TECHONOLOGY AND CONSTRUCTION COURT
1 Bridge Street West, Manchester M60 9DJ |
||
B e f o r e :
____________________
NP INTERGRATED TECHNOLOGY LIMITED |
Claimant |
|
- and - |
||
GRAHAM AND KAY ENTWISTLE |
Defendants |
____________________
Simon Charles (instructed by Blackstone Solicitors, Hale) for the Defendants
Hearing dates: 24 27 April 2017
Draft judgment circulated 11 May 2017
____________________
Crown Copyright ©
His Honour Judge Stephen Davies
Contents
1 | Summary | 1 - 4 |
2 | Introduction | 5 - 14 |
3 | Witnesses | 15 - 25 |
4 | Contract | 26 - 47 |
5 | Claims | 48 - 147 |
6 | Counterclaims | 148 - 188 |
7 | Payments | 189 |
8 | Conclusion | 190 - 192 |
Summary
Introduction
The witnesses
Mr Oliver Hall
Mr Nigel Pilling
Mr John Thompson
Mr Graham Shallis
Mrs Kay Entwistle
Mr Graham Entwistle
The experts
The contract
VAT
(a) The supply only of building materials is not zero-rated; it has to be the supply of building materials by the supplier of the services who is going to incorporate them as part of those services. If a self-builder purchases building materials from a retailer or builders merchant or any other supplier and either installs them himself, or pays for someone else to do so, then whilst he may be able to recover the VAT under a VAT refund scheme it must still be charged in the first instance. (Notice paragraphs 1.3, 2.2, 11.)(b) The supplier is obliged to charge the lowest VAT rate applicable to his supply. He is not entitled to choose to charge higher rate VAT even where he is not required to do so. (Notice, paragraph 2.1.1.)
(c) Once the construction works are complete, further supplies are no longer zero-rated unless the services are "closely connected to the construction of the building" whether in terms of their nature or their timing. (Notice, paragraph 3.3.)
(d) To qualify for zero-rating, the building materials must be: (a) incorporated into the building, so that they cannot be removed without tools or causing damage; (b) of a type which would ordinarily be incorporated into a dwelling, whether large or small. They must not be electrical appliances. (Notice, paragraph 13.2.)
(e) Electrical appliances means most devices which are powered by electricity. (Notice, paragraph 13.6.)
(f) Given examples of materials which would ordinarily be incorporated into a dwelling include central controls relating to heat, light and ventilation, curtain poles and rails, light fittings including intelligent lighting and touch pads, and wiring including cabling (Notice, paragraph 13.8.1.). Given examples of materials which would not ordinarily be incorporated into a dwelling include appliances whether free standing or integrated, and audio equipment (Notice, paragraph 13.9.)
(g) There is no requirement for a contractor to hold a certificate for supplies in connection with a supply to a normal dwelling, or for a customer in such a case to issue a certificate. (Notice, paragraph 17.)
The usual implied terms
(1) The first point is that, as Mr Connolly submitted, since the claimant did not design the system it was not to be regarded as assuming any responsibility for any inadequacies or deficiencies in that design. It was asked to quote against a pre-designed specification, and did so, and was not asked to undertake a re-design or to warrant the existing design.(2) The second point is that, as Mr Charles submitted, the claimant is responsible in contract for the acts and defaults of its subcontractors in the same way as the acts and defaults of its employees. Thus if and insofar as there was any defect in the items supplied or the work done for example by Crestron as the supplier of the system, or by SilentGliss as the supplier of the electronically operated curtain and blind track system, or by Ultimation as the replacement programmer of the system, the claimant cannot avoid responsibility for such defects.
An entitlement to interim payments?
What was paid at the outset?
The claims
1. Invoice 6147 / 6147A
2. Invoice 6114 / 6114A
3. Invoice 6562
4 & 24. Invoices 6608 and 7019
5. Invoice 6585
6. Invoice 6615
(1) Invoice 6615 dated July 2012 includes in the narrative for the cost of a "visit to test and install faulty units" (underlining added). That is as close to a contemporaneous admission as to the units being faulty, rather than the installation being faulty, as one can imagine. I appreciate that the invoice also states: "The original lighting dimmers had been wired incorrectly by the electrician and damaged beyond economical repair". However since the invoice is headed "proforma invoice 6615 copy" it is not entirely clear to me why and when this further narrative had been added. It is distinctly possible in my view that it was added subsequently. On any view the invoice is not completely consistent with the claimant's case.(2) The statement that the original units were faulty is consistent with John Thompson's approach, not just at the later discussions but also in his witness statement. It is difficult to understand and he was unable to explain his failure to make any reference at all to the damage he said he had observed or his belief as to its cause in his witness statement, or how he came to make and to adopt his witness statement in his evidence when what was in his witness statement was so clearly inconsistent with his oral evidence.
(3) The absence of any evidence, whether contemporaneous or otherwise, from Crestron to support the claimant's case is telling.
(4) Whilst the defendants' failure to adduce evidence from the electrician is not ideal, the reality is that the faulty units were in the claimant's hands and then in Crestron's hands, and no explanation as to precisely what the electrician was ever said to have done to cause the failure has ever been provided, so that it would in any event have been impossible for the electrician to say anything more than: "I believe I wired the units in correctly", which is effectively what Mrs Entwistle has said that he did say when asked.
7. Invoices 6616 / 6795
(i) The ordinary incorporation requirement is met, since whilst the lighting rails and pelmets may not be ordinary in every house, lighting and pelmets are ordinary, so that this particular way of providing lighting is akin to the example of the gold-plated tap given in the Notice at paragraph 13.4; a tap is ordinarily fitted so that a gold plated tap is covered as much as a chrome plated tap.(ii) These items cannot credibly be regarded as fitted furniture.
(iii) The invoices being dated July and November 2012 pre-date the date of practical completion as a whole; there is no magic in the date of completion of decoration in a modern house.
8. Invoice 6814
9. Invoice 6815
10 & 11. Invoices 6598 and 6817
12. Invoice 6946
13. Invoice 6947
14. Invoice 6948
"26-036In a contract to perform services or for work and materials it will be assumed that the claimant will have the incomplete or defective performance completed or corrected and the damages will be assessed by the cost of getting this done; however, in Ruxley Electronics and Construction Ltd v Forsyth the House of Lords held that if the claimant will not have the work done or it would be unreasonable to do so, the damages will again be measured by the difference in value, which may be less than the cost of having the work done. The claimant is entitled to the reasonable cost of having the remedial work done if, in all the circumstances, it is (or was) reasonable for him to insist on having the work done. Factors which are relevant to the issue of reasonableness include:
(i) the claimant has actually had the work done; or
(ii) he undertakes to have it done (but such an undertaking will not, on its own, make it reasonable for the claimant to have it done); or
(iii) he shows a "sufficient intention" to have the work done if he receives damages on this basis: the claimant's subjective intention is relevant.
26-037
In Ruxley Electronics and Construction Ltd v Forsyth above, the House of Lords emphasised the role of reasonableness and held that where the cost of reinstatement was out of all proportion to the advantage to be gained by the plaintiff from reinstatement, it would be unreasonable for the plaintiff to insist on it. In this case, a swimming pool was not built to the depth specified in the contract but was sufficiently deep for diving according to normal standards so that the market value of the property was not reduced. It was held that it was unreasonable for the plaintiff to claim the cost of rebuilding the pool to the contractual specification. (However, the House of Lords did approve the award of £2,500 as damages for loss of amenity or loss of consumer surplus.) "
"26-145In Ruxley Electronics and Construction Ltd v Forsyth the House of Lords accepted that damages may be awarded for the "loss of amenity" suffered by the claimant where the purpose of the contract was to give him a subjective, even idiosyncratic pleasure or amenity. The defendant, in breach of contract, built a swimming pool whose depth was only six feet in the diving area, instead of the specified seven feet six inches. Despite evidence that a depth of six feet was perfectly safe for diving, and that the market value of the property was not adversely affected by the breach, the Court of Appeal had allowed the full cost of re-building the pool. Their Lordships reversed this decision and appeared to support the trial judge's award (not appealed) of £2,500 as substantial damages for "loss of amenity" because the purpose of the contract was "the provision of a pleasurable amenity". Two Lords agreed with Lord Mustill's speech: he upheld the award as representing the loss of the "consumer surplus", the personal, subjective gain which the claimant expected to receive from full performance - an advantage not measured by any increase in the market value of his property."
15 - 17. Invoices 6949, 6950 & 6951
18. Invoice 6941
19. Invoice 6942
20 & 23. Invoices 6956 and 7014
21. Invoice 6957
22. Invoice 6958
23. Invoice 7014
See 20 above.
24. Invoice 7019
See 4 above.
25. Invoice 7020
26. Invoice 7021
27. Invoices 7030, 7031 & 7032
28. Invoice 85371
The counterclaims
Cinema screen
Head End AV Rack
Underfloor heating sensors
System software
Keypad engraving
Redecoration
Other matters
Payments
Conclusion
Item no | Item (claim / counterclaim) | Amount allowed (£) | Subtotal / total |
Claim invoice | |||
1 | 6147 | 0 | |
2 | 6114 | 475.58 | |
3 | 6562 | 0 | |
4 | 6608 | 0 | |
5 | 6585 | 9,651.76 | |
6 | 6615 | 0 | |
7 | 6616 / 6795 | -374 | |
8 | 6814 | 10,589.22 | |
9 | 6815 | 3,240 | |
10 | 6598 | 0 | |
11 | 6817 | 0 | |
12 | 6946 | 8,000 | |
13 | 6947 | 11,502 | |
14 | 6948 | 13,566 | |
15 | 6949 | 4,020 | |
16 | 6950 | 1,380 | |
17 | 6951 | 82.08 | |
18 | 6941 | 1,035.04 | |
19 | 6942 | 0 | |
20 | 6956 | 0 | |
21 | 6957 | 0 | |
22 | 6958 | 720 | |
23 | 7014 | 0 | |
24 | 7019 | 0 | |
25 | 7020 | 4,045.50 | |
26 | 7021 | 492 | |
27 | 7030, 7031, 7032 | 0 | |
28 | 85371 | 0 | |
Total due to the claimant on claim | 68,425.18 | ||
Payments made by the defendants | -66,265.37 | ||
Net amount due to the claimant | 2,159.81 | ||
Counterclaim items | |||
1 | Cinema screen (taken into account in claim item 14) | 0 | |
2 | Head end AV rack | -3,804 | |
3 | Underfloor heating sensors | -7,406.40 | |
4 | System software | -4,590 | |
5 | Keypad engraving | -1,800 | |
6 | Redecoration | - 1,200 | |
Total due to the defendants on counterclaim | -18,800.40 | ||
Balance due to the defendants | £16,640.59 |
Note 1 Short for heating, ventilation and air conditioning. [Back]