BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHONOLOGY AND CONSTRUCTION COURT (QBD)
Fetter Lane, London EC4A 1NL Date handed down (at Manchester Civil Justice Centre): |
||
B e f o r e :
SITTING AS A JUDGE OF THE HIGH COURT
____________________
BDW TRADING LIMITED |
Claimant |
|
- and - |
||
INTEGRAL GEOTECHNIQUE (WALES) LIMITED |
Defendant |
____________________
Sean Brannigan QC and Jessica Stephens (instructed by Weightmans, London) for the Defendant
Hearing dates: 17, 21, 22, 23, 24 May, 8 June 2018
Draft judgment circulated: 6 July 2018
____________________
Crown Copyright ©
His Honour Judge Stephen Davies:
Contents
Section No | Section heading | Paragraphs |
1 | Introduction | 1 - 3 |
2 | Witnesses | 4 - 23 |
3 | The relevant facts | 24 - 136 |
4 | Did IGL owe a duty of care to BDW? | 137 - 177 |
5 | Was IGL negligent? | 178 - 206 |
6 | What, if any, recoverable loss has BDW sustained? | 207 - 259 |
7 | Contributory negligence | 260 - 265 |
8 | Conclusions | 266 - 267 |
Introduction
Witnesses
Witnesses of fact:
I did not hear from his then superior Mr Huw Llewellyn, who was the technical director for the South Wales division at the relevant time, but who left BDW some time ago.
Expert witnesses:
"Whilst the parties' legal advisers may assist in identifying issues which the statement should address, those legal advisers must not be involved in either negotiating or drafting the experts' joint statement.
Legal advisers should only invite the experts to consider amending any draft joint statement in exceptional circumstances where there are serious concerns that the court may misunderstand or be misled by the terms of that joint statement.
Any such concerns should be raised with all experts involved in the joint statement."
This is consistent with the Practice Direction to Part 35, which at paragraph 9 makes clear that:
(1) The role of the legal representatives in expert discussions is limited to agreeing an agenda where necessary and, whilst they may attend the discussions if ordered or agreed, they must not intervene and may only answer questions or advise on the law.
(2) Experts do not require the authority of the parties to sign a statement, which should be done at the conclusion of the discussion or as soon thereafter as practicable and in any event within 7 days.
3. The relevant facts
Section No | Section heading | Paragraphs |
(i) | Preliminary | 24 - 27 |
(ii) | The contract between IGL and Bridgend to undertake the site investigation | 28 - 42 |
(iii) | The site investigation and report | 43 - 82 |
(iv) | BDW's receipt of the report and the contract to acquire the site subject to contract | 83 - 101 |
(v) | From agreement to exchange | 102 - 113 |
(vi) | Why was the report not assigned to BDW? | 114 - 122 |
(vii) | Completion and the subsequent discovery of ACMs | 123 - 136 |
(i) Preliminary
(ii) The contract between IGL and Bridgend to undertake the site investigation
"I act for Bridgend, the owners of the above site, we are instructed to shortly commence marketing the property with a view to its sale by residential development.
We require a geotechnical report to include an enviro check, historic ordnance survey plans plus services and utility records.
Your geotechnical report must provide foundation recommendations and a remedial strategy if contaminated material is found. Please note an asbestos survey has already been undertaken.
It is intended that your report should be relied upon by the eventual purchaser therefore it must be capable of assignment with warranties at least twice. A statement on this is to be included in your report.
The commissioning party will be Bridgend [who] will be responsible for payment of your invoice."
(i) Clause 1: "Unless otherwise amended the appointment will be in accordance with the Association of Consulting Engineers Conditions of Engagement 1995 or the latest revision thereof, inclusive of all current amendments."
(ii) Clause 5: "Nothing in [this contract] confers or purports to confer any third-party benefit or any rights to enforce any term of this contract."
(iii) Clause 10: "For any matter arising out of or in connection with pollution or environmental contamination the total liability under or in connection with this agreement at any time shall be limited to the lesser of: the direct costs incurred by the Client [Bridgend] in cleaning up the site of the works or any part thereof: and the amount if any recoverable by [IGL] in respect of such claims under any professional indemnity insurance taken out by [IGL]."
(iv) Clause 11: "Subject to a limit of £300,000 for all such claims."
(iii) The site investigation and report
"However, it would be prudent to undertake confirmatory laboratory chemical analysis once access to the eastern half of the site is readily available following demolition of the existing buildings and the removal of the numerous underground services. The testing should include a general suite of determinants, and more specific hydrocarbon analysis around the location of the fuel storage tanks/boiler room."
There is no suggestion either that the chemical analysis should be limited to the eastern half of the site or that the chemical analysis should not include testing in relation to asbestos.
"During site clearance the exposed formations should be inspected by a suitably qualified engineer for signs of contamination, and samples taken on a 25m grid. Additional sampling and testing should be carried out as deemed necessary."
(iv) BDW's receipt of the report and the contract to acquire the site subject to contract
"This technical pack provides useful information for interested parties to consider prior to making an offer to purchase the site. The majority of the information provided is for guidance only and interested parties should satisfy themselves in respect of statements made, and in particular the capacity of services and utilities. The budget demolition quotes are for guidance only. Interested parties must satisfy themselves in respect of the costs of removing asbestos, demolition and site clearance. The ground investigation report prepared by IGL will be assignable to the successful purchaser if required."
(v) From agreement to exchange
(vi) Why was the report not assigned to BDW prior to exchange of contracts?
(vii) Completion and the subsequent discovery of ACMs
"To remove and dispose of all asbestos products … that are identified in the West reports or encountered within the buildings or structures during the demolition but excluding any material that may be buried or encountered during your development works.
To soft strip buildings … To remotely demolish identified structures on site. To grub up building slabs (assumed 0.2m) and foundations to a depth of 1.5m …. To dispose of all other materials arising from the demolition works to suitable licensed facilities …
No allowance within the above has been made for … removal of any hazardous materials other than mentioned above …"
"When the buildings were demolished we also carried out work on the foundations underneath. There were extensive materials which had been used as a sub-base for the slab. We had agreed with BDW at the outset of the contract when giving a price that any contaminated material under the slab was at the contractor's risk. This is fairly standard industry practice."
Did IGL owe a duty of care to BDW?
The relevant legal principles
"A disclaimer of liability in respect of a statement or service may be sufficient to preclude a finding of assumption of responsibility and reasonable reliance. This was the case in Hedley Byrne itself where the credit reference provided by the defendant bank was stated to be given without responsibility and as a result the bank was held to owe no duty. In McCullagh v Lane Fox & Partners Ltd Hobhouse LJ explained that a disclaimer was not to be construed narrowly in the same way as an exclusion clause, rather the court should "treat the existence of the disclaimer as one of the facts relevant to answering the question whether there had been an assumption of responsibility by the defendants for the relevant statement. This question must be answered objectively by reference to what the reasonable person in the position of [the claimant] would have understood at the time he finally relied upon the representation."
"We understand that there is a possibility of the Design Team being novated to a contractor at some stage in the project. We confirm that we have had experience of this type of situation and are comfortable with this arrangement. Our fees would still stand if novation took place."
There was, however, ultimately no novation.
(c) It is always necessary to consider the circumstances and context, commercial, contractual and factual, including the contractual structure, in which the inter-relationship between the parties to and by whom tortious duties are said to be owed arises. Thus, it is not every careless misstatement which is actionable or gives rise to a duty of care. Foreseeability of loss is not enough.
(d) It is necessary for the party seeking to establish a duty of care to establish that the duty relates to the kind of loss which it has suffered. One must determine the scope of any duty of care.
(h) So far as disclaimers are concerned, they are simply one factor, albeit possibly an important one, in determining whether a duty of care arises. One can not, usually, voluntarily undertake a responsibility when one tells all concerned that one is not accepting such responsibility.
(i) The context of and the circumstances in which statements are made by one party to another need to be considered to determine not only if there is a duty but also the scope of any duty. The facts that a statement is made by A to B, that A knows that B will rely upon it and that B does rely upon it are not or at least not always enough to found a duty of care."
"One needs to determine what responsibility, if any, judged objectively was assumed by MM towards MCL in this case. One can have regard, amongst other matters, to:
(a) The contractual nexus or lack of contractual nexus between the party said to owe the duty of care and the party said to have been owed it;
(b) What was said in writing and orally by MM to MCL and in what context it was said;
(c) Any disclaimers issued by MM to MCL in relation to what was said;
(d) What was said to MM or mutually understood by MCL and MM as to why information was sought; put another way, what was the express or necessarily implied purpose for the information being sought and supplied."
"In my view, the very fact that the parties were trying to agree terms points more to there being no duty of care than there being one. The parties were seeking to legislate for their relationship by way of a proposed contract; it would be odd if, the contractual route having failed or not being achieved, MCL could procure for free an enforceable duty or warranty on the part of MM to exercise reasonable care together effectively with duties to perform services for MCL."
Discussion
(a) IGL had been asked on behalf of Bridgend to prepare a report which it knew was intended should be provided to all prospective purchasers and which was capable of assignment to the eventual site purchaser.
(b) IGL had agreed to do so, but pursuant to a contract which excluded third party rights ("the third party rights exclusion") and which limited liability for environmental contamination to the lesser of the direct clean-up costs incurred by the client or of IGL's insurance recovery but in any event no more than £300,000 ("the liability limitation").
(c) The report as provided to BDW clearly stated that it was for Bridgend's use only and should not be passed onto others without IGL's express consent, but that it could be assigned to the eventual site purchaser ("the assignment statement"). It did not however expressly refer to the third party rights exclusion or to the liability limitation.
(d) Notwithstanding the statements that the report had been prepared for Bridgend's use only ("the limited use statement") and should not be passed to others without IGL's express consent ("the no passing on statement") IGL knew that the report would be passed to and used by prospective purchasers and, if any had asked, would willingly have consented to this being done. However BDW did not know this for sure and did not ask for IGL's consent to use the report.
(e) When IGL became aware that BDW had been given the report as a prospective purchaser and was using it and relying on it in such capacity it did not communicate any objection to BDW doing so and, indeed, entered into discussions with BDW from which BDW could reasonably have assumed that IGL knew that it had he report and was using it and did not object.
(f) BDW did not ask for confirmation from IGL that it was willing to allow BDW to place legal reliance on the report or that it was willing to assign the benefit of the report to it if it purchased the site. Neither did BDW make any enquiries as to the contractual terms agreed as between Bridgend and IGL so as to understand whether it excluded or restricted either third party rights or IGL's liability under the contract, even though BDW knew (or at least would have known, had it applied its mind to it) that it might contain clauses which would affect what if any reliance it might place on the report.
(g) BDW always intended to obtain a formal assignment of the benefit of the report from IGL and – although internally its thinking was muddled – knew that it was important that it should do so if it was intended to place legal reliance on the report. The only reason it did not do so was due to some internal mistake or confusion. It was not reasonable for BDW to assume, if it did, that because IGL had provided many reports to BDW under the Term Agreement which contained no relevant exclusions or restrictions the provision of this report could also be treated as if provided under the Term Agreement.
(f) Nonetheless BDW in fact decided to purchase the site in reliance on the report.
(h) Had IGL been asked it would have been willing to assign the benefit of the report to BDW. In fact it would have been quite willing to provide BDW with a letter of reliance or some other legal document which would have enabled BDW to rely upon it in full and without any limitation of liability of £300,000. If there had been any express discussion about limitation of liability IGL would have suggested and BDW would have agreed a limit of liability of £5M. However none of this was actually known to BDW. The most that could be said is that it would have been reasonable for BDW to assume that IGL would have been willing – indeed would have been unable to object – to the benefit of the report being assigned. BDW might also reasonably have believed that IGL might have been willing, given their previous dealings, to provide an unlimited letter of reliance, but it could not have been sure about that. This is not a case where BDW and IGL agreed on an unqualified basis that there would be an assignment or a reliance letter but then, through simple inadvertence, that agreement was not put into effect.
Decision
BDW's fall-back argument
Was IGL negligent?
(1) Identify the fact that extensive past demolition activity within the site and potential re-use of demolition arisings could have resulted in contamination with ACMs on site.
(2) Identify the fact that the use of made ground to construct the old ski slope could potentially contain contaminants including ACMs.
(3) Undertake a wider assessment of the site and intrusive ground investigation.
(4) Carry out analyses of the ground chemistry to identify the presence or otherwise of contamination.
(5) Identify the existence of and report on the fact that the site was contaminated by asbestos.
(6) The brief reference in section 4.5 to asbestos within the building structures without further elucidation or explanation and without reference is made to previous demolition works over a significant area of the site which would have highlighted the potential presence of ACMs on site was insufficient.
(7) There was a failure in Section 5.6 to list asbestos as a potential contaminant of concern.
(8) Section 8.1 wrongly stated that: "No obvious contaminative practices have been undertaken on site or within the immediate surrounding area, other than the use of oil fired heating. Therefore, it is considered that there is very little risk of any sources of contamination being located on site."
"I would have expected a reasonably competent professional to identify there had been extensive demolition on the site, that there was a significant risk with regard to contamination, with potential demolition materials, which needed to be fully assessed. And that's my conclusion and view."
(1) It would clearly not have been possible to undertake a wider assessment of the site before the existing building structures were demolished and it is fanciful to suggest either that IGL should have advised Bridgend to undertake the demolition before it produced its report or that Bridgend would have agreed to do so.
(2) It would not have made any sense for IGL to recommend a wider or more intrusive investigation of the grassed-over area in isolation and before the whole site could be investigated on a 25m grid as advised by IGL in its report. Given the absence of evidence of contamination in the trial pits which were carried out there was no reason to advise further trial pitting in the grassed-over area in isolation and in advance of the full investigation. That is a suggestion made entirely with the benefit of hindsight.
(3) I do not accept that it could be said to have been negligent of IGL to decide that given all of the circumstances there was no need to hold up production of the report in order to advise Bridgend that it could always consider having these further investigations done even though IGL had taken the perfectly reasonable view that they were not necessary at that stage.
What, if any, recoverable loss has BDW sustained?
(1) That the calculation for the primary case based on the "high-level estimate" approach was not supported by either expert.
(2) That there was no basis for using the actual costs of remediation as an alternative measure for valuing the primary case based on a reduction.
(3) That there was no basis for including the alleged delay costs in the claim.
(4) That on proper analysis this was a loss of a chance claim, because it depended on what a third party, here Bridgend, would have done in the counter-factual situation under consideration, so that in accordance with authority it was necessary for the claimant to prove that there was a real or substantial chance that the third party would have acted in a way favourable to the claimant and, if so, for the court to assess damages based on the evaluation of that chance in percentage terms: McGill v Sports & Entertainment Media Group [2016] EWCA Civ 1063, following Allied Maples Group v Simmoms & Simmons [1995] 1 WLR 1602 and Wellesley Partners v Withers [2015] RWCA Civ 1146. This involved a consideration of BDW's negotiating position, Bridgend's negotiating position and the position of the other interested parties, not just in relation to the site but also in relation to the adjacent caravan park site.
BDW's high level cost estimate.
(1) Remediation works
(2) Geotechnical engineer
(3) Imported topsoil
(4) Road sweeps
(5) Additional preliminaries/supervision
Further points
Contributory negligence
Conclusions