QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, 7 Rolls Buildings, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
Sitting as a Deputy High Court Judge
____________________
MALCOLM GOLDSWORTHY GRAHAM GOLDSWORTHY PAUL GOLDSWORTHY (ALL TRADING AS GOLDSWORTHY BUILDERS) |
Claimants |
|
- and - |
||
JOHN HARRISON CAROLINE HARRISON |
Defendants |
____________________
Robert Stokell (instructed by Michelmores LLP) for the Defendants
Hearing date: 27 June 2016
____________________
Crown Copyright ©
Mr Andrew Bartlett QC:
Introduction
The contract issue
The secondary issue
The Minor Works Contract
i) Elements for which the printed wording stipulates a default option which applies if no positive choice is indicated. For example, if the retention percentage for the purposes of clause 4.3 is not filled in, the percentage is 95%, and if no rectification period is specified, the default period is three months from practical completion.ii) Elements which are only applicable in certain circumstances, so can be left uncompleted if they are not required. For example, the contract is only supplemented by a Framework Agreement if such an agreement is identified in the Contract Particulars, and the insurance provisions in clauses 5.4A, 5.4B and 5.4C only apply if positively selected.
iii) Elements which need to be filled in or otherwise agreed by the parties in order to make a Minor Works contract sufficiently complete and workable. These include the identity of the contracting parties and the Contract Sum.
If any dispute or difference arises under this Contract either Party may refer it to adjudication in accordance with clause 7.2.
If a dispute or difference arises under this Contract which either Party wishes to refer to adjudication, the Scheme shall apply except that for the purposes of the Scheme the Adjudicator shall be the person (if any) and the nominating body shall be that stated in the Contract Particulars.
a contract with a residential occupier within the meaning of section 106 of the Act does not need to contain adjudication provisions, but, unless amendments are made, a residential occupier in entering into a Minor Works Building Contract will be accepting adjudication as a means of resolving disputes.
i) The 'due' dates are at intervals of 4 weeks calculated from the Date for Commencement of the Works.ii) Not later than 5 days after each due date the Contract Administrator is required to issue interim certificates for 95% (or other chosen percentage) of the value of the work and materials, net of VAT.
iii) The final date for payment is 14 days from the due date (ie, if the certificate is issued on the last possible day, 9 days after the certificate).
iv) The Employer must pay, in addition to the certified sum, any VAT properly chargeable. (There is no express provision for Contractor's invoices but in practice a Contractor would provide an invoice before the final date for payment showing any VAT due.)
v) If the Contract Administrator does not issue an interim certificate within the stipulated time, the Contractor may issue a payment notice, and the final date for payment is then adjusted to allow for any delay between the last date for an interim certificate and the date of the Contractor's payment notice.
Facts
The work will be certified for payment by the architect within 7 days of valuation and the Employer is to pay within 14 days of the certification.
It seems there has been confusion.
I thought you were pricing the remaining work on the main house following on from your price for the demolition and garage etc.,
Any queries please e mail in so we can record tha[1] conversations. As discussed previously the contract will be a JCT Minor Work.
If at all possible can you price this in the next 14 days.
We will see you on site tomorrow at 9.00am., therefore we can clarify other queries regarding pricing.
Gentlemen,
My apologies for not confirming the details below formally earlier.
Mr and Mrs Harrison have been forwarded your price for the roof works, and windows along with the demolitions / works to the garden walls opposite the house. They confirmed to us approval for you proceed. We therefore confirm this instruction.
As discussed with you prior to forwarding the quotations we added in a provisional sum for the second chimney as this is of course required.
The "contract" to date is therefore as follows:
Accordingly please proceed with the slate order, scaffolding and roof works as quoted. Please forward your monthly invoice to us and we will certify the monies as normal to Mr and Mrs Harrison. They will then pay you direct in the normal manner.
We understand this work is net of VAT due to the buildings listing. Mr and Mrs Harrison should then pay within 14 days of our certificate.
If you are successful in the quotation for the garage and summer house, and main works please note at that time there will be retentions applied and the JCT Minor works contract. It is hoped that we can extend "the contract" to include these later additional works.[2]
I need to fill in the JCT minor works contract
I have the figures for the demolition and the roof which I can put in as the current contract sum.
I want to add provisional sums for the remainder of the work even if it is a guess at the moment.
I suggest the breakdown is as follows:
i) This was a different list from the list of 49 items in the schedule of 30 October 2012. It may be that all or most of the 49 items were included within it, but the evidence is not clear on this at present.ii) The first item was 'Demolitions (no retention)'. This evidently referred to the demolition work quoted on 15 August 2012 at £21,919. I take 'no retention' to mean that the retention specified in the Minor Works terms would not apply to this sum.
iii) The second item was 'Roof works as previously quoted'. This evidently referred to the roof works as quoted on 23 November 2011 at £26,945 and extended by the further works for £8,833 and £1,000 (provisional) in the email of 6 November 2012.
iv) Provisional sums were proposed for four items, and another item was a contingency sum.
v) On present evidence it is not clear to me whether the work to windows and dummy door to front elevation (for which the sum of £21,666 had previously been mentioned) is included somewhere within GJR's list or not.
vi) This email shows that as at 4 January 2013 the defendants' intention, through GJR, to enter into a Minor Works contract, was still subsisting and was communicated to the claimants.
All party wall agreements are in place so you may now commence works in reducing levels and building up the rear extensions.
I will also be preparing the formal contracts for signature when I return using the budget figures as provisional sums against which I can write instructions. Bridget can you order 2 copies of the Minor Works JCT (as that is the tender basis).[3]
Now that the roof work is under way and most unknowns are opened up I would like to ensure the figures firm up where we can.
Mr and Mrs Harrison are in the country on the 12th April so I would like to get the formal documents all signed up at that time.
no liquidated damages and no additional conditions were put forward which would effect[4] our tendering. You had specified that retentions would apply.
We would be happy if you could provide us with the JCT Minor Works contract discussed and agreed.
I guess we should be able to use minor works. Cost high but jobs simple.
Payments should be as follows:
1 you issue me the valuation
7 days later (max) we certify payment
[The?][5] Harrisons should pay within 14 days of that certificate.
[13] I spoke with Malcolm Goldsworthy and he told us that he was not going to agree the JCT MW 2011 contract we had prepared. They wished to continue the ad hoc arrangements as before, as recorded in my email of 19 November 2013 such that Goldsworthy would provide me with a monthly valuation, 7 days later we would certify the sum due pursuant to their application and Mr and Mrs Harrison should pay the certificated sum within 14 days of the certificate.
[14] In fact, there was no express agreement of the parties to this arrangement; I was simply trying to impose some formality of arrangement in the absence of written agreed terms.
Please find attached our Certificate of Practical Completion together with the Penultimate Valuation which is for the release of half of the retention amount as set out in the JCT Minor Works Contract dated 16th January 2012.
the Minor Works Contract was only produced to his clients for the first time a couple of months ago, that his clients did not agree to sign it and insofar as he was concerned his client had quoted for the works and that was the basis of the contract, not a JCT Form.
Analysis of the secondary issue
Legal considerations relating to the contract issue
The general principles are not in doubt. Whether there is a binding contract between the parties and, if so, upon what terms depends upon what they have agreed. It depends not upon their subjective state of mind, but upon a consideration of what was communicated between them by words or conduct, and whether that leads objectively to a conclusion that they intended to create legal relations and had agreed upon all the terms which they regarded or the law requires as essential for the formation of legally binding relations. Even if certain terms of economic or other significance to the parties have not been finalised, an objective appraisal of their words and conduct may lead to the conclusion that they did not intend agreement of such terms to be a precondition to a concluded and legally binding agreement.
i) It is possible that parties may agree to be contractually bound by agreed terms even though they defer other important matters to be agreed later. [49]
ii) Contracts may come into existence, not as a result of offer and acceptance, but during and as a result of performance. [50]
Analysis of the contract issue
i) The role of contract administrator certifying payments does not necessarily depend upon Minor Works terms being agreed, as the proposal of 27 October 2011 illustrates. Architects working on relatively small projects are accustomed to fulfilling a role as contract administrator and certifier under a variety of formal or informal contracts.ii) The heading 'GJRMW' could as easily reflect GJR's expectation of what would be agreed as any belief that the Minor Works terms had been agreed in a contractually binding manner.
iii) The 5% retention reflects the Minor Works terms, but it is not an unusual amount, and other payment features are inconsistent with the Minor Works terms: in particular (a) the retention did not apply to all items, demolition being excepted, and (b) the payment terms on the basis of 14 days from certification, which run like a thread through the parties' dealings (see paragraphs 18, 30-31 and 43-44 above), are in conflict with the Minor Works terms.
iv) The reference to the MW form in the email of 16 June 2014 is a fragile basis for a definite finding, given that it erroneously referred to a contract dated 16 January 2012 (perhaps this was a mistake for 16 January 2014, but the form bearing the latter date had been expressly rejected by the claimants).
v) The reference to clause 4.8.1 in the final certificate is explained as instigated by the defendants' solicitor and falls far short of conclusive evidence of what the parties had agreed.
i) He said the parties had not agreed which edition of the Minor Works form was to be used. In the absence of contrary indication, their reference to the form would be to the edition current at the time of negotiation and contracting.ii) He said the identity of the Contractor was unclear, because as far as the evidence went 'Goldsworthy Builders' was not a legal entity. I do not consider that there was any real doubt that the contract (whatever it was) was with those persons trading as 'Goldsworthy Builders'.
Conclusions
Costs
Note 1 I cite the relevant emails without noting typographical errors in them. [Back] Note 2 Paragraph underlined in the original. [Back] Note 3 Sentence underlined and italicised in the original. [Back] Note 5 Text obscured on photocopy. [Back] Note 6 The current evidence includes the interim certificates numbered 5, 6 and 7, dated respectively 14 February 2014, 2 April 2014 and 20 May 2014. [Back] Note 7 Provision of a breakdown was subsequently promised on 8 June 2016. [Back]