QUEEN''S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Merit Holdings Limited |
Claimant |
|
- and - |
||
Michael J Lonsdale Limited |
Defendant |
____________________
Alexander Hickey QC (instructed by Stevens & Bolton LLP) for the Defendant
Hearing date: 22 June 2017
____________________
Crown Copyright ©
Introduction
The facts and background
“"We refer to our recent discussion regarding the supply and installation of the mechanical pipework package, pending execution of our formal contract with Merit Holdings Ltd., we hereby confirm by way of LOI expenditure authority / appointment for you to undertake the off-site prefabrication of materials for LTHW, Condenser Water and CHW system and commencement of the on-site installation works for the above mentioned project to a capped value of £330,000.00.….
In relation to any works properly carried out by you in accordance with this letter, we agree to reimburse you the costs wholly and necessarily incurred by you pursuant to this letter up to a maximum sum of £330,000.00. (Three Hundred and Thirty Thousand Pounds and Zero Pence). Such costs shall be paid in accordance with MJ Lonsdale payment procedures to be agreed and shall be subject to retention of 0%. This maximum sum shall not be exceeded except where specifically notified to you in writing and any costs incurred by you in excess of such sum shall be borne by you. This letter will expire Thursday 31st December 2015 and another LOI will have to be issued in its place if the formal sub-subcontract order is not in place.
…
In the event that a binding contract is entered into by the parties, all work authorised by Michael J Lonsdale and carried out by Merit Holdings Ltd. pursuant to this letter shall be treated as work performed under the Sub-subcontract Agreement for mechanical pipework services installation. Any monies paid to Merit Holdings Ltd. in respect of this letter shall form part of the Contract Sum under the Sub-Subcontract Agreement.
We may terminate these arrangements at any time by notice in writing to you in which case you shall forthwith vacate the site and leave your work in a safe and secure condition as appropriate, we will pay you, subject to the maximum sum referred to above, the costs accrued due under this letter, up to the date of such termination. We shall have no further obligation or other liability to you in relation to the Works or this letter and you will have no claim against Michael J Lonsdale or any party for any breach or loss of contact (sic), loss of profit, loss of expectation, consequential loss or any other indirect loss in the event that a binding contract does not come into existence.
By your acceptance of the terms of this letter, you acknowledge that there is no contract between us, except as set out in this letter.”"
The letter was countersigned on behalf of Merit under the words “"We hereby confirm our agreement to commence and complete the Works in accordance with the terms of this letter …”"
“"In Adjudication No. 1, I accepted that the parties’' contractual relationship continued after the expiry of the 6th April 2016 letter of intent, i.e. after 29th April 2016. By that date, the parties had evidently agreed a Contract Sum and a scope of work, but a formal contract had not been concluded or terms agreed. The fact that Merit submitted subsequent applications for payment based on the agreed scope of works and the agreed Contract Sum, and the fact that MJL had made payments based on that agreed scope and Contract Sum points heavily towards the conclusion that the parties are taken to have agreed by their conduct that the basis of payment after the expiry of the 6th April 2016 letter of intent was by reference to the agreed Contract Sum and the QSOR. Alternatively, I also consider there to be some force in MJL’'s submission that, if there was no formal agreement regarding the basis of payment following the expiry of 6th April 2016 letter of intent, then Merit would be entitled to a quantum meruit to be valued by reference to the Contract Sum which had been agreed. My view is that either analysis is consistent with the basis upon which Merit advanced its case in Adjudication No. 1 and the Decision reached.
Accordingly, I find that the basis of Merit’'s entitlement to payment is to be based on the agreed Contract Sum and the QSOR.”"
Procedure
Analysis
(i) Merit says that the conduct of the parties after that date evidences an agreement to extend the application of the letter of intent beyond the expiry date and without regard to the cap on payment. Under the terms of the April letter, following termination, Merit was entitled to be paid its costs wholly and necessarily incurred for all the works carried out until it ceased work.(ii) MJL disputes this. Mr Hickey QC says that the conduct of the parties evidences an agreement to carry out the works on the basis of a simple contract in which the scope of works and price was agreed. That contract is one for the whole of the works (not just those works carried out after 29 April).
(i) Firstly, it is inherent in that argument that the parties must be taken to have agreed to remove the cap on the sums to be paid for costs wholly and necessarily incurred. There is not a shred of evidence to support that proposition. The only evidence is of applications for payment being made for the value of the works in excess of the cap and such payments being made. The most obvious inference to be drawn from the continuation of that conduct after 29 April 2016 is indeed that they continued on the same basis as before – namely that payment would be made for the value of work done (necessarily exceeding the cap). That is consistent with the conduct of the parties throughout the project including in the periods between the letters of intent. Merit argued that the obvious inference during these gaps was that the parties had agreed to continue under the terms of each of the letters of intent despite their expiry and thus on the basis that Merit was entitled to be paid costs wholly and necessarily incurred but, at no point, did Merit apply for or receive payment on this basis. I can thus see no basis for concluding from the parties’' conduct after 29 April 2016 that what they had agreed was that payment should be made for work done on a costs basis in excess of the stated cap.(ii) Secondly, the terms of each of the letters of intent, including the April letter, required the parties to agree in writing if the cap was to be exceeded. It is, of course, right that payment was made of greater amounts but they were a percentage of a putative contract sum not costs. It seems to me to go too far to infer that the parties had agreed to dispense with the requirement to agree in writing if the cap was to be exceeded for payment on the basis of costs incurred and is inconsistent with Mr Mort QC’'s “"least damage”" argument.
Alternative declarations?
(i) the letters of intent governed work up to 29 April 2016 but with payments made on the basis of the valuation of the works. After 29 April 2016, the parties agreed to continue on the basis of the April letter but still with payments made on the basis of the valuation of the works. Under such an arrangement, there would be no obligation on Merit to carry out and complete any defined scope of works and no entitlement to do so.(ii) The letters of intent governed work up to 29 April 2016 but with payments made on the basis of the valuation of the works. Thereafter there was a fresh agreement in respect of work after that date. That agreement was that Merit would carry out works as requested or instructed which were to be valued and paid by reference to the contract sum (and were not subject to the cap in the April letter). Under such an arrangement, there would similarly be no obligation on Merit to carry out and complete any defined scope of works and no entitlement to do so.
(iii) The letters of intent governed work up to 29 April 2016. After 29 April 2016, there was a “"simple”" contract pursuant to which the balance of the (I am told agreed) scope of works would be carried out by Merit for the agreed contractual sum.
(iv) After 29 April 2016, the arrangements under the letters of intent were replaced by a “"simple”" contract for the whole of works for the contract sum.
(v) After 29 April 2016, there was a contract for the whole of the works which incorporated MJL’'s standard terms and conditions.
Conclusions