QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
(Sitting as a Deputy High Court Judge)
____________________
EVERWARM LIMITED |
Claimant |
|
- and - |
||
BN RENDERING LIMITED |
Defendant |
____________________
CATHERINE PIERCY (instructed by Goodman Derrick LLP) for the Defendant
Hearing dates: 19 July 2019
____________________
Crown Copyright ©
MR ALEXANDER NISSEN QC :
Introduction
The original Orders
"Unless the Defendant makes provision for security for costs in the sum of £145,000 by way of payment into Court or a guarantee from a first class UK bank in accordance [with] Mrs Justice Cockerill's Order dated 13 June 2019 by 4:00pm on Thursday 11 July 2019 its Counterclaim will be stuck out and judgment on the Counterclaim will be entered for the Claimant."
The Present Application
(a) As directed, both parties provided written submissions in respect of the application with or as part of their skeleton openings for the trial. These were received on 16 July 2019 in respect of Everwarm and 17 July 2019 in respect of BN;
(b) Everwarm provided the sixth witness statement of Carolyn Morgan dated 18 July 2019 in opposition to the application;
(c) At 3.25pm on 18 July 2019, BN paid the sum of £145,000 into Court.
The Effect of the Unless Order
"[34] In my view it should now be clearly recognised that the sanction embodied in an "unless" order in traditional form takes effect without the need for any further order if the party to whom it is addressed fails to comply with it in any material respect. This has a number of consequences, to three of which I think it is worth drawing particular attention. The first is that it is unnecessary, and indeed inappropriate, for a party who seeks to rely on non-compliance with an order of that kind to make an application to the court for the sanction to be imposed or, as the judge put it, "activated". The sanction prescribed by the order takes effect automatically as a result of the failure to comply with its terms."
The Test – the Submissions and the Authorities
"(2) Except where these Rules provide otherwise, the court may –
(a) extend or shorten the time for compliance with any rule, practice direction or court order (even if an application for extension is made after the time for compliance has expired);"
"(1) On an application for relief from any sanction imposed for a failure to comply with any rule, practice direction or court order, the court will consider all the circumstances of the case, so as to enable it to deal justly with the application, including the need –
(a) for litigation to be conducted efficiently and at proportionate cost; and
(b) to enforce compliance with rules, practice directions and orders."
"(1) These Rules are a new procedural code with the overriding objective of enabling the court to deal with cases justly and at proportionate cost.
(2) Dealing with a case justly and at proportionate cost includes, so far as is practicable –
(a) ensuring that the parties are on an equal footing;
(b) saving expense;
(c) dealing with the case in ways which are proportionate –
(i) to the amount of money involved;
(ii) to the importance of the case;
(iii) to the complexity of the issues; and
(iv) to the financial position of each party;
(d) ensuring that it is dealt with expeditiously and fairly;
(e) allotting to it an appropriate share of the court's resources, while taking into account the need to allot resources to other cases; and
(f) enforcing compliance with rules, practice directions and orders."
"[33] It is clear that Brooke LJ treated Sayers's case as a relief from sanctions case, or at least closely analogous to such a case. That is because the time for appealing had already expired when the application for an extension of time was made. I see no reason to import the rule 3.9(1) checklists by implication into rule 3.1(2)(a) where an application for an extension of time is made before the expiry of the relevant time limit. There is a difference in principle between on the one hand seeking relief from a sanction imposed for failure to comply with a rule, practice direction or court order, where such failure has already occurred, and on the other hand seeking an extension of time for doing something required by a rule, practice direction or court order before the time for doing it has arrived. The latter cannot sensibly be regarded as, or even closely analogous to, a relief from sanctions case. If the draftsman of the rule had intended that the checklist set out in rule 3.9(1) should be applied when the court is exercising its discretion under CPR 3.1(2)(a) in such a case, then he could and, in my judgment, would have said so. By not spelling out a checklist in rule 3.1(2)(a), it seems to me that the draftsman was intending that the discretion should be exercised by simply having regard to the overriding objective of enabling the court to deal with cases justly including, so far as practicable, the matters set out in rule 1.1(2).
[34] It follows that, in my judgment, the judge was wrong to criticise the district judge for failing to apply the rule 3.9(1) checklist. In the result the two reasons given by him for exercising his discretion afresh fail."
"a close analogy to an application for relief from sanctions".
"[31] This case by contrast is one of an in-time application for an extension. Mr Jones submitted that once it was accepted that the Mitchell principles applied to an out of time application for an extension, it was illogical not to apply the same approach to an in-time application for an extension. I do not agree. Of course if time is due to expire on 14 February, there is little practical difference between an application made on 13 February (or 11 February as in this case) and one made on 15 February. Realistically it is unlikely that an application made on 11 February could be heard before 14 February, and even if the court could in theory hear it immediately, it would no doubt usually already be too late for the applicant to comply with the original time limit: that is after all the reason why the application is made. One can see the strict logic of saying that in such a case the realistic position is that unless an extension is granted the applicant is inevitably going to fail to comply with the time limit, and should be treated in the same way as one who has already failed to do so.
[32] But this is not the approach that has been adopted as a matter of precedent, and I can see sound practical and policy reasons for not doing so. So far as precedent is concerned, in Robert v Momentum Services Ltd [2003] 1 WLR 1577 ("Robert"), the Court of Appeal expressly held that an in-time application for an extension of time (in that case for service of the particulars of claim) was not, and should not be treated as, an application for relief from sanctions. Dyson LJ (with whom Hale LJ and Sir Andrew Morritt V-C agreed) referred to what Brooke LJ had said in Sayers and continued, at para 33:
"It is clear that Brooke LJ treated the Sayers case as a relief from sanctions case, or at least closely analogous to such a case. That is because the time for appealing had already expired when the application for an extension of time was made. I see no reason to import the rule 3.9(1) check lists by implication into rule 3.1(2)(a) where an application for an extension of time is made before the expiry of the relevant time limit. There is a difference in principle between on the one hand seeking relief from a sanction imposed for failure to comply with a rule, practice direction or court order, where such failure has already occurred, and on the other hand seeking an extension of time for doing something required by a rule, practice direction or court order before the time for doing it has arrived. The latter cannot sensibly be regarded as, or even closely analogous to, a relief from sanctions case. If the draftsman of the rule had intended that the check list set out in rule 3.9(1) should be applied when the court is exercising its discretion under CPR r 3.1(2)(a) in such a case, then he could and, in my judgment, would have said so. By not spelling out a check list in rule 3.1(2)(a) , it seems to me that the draftsman was intending that the discretion should be exercised by simply having regard to the overriding objective of enabling the court to deal with cases justly including, so far as practicable, the matters set out in rule 1.1(2)."
[33] Mr Harty submitted that there was nothing in Mitchell [2014] 1 WLR 795, or the new approach there endorsed, which affected the decision in Robert [2003] 1 WLR 1577. Robert was cited in argument in Mitchell, but the Court of Appeal did not refer to it in their judgment and could not sensibly be regarded as departing from it (even if it was open to them to do so). He referred me to the fact that Robert is still cited in the most recent edition of the White Book ( Civil Procedure 2014 , vol 1, p 58), at section 3.1.2 with an editorial comment that it is likely that the distinction between Sayers and Robert remains good law, namely that it is easier to persuade the court to grant an in-time application for an extension than an out of time one.
[34] I accept this submission. It seems to me that unless and until a higher court has said that the approach in Robert is no longer to be followed, I am bound by that decision (i) to regard an in-time application for an extension of time as neither an application for relief from sanctions, nor as closely analogous to one, and (ii) to exercise the discretion under that rule by applying the overriding objective rather than the terms of CPR r 3.9".
"[26] An application for an extension of the time allowed to take any particular step in litigation is not an application for relief from sanctions, provided that the applicant files his application notice before expiry of the permitted time period. This is the case even if the court deals with that application after the expiry of the relevant period. The Court of Appeal established this principle in Robert v Momentum Services Limited[2003] EWCA Civ 299; [2003] 1 WLR 1577: see in particular [33]. This still remains the case following the recent civil justice reforms. See Kaneria v Kaneria [2014] EWHC 1165 (Ch) at [31] to [34]. I agree with those four paragraphs in the judgment of Nugee J.
[27] It therefore follows that on 16th May 2013 the costs judge was dealing with an in-time application. This was a straightforward application to extend time under rule 3.1(2)(a). The principles concerning relief from sanctions which the Court of Appeal enunciated in Mitchell v News Group Newspapers Ltd [2013] EWCA Civ 1537; [2014] 1 WLR 795 are not applicable."
"[34] … If an application to enter judgment is made under rule 3.5(5) , the court's function is limited to deciding what order should properly be made to reflect the sanction which has already taken effect. Unless the party in default has applied for relief, or the court itself decides for some exceptional reason that it should act of its own initiative, the question whether the sanction ought to apply does not arise. It must be assumed that at the time of making the order the court considered all the relevant factors and reached the decision that the sanction should take effect in the event of default. If it is thought that the court should not have made an order in those terms in the first place, the right course is to challenge it on appeal, but it may often be better to make all reasonable efforts to comply and to seek relief in the event of default.
[35] The second consequence, which follows from the first, is that the party in default must apply for relief from the sanction under rule 3.8 if he wishes to escape its consequences. Although the court can act of its own motion, it is under no duty to do so and the party in default cannot complain if he fails to take appropriate steps to protect his own interests. Any application of this kind must deal with the matters which the court is required by rule 3.9 to consider."
"[6] The unless order was not complied with. An unless order means what it says. If a party does not comply with it, the sanctions automatically follow. Even if the consequences in the individual litigation are not immense, the consequences for the system are. It is also important to appreciate that by 2014 seven years had passed since from the date of the incident. Miss C had also benefited from a number of stays and a certain degree of indulgence in the procedural timetable, flowing from having been a litigant in person at various points in time. There is, however, nothing which allows a litigant in person to simply depart from the rules completely."
"[38] An "unless" order, however, does not stand on its own. The court usually only makes an "unless" order against a party which is already in breach. The "unless" order gives that party additional time for compliance with the original obligation and specifies an automatic sanction in default of compliance. It is not possible to look at an "unless" order in isolation. A party who fails to comply with an "unless" order is normally in breach of an original order or rule as well as the "unless" order.
[39] In order to assess the seriousness and significance of a breach of an unless" order, it is necessary also to look at the underlying breach. The court must look at what X failed to do in the first place, when assessing X's failure to take advantage of the second chance which he was given.
[41] In my view the phrase "the very breach" in para 27 of the Denton case, when applied imposed by the original order or rule and (b) extended by the "unless" order."
"[24] What Richards LJ said at paragraph 38 of Michael Wilson & Partners is also in point:
"In the ordinary course there is a clear distinction between the initial imposition of a sanction and the exercise to be conducted under rule 3.9 in considering whether to grant relief from sanction. I made that point, in relation to the sanction of strike-out, in my judgment in Walsham Chalet Park (t/a The Dream Lodge Group) v Tallington Lakes Ltd [2014] EWCA Civ 1607; [2014] 1 Costs LO 157, at paragraph 44:
"It must be stressed, however, that the ultimate question for the court in deciding whether to impose the sanction of strike-out is materially different from that in deciding whether to grant relief from a sanction that has already been imposed. In a strike-out application under rule 3.4 the proportionality of the sanction itself is in issue, whereas an application under rule 3.9 for relief from sanction has to proceed on the basis that the sanction was properly imposed (see Mitchell, paras 44-45). The importance of that distinction is particularly obvious where the sanction being sought is as fundamental as a strike-out…""
[25] Likewise, it seems to me that when a court is considering an application for relief from sanction where there has been a failure to comply with an unless order which has specified that a strike out is the sanction for failure to comply, the court must proceed on the basis that the sanction of strike out contained in the unless order was properly imposed as a proportionate sanction for failure to comply. It will, therefore, be a comparatively rare case in which the applicant can persuade the court, absent a material change of circumstances, that it would now be appropriate to grant relief from the sanction as being disproportionate.
[26] I turn, therefore, to apply the three stage approach. The first stage is to enquire whether the breach is serious or significant. I have no doubt that in this case the breach ought properly to be categorised as very serious. The starting point is that breach of an unless order will almost always be treated as serious. It is a failure to comply with a court order in the knowledge that the court has already attached sufficient importance to the need to comply with it so as to impose the sanction of strike out as the proportionate consequence of non-compliance. Secondly, the requirement in this case that the claimants provide security for costs is an important one. The first claimant is resident in the United Arab Emirates, the second claimant is a Delaware corporation. Neither has at any stage, including on the present application, given a full and frank account in a witness statement of their assets. There are very real and justifiable concerns about their ability or willingness to meet a costs order in favour of the defendants if and when one is made."
"[42] So far as the other particular aspect which rule 3.9 requires to be given particular importance, that is to say the imperative in subparagraph (b) of enforcing compliance with rules, practice directions and orders, that is a consideration of particular weight in this case against the grant of relief from sanctions. There has been an unless order. There has been no proper excuse for failure to comply. It was accepted at the hearing on 11 September 2015 that this would be a last chance and there is a very powerful public interest in ensuring that parties recognise the importance of complying with unless orders.
[43] In addition, all the factors I mentioned under the first heading which make this a very serious breach come into play again at the third stage. Of particular importance to my mind at the third stage, is the fact that Flaux J has already determined that the striking out of the claims is an appropriate and proportionate sanction for failure to comply with the provision of security for costs. He made that determination when considering whether to make, and in making, the unless order and in granting an additional period of 14 days. There is nothing to put this case in that rare category of cases where that value judgment should be revisited. There has been no material change in circumstances which has led to a failure to comply from what could reasonably have been contemplated and as being within Flaux J's expectation at the time that the order was made."
"[4] The Defendant has still not fully complied, although four more weeks have passed; and it is seeking up to a further two months' indulgence. A party who faces genuine difficulties in compliance with a court Order, particularly an Unless Order, should come back to the Court and explain the problems that it is facing as soon as they arise, if those problems are sufficiently serious to give rise to a real risk of non-compliance.
[5] The effect of issuing an application notice at the latest possible moment was that although it was impossible to list a hearing before the deadline for compliance expired, technically this is not an application for relief against sanctions because the sanction has yet to bite, see Hallam Estates Ltd v Baker [2014] EWCA Civ 661 . However, Mr Heppinstall realistically conceded that the Court of Appeal's reasoning and approach in Denton v TH White Ltd [2014] 1 WLR 3926 should be applied, as they were by Laing J on the previous occasion. The observations of Jackson LJ in Oak Cash & Carry Ltd v British Gas Trading Ltd [2016] EWCA Civ 153 at [38]-[41] are also relevant, given that this is a case of non-compliance with an Unless Order."
"[39] The burden is on the Defendant to persuade the Court that this is an appropriate case in which to grant the extension of time for compliance. In dealing with this application I must, of course, bear in mind the overriding objective. In the present context the factors listed in CPR 1.2(d)(e) and (f) are of particular importance. The Court must endeavour to ensure that cases are dealt with expeditiously and fairly; it must allot to a case an appropriate share of the court's resources, whilst taking into account the need to allot resources to other cases; and it must seek to enforce compliance with rules, practice directions and orders. An "Unless Order" is an order of last resort and the nature of the Court's indulgence to the Defendant in the present case was underlined by Laing J's warning that if the Defendant did not comply it was very unlikely to be given any further leeway to do so."
The Test – Decision
(a) An application for an extension of time allowed to take a particular step in litigation is not an application for relief from sanctions provided that the applicant files his application notice before the expiry of the permitted period: Robert v Momentum and Hallam Estates.
(b) This is the case even if the court actually deals with the application after the expiry of the relevant period: Hallam Estates.
(c) Although there may be little practical difference between an application made just before the expiry of the permitted period and one made just after it had expired, the law has sound practical and policy reasons for distinguishing between the two: Kaneria and Hallam Estates.
(d) An in-time application for an extension of time is neither an application for relief from sanctions nor is it closely analogous to one: Kaneria and Hallam Estates.
(e) An "unless" order is an order of last resort. There is a powerful public interest in ensuring that parties recognise the importance of complying with "unless" orders: Sinclair v Dorsey.
(f) However, the power to extend time for compliance with a court order pursuant to Rule 3.1(2)(a) does not distinguish between routine court orders on the one hand and "unless" orders on the other.
(g) Accordingly, when determining an in-time application for an extension of time for compliance with both routine court orders and "unless" orders, the Court applies the overriding objective.
The Facts
Application of the Test
Unless Order
(1) As set out above, an "unless" order is of a special character. It is an order of last resort which usually reflects the fact that a party has already been in breach of a prior order. But the Unless Order in this case has three particular characteristics. First, BN was not in breach of the prior Order made by Cockerill J. It made an in-time application for further time before time for compliance had expired. Second, the period set by O'Farrell J within the Unless Order was short. This was necessarily dictated by the need to have security in place before the trial began, itself a product of the relatively late application for security. If the application for security for costs had been made earlier and the parties had been further away from trial, I can conceive of circumstances in which a party such as BN would have been given a more generous period of time within which to comply with the Unless Order: see Radu v Houston [2006] EWCA Civ 1575 at [18]. In this regard, I note that because of the impending trial the periods of time given to BN to obtain security were less than allowed in two of the cases cited to me. In Sinclair, six weeks was given in the first place and a further month was then allowed. In Radu v Houston [2006] EWCA Civ 1575, the initial period given was also about six weeks. In the present case, the initial period given to BN was three weeks and, subsequently, two further weeks will have been sought. Third, there was no history of prior disobedience by BN with other court orders. I accept the application was made at the last minute but in this case the whole period for compliance with the Unless Order was only one week anyway so this factor is less important than might otherwise apply in other cases.
Compliance
(2) Most obviously, BN has ultimately provided security, albeit late. This means that Everwarm is now fully protected to the extent required by the Court. It has exactly what it was entitled to. It is true that it has received the security later than ordered, but that is a question of prejudice, which I consider below. Ms Piercy was right to rely on Radu v Houston [2006] EWCA Civ 1575 at both [18] and [20]. In that case, Walker LJ said at [18]:
"The making of an order for security is not intended to be a weapon by which a defendant can obtain a speedy summary judgement without a trial".
I agree that, in circumstances where security has now been provided, which is the very thing which the Court ordered, Everwarm's pursuit of its objection to further time should be regarded as the deployment of a weapon. Rather than keep the security which the court had ordered, Everwarm would now prefer to have the benefit of the sanction. In the absence of prejudice, that is unacceptable. At [20], Walker LJ said:
"In my experience, if a court has ultimately made an unless order, and even if judgment has been entered pursuant to it, the security not having been paid, if a claimant within a short period of time has come to court with the right sum, the court is and indeed should be willing to consider granting relief and setting the judgment so obtained aside."
The present case is a fortiori, as the application for more time was made before judgment would have been entered.
Prejudice
(3) Realistically, Mr Quirk did not suggest that there had been any prejudice caused to Everwarm as a result of the delay in compliance with the Unless Order. Necessarily Everwarm had to continue with its preparations for trial, including the Counterclaim, because it could not be confident that security would not be provided within the time limit. Before the time limit expired, an application for an extension of time was made. Once again, there was no suggestion that, in the intervening week before this application was heard, Everwarm's subsequent preparations for trial were impaired in any way by the uncertainty over whether the extension would retrospectively be granted.
Overriding objective
(4) I now turn to the specific factors that are worthy of mention. As to (a), if more time is granted, the parties will be on an equal footing. Everwarm has the protection of security which Cockerill J ordered. By contrast, if I refuse more time, BN will never have its Counterclaim determined in circumstances where the degree of overlap between the issues raised in defence of the Claim and Counterclaim is potentially significant. As to (c), the Counterclaim is worth nearly £2m in circumstances where, as subcontractor, BN is the weaker financial party. As to (d), the case can be dealt with fairly and expeditiously if more time is allowed. It would be fair to allow the Counterclaim to be heard. There is no delay to the trial and none was sought. No prejudice is alleged to have flowed from the additional time required. As to (f), it is important to have regard to the fact that it was an Unless Order, but it was one with the characteristics mentioned above. BN did not ignore the Order. It tried to comply with it but under-estimated the length of time it needed in order to comply.
Rule 3.9
Conclusion
Note 1 It is right to record that the original draft Order submitted by Everwarm with its letter of 4 July 2019 had proposed that, in default of provision of security for costs, the sanction would be that both BN’s defence of the Claim and its Counterclaim would be struck out and this form of Order was originally issued by the Court in that form. BN objected to this on the grounds that the sanction could only ever extend to the Counterclaim and O’Farrell J agreed, issuing a corrected order in the terms set out. [Back] Note 2 Mitchell v News Group Newspapers Ltd [2013] EWCA Civ 1537 [Back]