BUSINESS AND PROPERTY COURTS AT BRISTOL
TECHNOLOGY & CONSTRUCTION COURT (QBD)
Bristol BS1 6GR |
||
B e f o r e :
____________________
LJR Interiors Limited |
Claimant |
|
- and - |
||
Cooper Construction Limited |
Defendant |
|
And Between: |
||
Cooper Construction Limited |
Claimant |
|
- and - |
||
LJR Interiors Limited |
Defendant |
____________________
Harry East (instructed by Hill Dickinson LLP) for Cooper Construction Limited
Hearing dates: Thursday 17th November and 22nd December 2022
____________________
Crown Copyright ©
This judgment (a draft of which was circulated to the parties on 7 January 2023) was handed down remotely at 10.00am on 11 January 2023 by circulation to the parties by email and its release to The National Archives.
HHJ Russen KC:
Introduction
"……….. the defendant must be able to demonstrate that: (a) there is a short and self-contained issue which arose in the adjudication and which the defendant continues to contest; (b) that issue requires no oral evidence, or any other elaboration beyond that which is capable of being provided during the interlocutory hearing set aside for the enforcement; (c) the issue is one which, on a summary judgment application, it would be unconscionable for the court to ignore."
"I am writing in advance of the adjourned hearing of the Part 7 adjudication enforcement claim and the Part 8 Claim listed for 22nd December. I have decided to write to you because I am conscious that LJR is not legally represented in circumstances where Cooper's challenge to the adjudicator's decision is based upon the adjudicator having made a clear error of law. In advance of the next hearing, I would therefore be grateful if the parties (and in particular Cooper) would address their minds further to the following points:
1. The basis on which the Limitation Act 1980 (in this case section 5) is said to apply to adjudication proceedings. Mr East has pointed to the obiter dicta in the Anglian Water and Connex cases which assume a limitation defence may be taken in adjudication proceedings. On a very quick review of the textbooks, I also see that Keating on Construction Contracts (11th ed), at para.16-047 states that, when raised, limitation is a "substantive defence" to be considered by an adjudicator (no authority is cited); though I could not immediately see anything directly on the point in Coulson on Construction Adjudication (4th ed). I raise this now, on a point which most lawyers and judges might otherwise be guided by instinct, because s. 5 (and s. 8) of the 1980 Act applies to an "action" under a contract; and section 38 provides that "unless the context otherwise requires, "action" includes any proceedings in a court of law, including an ecclesiastical court." I recognise that this definition has been expressly extended by section 13(1) of the Arbitration Act 1996 to cover arbitral proceedings. Are you able to assist me further as to the legal basis on which the "cause of action" (per s. 5) may barred in a dispute referred to adjudication more than 6 years after its accrual?
2. In relation to accrual, the adjudicator essentially proceeded on the basis that only the provisions of Part II of the Scheme (once triggered by the making of a claim for payment) and specifically the deadline for Cooper to give a pay less notice were relevant to the question of lapse of time (or "delay"). His conclusion was that Application No. 4 was not invalid because "the Scheme does not contain any provision limiting when a claim for payment under a relevant construction contract may be made" (paragraphs 22 and 28). I recognise that Cooper's position in Mr Oram's first witness statement is that the cause of action accrued on completion of the works (the missing date of which was to be clarified in further evidence after the last hearing). The parties will need to address me on the applicability or otherwise of the payment provisions in Part II of the Scheme (or some of them) to the terms of the contract created by LJR's quote dated 9 July 2014 and Cooper's purchase order dated 26 August 2014.
Thank you in advance."
Background
"1. Terms
a) Our rates make allowance for 2.5% mcd, based on payment to be made 28 days from Invoice / Valuation, based on an Invoice being submitted on the last day of each month. We reserve the right to recover any costs incurred as a result of late payment".
"Also, it was issued outside the Limitation Period of six years, in accordance with section 5 of the Limitation Act 1980 as the Limitation Period commenced upon the issue of the Referring Party's Application No. 3 that the Referring Party issued on 31 October 2014."
"LJR Interiors Ltd have on record, further requests for outstanding monies/retention to be paid as follows:
28th November 2016
31st October 2016
13th March 2015
11th February 2015."
"12. For the avoidance of doubt, the "cause of action" was either 28 November 2014 when the Respondent failed to pay the sum invoiced for by the Referring Party, or, although denied by the Respondent, on 12 March 2015 when the Respondent issued the email refusing to pay the sum invoiced by the Referring Party and provided its reasons for refusal. In either case and in accordance with the above mentioned Supreme Court's Judgment – [this was a references to the decision in Matthew & Others v Sedman & Others [2021] UKSC 19 which was appended to the Rejoinder] – the Limitation Period had expired prior to the Referring Party issuing its invalid Application for Payment No. 4 that it issued on 29 July [sic] 2022."
"39.00 While Cooper raised the issue of the Limitation Period in respect of the validity of the Application, I consider also whether section 5 of the Limitation Act 1980 operates to bar the remedy sought by LJR.
40.00 I understand the general rule in contract is that a cause of action accrues when the breach takes place.
41.00 The breach alleged here by LJR is the failure to make payment of a sum claimed due by the final date for payment, namely 28 August 2022.
42.00 On that basis the limitation period pursuant to section 5 of the Limitation Act 1980 has not expired.
43.00 Accordingly, I find that LJR was entitled to the notified sum of £3,256.58 by the final date for payment."
"The delay in applying for payment:
22.00 The Contract does not contain any such provisions as are mentioned in subsection 110(1) of the Housing Grants, Construction and Regeneration Act 1996 as amended (the Construction Act) and accordingly the relevant provisions of the Scheme for Construction Contracts (England and Wales) 1998 as amended (the Scheme) apply.
23.00 The Scheme does not contain any provision limiting when a claim for payment under a relevant construction contract may be made. I am not persuaded that any delay in the submission of the Application renders it invalid."
…….
"Limitation Period and Section 5 of the Limitation Act 1980
28.00 The limitation period under section 5 of the Limitation Act 1980 operates to bar a remedy, it does not extinguish a right. Section 5 of the Limitation Act 1980 is not relevant to the matter of the validity of the Application."
……..
"Conclusion
30.00 The application of the relevant provisions of Part II of the Scheme operate on the basis that the payee may make a claim for payment. Accordingly, I am satisfied that pursuant to S. 110B(4) of the Construction Act the Application is a valid payees payment notice complying with S. 110A(3)."
"17. From the submissions put forward within the Adjudication, it is common ground that the contract was entered on 28 August 2014 and the works were completed on. It is further common ground that application 4 was submitted on 31 July 2022, and the Adjudication was commenced on 9 September 2022 by service of a Notice of Intention to refer the dispute to Adjudication."
[I have already noted that the missing date for completion of the works was in fact given in paragraph 6 of the statement as "on or about 19 October 2014".]
"18. I would submit it is clear on its face that in those circumstances the sums claimed by LJR within application 4 are and always were statute-barred. Further, the onus is on LJR to explain why that is not the case and they have felt fit to put no submissions forward in relation to the same."
"It is relevant that whilst the sums in the current action and the Adjudicated Decision are modest, behind this action LJR has submitted similar applications in July 2022 to Cooper across a myriad of other contracts. Cooper's position in relation to all of those other contracts is that they are all statute-barred. It is anticipated that LJR are awaiting the results of this current action before deciding how to deal and progress those other applications."
"…….. Application 4 is simply a rehashing of Application 3 with the addition of a £750.00 admin fee that is not a contractual obligation, nor has it been explained by LJR. The retention release is a request for withheld monies to be paid, they should not be a new sum."
Analysis and Conclusions
(1) The Permissible Scope of Challenge
i) Was the Decision wrong in concluding that Application No. 4 was not statute barred?
ii) If so, is the adjudicator's error one which it would (adopting the Hutton v Wilson test) be unconscionable for the court to ignore on the Part 7 adjudication enforcement claim?
(2) Limitation and Adjudication Proceedings
"An action founded on simple contract shall not be brought after the expiration of 6 years from the date on which the cause of action accrued."
"39. There is, therefore, no time limit. There may be circumstances as a result of which a party loses the right to refer a dispute to adjudication: the right may have been waived or the subject of an estoppel. But subject to considerations of this kind, there is nothing to prevent a party from referring a dispute to adjudication at any time, even after the expiry of the relevant limitation period. Similarly, there is nothing to stop a party from issuing court proceedings after the expiry of the relevant limitation period. Just as a party who takes that course in court proceedings runs the risk that, if the limitation defence is pleaded, the claim will fail (and indeed may be struck out), so a party who takes that course in an adjudication runs the risk that, if the limitation defence is taken, the adjudicator will make an award in favour of the respondent."
"…. If there is an adjudication award within 6 years of performance, without any further proceedings being commenced, both sides are after the six year period time-barred in respect of any claim to any balance which they originally contended to be due to them. Any further proceedings would be limited to a claim for repayment by the party required to pay a net balance to the other."
"The Limitation Act 1980 and other enactments apply equally to adjudication in the sense that an adjudicator must treat the law of limitation as a substantive defence just as any other defence."
(3) The limitation period applicable to Application No. 4
"Most standard forms for construction works provide for interim certification of sums due. Where such certificates are a condition precedent to the right to payment, the contractor's cause of action to be paid and to challenge the adequacy of the certificate accrues when the certificate is issued or ought to have been issued in accordance with the contract and not when the work giving rise to the certified sum is carried out. Further, depending on the precise wording of the contract, a further cause of action may arise when the final certificate is issued or ought to have been issued even though the sum in issue happens to be the same as that arising under an interim certificate."
"24. I am wholly satisfied, and this is primarily a legal view, that there is no implied term or term of the contract by way of construction that the retention is only payable once the final accounting process has been finalised. It is not necessary to imply any such term because retention money really represents a credit that is already due to the sub-subcontractor in this case. It will broadly be payable following completion when the sub-sub-contractor wishes to claim for it after completion; it will be payable by implication by Harrington within a reasonable time of completion by Tyroddy. At that stage, it may be met by a defence which may in part be abatement, a set-off or counterclaim or it may raise valuation issues; however, there is no need to imply a term and I certainly cannot construe any of the words that are used here to say that retention only becomes payable at some future final accounting stage. There is no room either by way of interpretation of the words used or by way of implication to imply any such term."
"Please see our email dated 12 March 2015 we had already overpaid you on the account and so therefore retention on this contract is £9.84."
Disposal