QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS
OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
7 Rolls Buildings, Holborn, London EC4A 1NL |
||
B e f o r e :
____________________
VODAFONE LIMITED |
Claimant |
|
- and - |
||
(1) SECRETARY OF STATE FOR FOREIGN, COMMONWEALTH AND DEVELOPMENT AFFAIRS (2) THE BRITISH COUNCIL |
Defendants |
____________________
Ms Sarah Hannaford QC and Mr Jonathan Lewis (instructed by Gowling WLG (UK) LLP) for the Defendants
Hearing date: 6 October 2021
____________________
Crown Copyright ©
Mr Justice Kerr :
Introduction and Summary
"Assuming the outcome of the evaluation of tender responses was lawfully undertaken, were the Defendants lawfully entitled to proceed to and award the Framework to Fujitsu on the basis of the Defendants' evaluation of the Initial Tenders submitted?"
An Outline of the Facts
"6.6. Stage 3 (Award on Initial Tender) (Optional)
6.6.1. As per the Competitive Procedure with Negotiation, the Authority reserves the right to award a Framework Agreement to a highest scoring Tenderer at the conclusion of evaluation of the Initial Tenders (based on the Award Criteria specified within the ISIT).
6.6.2. The Authority may determine that it is able to award the Framework Agreement on the basis of an Initial Tender without further negotiation where the following conditions are met:
6.6.2.1. The Initial Tender is complete in all respects, has been reviewed for compliance and is capable of assessment;
6.6.2.2. The Initial Tender meets the Minimum Requirements;
6.6.2.3. The Initial Tender has been evaluated by the Authority in accordance with the published Award Criteria resulting in a clear winner. There are no outstanding queries, errors and omissions that require further clarification and there are no issues that would warrant disqualification from the Process; and
6.6.2.4. The Draft Contract is capable of being awarded without negotiation."
"In the event that there are insufficient Tenders deemed satisfactory (and without prejudice to any other rights to terminate the Procurement), the Authority reserves the right to terminate the Procurement and where appropriate to re-advertise the procurement."
"18.9.1. The component scores for the Quality and Price for each Tender will be combined in accordance with the evaluation model to generate an overall total score for each Tender.
18.9.2. A Tender must meet the Minimum Quality Threshold as described in Paragraph 20.13[1] to be considered further.
"18.9.3. Tenders will be ranked according to their total score which will determine the MEAT and the successful Tenderer ("the Supplier").
18.9.4. In the circumstance that there is a tie in the total score, the Authority will apply the three tests described more fully in Paragraph 23 of this ISIT."
"18.13.1. A Minimum Quality Threshold is set for each of the quality aspects of each Tender as described in the Table 4 below. A Tenderer need [sic] to be awarded a minimum score of 'Adequate' for each of the Level 3 Criteria and a minimum score of 'Good' for the Level 2 Criteria. Weighted scores and the Minimum Quality Thresholds are described more fully at Paragraph 19.15 below."
"The Tenderer with the highest Weighted Quality Score shall be awarded 60% as its Final Quality Score, with remaining Tenderers being awarded a percentage equal to their Weighted Quality Score, relative to the highest total Weighted [Quality] Score. If two or more Tenderers achieve the same Weighted Quality Score, each will receive the same Final Quality Score."
"19.15 A minimum quality threshold has been set for each of the quality aspects of each Tender. A Tenderer will need to be awarded a minimum score of 'Adequate' for each of the Level 3 Criteria and a minimum score of 'Good' for the Level 2 Criteria. Tenderers will need to achieve a minimum score of 'Good' for the Level 2 Criteria as stated below:
a) a weighted score of at least 1.71 out of a maximum weighted score of 3.04 for Elective Services;
b) a weighted score of at least 1.71 out of a maximum weighted score of 3.04 for Service Management and Performance Management;
c) a weighted score of at least 0.18 out of a maximum weighted score of 0.32 for Optional Services;
d) a weighted score of at least 0.45 out of a maximum weighted score of 0.8 for Security Management; and
e) a weighted score of at least 1.35 out of a maximum weighted score of 2.4 for Implementation.
19.16 The Authority reserves the right to exclude from the Procurement any Tenderer that fails to meet the minimum quality thresholds set out in Paragraph 19.15."
"would deliver a signed contract earlier than originally planned and enable the winning Tenderer to commence transition earlier, reducing the time pressure on the September 2023 deadline for the end of the ECHO 1 contract. This would represent savings of circa £400K per month in ECHO 2 Programme costs and potentially earlier delivery of savings."
"The first concerns the process the Defendants have followed, namely to proceed to an award of the Framework on the basis of Initial Tenders without undertaking any process of negotiation, in particular in circumstances where all tenderers have purportedly failed to meet the Minimum Quality Threshold and where Fujitsu's tender response has been evaluated as having "significant deficiencies resulting in a technical solution that is likely to be unfit for purpose, and requiring workarounds": see Particulars of Claim, §§82-85. If Vodafone is correct that in those circumstances the Defendants were not entitled to proceed to award the Framework, the contract award decision will be rendered unlawful.
.. the deficiencies in Level 3 criterion 4, (Network Platform (Quality, Performance and Service assurance features), and the deficiencies in Fujitsu's tender identified by the Defendants, go to the heart of the concerns . in relation to network security and performance .
The second basis of the Claim concerns the actual evaluation of the tender responses of Vodafone and Fujitsu. This is in all material respects a conventional scoring challenge. However, it would only fall for determination if it were held that the Defendants were entitled, in all the circumstances, to proceed to award the Framework on the basis of the Initial Tenders. "
The Issues, Reasoning and Conclusions
The application to lift the automatic stay
"21. When determining an application to lift the automatic suspension in a procurement challenge case, the Court must consider the following issues:
i) Is there a serious issue to be tried?
ii) If so, would damages be an adequate remedy for the claimant if the suspension were lifted and they succeeded at trial; is it just in all the circumstances that the claimant should be confined to its remedy of damages?
iii) If not, would damages be an adequate remedy for the defendant if the suspension remained in place and it succeeded at trial?
iv) Where there is doubt as to the adequacy of damages for either of the parties, which course of action is likely to carry the least risk of injustice if it transpires that it was wrong, that is, where does the balance of convenience lie?"
Serious issue to be tried
Adequacy of damages for Vodafone
"In my judgment the modern approach has been accurately summarised by Coulson J in Covanta Energy Ltd v Merseyside Waste Disposal Authority (No 2) [2013] EWHC 2922 (TCC), (2013) 151 Con LR 146 at [48] and again in Bristol Missing Link Ltd v Bristol City Council [2015] EWHC 876 (TCC), (2015) 160 ConLR 93, [2015] LGR 480 (at [49]) as follows:
' (a) If damages are an adequate remedy, that will normally be sufficient to defeat an application for an interim injunction, but that will not always be so (American Cyanamid, [Fellowes & Son v Fisher [1975] 2 All ER 829, [1976] QB 122], [National Commercial Bank Jamaica Ltd v Olint Corp Ltd [2009] UKPC 16, [2009] 5 LRC 370, [2009] 1 WLR 1405]);
(b) In more recent times, the simple concept of the adequacy of damages has been modified at least to an extent, so that the court must assess whether it is just, in all the circumstances, that the claimant be confined to his remedy of damages (as in [Evans Marshall & Co v Bertola SA [1973] 1 All ER 992, [1973] 1 WLR 349] and the passage from [Chitty on Contracts]) '"
"Counsel were unable to identify (and I have not found) any statements of general principle about what uncompensatable disadvantages should or should not be regarded as rendering damages an inadequate remedy."
"loss to the firm of general damage to its insolvency department, not only loss of or damage to an individual team but also loss of reputation. That is quite impossible to quantify fairly".
"it is fundamentally wrong in principle to say that an award of damages would not restore a reputation lost because of the rejection of a tender, but the award of the contract itself would. What would matter in those circumstances would be the public acknowledgement that their bid had been wrongly rejected, not the precise remedy which the court provides in consequence of that finding."
"i) Loss of reputation is unlikely to be of consequence when considering the adequacy of damages unless the Court is left with a reasonable degree of confidence that a failure to impose interim relief will lead to financial losses that would be significant and irrecoverable as damages;
ii) It follows that the burden of proof lies upon the party supporting the continuance of the automatic suspension and the standard of proof is that there is (at least) a real prospect of loss that would retrospectively be identifiable as being attributable to the loss of the contract at issue but not recoverable in damages;
iii) The relevant person who must generally be shown to be affected by the loss of reputation is the future provider of profitable work."
"40. As this court stated in Bombardier Transportation UK Limited v London Underground Limited [2018] EWHC 2926 TCC at [58]:
'In most cases, unsuccessful bids are part of the normal commercial risks taken by a business and will not have any adverse impact apart from potential wasted costs of the tender and lost profits. Not every failed bid will result in damage to reputation causing uncompensatable loss. There must be cogent evidence showing that the loss of reputation alleged would lead to financial losses that would be significant and irrecoverable as damages or very difficult to quantify fairly.'
41. The evidence before the Court does not indicate that this procurement is unique or high value. However, it is being closely watched by a number of other fire and rescue services and is likely to be perceived as setting the standard for improved protective equipment in this sector. On that basis, it is arguable that, if the automatic suspension is lifted and Draeger is ousted from its position as the incumbent provider of breathing apparatus for LFB, it will suffer a loss for which damages are not an adequate remedy."
Adequacy of damages for defendants
Balance of convenience and justice
The application for trial of a preliminary issue with expedition
"The applicable principles were then succinctly expressed by Neuberger LJ (as he then was) in WL Gore and Associates GmbH v Geox SpA [2008] EWCA Civ 622 where he alluded to four factors to be taken into account as follows: (1) whether the applicants have shown good reason for expedition; (2) whether expedition would interfere with the good administration of justice; (3) whether expedition would cause prejudice to the party; and (4) whether there are any other special factors."
"content that any trial of preliminary issues should be conducted on the basis that the scores and rationales produced after the moderation stage should be treated as reflecting the outcome of a lawful evaluation and moderation process.
. the focus of a trial of preliminary issues would be on whether or not it was lawful to award the Framework to Fujitsu.
there is no intention to challenge the underlying evaluation and moderation of tenders on a trial of preliminary issues. Any references to manifest error are to manifest error in the decision-making process following the moderation stage.
The second sentence of paragraph 84(l) ["In circumstances where all tenderers had purportedly failed the Minimum Quality Threshold, the Defendants should have considered what led to the curious and anomalous outcome whereby major international providers of the services sought, with established track records, failed to satisfy a minimal standard."] is not seeking to challenge the underlying evaluation and moderation of tenders but is rather intended to indicate the factors that the decision-makers should have considered once all tenderers had failed the Minimum Quality Threshold."
Note 1 It is agreed that this reference is mistaken and should read 18.13.1. [Back]