QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, 7 Rolls Buildings London EC4A 1NL |
||
B e f o r e :
____________________
Howmet Ltd |
Claimant |
|
- and - |
||
1) Economy Devices Limited 2) Electrochemical Supplies Limited 3) MJD Supplies Limited |
Defendants |
____________________
(instructed by Reynolds Porter Chamberlain LLP) for the Claimant
Andrew Bartlett Esq, QC & Alexander Antelme Esq, QC
(instructed by Weightmans) for the First Defendant
Hearing dates: 23rd - 26th June 2014; 30th June 2014 - 2nd July 2014; and 10th July 2014
____________________
Crown Copyright ©
See: Schedule to Judgment
Mr. Justice Edwards-Stuart:
Introduction
The operation of the grain etch line ("GEL")
The background to the claim
"The current etching line is 20 years old and requires full chemical resistant Personal Protective Equipment to be worn during operation. Due to the aggressive environment causing corrosion, excessive periods of maintenance are required with increasing failure costs.
The corrosion is such that there is the risk of a potential collapse of the tanks which would lead to an EHS incident. This could also result in the loss of at least 4 weeks production, due to manufacturing lead time. The loss in sales if such an incident was to occur would be approximately $10M."
The evidence at the trial
The operation of the thermolevel
The events leading up to the fire
The small fire on 12 December 2006
"The probe that I changed was on the ferric tank on 12/1/07"
The heater burnout and possible small fire at the end of January 2007
" | Chris told me that he forgot to turn off the heater at control panel which shouldn't make difference because they are fitted with level probes but the heater still burnt. He told me there had been smoke from heater. Nobody else there. No supervisor around Chris came and saw me. Not logged on mtce system. Heaters not stock item, went to see Damon. Talked to Damon about it. Found a heater under P Reed's desk. |
Not on 29/30 Jan actually on 12/1/07[7] | Looked at level probe, changed level probe for one under P Reed's desk. But after I changed the probe the tank would[n't] heat up at all. I went off to do something else. Probe measures temp and level. I'd not come across that type of sensor before." |
12/1/07 | Probe I fitted wasn't in a packet, not sure whether it was new. Temperature display wasn't reading correctly. Didn't make any adjustments when fitted probe." |
"Low-level alarm would come on when you drained tank but possibly not if heater turned off - not sure."
"6 pm accidentally switched off hot ferric heater.
Opened valve on water tank and tank started draining after 5 minutes.
Washing castings near the anodic panel.
Saw smoke from hot water tank. Flames ~ 8" above level of tank.
Both heaters burnt out.
Reported to?
Might have put a ticket in
went to find Andy Dart (Darke), electrician and he came and fitted one heater
Think Andy might have reported it.
After Jan switched off at both plugs and panel.
Told Graham Moxey.
Can't remember speaking to either supervisor."
"Heater burnt out, couple of weeks before main fire.
…
The heaters that were taken out the centre core section was blackened not just the top section of the heater.
Replaced one heater but took two out. Threw old heaters away. Both heaters burnt.
Heaters sat side by side in end of tank. Two slots in plastic at end of tank."
"I explained to Damon that the heater had burnt out and this seemed similar to fire on old grain etch."
Whilst in this version Mr. Darke appears to be making a comparison with the fire on the grain etch line that occurred in the 1990s, he still refers to the heater as having "burnt out".
"When A Dark came to see me he told me the heater had burnt out but for an electrician to describe something as burnt out means that it has failed not that it has caught fire. I interpreted this to mean that the heater had failed but I wasn't aware that there had been a fire.
I didn't follow this event up."
"10) new grain etch - 2x heaters replaced hot water tank as old were down to earth and taking out rcd. completed."[8]
"9) grain etch hot water tank - heater replaced. completed."
"GRAIN ETCH HOT WATER TANK HEATERS U/S REPLACED ONLY ONE HEATER FOUND NEEDS SOME MORE PRONTO. INFO"
"Aware of two fires on plant After draining tank fires have started within 5 mins
Old grain etch line automatic switch
12/12 1st fire David Leeming (Lemon) shell l each
end Jan 2nd fire Chris Palfrey Sunday pm - DL noticed hot water switched off
Procedures say to re-fill tank and switch heater back on, but more sensible to have tank drained with heater switched off
When tanks drained low level alarms come on, but on hot water tank low level alarm hasn't worked recently.
Low level alarms on other tanks don't come on because heaters/agitators switched off when tanks drained"
(My emphasis)
"A. … that is what my statement says at that time, yes.
Q. So that's how it looks, isn't it?
A. Yes.
Q. That's probably right?
A. I would think so, yes.
Q. That reference to 'changing something', they were looking to replace level probe, could mean they were going to fit a different kind of level device?
A. I would think so, yes."
The involvement of Mr. Hunt
"The hot water tank will not turn off when the water level is low, this has already caused a fire and could happen again. Grain Etch."
Short Text | Long Text Indicator |
Bolt down barrier by G/E shower | |
Hot Water tank | X |
Desmut/Ferric cutting out Grain Act | |
Hot water element needs replacing | |
Cold water tank does not fill in auto | X |
Cold water tank no 6 | X |
"Bruce Hunt, continuous improvements mgr (manager) post cast
Ian McGill, manufacturing engineer was on a Kaizen event, asked me to put a ticket in because tanks weren't heating up quick enough.
Second Kaizen:
Ian McGill - manufacturing engineer
Graham Moxey - operator
Ian Harris - manufacturing engineer Said that heater element wasn't very Good.
Ticket 02.02.07
I initiated first Kaizen event.
2 day - 30.11.06 - Chris Palfrey
01.12.06 - Martin Leaman
Second event - 1&2/02/07."
A "Kaizen event" is an exercise involving the analysis of a particular activity and seeing how it can be improved[9]. The first Kaizen event recorded here took place before the fire on 12 December 2006. The second occurred just after the incident on 29 January 2007.
The witnesses
Mr. Damon Gill
"Q. Whatever the details were, this incident demonstrated to you and to everyone who received Mr. Hughes' e-mail that the Therm-o-level wasn't a fail-safe device, didn't it? In other words, when it failed, it didn't fail in such a way that the heater went to a safe condition of being on?
A. Well, yes, but our understanding was that it should be a fail-safe device. It should fail - if the plug had corroded, the heater should stop working, you know.
Q. Yes, if the plug corroded so that a connection was broken, you're saying with a fail-safe device, that would mean the heater would stop working?
A. Yes.
Q. What this incident showed you was that the heater didn't stop working?
A. Our understanding was that it should be a fail-safe device. It became apparent that it probably had issues around its integrity as a fail-safe device.
Q. So it became apparent that it wasn't?
A. Well, there were concerns about its integrity as a fail-safe device.
Q. Well, it was clear to you -
A. Our confidence in it as a fail-safe device.
Q. It was clear to you it hadn't failed safe on that occasion?
A. Yes, it was clear then."
Mr. Simon Farrimond
"Q. So, putting those two together, there was an obvious risk of a fire?
A. Well, that's where we disagree, because at the time I did not believe that there was a risk of a fire. Had we believed there was, we wouldn't have released the equipment.
Q. Well, did you not think there was a chance that the operators would not follow their procedures?
A. No.
Q. You thought they would?
A. Yes.
Q. Exactly, yes.
A. Because we had an incident, so they would follow them.
Q. So you believed there wasn't a risk of fire because you believed that the operators would follow their procedures?
A. And we had an engineer working on the problem, yes.
Q. Well, while the engineer was working on the problem, you didn't have a solution, so on the electrical/mechanical side, that was still under investigation, but I understand that you decided that the operators carrying out the procedures properly was sufficient to guard against fire?
A. Correct.
Q. That remained the position until the major fire?
A. Correct."
"A. ... I can only keep repeating to you that the safety culture in the business is extreme, and I can give you examples where I have shut equipment down, the alloy furnaces at the alloy plant were shut. Last year we had an incident at the Hampton plant where four of the inspection lines, I shut those down because we had an accident on one of them and so I shut all four of them down, so we could be sure that we didn't have risk on the other three. I can only say to you had we been aware that there was a risk, it would not have been ignored. It would have been dealt with and shutting the line down, we have a good history of doing that. We're not afraid to do that, even at the cost of manufacturing."
Mr. Roger Gildersleve
"Rod called Roger Gildersleve who attended plant.
Roger and Peter Reed made an investigation into the event which appeared to have happened partly due to electrical/mechanical failure.
They may also be partly due to operator procedural/training issues.
As we now need to establish root causes and I would suggest the following ownership.
Establishing any electrical/mechanical failures R Gildersleve/P Reed
Establishing any operator training/compliance issues D Vayle/N Cartwright.
You may wish to formally review and discuss the incident and set the timescales for responses, actions and any notifications (major incident) ?? required."
"On 12 Dec I was on my way home when I received a phone call. Rod Turner rang me and told me that there had been a minor fire in the grain etch area. I came into work. I was surprised. The heaters on the hot water tank had caused a problem. I didn't look at the heaters, made sure everything was safe, left relevant people to isolate cause and fix problem. At this time all production is going through this piece of equipment. The old line had been shut down.
I'm not sure who was working on it from a mtce [maintenance] point but PR was on shift and was dealing with it.
I spoke to PR before he finished his shift at 10 pm. The original assumption was it was a level probe problem. PR investigated and found that the probe was operating satisfactorily but he discovered corrosion on the plug and socket. He stripped it down and cleaned it up and re-soldered some of the pins and checked all the other plugs and sockets and then wrapped all the plugs and sockets with heatshrink. This was all done that evening. There was no further formal investigation by plant engineering.
I was satisfied that the problem had been found. I didn't arrange for any additional measures to be put in place."
Mr. Gildersleve confirmed that this was a reliable account of what had happened, and I accept it.
"A. ... He [Mr. Reed] would be working through to 10 o'clock because of another project that he was on so he took it on to actually carry out the investigation within the equipment and to find out the cause of the problem within the hot water tank area and, if possible, put a fix in place.
I spoke to Peter later in the evening and he told me what he had done, which was he had carried out a systematic, in my opinion, a systematic diagnosis where he had moved the probe into another tank to ensure that it was functioning correctly, which it was, and then he looked further and found that there was a corrosion situation in the plug and socket assembly which connects the probe through the thermolevel control unit."
"I was firmly of the belief, as were various other people, including, I believe, the health and safety manager, that we had actually found a root cause of the problem and had put something in place to avoid a repercussion of the incident."
I find that it was understandable of Mr. Gildersleve to have left the site that evening under the impression that the probe was functioning correctly and that the problem lay with the connection in the lead between the probe and its control box. (For the reasons given later in this judgment, I find that this connection had been made because the original lead was not long enough.) However, in cross-examination Mr. Gildersleve did accept that, with hindsight, he should have appreciated at the time that the thermolevel was not a failsafe device (Day 3/155).
Mr. Paul Webber
"My understanding was that the fire was caused because the Therm-o-level had failed to operate. Peter Reed had investigated the cause of the fire and worked out what the problem was with the Therm-o-level. No action was required by the Maintenance Team although of course we helped Peter out where we could."
A little later he said that the plugs on the thermolevel had to be changed a number of times because they kept corroding.
"It's possible. Andy is the sort of guy who makes it his business to know about most things. I would be surprised, but things pass by. It's a busy factory so it's possible he didn't get trained. I don't know."
Mr. Chris Hughes
"Gentlemen,
As you will be aware, last night there was a fire in one of the grain etch tanks.
Thanks to the prompt action from Danny Vale, a plant evacuation and a visit from the fire services was avoided.
Rapid responses were forthcoming from Plant Engineering and Maintenance.
An overview of the events are detailed below.
At 17:46 I received a call on the mobile from Danny Vayle Pre finishing supervisor saying that there was a fire on the grain etch line.
I made my way to the line calling in on Richard Easterbrook in the Foundry asking him to contact Maintenance as we had a fire on the grain etch line.
When I arrived at the line Danny Vayle and the operator (D Lemon) had extinguished the fire which had taken hold in one of the water tanks being emptied.
The fire itself being contained in the tank and emanating from the tank heaters.
When I arrived the operator (D Lemon) stated that he thought the tanks had a "level cut out" on which is why he did not turn off the heater prior to empting [sic] the tank.
(As I understand it the tank is fitted with a 'level cut out' but the probe had failed.
According to the procedure the operator should also have turned off the heaters prior to emptying the tank
The black file containing the procedure was not available on the line but was later retrieved from Plant engineering)
Maintenance (M Pardey and M Holmes) arrived shortly afterwards armed with fire extinguishers.
I requested the operator to turn off the power to the line which he did.
The fire was confirmed to be out and after an inspection of the area and tank with Maintenance (Mark Pardey) it was decided to leave the tank and heaters to cool and allow any fumes to dissipate.
I then called Rod Turner to advise him of the incident.
Rod called Roger Gildersleve who attended plant.
Roger and Peter Reed made an investigation into the event which appeared to have happened partly due to electrical/mechanical failure.
They may also be partly due to operator procedural/training issues.
As we now need to establish root causes and I would suggest the following ownership.
Establishing any electrical/mechanical failures R Gildersleve/P Reed
Establishing any operator training/compliance issues D Vayle/N Cartwright.
You may wish to formally review and discuss the incident and set timescales for responses, actions and any notifications (major incident)?? required."
Mr. Rodney Turner
"A. No, I am not saying it wouldn't have struck me as important, but my perception of risk might have been different to seeing it all in front of me now, rather than bits coming in on a daily basis or weekly basis."
The experts
Mr. Jonathan Boyle
"Q. ... We don't see any reference in your notes to the use of adhesive heat shrink, do we?
A. I don't know.
Q. Well, there are two kinds, aren't there? There are two kinds of heat shrink, one of which has adhesive and one doesn't?
A. Yes.
Q. And one is more expensive than the other?
A. Yes. Probably. I don't know.
Q. When you were telling his Lordship about what you understood Mr. Reed to have done, you simply assumed that he had used the adhesive kind?
A. I did assume, yes.
Q. You had no basis for that assumption, did you?
A. No.
Q. If you had no basis for that assumption, why did you make it?
A. Because I think it's likely that Mr. Reed being -- he came across as a very competent technician, that he would have used adhesive heat shrink. It's very rare that you would use any other kind of heat shrink."
"A. ... You make the solder connection and then you slide the tube over the whole lot, and then you use a heat source to just warm it up.
MR. JUSTICE EDWARDS-STUART: What, a hairdryer, as it were?
A. Yes, and the tube shrinks and it has adhesive on the inside of the tube usually.
MR. JUSTICE EDWARDS-STUART: Yes.
A. So that it shrinks tightly around the cable and it also sticks to the cable.
MR. JUSTICE EDWARDS-STUART: Yes, I see.
A. So, done correctly, it's a very robust connection.
MR. BARTLETT: I think it follows that you agree with the next sentence, which is that if these were insufficient, that is if the soldering wasn't done well, or if the use of the shrink wrap wasn't done well, then the connection would have remained susceptible to damage caused by a humid and/or corrosive atmosphere?
A. Well, there is quite a lot of ifs there.
Q. Yes, there are. They are quite deliberate, because I think the principle is clear, isn't it?
A. Well --
Q. If it wasn't done well.
A. Mr. Reed was an experienced sort of technician working with Howmet. He was familiar with the environment in which the equipment had to operate. I would expect him to be able to do a joint and heat shrink it in a manner which made it a robust connection.
MR. JUSTICE EDWARDS-STUART: Sorry, do you want to just pause for a moment. Okay. Carry on.
A. My Lord, I would expect Mr. Reed to be in a good position to know and to have completed a good joint on that cable.
MR. BARTLETT: You might but we might not, because he's not a witness. So could you please answer the question instead, which is on a hypothetical basis because he's not here as a witness, which was if he didn't do the soldering well or if he didn't do the shrink wrap well, an in-line soldered connection could have been susceptible to damage caused by a humid or corrosive atmosphere in the grain etch line?
A. Yes.
Q. Thank you. You were not trying to argue the claimant's case, were you, when you talked about how well you think Mr. Reed would have done it?
A. I don't think so, no. I was just merely -- I have met Mr. Reed. He came across as a competent technician.
Q. Moving on to the next point, it's right, isn't it, that solder joints are not flexible so strain on or flexing of a cable can damage a solder joint?
A. The actual soldered joint where the action between the two conductors is not flexible, no. So you get a small region which is inflexible.
Q. So strain on or flexing of a cable can damage a soldered joint?
A. Well, it can, but if you have -- heat shrink provides a robust sort of mechanical basis for that connection. So you are not relying on -- the solder joint effectively provides some of the mechanical strength, but primarily it is for the electrical strength. So the heat shrink would affect -- because it's got adhesive, if that's the type of heat shrink he used, which it almost certainly was, the adhesive and the heat shrink provides the mechanical strength of the joint.
Q. So your answer is: yes but remember that heat shrink helps with the mechanical strength?
A. Yes."
Mr. Stephen Braund
Mr. Richard Ward
"... I think that the concept of failure to safety is one that in my experience is, I regret to say, not fully understood, even by some chartered engineers. I think that an ordinary person reading the Therm-o-level document might be led to the expectation that in our terminology this was a fail-safe device when in fact it isn't."
The fire on the old grain etch line
The extent to which employees of Howmet knew about the incident on 29 January 2007
"A. The way this incident came out was quite interesting because most people in the first instance when I arrived at Howmet were not aware of it and it was only when I think Mr. Moxey or some gentleman mentioned something and said, oh, there was another incident, so I think this is the context of the incident and was kept quite closely between Mr. Darke and Mr. Palfrey.
Q. You do understand, don't you, Mr. Boyle, just to be clear that if in fact the evidence shows that virtually everybody was aware of it, it follows that the wool has been pulled over your eyes, doesn't it? Do you see that?
A. I don't know what the evidence - what other evidence you have seen."
The testing of thermolevels by the experts
The joint statement of the electrical experts
"In our view, there ought to have been a robust and reliable automatic 'fail safe' device in the GEL to provide protection against low liquid level and overheating of the process heaters. Thermolevel did not provide robust and reliable fail safe protection." (Paragraph 2.12)
"The fact that an item of equipment has not been designed or shown (e.g. by test or certification) to comply with relevant Technical Standards does not mean that it would not meet those standards. However, where there is no compliance with relevant standards there would be an onus on the manufacturer to show by other means that the equipment is safe." (Paragraph 2.14)
"We consider that Thermolevel was unsuitable for use as a low liquid level sensing device in a safety-related application, because it had no safety approvals or CE marking, it was unreliable and it had uncertain operating characteristics." (Paragraph 2.22)
"In relation to adjustment of the 'sensitivity' control, Mr. Braund and Dr Lipczynsky consider that the precise setting is critical to the operation of the low level sensing function ... [EDL's] instructions did not indicate or state how critical the adjustment actually was." (Paragraph 2.27)
"The potential effect of mal-adjustment of the 'sensitivity' control would have been for the heaters to remain on warm, irrespective of the liquid level." (Paragraph 2.28)
"From a theoretical point of view, we would expect Thermolevel to have suffered from a degree of drift in operating characteristics eg. as a result of short-term thermal effects and long-term drift (ageing). This would have affected the level sensing function, but any such problems should have been insignificant if Thermolevel had been suitably designed. It would have been necessary to consider these effects in the design, commissioning and use of the GEL." (Paragraph 2.29)
"In our view, the literature published by ED for Thermolevel was inadequate as a reference for equipment selection and system design purposes in a safety-related application. The documentation supplied by ECS in relation to Thermolevel did not address any of those inadequacies." (Paragraph 2.37)
"We agree that MJD and ECS should have considered the possibility that Thermolevel might be unreliable and should have sought assurance from the manufacturer before using it in a safety-related application." (Paragraph 2.38)
The material provided by EDL
"… will automatically switch heater off and flash the display when the probe is out of liquid. Prevents heater burn-outs, fires or solution boiling, caused by evaporation, leaks or withdrawing probe".
It gave the temperature range as 20-99°C.
"... included in the device is a safety low level cut out which will switch off the heater whatever the setting should the liquid fall below the probe.
...
The probe must be wired correctly to avoid damage. It should be positioned in the tank near to the heater to avoid thermal black overshoot.
It should be mounted completely surrounded by liquid ...
... The level cut out operates with the bottom 100 mm of the probe exposed. The probe should not be continually immersed above the red level label otherwise the probe/cable seal can eventually break down under chemical attack. If rise and fall of the liquid due to work loading is excessive or surface agitation causes splashing of the chemical onto the seal/cable then longer or right angle probes should be considered.
The unit leaves the works preset for safety cutout to operate on water. However other liquids may require sensor adjustment as follows.
Remove the cover by undoing the four plastic screws. Locate the blue preset situated in the top right corner of the main PCB turning this preset clockwise will increase the cut out sensitivity. With the probe immersed the display should remain constant when the probe is withdrawn from the solution the display should flash indicating the heater is switched off.
MAINTENANCE
The only regular maintenance required is with the probe. Test the level cut out monthly by removing from the liquid. This should make the display flash and turn off the heater load."
i) It was a safety device designed to switch off the heater when the liquid fell below a particular level.
ii) It would therefore prevent heater burn-outs or fires caused by evaporation, leaks or withdrawing the probe.
iii) The thermolevel left the factory preset for operation in water.
iv) If the thermolevel was not immersed in liquid it would turn off the heater and make the display flash.
Relevant guidance and Codes of Practice
"The high incidence of fires in plating and anodising shops caused by inadequate design and poor maintenance of electrical process heating systems in open tanks needs to be controlled. Fires are especially prevalent where plastic materials are used as a material of construction for tanks, fume exhaust hoods, exhaust fans and ducting. The primary cause is the loss of process liquid level through leakage or evaporation. This lowers the solution level, exposing the hot surfaces of the immersion heater and allowing high temperatures to develop. This is sufficient to ignite the tank walls and fire then spreads to the fume extraction system. Such fires commonly occur during night time and weekends when production operations have ceased.
... A typical process tank layout is shown in figure 1."
"2.8 Preferably the heater should have a built-in device to detect overtemperature of the heater."
and:
"5.1 It is necessary to ensure that the process liquid level does not fall and thus expose the hot zone of the heater. This can be achieved through the installation of an automated device such as a float valve which admits water and thus maintains liquid level in the event of uncontrolled evaporation, tank leakage, maloperation or other cause.
5.2 In the event that the level maintaining device becomes inoperative, a low-level sensor positioned above the heater hot zone will automatically disconnect the power supply to the heater and initiate a visual and audible alarm.
5.3 Preferably, the heater should have a built-in over-temperature device incorporated into the low level sensor control circuit as a further safeguard, in the event that the tank low level sensor malfunctions."
i) automatic fluid make up to maintain the process liquid level
ii) a low level cut-out in the event of catastrophic loss of process fluid
iii) built in overtemperature device for the heater
iv) construction of process tanks from fire retardant polypropylene
This section then referred the reader for further guidance to the BSTSA/LPC Code of Practice, to which I have already referred. There is no suggestion that this guidance was intended to supersede the Code of Practice.
"To an extent I agree with that but it did state that it was designed for use in electroplating shops and similar, which in my view is precisely the application for which it was used. Well actually not quite precisely, but very similar."
Mr. Ward's evidence was to similar effect: see paragraph 148 above.
Were the thermolevels designed and manufactured with reasonable care?
The scope of the duty of care and the possibility of intermediate examination
"A manufacturer of products, which he sells in such a form as to show that he intends them to reach the ultimate consumer in the form in which they left him with no reasonable possibility of intermediate examination, and with the knowledge that the absence of reasonable care in the preparation or putting up of the products will result in an injury to the consumer's life or property, owes a duty to the consumer to take that reasonable care."
"Q. The next proposition: "Overall Economy Devices' literature was inadequate as a reference for equipment selection and system design in a safety related application since it did not give detailed information about performance, safety or reliability as would be required by anyone intending to select and rely upon the equipment." Do you agree?
A. I do agree.
Q. And the above overall inadequacy that refers to that previous proposition [sic] should have been obvious to an engineer who considered the literature since there was nothing in the literature to suggest that the Therm-o-level would operate to any particular standard of reliability or would fail safe. Do you agree?
A. It should have been obvious to an experienced engineer who was familiar with the potential problems that can occur.
Q. So applying that to this case, certainly it should have been obvious to ECS given the role that they were undertaking?
A. Well, certainly the question of whether the equipment was adequate should have been apparent but I think it is reasonable to assume or reasonable for a designer to assume that a piece of equipment that is placed on the market for a particular purpose is going to be suitable and designed with all the necessary safety features without it having to say so explicitly."
"... equally the absence of a CE mark need not immediately raise alarm bells because there is an assumption that every electrical product sold in the UK has been checked for safety and complies with the relevant standard. There should be a CE mark, but even if there is not I think it would be reasonable for anyone to assume that a product put on the market by a reputable company would indeed comply."
Breach of statutory duty
"'safe', in relation to any goods, means such that there is no risk, or no risk apart from one reduced to a minimum, that any of the following will (whether immediately or after a definite or indefinite period) cause the death of, or any personal injury to, any person whatsoever, that is to say-
(a) the goods;
(b) the keeping, use or consumption of the goods;
...
(e) reliance on the accuracy of any measurement, calculation or other reading made by or by means of the goods,
and 'unsafe' shall be construed accordingly."
"… to ensure that electrical equipment may be placed on the market only if, having been constructed in accordance with good engineering practice in safety matters in force in the Community, it does not endanger the safety of persons, domestic animals or property when properly installed and maintained and used in applications for which it was made."
"(a) that persons and domestic animals are adequately protected against the danger of physical injury or other harm which might be caused by direct or indirect contact;
(b) that temperatures, arcs or radiation which would cause a danger, are not produced;
(c) that persons, domestic animals and property are adequately protected against non-electrical dangers caused by the electrical equipment which are revealed by experience;
(d) that the insulation must be suitable for foreseeable conditions."
The circumstances of the fire on 12 February 2007
What actually caused the fire on 12 February 2007?
The claim in negligence
7.4 It has not been possible to identify with certainty why the Therm-o-level did not prevent the heater from being energised on this occasion but the two most likely explanations are as follows -
• The Therm-o-level malfunctioned possibly because either the sensitivity control was incorrectly set or the design of the instrument resulted in the operating parameters changing (drifting) whilst in service.
• There was a fault with the Therm-o-level.
7.5 I have not established the relative likelihood of these explanations, however, my tests have shown that the Therm-o-level system is prone to malfunction and would not reliably prevent the heaters from being energised when there was insufficient water in the tank, particularly at elevated water temperatures. Similarly, the design of the Therm-o-level system is such that should a fault or poor connection develop on one of the wires connected between the probe and the controller, the device does not 'fail safe' and does not prevent the heaters from being energised. In my view these features indicate that this probe was unsuitable for reliably preventing the heaters from being energised when there was insufficient water in the tank …. It is my opinion that the most probable cause of the fire in the hot water tank of the GEL was a failure of the Therm-o-level to prevent the heaters from being energised when there was insufficient water in the tank.
7.6 I consider it unlikely that the heaters were energised because the Therm-o-level probe was not correctly positioned or secured within the hot water tank."
The claim for breach of statutory duty
"67. Whatever be the correct approach, I have no doubt that it is critical to a proper analysis to determine whether the knowledge alleged to break the chain of causation or to give rise to a duty to mitigate can properly be attributed to the claimant party. The basis for denying recovery on the first footing is that continuing to operate the production line in the knowledge that the fire detection or suppression system is defective is a voluntary act which can be held to be the cause of the subsequent damage – see per Purchas LJ in Schering at pages 4, 5 and 9 of the transcript of his judgment. On the second basis, the analysis is that it is reasonable to expect the claimant party to take appropriate steps to minimise the consequences of the breach-caused defect of which he has become aware – see in particular per Hobhouse LJ in the County case at pages 858/9. On both bases the act can only be said to be voluntary or the duty to mitigate to arise if the relevant knowledge comes to the attention of the claimant party. The identification of the natural person whose knowledge is appropriate for this purpose will depend upon questions of delegation of duty within the organisation and, in the present context, the system of supervision which Cadbury might reasonably have been expected to have in place. The problem was addressed in these terms in the Schering case by Hobhouse J at page 22 of the transcript of his judgment and by Purchas LJ at page 4 of his judgment in the Court of Appeal.
68. The judge here refers at paragraph 554 of his judgment to the Cadbury management at Monkhill and says of it that it would have reacted very differently to the June 2004 fire had it thought that ADT had given a guarantee or warranty as to the efficacy of the system. However, with respect to the judge, he had made no finding upon the basis of which knowledge of the June 2004 fire can properly be attributed to the Cadbury management. That is unsurprising, given that the point was neither pleaded nor explored at trial."
"The implied warranty of fitness for a particular purpose relates to the goods at the time of delivery under the contract of sale in the state in which they were delivered. I do not doubt that it is a continuing warranty that the goods will continue to be fit for that purpose for a reasonable time after delivery, so long as they remain in the same apparent state as that in which they were delivered, apart from normal wear and tear. What is a reasonable time will depend upon the nature of the goods but I would accept that in the case of the coupling the warranty was still continuing up to the date, some three to six months before the accident, when it first became known to the farmer that the handle of the locking mechanism was missing. Up to that time the farmer would have had a right to rely on the dealers' warranty as excusing him from making his own examination of the coupling to see if it were safe; but if the accident had happened before then, the farmer would not have been held to have been guilty of any negligence to the plaintiff. After it had become apparent to the farmer that the locking mechanism of the coupling was broken, and consequently that it was no longer in the same state as when it was delivered, the only implied warranty which could justify his failure to take the precaution either to get it mended or at least find out whether it was safe to continue to use it in that condition, would be a warranty that the coupling could continue to be safely used to tow a trailer on a public highway."
(My emphasis)
i) Mr. Moxey must have known that, at the time of the fire on 12 February 2007, that the low level alarm had not "worked recently" on the hot water tank, because that is what he told Mr. Boyle after the fire.
ii) On the basis of the evidence of Mr. Boyle that I have already mentioned, this must have referred to the operation of the thermolevel.
iii) Mr. Reed was told about the incident on 29 January 2007, probably very shortly after it happened.
iv) It is more likely than not that Mr. Reed also knew, or at least strongly suspected, that the thermolevel was not working at the time of the fire and that it had not been working properly for several days.
v) The evidence of Mr. Gill in his witness statement that Mr. Reed was concerned at that stage that the thermolevel in the hot water tank was not "… operating correctly as it kept failing" is consistent with this.
vi) The fact that Mr. Reed ordered a float switch on 1 February 2007 tends to confirm that he knew or suspected that the thermolevel in the hot water tank was not working properly.
vii) Mr. Reed's knowledge that the thermolevel was not or might not be working properly in February 2007 is knowledge that is to be attributed to Howmet. But, irrespective of this, since Mr. Gill also knew this before the fire his knowledge is plainly that of Howmet.
viii) The evidence shows that, following the fire on 12 December 2006, Howmet relied on its operators to follow instructions about switching off the heaters whenever tanks were drained. I accept that Howmet did not do this because it knew that the thermolevels were unreliable, but rather because it knew that there had been an occasion on which a thermolevel had not operated as it should have done when in an empty tank (probably as a result of a corroded connection). However, this does suggest that Howmet - through Mr. Reed and Mr. Gill - might have been prepared to accept operator vigilance as a suitable safeguard during a short period in February 2007 before a replacement low level cut-out device could be obtained and fitted in the hot water tank.
Break in the chain of causation
"44. Secondly, in order to comprise a novus actus interveniens, so breaking the chain of causation, the conduct of the claimant 'must constitute an event of such impact that it 'obliterates' the wrongdoing…' of the defendant: Clerk & Lindsell on Torts (19th ed.), at para. 2-78. The same test applies in contract. For there to be a break in the chain of causation, the true cause of the loss must be the conduct of the claimant rather than the breach of contract on the part of the defendant; if the breach of contract by the defendant and the claimant's subsequent conduct are concurrent causes, it must be unlikely that the chain of causation will be broken. In circumstances where the defendant's breach of contract remains an effective cause of the loss, at least ordinarily, the chain of causation will not be broken: County Ltd v Girozentrale [1996] 3 All ER 834, at p. 849 b-c, per Beldam LJ and at pp. 857 f-g and 858 b-c, per Hobhouse LJ (as he then was) ... .
45. Thirdly, it is difficult to conceive that anything less than unreasonable conduct on the part of the claimant would be capable of breaking the chain of causation. It is, however, also plain that mere unreasonable conduct on a claimant's part will not necessarily do so – for example where the defendant's breach remains an effective cause of the loss, albeit in combination with the claimant's failure to take reasonable precautions in its own interest: see, for example, County Ltd v Girozentrale, per Beldam LJ (loc cit). By its nature, reckless conduct by the claimant would or would ordinarily break the chain of causation, though there is no rule of law that only recklessness on the part of the claimant will do so: Lambert v Lewis [1982] AC 225, per Roskill LJ (as he then was) in the Court of Appeal, at p.252; County Ltd v Girozentrale (supra), per Hobhouse LJ at p. 857, more conveniently discussed below, when dealing with the claimant's knowledge or lack of it.
46. Fourthly, the claimant's state of knowledge at the time of and following the defendant's breach of contract is likely to be a factor of very great significance. For the chain of causation to be broken, the claimant need not have knowledge of the legal niceties of the breach of contract; nor, as it seems to me, will the chain of causation only be broken if the claimant has actual knowledge that a breach of contract has occurred – otherwise there would be a premium on ignorance. However, the more the claimant has actual knowledge of the breach, of the dangerousness of the situation which has thus arisen and of the need to take appropriate remedial measures, the greater the likelihood that the chain of causation will be broken. Conversely, the less the claimant knows the more likely it is that only recklessness will suffice to break the chain of causation."
i) Howmet's management thought that the fire in December 2006 was caused by a corroded connection and that the probe itself was functioning satisfactorily. This appears to have been Mr. Reed's conclusion as understood by Mr. Gildersleve.
ii) There is no mention in the contemporaneous documents or the evidence of any incident in which a probe failed to cut the supply to the heater when the liquid in a tank fell below the set level until the incident of 29 January 2007.
iii) Following that incident, known to Howmet's management through Mr. Reed and, little later, Mr. Gill also, Howmet decided to install a float switch as an added level of protection.
iv) Howmet appears to have acted promptly in taking this decision because a float switch was ordered on 1 February 2007 with a request for next day delivery.
v) In the meantime Howmet must have been relying on operator vigilance, together with a procedure for leaving the hot water tank drained over the weekend (which is how it had been left until Mr. Woodland switched it on).
Contributory negligence
Conclusions
Paragraph | Finding |
17, 89 | Rejection of the criticisms of Howmet's continued use of the old grain etch line prior to the installation of the new GEL. |
29 | Howmet's own employees played no part in the decision to purchase EDL's thermolevels, but relied on ECS to choose them. |
33 | Mr Reed prepared the procedure for emptying the hot water tank on the GEL which required the operator to ensure that the heater was switched off before draining the tank. |
52 | Mr Darke probably told Mr Gill shortly after the incident on 29 January 2007 that the heater had "burnt out". |
73 | When he entered the Long Text into the SAP system on 2 February 2007 Mr Hunt was unaware of one or other of the two incidents that occurred on 12 December 2006 and 29/30 January 2007, but on the balance of probability he was aware of the first and but not of the second. |
74 | When Mr Hunt was interviewed by Mr Boyle on 16 May 2007 he did not mention the fire risk presented by the hot water tank because, on the balance of probability, he had been reassured that the risk had been addressed. |
122 | Findings as to the sequence of events 12 December 2006 and Howmet's understanding of the root cause of that incident. |
155 | There was no generally accepted understanding amongst Howmet's management of the cause of the fire in the mid 1990s. |
156 | Any knowledge of Mr Lemon as to the cause of that fire is not to be attributed to Howmet as a company. |
159 | There was no general conspiracy within Howmet to pull the wool over Mr Boyle's eyes about the incident on 29 January 2007. |
160 & 262 | It is very likely that Mr Reed knew about the incident on 29 January 2007. |
171 | The descriptions of the tests carried out by the experts and the results, as set out at paragraphs 161-170, were accurate. |
173 | The thermolevels produced by EDL were both unreliable and unpredictable in operation. This was not acceptable in a safety device. Further, the difficulty of setting the potentiometer made the thermolevel unsuitable as a safety device. |
177 | Conclusions as to what the reader would understand about the thermolevel from EDL's literature. |
179 | The instructions provided by EDL fell far short of being a satisfactory guide on how to set the "sensitivity" control. The absence of any warning that it was such that, if turned too far in one direction, it would prevent the probe from de-energising the heater irrespective of the level of liquid in the tank was a serious omission. |
180 | If there was a failure by ECS or MJD to make further enquiries of EDL about the operation of the thermolevel, this did not break the chain of causation between the negligent manufacture or supply of the thermolevel and the occurrence of the fire. |
186, 189 & 206 | The configuration in place on the hot water tank in the GEL at the time of the fire on 12 February 2007 was effectively the same as that shown in figure 1 in the Code of Practice. The installation in the hot water tank complied with the Code (189). |
191 | A built in over-temperature device for the heater was not a mandatory requirement of the Code. |
194 | The process carried on by Howmet in the GEL involved very similar plant and equipment to that which would be found in a typical plating shop. |
195 | The use to which the thermolevels were put at Howmet's factory was well within the contemplation of a manufacturer in the position of EDL. |
196 | At face value the thermolevel supplied by EDL appeared to be a reliable device that would cut the supply to the heater in the event that the level of liquid in the tank fell below the point at which the heating element was no longer immersed in liquid. It was therefore not negligent to design and install the GEL without requiring the heaters to have built in over-temperature devices. |
197 | The thermolevel was not capable of detecting whether its probe was in or out of liquid so as to operate an on/off switch accordingly, or at least not reliably. |
200 | EDL should have had in place a proper system of testing a reasonable proportion of the thermolevels that it manufactured: its failure to do so amounted to a want of proper care. |
201 | The "sensitivity" control was badly designed because it was difficult to set properly and the existence of voltage drift indicates a want of proper care in the design of the thermolevels. |
202 | The instructions provided by EDL for the operation of the thermolevels were manifestly unsatisfactory, particularly in that they failed to warn the user that the thermolevel might not work as a level sensor if the sensitivity control was not correctly adjusted, and that this demonstrated a lack of reasonable care by EDL. |
203 | If the cause of the fire on 12 February 2007 was a defect in the thermolevel and if, as a matter of law, EDL owed a duty of care to Howmet to take reasonable care to prevent a thermolevel causing damage to Howmet's property, then EDL was in breach of that duty because, as a matter of probability, the fire was not caused by a one-off defect in a thermolevel (see paragraph 204). |
205 | The thermolevel was not a safe device for use as a level sensor in a heating tank. |
207 | The thermolevel in the hot water tank was, immediately prior to the fire on 12 February 2007, in its correct or at least a serviceable position. |
213 | It was reasonable for a designer to assume that the thermolevel had been properly designed with appropriate safety features so as to make it fit for its purpose. |
216 | A failure to reject the thermolevel for want of a CE mark did not discharge any duty that EDL might otherwise have owed to Howmet. |
217 | A designer in the position of ECS should not have appreciated, on the basis of EDL's literature, that the thermolevel was or might be inadequate for its purpose. |
218 | If Howmet reasonably relied on the thermolevel as a protection against fire at the relevant time, then a failure by the thermolevel to operate properly was within the scope of the duty of care owed by EDL to Howmet. |
236 | The fire on 12 February 2007 started in the hot water tank of the GEL and was the result of a heater in that tank overheating and catching fire. |
242 | The failure of a component within the probe of the thermolevel was an unlikely cause of the fire on 12 February 2007. |
246 | Following the fire on 12 December 2006 Mr Reed repaired the connection in the hot water tank probe cable and then applied heat shrink to it for additional protection. |
246 | The failure of the connections in the cable to the thermolevel in the hot water tank was an unlikely cause of the fire on 12 February 2007. |
247 | Of the various possible reasons why the thermolevel might not have cut off the supply to the heater immediately prior to the fire on 12 February 2007, incorrect setting of the potentiometer is the least unlikely. |
256 | If the fire was caused by incorrect setting of the potentiometer, this was the result of, or at least materially contributed to by, the negligent instructions supplied by EDL. |
266 | It is more likely than not that by 1 February 2007 Mr Reed knew, or at least strongly suspected, that the thermolevel in the hot water tank was not working properly. |
268 | The knowledge of Mr Reed that a thermolevel was not working properly is knowledge that is to be attributed to Howmet. |
273 | Following the fire on 12 December 2006 (and until the incident on 29 January 2007) Howmet had no reason to think that the thermolevel was or might be unreliable. |
274 | Howmet has not satisfied the court that it was entitled to, or did, rely on the thermolevel operating correctly or reliably as a low level cutout between the incident on 29 January 2007 and the occurrence of the fire. |
278 | In continuing to use the thermolevels after the fire in December 2006 and until 2 February 2007 Howmet did not act in a manner that was so unreasonable as to break the chain of causation. |
283 | In the absence of any reliable evidence it is not possible to reach a conclusion as to whether or not the chain of causation was broken by Howmet's conduct between 2 and 12 February 2007. |
291 | If the fire on 12 February 2007 was caused or contributed to by the negligence of both Howmet and EDL, liability should be apportioned 75%/25% against Howmet. |
Note 1 EDL did put it in a witness statement from one of the fire officers, a Mr. Jones, on the basis that he was deemed to have been tendered for crossexamination but was not asked any questions. In the event, therefore, no live evidence was called on its behalf. [Back] Note 2 I have said “him” because it was always a man. No woman gave evidence. [Back] Note 3 Mr Braund was Howmet’s electrical expert. [Back] Note 4 For example, in the witness statement of Mr. Gildersleve, at paragraph 36. [Back] Note 5 The desmut tank was one of the eight tanks on the new GEL. [Back] Note 6 The SAP system was a computer database that enabled operators to request assistance from the Maintenance Team: it is explained in more detail in the section of this judgment that deals with Mr. Webber’s evidence. [Back] Note 7 The whole of the paragraph in the note from “Looked” to “something else” appears to have been originally taken down by Mr. Boyle in the belief that it related to the incident on 29/30 January 2007, but it seems that Mr. Darke then explained that it related to the earlier incident on 12 January 2007. [Back] Note 8 I assume that “rcd” stands for residual current device. [Back] Note 9 The word “Kaizen”, meaning good change or improvement, is probably derived from the Japanese words “kai”, meaning change, and “zen” meaning (in this context) betterment. [Back] Note 10 The e-mail sent by Mr. Hughes on 12 December 2006 was circulated to ten people. [Back] Note 11 A further handicap that emerged in the course of his evidence was that it appeared that Mr. Gildersleve was not able to hear anything that I said because it seems that the only microphone that was transmitting was the one placed in front of counsel. Unfortunately, there was a defect in the court equipment, as a result of which the evidence was interrupted for about an hour. In addition, Mr. Gildersleve was sitting some way away from the camera so that it was not possible to observe him from reasonably close up, and I was not prepared to lose any further time in an attempt to improve the arrangements in the video room in which Mr. Gildersleve was giving evidence. [Back] Note 12 In relation to information derived from witnesses generally, Mr. Bartlett made a similar point to Mr. Boyle in crossexamination (at Day 5/126-7). [Back] Note 13 See the authorities discussed below at paragraphs 263-265 and 277. [Back] Note 14 Mr. Boyle’s note of a conversation with Mr. Reed on 26 February 2007 refers to Mr. Reed having designed and installed an auto fill system, so it must have been there the time of the fire. [Back] Note 15 Although this submission appears be inconsistent with the assertion at paragraph 63 of EDL’s written closing submissions that the auto fill system was a process control feature, not a safety feature. [Back] Note 16 I have already eliminated incorrect positioning as a cause: see paragraph 207. [Back] Note 17 See paragraphs 3.5.13 and 5.14.3 of Mr. Braund’s report. [Back] Note 18 When Mr. Boyle spoke to Mr. Reed in February 2007, Mr. Reed told him that he “… checked the level system” and that “… the low level alarm worked”. When asked about this again in January 2008 he said that he could not remember doing this himself, but that he thought that it was done by somebody. [Back] Note 19 Mr. Reed knew how to do it because he explained the procedure to Mr. Boyle during the interview on 26 February 2007. [Back]