QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
IOURI CHLIAIFCHTEIN |
Claimant |
|
- and - |
||
WAINBRIDGE ESTATES BELGRAVIA LIMITED |
Defendant |
____________________
Mr Tom Weekes (instructed by Child & Child Solicitors) for the Defendant
Hearing date: 14 January 2015
____________________
Crown Copyright ©
The Hon. Mr Justice Coulson:
1. INTRODUCTION
2. THE PARTY WALL AWARD
(a) "ProbingThe pile probing will be undertaken using a probing attachment mounted on a 21T excavator. The excavator will be operated by an operator competent with the use of the probe. The probing attachment will consist of a standard breaker fitted with a 3 metre long pin. Any obstructions that the pin refuses to penetrate will require removal. Probing will continue to establish the extent of the obstruction along the line of the pile wall."(b) "Obstruction Removal
… depending on the extent of the obstruction, a 900mm or 1200mm wide trench box will be placed at 90° to the boundary extending into the site. The box will be installed to the depth of the obstruction using the dig-and-push method. This process involves the ground being carefully excavated in layers of around 600mm with a box being pushed down as the excavation proceeds…"
3. THE EVENTS ON 8 DECEMBER: THE PARTIES' RESPECTIVE CASES.
4. THE EVENTS ON 8 DECEMBER: FINDINGS
"In my opinion it is clear that the contractor was not using a standard breaker for pile probing and instead was removing a piece of metal, which was probably buried in the ground.
The object shown in the photo is not the equipment described [in the method statement]...
A careful examination of the photographs reveal that the piece of metal was rusted which indicates that this piece of metal was partly buried in the ground."
5. THE CLAIMANT'S CONDUCT
(a) The claimant unsuccessfully sought judicial review of the decision granting planning permission for this major redevelopment. As a result of changes to the planning law that is now the only way in which a householder can effectively appeal against the grant of planning permission for a neighbouring property, so in my view no criticism can be made of the claimant for taking this course.(b) The claimant appealed an earlier party wall award. I am told that that appeal was allowed by consent, so plainly no criticism can be made of the claimant as a result. I also understand that there is an existing appeal against this party wall award, but that was not issued until after the injunction, so it is irrelevant for these purposes.
(c) There have been threats of litigation by the claimant on a number of occasions. I also understand that the defendant has responded to the effect that any disruption to the building works might cost the claimant up to £500,000 per week.
a) Once the claimant had noticed the digging of the hole he contacted his solicitors, they sent an email at 10:20am saying (correctly) that the defendant was in breach of the party wall award by failing to install a trench box;(b) The defendant's solicitors responded at 12:41 denying (incorrectly) that they were in breach of the method statement. There is a reference in that letter to an undertaking that the defendant would comply with the method statement. It is therefore that letter in particular on which Mr Weekes relies to say that the claimant's subsequent resort to court was unnecessary.
(c) The claimant responded to that just after 2:00pm by indicating that an appointment had been arranged with Edwards-Stuart J at 3:00pm and asking for a formal undertaking to the court. The defendant's response was again to argue that there was no breach of the party wall award. No formal undertaking to the court was offered.
(a) No 10, Grosvenor Crescent is the claimant's family home. He is entitled to take what steps he reasonably can to protect his property and his right to enjoy it with his family. Given the history that I have summarised, I can sympathise with the claimant's concerns on the morning of 8 December, when works which were plainly and obviously in breach of the party wall award were being carried out without warning or notice.(b) By contrast, the defendant's conduct on site was cavalier, again for the reasons that I have noted. The claimant was therefore entitled to be concerned, both about what was happening on site and the fact that, notwithstanding that conduct, the defendant was resolutely maintaining that it was not in breach of the party wall award.
(c) The defendant did not accept liability either on 8 December or indeed, at any time thereafter. The informal undertaking that was offered has to be seen against the background of the repeated denials of liability by the defendant. Furthermore, these denials were advanced on a number of bases, such as the ground levels, and the nature of the material in which the excavations were being carried out, which were, as I have found, obviously wrong, and which the defendant would or should have known were wrong.
(d) The fact that the claimant successfully obtained an injunction on 8 December, which was maintained on 10 December, is clearly a relevant factor. I accept Mr Weekes' point that this cannot alone be determinative, and the defendant is entitled to raise what points it wishes to on the argument about costs. But I cannot escape the fact that the claimant was successful in obtaining, and maintaining, an injunction from Edwards-Stuart J.
(e) For the reasons that I earlier indicated, I am concerned about the costs that have been incurred in relation to these proceedings since 10 December. It does seem to me that, given my findings as to what happened on 8 December, it would have been much better for the defendant to acknowledge that a mistake had been made and that the usual costs consequences flowed, so that the parties could then move on. The defendant acted unreasonably in refusing ever to accept liability.
6. OTHER MATTERS