CHANCERY DIVISION
B e f o r e :
(Sitting as a Judge of the High Court)
____________________
HISCOX SYNDICATES LTD. & Anor |
Claimant |
|
- and - |
||
THE PINNACLE LTD. & Ors |
Defendant |
____________________
Official Shorthand Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane, London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
MR. P. DARLING QC and MR P. STANSFIELD (instructed by Davies Arnold Cooper) appeared on behalf of the Defendants.
____________________
Crown Copyright ©
JUDGE HODGE QC:
"Building operations often substantially interfere with adjoining owners' enjoyment of their property because of noise, dust and perhaps vibration. Such matters in some circumstances might be held to be a nuisance and form grounds for an injunction prohibiting their continuance or an action for damages or both. If this were the result of ordinary building operations the business of life could not be carried on for old buildings could not be pulled down and new erected in their place. But the law takes a commonsense view of the matter and, if operations' such as demolition and building are reasonably carried on and all proper and reasonable steps are taken to ensure that no undue inconvenience is caused to neighbours, whether from noise, dust or other reasons, the neighbours must put up with it".
That is a citation from the judgment of Sir Wilfred Greene in the Andreae v Selfridge case.
"Those who say that their interference with the comfort of their neighbours is justified because their operations are normal and usual and conducted with proper care and skill, are under a specific duty if they wish to make good that defence to use that reasonable and proper care and skill. It is not a correct attitude to take to say, We will go on and do what we like until somebody complains'. That is not their duty to their neighbours. Their duty is to take proper precautions and to see that the nuisance is reduced to a minimum. It is no answer for them to say, But this would mean that we should have to do the work more slowly than we would like to do it or it would involve putting us to some extra expense'. All those questions are matters of commonsense and degree, and quite clearly it would be unreasonable to expect people to conduct their work so slowly or so expensively for the purpose of preventing a transient inconvenience that the cost or trouble would be prohibitive. It is all a question of fact and degree and must necessarily be so. In this case the defendant company's attitude seems to have been to go on until somebody complained and, further, that its desire to hurry its work and conduct it according to its own ideas and its own convenience was to prevail if there was a real conflict between it and the comfort of its neighbours. That, to my mind, is not carrying out the obligation of using reasonable care and skill".
I think that is probably a convenient point at which to break this judgment. I will resume at 10 past 2.
"Sometimes damages are not an adequate remedy for the claimant because of the great difficulties which will be involved in assessing them. For example, the nature of the case may involve assessing imponderables about what hypothetically would have happened in a business over a period of years. Another factor which may make damages inadequate as a remedy is when to refuse an injunction would lead to the destruction of the claimant's business".
I was also referred by Mr. Darling to observations of Sachs LJ in the case of Evans Marshall & Co. Ltd. v Bertola SA [1973] 1 WLR 349 , a decision of the Court of Appeal comprising Sachs, Edmund Davies and Cairns LJJ. At p.379H Lord Justice Sachs considered the question whether damages were an adequate remedy. He said:
"The standard question in relation to the grant of an injunction, Are damages an adequate remedy?' might perhaps, in the light of the authorities of recent years, be re-written as, Is it just, in all the circumstances, that a plaintiff should be confined to his remedy in damages?'."
Later, at p.380C, Lord Justice Sachs said this:
"The courts have repeatedly recognised there can be claims under contracts in which, as here, it is unjust to confine a plaintiff to his damages for their breach. Great difficulty in estimating these damages is one factor that can be and has been taken into account. Another factor is the creation of certain areas of damage which cannot be taken into monetary account in a common law action for breach of contract. Loss of goodwill and trade reputation are examples. Generally, indeed, the grant of injunctions in contract cases stems from such factors".
"On this day we were carrying out the same work which we had been doing during the period between 8th and 29th November 2007".
I am therefore satisfied that it is perfectly possible to carry out work of demolition to the north building adjoining the Hiscox premises if all proper and reasonable care is taken. Mr. Fancourt invites me to draw the clear inference (which I do) that work of demolition can be done properly and carefully without infringing the vibration levels set out in the standstill agreement, provided appropriate care is used in the undertaking of those demolition works.
"Forthwith to enter into a contract on the terms which represent an extension of the current standstill agreement with paragraph 7.4 replaced by the draft attached to the letter".
Mr. Darling goes on to explain the reasons why the undertaking is in that form, and does not go as far as an undertaking to comply with some or all of the terms of the standstill agreement. He explains that there may well be debate about exactly how such a wider undertaking would operate; but there would at least be the question, identified by the court, of whether the distinction between the injunctions sought and the undertaking offered was simply a matter of the burden of proof. That was said to be in no sense the intention of those giving instructions. Furthermore, the undertaking would have included obligations in relation to noise levels, which were no part of the injunction sought. As to that, I am satisfied that the undertaking could have been suitably modified so as to include reference to vibration levels only. Mr. Darling's letter continues that the respondents' position is that the necessary conditions for the injunction to be granted were not made out, and that it would be inappropriate in all the circumstances identified in argument for performance to be policed by injunctive relief or equivalent undertakings. Specifically, the concern is that the claimants would immediately commence contempt proceedings against Mr. Affara personally if the trigger levels were not achieved, on the basis of the claimants' submission that the excess itself showed breach of the obligation in clause 7.2 of the standstill agreement to use reasonable endeavours. He indicated, in the event unnecessarily, that if any further elaboration of those points was required, Mr. Stansfield would be in a position to offer it today in the absence of Mr. Darling, who is in court in Manchester.