BUSINESS AND PROPERTY COURTS
TECHNOLOGY AND CONSTRUCTION COURT (KB)
Fetter Lane London, EC4A 1NL |
||
B e f o r e :
____________________
INHEALTH INTELLIGENCE LIMITED |
Claimant |
|
- and – |
||
NHS ENGLAND |
Defendant |
____________________
for the Claimant
Rhodri Williams KC and Jonathan Lewis (instructed by Hempsons LLP)
for the Defendant
Hearing Date: 29 September 2022
____________________
Crown Copyright ©
Mr Justice Fraser:
Introduction
The basis of the substantive claim
An application for suspension
"95.—(1) Where—
(a) a claim form has been issued in respect of a contracting authority's decision to award the contract,
(b) the contracting authority has become aware that the claim form has been issued and that it relates to that decision, and
(c) the contract has not been entered into,
the contracting authority is required to refrain from entering into the contract.
(2) The requirement continues until any of the following occurs—
(a) the Court brings the requirement to an end by interim order under regulation 96(1)(a);
(b) the proceedings at first instance are determined, discontinued or otherwise disposed of and no order has been made continuing the requirement (for example in connection with an appeal or the possibility of an appeal)."
"[47] The applicable principles for determining such an application are set out in American Cyanamid v Ethicon [1975] AC 396 per Lord Diplock at pp.407G-408H; National Commercial Bank Jamaica Limited v Olint Corporation Limited [2009] UKPC 16 per Lord Hoffmann at [17]-[18]; Covanta Energy Ltd v Merseyside Waste Disposal Authority [2013] EWHC 2922 per Coulson J (as he then was) at [34] and [48]; and summarised in Alstom v Network Rail Infrastructure Ltd [2019] EWHC 3585 (TCC) at [29].
[48] The relevant questions for the court, when determining an application to lift the automatic suspension in a procurement challenge case, are as follows:
i) Is there a serious issue to be tried?
ii) If so, would damages be an adequate remedy for the claimant(s) if the suspension were lifted and they succeeded at trial; is it just in all the circumstances that the claimant(s) should be confined to a remedy of damages?
iii) If not, would damages be an adequate remedy for the defendant if the suspension remained in place and it succeeded at trial?
iv) Where there is doubt as to the adequacy of damages for either of the parties, which course of action is likely to carry the least risk of injustice if it transpires that it was wrong; that is, where does the balance of convenience lie?"
"96.—(1) In proceedings, the Court may, where relevant, make an interim order—
(a) bringing to an end the requirement imposed by regulation 95(1);
(b) restoring or modifying that requirement;
(c) suspending the procedure leading to—
(i) the award of the contract, or
(ii) the determination of the design contest,
in relation to which the breach of the duty owed in accordance with regulation 89 or 90 is alleged;
(d) suspending the implementation of any decision or action taken by the contracting authority in the course of following such a procedure.
(2) When deciding whether to make an order under paragraph (1)(a)—
(a) the Court must consider whether, if regulation 95(1) were not applicable, it would be appropriate to make an interim order requiring the contracting authority to refrain from entering into the contract; and
(b) only if the Court considers that it would not be appropriate to make such an interim order may it make an order under paragraph (1)(a).
(3) If the Court considers that it would not be appropriate to make an interim order of the kind mentioned in paragraph (2)(a) in the absence of undertakings or conditions, it may require or impose such undertakings or conditions in relation to the requirement in regulation 95(1).
(4) The Court may not make an order under paragraph (1)(a) or (b) or (3) before the end of the standstill period.
(5) This regulation does not prejudice any other powers of the Court."
"[39] The scheme of the Remedies Directive is a balanced one. The Francovich conditions represent the Court of Justice's conclusion as to the appropriate minimum protection by way of damages which an economic operator can expect. Although there is no Marleasing imperative to construe the scheme so far as possible consistently with the Francovich conditions, it is I think a natural assumption that the UK legislator will not go further than required by EU law when implementing such a scheme, without considering this and making it clear. That is fortified by the legislator's clear intention not to gold plate when substituting the new Part 9 scheme for the old in 2009. In these circumstances, I consider that the 2006 Regulations as amended in 2009 should be read as providing for damages only upon satisfaction of the Francovich conditions. That is also consistent with the use of the word "may" which otherwise seems to me to have no real significance."
(emphasis added)
Expedition and the compromise of the Suspension Application
The undertaking in damages
"[54] The provision of an undertaking or security as a condition of the continuation of a stop order or stay is a matter of free choice for a party. There is no basis for regarding the victim of an alleged breach seeking interim relief as obliged to exercise that choice in the interests of the other party, or indeed of anyone save itself. I am unable to accept the NDA's proposition that, because the court could reasonably demand a cross-undertaking or security as a condition of a continuation of the stop order, it would or could be regarded as unreasonable for ATK to refuse to put this up. For the court to impose a condition as the price of continued relief which a party is seeking is quite different from treating the victim of a breach as acting unreasonably if it fails to seek a particular form of relief or to back it with an undertaking or security."
(emphasis added)
Conclusion