QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
KERSFIELD DEVELOPMENTS (BRIDGE ROAD) LIMITED |
Claimant |
|
- and - |
||
BRAY AND SLAUGHTER LIMITED |
Defendant |
____________________
Mr Michael Wheater and Mr Michael Levenstein (instructed by Temple Bright LLP) for the Defendant
Hearing date: 13 December 2016
____________________
Crown Copyright ©
Mrs Justice O'Farrell :
Introduction
i) a final determination of the dispute between the parties determined in the adjudication decision of Mr Peter Gracia dated 31 October 2016; andii) a declaration that:
"Without prejudice to the claimant's obligation arising under section 111(1) of the Housing Grants, Construction and Regeneration Act 1996 as amended ("the Act") to pay the "notified sum," the claimant is entitled to dispute such valuation if and insofar as it conflicts with what the parties have agreed is to be paid at clauses 4.7 and 4.14 of the contract conditions, and to refer such dispute to adjudication or other proceedings."
Factual Background
The Issues
i) whether Application No.19 was a valid application for payment under the contract and/or whether Kersfield is estopped from challenging its validity;ii) whether Bray is precluded from relying on the late service of the payment notice to challenge its validity;
iii) whether the pay less notice was late and therefore invalid;
iv) whether the court should decline to enforce the adjudication award on the ground of procedural unfairness;
v) whether Kersfield is entitled to refer to adjudication a dispute concerning the proper valuation of the claims in Application No.19;
vi) whether there should be a stay of any judgment.
Application No.19
"In relation to each Interim Payment, the Contractor shall make an application to the Employer (an 'Interim Application') in accordance with the following provisions of this clause 4.8, stating the sum that the Contractor considers to be due to him and the basis on which that sum has been calculated."
"Where Alternative B applies, for the period up to practical completion of the Works, Interim Applications shall be made as at the monthly dates specified in the Contract Particulars for Alternative B up to the date of practical completion or the specified date within one month thereafter The due date in each case shall be the later of the specified date and the date of receipt by the Employer of the Interim Application."
"Interim Applications may be made on or after completion of the relevant stage or the monthly date and shall be accompanied by such further information as may be specified in the Employer's Requirements."
"1. At least 2 days before the established dates for interim payments submit to the Employer's Agent a detailed application for amounts due under the Contract together with all necessary supporting information.
2. Such application details are to be based on the elemental breakdown of the Contract Sum Analysis to the approval of the Quantity Surveyor including:
Percentage completions in respect of each element of the Contract Sum Analysis
Supporting evidence of the above by means of progress reports
Full substantiation of all sums claimed in respect of changes including labour, plant and material expenditure, detailed calculations, measurements and invoices (where applicable) together with a copy of the instruction giving rise to the change ...
No variations will be included in the valuation until a valid Change Order is issued.
Comprehensive list of materials on site with proof of cost.
3. At the same time submit a statement from each of the specialist sub-contractors stating:
The gross amount claimed for inclusion in the current valuation "
The application
i) an excel spreadsheet, setting out a breakdown of the works, percentage completion and value, materials on site and variations;ii) a loss and expense claim, set out in the variations part of the above spreadsheet and a supporting spreadsheet, containing a narrative of the claims, pictograph and extracts from Bray's sage records, and pdf cost reports from individual agency resources;
iii) an excel spreadsheet showing a breakdown of the external works.
Submissions
i) it included an item in the sum of £150,000 identified as "Scott Ref 128" with the description: "Disruption Groundworks, brickwork and following trades" but there was no explanation of the calculation of this item, no detailed calculations and it did not include the required substantiation or supporting documentation;ii) it included an item in the sum of £307,965 identified as "Scott Ref 112" with the description: "additional labour and supervision to carry out and complete the balance to the £2.0m additional works to the Main Contract" but did not include the required substantiation or supporting documentation.
Validity of Application No.19
Estoppel by convention
i) CS2 agreed the format of the applications;ii) CS2 allowed Bray to believe that its applications were valid and certified payments on account pending further information, which reinforced Bray's belief;
iii) Bray acted to its detriment in continuing to submit the applications in that form;
iv) it would be unconscionable now to permit Kersfield to resile from that shared assumption.
i) CS2 had no authority to vary the terms of the contract;ii) there was no unequivocal conduct on the part of Kersfield in issuing payment notices and making interim payments as that could equally be seen as co-operation on the part of the employer to ensure continued cash flow for the contractor;
iii) there was no reliance by Bray on any course of dealing; in truth the reason that Bray did not provide the substantiation of its claims was that it did not have such substantiation;
iv) there would be nothing unconscionable about permitting Kersfield to rely on the requirements of the contract in order to defeat Bray's claim for unsubstantiated sums.
Payment Notice
Factual background
"We refer to the purported Pay Less Notice referencing instalment No.19 Any queries we have in relation to the certificate/notice which has been issued will continue but will not hold up our invoice."
"We refer to the above Contract and to the purported Pay Less Notice referencing instalment No.19 dated the 12th August 2016 and to our invoice no. 54364 dated 31st July 2016, a copy of each of which we attach for ease of reference.
The contractual final date for payment of the certified and invoiced sum of £78,224.26 is 19th August 2016, however, as at today's date, payment still remains outstanding.
We therefore wish to record the following and hereby provide notice accordingly:
Under clause 4.9.5, we are entitled to be paid simple interest on the outstanding sum
Under clause 4.11, we give you notice that we intend to suspend all or part of the performance of our contractual obligations, on the ground that you have failed to make payment in accordance with the Contract, should the above sum not be paid within 7 days after the date of this notice. We note that we will also seek to recover our costs and expenses incurred in the exercise of this right.
In the meantime, our rights remain reserved in their entirety, including our right to commence adjudication or court proceedings to recover the above and any other sums properly due under the Contract."
Submissions
Finding
"The doctrine of approbation and reprobation requires for its foundation inconsistency of conduct as, where a man, having accepted a benefit given him by a judgment, cannot allege the invalidity of the judgment which conferred the benefit."
Pay Less Notice
"If the Employer intends to pay less than the sum stated as due from him in the Payment Notice or Interim Application, as the case may be, he shall not later than 5 days before the final date for payment give the Contractor notice of that intention in accordance with clause 4.10.2 (a 'Pay Less Notice'). Where a Pay Less Notice is given, the amount of the Interim Payment to be made by the Employer on or before the final date for payment shall be the sum stated as due in the Pay Less Notice."
"Any notice, certificate or other communication (notice) to be given under Section 4 (Payment) may, in addition to any other permitted method of service, be delivered by hand or sent electronically to the e-mail address of the addressee, provided, if sent by email and not delivered by hand, a copy is sent on the same day to the addressee by pre-paid first class post. Any notice served in accordance with this clause 1.7.3A takes effect as being given and served:
(a) if delivered by hand or sent by email by 4.00 pm on a Business Day, on that day; but otherwise
(b) on the next Business Day."
Submissions
Finding
Enforcement
Further challenge
Submissions
Finding
i) Clause 4.7.2 provides that the sum due as an interim payment shall be an amount equal to the gross valuation of the works (subject to deductions for retention and earlier payments). However, that provision has to be read subject to the provisions that follow, setting out the procedure for determining the amount of any such sum.ii) Clause 4.8.1 obliges the contractor to make an interim application for payment, stating the sum that the contractor considers to be due and the basis on which it is calculated.
iii) Clauses 4.9.2 and 4.10.1 oblige the employer to issue a payment notice, stating the sum that the employer considers to be due and the basis on which it is calculated.
iv) Clause 4.9.2 provides that where a payment notice is given, subject to any pay less notice, the interim payment to be made by the employer shall be the sum stated as due in the payment notice.
v) Clause 4.9.3 provides that where no valid payment notice is given, subject to any pay less notice, the interim payment to be made by the employer shall be the sum stated as due in the interim application.
vi) Clause 4.9.4 provides that where a pay less notice is given in accordance with clause 4.10.2, the interim payment to be made by the employer shall be the sum stated as due in the pay less notice.
"Subsection (9) applies where in respect of a payment
(a) a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract (and no notice under subsection (3) is given), or
(b) a notice under subsection (3) is given in accordance with this section,
but on the matter being referred to adjudication the adjudicator decides that more than the sum specified in the notice should be paid."
"In a case where this subsection applies, the decision of the adjudicator referred to in subsection (8) shall be construed as requiring payment of the additional amount not later than
(a) seven days from the date of the decision, or
(b) the date which apart from the notice would have been the final date for payment,
whichever is the later."
Application for stay
"(a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute.
(b) In consequence, adjudicators' decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money.
(c) In an application to stay the execution of summary judgment arising out of an adjudicator's decision, the court must exercise its discretion under Order 47 with considerations (a) and (b) firmly in mind (see AWG).
(d) The probable inability of the claimant to repay the judgment sum (awarded by the adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a) rendering it appropriate to grant a stay (see Herschell).
(e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House).
(f) Even if the evidence of the claimant's present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if:
(i) the claimant's financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or
(ii) The claimant's financial position is due, either wholly, or in significant part, to the defendant's failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals)."
i) The most recent accounts filed by Bray are for the year ended 31 March 2015, showing a profit on ordinary activities to 31 March 2015 before taxation of £41,000, against turnover of nearly £20 million.ii) The balance sheet shows net assets of £1,540,000 as at 31 March 2015. That can be compared with net assets as at 31 March 2014 of £1.9 million, and projected net assets of £156,376 as at 30 September 2016 i.e. a deteriorating position.
iii) Bray's draft management accounts show an overall loss of £1.45 million for the 18 months to 30 September 2016 and net current liabilities of £506,142.59, as the result of carried forward losses from its residential projects.
iv) Bray has secured other sector projects with a value of £12.75 million and considers that it is likely to achieve or exceed its budgeted turnover of £20 million. The draft management accounts show a projected return to profitability for the year ended 31 March 2017.
v) Bray operates on a cash basis, and has done so since 1934. Between April 2014 and February 2015 it maintained a credit balance in its business account of between £4,043,770 and £6,210,491.
i) Kersfield is a special purpose vehicle set up for the Burwalls development. The works are financed by a secured loan from Wellesley Finance plc and unsecured directors' / shareholders' loans and loans from sister companies.ii) Kersfield's total assets are valued at £9,714,928.
iii) Kersfield's total liabilities are £10,350,667, including unsecured directors' loans of £344,144 but excluding the sums claimed by Bray in these proceedings.
iv) There is a net deficit of £635,740.
v) Current borrowing exceeds 90% loan to value, compared with the anticipated 70% maximum loan to value anticipated when the loan facility was taken out.
vi) There is a facility available to fund the remaining costs to completion of the project of £761,448 but that does not include any funds available to meet the judgment sum and no further support would be available from the shareholders and directors.
Conclusion