishable from those of McCoy v. Shillelagh Quarries Ltd. The original version of the
Page 36 ⇓
proposed development had been subject to EIA by An Bord Pleanála at the time of the
grant of the first planning permission in 2005. The Applicants did not seek to challenge
the 2011 planning permission, and would be precluded from doing so now by virtue of the
expiration of the eight-week statutory time-limit. It is said that there is no evidence
before the court that there had been any failure to comply with the EIA Directive at the
time of the grant of this planning permission.
144. Counsel made a cogent argument to the effect that the EIA Directive allowed for the
possibility of points of detail being agreed subsequent to the grant of development
consent, and submitted that the change in turbine type had been lawfully authorised by
the decision-letter of 13 December 2013 issued in response to the compliance
submission. This decision-letter had never been challenged by the Applicants, and,
therefore, neither they nor the court could go behind same. On this analysis, there
simply was no breach of EU law.
145. This argument was made with conviction, and merits careful consideration. Having
reflected on same for a number of weeks now, and having regard to the supplemental
written legal submissions filed on 5 December 2019, I have come to the conclusion that
the legal position is more nuanced. The argument advanced on behalf of the Developer
has, at its core, the proposition that the domestic law time-limits on judicial review
proceedings constrain the court’s jurisdiction in enforcement proceedings. The logic of
the argument is that even if a court considered that development consent had been
granted in breach of the EIA Directive, the court would be powerless to restrain the
continuation of a development project. This would be so irrespective of how egregious
the breach is or how obviously defective the decision relied upon is. This argument
cannot be reconciled with the requirements of the EIA Directive and the manner in which
domestic time-limits have been treated of in the case law of the CJEU.
146. Member States are obliged under Article 10A thereof to provide effective, proportionate
and dissuasive penalties for breaches of the EIA Directive. It would be inconsistent with
this obligation were an obviously deficient decision to be allowed block effective
enforcement against an EIA project which had been carried out in breach of the EIA
Directive. On the facts of the present case, as found by this court, the Developer carried
out development without the requisite planning permission. The 2011 planning
permission did not authorise the erection of wind turbines of the scale and dimensions
actually put up. The subsequent decision relied upon to authorise this, i.e. the decision-
letter of 13 December 2013, could not have had this purported legal effect for the reasons
outlined at paragraphs 135 et seq. above. This courts obligation to give effect to the EIA
Directive cannot be negated by the decision-letter of 13 December 2013.
DISCRETIONARY FACTORS
147. The Developer submits in the alternative—without prejudice to its principal argument that
there has been no “unauthorised development”—that the circumstances of the case are
such that relief should be refused as a matter of discretion. Counsel emphasises that the
court enjoys a broad discretion under Section 160 of the PDA 2000. The judgments of
the Supreme Court in Meath County Council v. Murray [2017] IESC 25; [2018] 1 I.R.
Page 37 ⇓
189; [2017] 2 I.L.R.M. 297 (“Murray”) and An Taisce v. McTigue Quarries Ltd.
[2018] IESC 54; [2019] 1 I.L.R.M. 118 (“McTigue Quarries”) are cited in this regard.
148. Counsel then identifies a number of factors which, it is said, indicate that the court’s
discretion should be exercised against the grant of relief. First, any departure from the
terms of the 2011 planning permission is not material and does not give rise to any
additional impacts on the environment when compared with the “as permitted” turbines.
Secondly, the developer has acted in good faith at all times and, in particular, sought and
obtained the agreement of Waterford County Council to the change in turbine type.
Thirdly, the Developer had made an application for leave to apply for “substitute consent”
under Part XA of the PDA 2000 as early as January 2019. An Bord Pleanála made a
decision in August 2019 to the effect that substitute consent was not necessary. (The
Board’s decision is the subject of judicial review proceedings, and the parties informed
this court that An Bord Pleanála has indicated an intention to consent to an order of
certiorari on certain, limited grounds). Fourthly, it is said that there has been delay on
the part of the Applicants: the wind farm has been operational since 2015, but the within
proceedings were not instituted until February 2019. Finally, it is said that there is a
public interest in the continued operation of the wind farm as a source of renewable
energy.
149. Counsel submits that the court’s discretion is unaffected by any considerations of EU law.
In particular, it is said that the Applicants have failed to demonstrate that there has been
any breach of the EIA Directive.
150. It is submitted that it does not necessarily follow from the judgment in C-261/18,
Commission v. Ireland (Derrybrien) that it is necessary for a development to cease
operations while an application for retrospective development consent is undertaken. Any
question in relation to the suspension or revocation of a consent can be addressed as part
of the substitute consent process. It is said that the grant of relief under Section 160 of
the PDA 2000 would be disproportionate. See §7 of the supplemental written legal
submissions of 5 December 2019, as follows.
“In the circumstances of this case, it is submitted that the grant of relief under
section 160 of the 2000 act would be disproportionate and is not required on foot of
the duty of sincere co-operation. The grant of relief in this case is not necessary to
achieve the objectives of the Treaty in relation to the assessment of environmental
impacts and, indeed, would go beyond what is necessary. What is necessary to
achieve the objectives of the Treaty is, at a maximum, the assessment of the use of
the particular turbine in accordance with the requirements of the EIA Directive.
That can be achieved through an application for Substitute Consent and there is no
requirement for the wind farm deceased operation for that to be achieved.”
151. The conduct of the Developer in the present case in seeking to regularise the planning
status of the wind turbines is said to stand in “stark contrast” to that of the operator of
the Derrybrien Wind Farm. See §10 of the supplemental written legal submissions.
Page 38 ⇓
FINDINGS OF THE COURT ON DISCRETION
152. For ease of exposition, it is proposed to address the various discretionary factors by
reference to the broad categories of considerations identified by the Supreme Court in
Murray and McTigue Quarries.
The nature of the breach: ranging from minor, technical and inconsequential up to
material, significant and gross
153. The breach in this case is material. An increase in rotor diameter of 13 metres cannot be
characterised as minor or technical. This breach also has to be seen in the context of a
development project which is subject to the EIA Directive. The discretion of the court to
“forgive” a breach of this type is more limited.
Conduct of Developer
154. The conduct of a developer and, in particular, its attitude to planning control, are relevant
considerations. It is important to recall, however, that the judgment in Murray states
that the fact that a developer had been acting in good faith, whilst important, will not
necessarily excuse him from an order. This point has been reiterated in McTigue
Quarries.
155. The judgment in Murray indicates that the reason for an infringement of planning control
may range from genuine mistake, through to indifference and up to culpable disregard.
The conduct of the Developer in the present case lies towards the former end of the scale.
The evidence before the court establishes that the Developer had been acting in good
faith. In particular, the Developer had engaged proactively with the planning authority.
See, for example, the records of meetings between the Developer’s consultants and the
planning authority. The mistaken attempt to rely on Condition 3 as the basis for changing
the turbine type is indicative of a mistake rather than any culpable disregard.
Nevertheless, ignorance of the law cannot be an excuse for non-compliance with a
planning permission. It was not reasonable for the Developer to rely on Condition No. 3
as a vehicle through which to introduce significant changes to the wind turbines.
Moreover, it is of little credit to the Developer that the terms of the compliance
submission did not make it expressly clear that what was being sought was the
agreement of the planning authority to a change in rotor blade diameter.
The attitude of the planning authority
156. Following upon the issuing of An Bord Pleanála’s Section 5 declaration, the planning
authority served an enforcement notice on the Developer. (The enforcement notice is
now the subject of separate judicial review proceedings). The fact that the local planning
authority has been moved to take enforcement action is a factor which points in favour of
granting relief.
The public interest in upholding the integrity of the planning and development system
Page 39 ⇓
157. The fact that this development is subject to the EIA Directive is a relevant consideration
under this category. Article 10A of the EIA Directive (as most recently amended by
Directive 2014/52/EU) provides as follows.
“Member States shall lay down rules on penalties applicable to infringements of the
national provisions adopted pursuant to this Directive. The penalties thus provided
for shall be effective, proportionate and dissuasive.”
158. Weight must be given to this the exercise of the court’s discretion. One of the
requirements of the EIA Directive is that any “change” or “extension” to a previously
permitted project which is likely to have a significant adverse effect must be subject to
(further) environmental impact assessment. It is necessary, therefore, to carry out a
form of screening exercise to determine whether a change or extension is likely to have a
significant adverse effect. Whereas it may well be the position that the outcome of a
screening exercise in relation to the change in the scale and dimensions of the turbines
would be that no EIA is required, this does not obviate the legal requirement to carry out
such a screening exercise. (See Case C-215/06, Commission v. Ireland to the effect that
the failure to carry out a screening exercise represents a breach of the EIA Directive).
159. The High Court (Baker J.) held in McCoy v. Shillelagh Quarries Ltd. [2015] IEHC 838, [84]
and [85]. that the exercise of the court’s discretion should be informed by reference to EU
environmental law.
“I consider myself constrained further by the requirements of European Community
law, and especially the EIA Directive and the Habitats Directive as each of these
mandates that an Environmental Impact Statement is required in respect of the
operation of this quarry.
Accordingly, were I to refuse injunctive relief or grant injunctive relief with respect
to some of only of the operation, I consider that my decision would be one which
could be characterised as a failure to respect the integrity of the environmental
legislation, and allow the development to continue when it is unauthorised under
Irish and when Irish law arises as a result of the obligations of Ireland and
Community law.”
160. Counsel for the Developer in the present case points out—entirely correctly—that the
breach of EU law at issue in Shillelagh Quarries Ltd. was very serious and had continued
for many years, and that an application for substitute consent had been refused.
Whereas the breach in the present case is of a much lesser order, the EU law dimension is
nevertheless a factor to which some weight must be given.
Public interest in general
161. The Developer relies in this regard on the fact that the development is of a type which
provides renewable energy and that this is in the public interest. As against this, it has to
Page 40 ⇓
be said that the overall impact of an order restraining the operation of this individual
development project would be minimal in the national context.
Conclusion
162. As appears from the foregoing discussion, there are a number of discretionary factors
which are in favour of the Developer. These have to be weighed against the factors which
point towards the grant of relief. The principal of these is that the development project is
of a type subject to the EIA Directive. The EIA Directive obliges a Member State to
provide effective, proportionate and dissuasive penalties for breaches of national
legislation. The importance of ensuring compliance with the EIA Directive has very
recently been emphasised by the judgment of the CJEU in Case C-261/18, Commission v.
Ireland (Derrybrien).
163. I have concluded that the court’s discretion should be exercised as follows. The
Developer should be afforded an opportunity to regularise the planning status of the wind
turbines. It would be inappropriate, therefore, to make an order requiring the immediate
removal of the wind turbines. Rather, the Developer is to be afforded a further
reasonable period of time within which to seek, if possible, to regularise the planning
status of the lands.
164. (The precise mechanism by which this might be achieved is itself the subject of separate
judicial review proceedings. More specifically, there is a dispute as to whether the
application for leave to apply for substitute consent should be remitted to An Bord
Pleanála. This dispute is listed for hearing before the Commercial List of the High Court
this morning (6 December 2019).)
165. It would not, however, be appropriate to allow the operation of the wind turbines to
continue uninterrupted pending the outcome of an application for leave to apply for
substitute consent. This is similar to the approach which had been adopted by the Court
of Appeal in Bailey v. Kilvinane Wind Farm. There has been a breach of EU law, and this
court is obliged to ensure that there is an effective and dissuasive remedy for same.
166. Counsel for the Developer has made a submission to the effect that—in circumstances
where An Bord Pleanála has an express statutory power to direct the cessation of
development pending the determination of an application for substitute consent—the
court should, in effect, leave it to An Bord Pleanála to decide whether any interim
measures are required. This submission is correct insofar as it goes. It is, however, clear
from the wording of the relevant provision, namely Section 177J of the PDA 2000, that
the Board’s jurisdiction to issue a direction only arises subsequent to a decision to grant
leave to apply for substitute consent. It seems that only the court has jurisdiction to
make an order requiring the cessation of operations pending the making of a decision to
grant leave to apply for substitute consent. I propose, therefore, to make an order
restraining the operation of the wind turbines pro tem. The Developer has liberty to
apply, on seven days’ notice to the Applicants, to have this order vacated in the event
Page 41 ⇓
that An Bord Pleanála makes a decision to grant leave to apply for substitute consent. I
will hear both parties at that stage.
167. In the event that substitute consent is granted, I would propose to vacate the order
entirely. Again, however, I will hear the parties before making any order to this effect.
CONCLUSIONS AND FORM OF ORDER
168. The Section 5 declaration precludes the Developer from reagitating the argument that the
“as built” wind turbines are authorised by the 2011 planning permission. The Developer
had a full opportunity of making its case in this regard to An Bord Pleanála. In particular,
the Developer had made submissions before the Board to the effect, first, that the
decision-letter of 13 December 2013 authorised the change in scale and dimensions of
the wind turbines; and, secondly, that the circumstances of the case were distinguishable
from those of the Kilvinane Wind Farm. Those submissions were, ultimately, rejected by
An Bord Pleanála.
169. In circumstances where the Developer did not challenge the Section 5 declaration, the
Developer is estopped from seeking to reopen the Board’s findings in these proceedings.
170. The 2011 planning permission did not authorise the erection of wind turbines of the scale
and dimensions actually put up. In circumstances where the wind farm is subject to the
requirements of the EIA Directive, the proposed increase in rotor diameter constituted a
“change” or “extension” of a permitted development, and could only have been lawfully
authorised by way of the making of an application for planning permission.
171. The Developer is not entitled to rely on the alleged agreement of the planning authority to
the compliance submission as providing authorisation for the “change” or “extension”. On
its correct interpretation, the decision-letter of 13 December 2013 does not have this
effect. Moreover, the planning authority would not, in any event, have had jurisdiction to
approve the “change” or “extension” pursuant to Section 34(5) of the PDA 2000.
172. The Developer should be afforded an opportunity to regularise the planning status of the
wind turbines. It would be inappropriate, therefore, to make an order requiring the
immediate removal of the wind turbines. Rather, the Developer is to be afforded a
further reasonable period of time within which to seek, if possible, to regularise the
planning status of the lands.
173. There will be an order made pursuant to Section 160 of the PDA 2000 restraining the
operation of the wind turbines pro tem. The Developer has liberty to apply, on seven
days’ notice to the Applicants, to have this order vacated in the event that An Bord
Pleanála makes a decision to grant leave to apply for substitute consent.
Result: Order restraining use of wind turbines granted.