QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, 7 Rolls Buildings, London EC4A 1NL |
||
B e f o r e :
____________________
Leeds City Council |
Claimant |
|
- and - |
||
Waco UK Ltd |
Defendant |
____________________
(instructed by Pinsent Masons LLP) for the Claimant
Luke Wygas Esq
(instructed by Contract & Construction Consultants Ltd) for the Defendant
Hearing dates: 12th May 2015
____________________
Crown Copyright ©
Mr. Justice Edwards-Stuart:
Introduction
The facts in more detail
The terms of the contract
"... full authority to receive and issue applications, consents, instructions, notices, requests or statements and otherwise to act for the Employer under any of the Conditions."
"Interim Payments shall be made by the Employer to the Contractor in accordance with section 4 and whichever of Alternatives A (clause 4.13) or B (clause 4.14) is stated in the Contract Particulars to apply."
"The amount due as an Interim Payment shall be an amount equal to the Gross Valuation pursuant to clause 4.13 or clause 4.14, whichever is applicable, less the aggregate of:
.1 any amount which may be deducted and retained by the Employer as provided in clauses 4.16 and 4.18 ("the Retention");
.2 the cumulative total of the amounts of any advance payment that have then become due for reimbursement to the Employer in accordance with the terms stated in the Contract Particulars for clause 4.6; and
.3 the amount paid in previous Interim Payments."
"… where Alternative B applies, Applications for Interim Payment shall be made on the dates provided for in the Contract Particulars for Alternative B up to the date named in the Employer's Practical Completion Statement or the date within one month thereafter. Applications for Interim Payment shall thereafter be made at intervals of 2 months (unless otherwise agreed) and upon whichever is the later of the expiry of the Rectification Period or the issue of the Notice of Completion of Making Good (or where there are Sections the last such period or notice)."
".1 The final date for payment of an Interim Payment shall be 19 days from the date of receipt by the Employer of the Application for Interim Payment.
.2 ...
.3 Not later than 5 days after the receipt of an Application for Interim Payment the Employer shall give a [payment] notice to the Contractor which shall, in respect of that application, specify the amount of the payment proposed to be made, to what the amount relates and the basis on which the amount has been calculated."
The scope of Jacobs' authority
"In consideration of the agreement that final payment is to be made by the client, we hereby agree that payment to us of THE FINAL PAYMENT will be accepted by us in full and final settlement of all our claims ... arising out of or in connection with the Trade Contract Works which have accrued up to and including the date of this statement ... ."
Waiver and estoppel - the law
"A party can represent that he will not enforce a specific legal right by words or conduct. He can say so expressly - this of course he can only do if he is aware of the right. Alternatively he can adopt a course of conduct which is inconsistent with the exercise of that right. Such a course of conduct will only constitute a representation that he will not exercise a right if the circumstances are such as to suggest either that he was aware of the right when he embarked on the course of conduct inconsistent with it or that he was content to abandon any rights that he might enjoy which were inconsistent with that course of conduct."
"If the defendant, as he did, led the plaintiffs to believe that he would not insist on the stipulation as to time, and that, if they carried out the work, he would accept it, and they did it, he could not afterwards set up the stipulation as to the time against them. Whether it be called waiver or forbearance on his part, or an agreed variation or substituted performance, does not matter. It is a kind of estoppel. By his conduct he evinced an intention to affect their legal relations. He made, in effect, a promise not to insist on his strict legal rights. That promise was intended to be acted on, and was in fact acted on. He cannot afterwards go back on it."
Was there an agreement to vary the dates or a waiver?
Application No | Date of email submitting the application | Date on which application was made | Contractual date | Issue Date of Payment Certificate |
1 | Not known | 27.04.12 | 26.04.12 | 01.05.12 |
2 | 25.05.12 | 25.05.12 | 25.05.12 | 29.05.12 |
3 | 29.06.12 | 29.06.12 | 26.06.12 | 06.07.12 |
4 | 26.07.12 | 29.07.12 | 26.07.12 | 31.07012 |
5 | 01.09.12 | 31.08.12 | 26.08.12 | 06.09.12 |
6 | 28.09.12 | 28.09.12 | 26.09.12 | 04.10.12 |
7 | 29.10.12 | 26.10.12 | 26.10.12 | 31.10.12 & 08.11.12 |
8 | 29.11.12 | 29.11.12 | 26.11.12 | 03.12.12 |
9 | 19.12.12 | 28.12.12 | 26.12.12 | 21.12.12 |
10 | 31.01.13 | 31.01.13 | 26.01.13 | 04.02.13 & 08.02.13 |
11 | 28.02.13 | 28.02.13 | 26.02.13 | 04.03.13 |
12 | 28.03.13 | 28.03.13 | 26.03.13 | 02.04.13 & 18.04.13 |
Practical Completion was certified as 28 March 2013.
13 | 30.04.13 | 30.04.13 | 28.05.13 | 03.05.13 |
13 numbering error | 31.07.13 | 30.04.13[1] [30.07.13] |
28.07.13 | 05.08.13 |
15 | 30.09.13 | 26.09.13 | 28.09.13 | None issued |
16 | 26.11.13 | 26.11.13 | 28.11.13 | None issued |
15 numbering error | 11.12.13 (re-submitted) |
26.11.13 | 16.12.13 | |
17 | Not used | |||
18 | Not used | |||
19 | Not used | |||
20 | 12.02.14 | 11.02.14 | 28.01.14 | 17.02.14 |
21 | 18.07.14 | 18.07.14 | 28.03.14 | 23.07.14 |
21 numbering error | 22.09.14 | 22.09.14 | 28.05.14 | None issued |
22 | 28.11.14 | 28.11.14 | 28.11.14 | 02.12.14 |
20 | 12.02.14 | 11.02.14 | 28.01.14 | 17.02.14 |
No application | 28.03.14 | |||
No application | 28.05.14 | |||
21 | 18.07.14 | 18.07.14 | 28.07.14 | 23.07.14 |
21 numbering error | 22.09.14 | 22.09.14 | 28.09.14 | None issued |
22 | 28.11.14 | 28.11.14 | 28.11.14 | 02.12.14 |
"Please note that following PC, applications for payment need to be made at intervals of 2 months. If a valuation is required you would need to submit an application on/after 30/11/2013.
I would also suggest that if any Loss and Expense is being claimed in the next application that the contractual procedures are followed."
The e-mail of 6 October 2014
"Further to your e-mail below, your application was not received on the date issued due to my being on holiday. It has therefore been received today. If you wish to update it before it is processed, please let me know."
Conclusion
Note 1 This looks like a cut and paste error taken from the previous application: the correct date was probably either 30 or 31 July 2013. [Back]