QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
CO-OPERATIVE GROUP LIMITED |
Claimant |
|
- and - |
||
BIRSE DEVELOPMENTS LIMITED (In Liquidation) |
Defendant |
|
- and - |
||
STUARTS INDUSTRIAL FLOORING LIMITED (In Administration) |
Third Party |
|
- and - |
||
JUBB & PARTNERS (a firm) |
Fourth Party |
____________________
Fiona Sinclair QC and Richard Liddell (instructed by Clyde & Co LLP) for the Defendant
Mark Cannon QC and Katie Powell (instructed by Reynolds Porter Chamberlain LLP) for the Third Party
Benjamin Pilling instructed by Beale & Co LLP) for the Fourth Party
Hearing date: 7 October 2013
____________________
Crown Copyright ©
Mr Justice Akenhead
Introduction
Date | Event |
18/9/98 | Practical Completion of the development |
5/10/98 | Lease between landlord and Co-op |
2001 | Lease assigned to Woolworths |
c. 2003 | Some defects in floor noted – Prof Robery first involved |
Nov 2008 | Woolworths in administration |
17/4/09 | Lease re-assumed by Co-op – pleaded losses began to be incurred |
Sept 2009 | Serious cracking/damage noted in slabs |
May 2010 | Watts had produced outline slab repair specification |
14/09/10 | Co-op issues claim against Birse, Stuarts and Jubb |
13/09/10 | Co-op's Particulars of Claim against Birse, Stuarts and Jubb |
22/12/10 | Order of HHJ Raynor QC Proceedings stayed until 3 June 2011 to allow the Pre-Action protocol to be followed |
Aug-Sept 2011 | Remedial works started and tender accepted |
12/10/11 | Order (by consent) of HHJ Raynor QC Defences to be filed by 30 November 2011 |
26/10/11 | Order of HHJ Raynor QC CMC listed for 20 December 2011 vacated |
26/10/11 | Order of HHJ Raynor QC Co-op to discontinue any and all claims it has or may have against Stuarts |
15/11/11 | Order of HHJ Raynor QC Directions given Co-op to serve Amended Particulars of Claim reflecting the discontinuance by it of proceedings against Stuarts and Jubb (para 1) Co-op to serve its Schedule of Causation Loss and Damage to include (so far as reasonably practicable and where not reasonably practicable a clear explanation as to the reasons) to provide full particulars of its loss and of the remedial works claimed Trial of all issues to commence on 26/11/2012 |
16/11/11 | Order of HHJ Raynor QC (by consent) Co-op's claim against Stuarts discontinued Co-op to pay Stuarts' costs in the sum of £40,000 |
21/12/11 | Co-op serves Amended Particulars of Claim |
21/12/ 11 | Birse serves its Defence to Co-op's Particulars of Claim |
21/12/ 11 | Birse issues Additional Claim against Jubb |
21/12/11 | Birse serves Particulars of Additional Claim against Jubb |
21/12/11 | Birse issues Additional Claim against Stuarts |
21/12/11 | Birse's Particulars of Additional Claim against Stuarts |
03/02/12 | Co-op's Reply to Birse's Defence |
14/03/12 | Jubb's Defence to Birse's Particulars of Additional Claim |
24/04/12 | DAC Beachcroft (acting for Co-op) writes to Clyde & Co (acting for Birse): "As we advised in our letter of 15 February 2012, in relation to the poor condition of the internal slabs, data had been shared between experts on sonic tests and core tests to determine slab thickness and other characteristics, so as to define the extent of the areas to be replaced in both the east and west warehouses. The slabs have also been subject to further extensive tests and analysis to determine the fibre content of the concrete. Regrettably, these tests have revealed inadequate density of the reinforcing fibres such that according to expert advice the slab is non-compliant with the specified loading capacity... .... the extent of the internal slab replacement works has had to be reviewed on the basis of the adverse results from the data gathered. Coop have been advised to break out and replace the entire internal slabs to both warehouses, in order to comply with the specification, and this is currently being considered by our client. We alert you to this aspect again since it clearly impacts substantially on the budget for the project, the programme for completion and of course the damages claimed from your client in the proceedings. We draw your attention to page 5 of the enclosed report which makes provision in "Advance Warnings" of £2,321,867.21 for the internal slab replacement, pending approval by the Coop." |
23/05/12 | Clyde & Co (for Birse) write to DAC Beachroft LLP (acting for Co-op) noting that the Reply pleads a number of new allegations not made in the Particulars of Claim, requesting clarification and reserving position. The attached schedule states, inter alia: Para of Reply Summary of new Allegation Warehouse floors 8(v) 30(i) 30(ii) 35(ii) The floors as constructed are not compliant with the thickness design and, consequently, fail to meet the loading classification in the contractual specification. The causes of inadequate thickness are poor sub-base level control and / or debris on the sub-base. |
15/06/12 |
Hearing before HHJ Raynor QC |
Hearing before HHJ Raynor QC | Birse's skeleton raises need for Co-op to re-amend its statements of cases because (amongst other things): "9.2 in recent correspondence, the Co-op's solicitors have intimated yet further, and financially very significant, new allegations:... (b) the Co-op now suggests that each of the warehouse internal floor slabs requires wholesale replacement, on the grounds that an inadequate density of reinforcing fibres prevents the slabs complying with their specified loading capacity: see DAC Beachcroft's letter dated 24 April 2012..." |
Birse's skeleton raises need for Co-op to re-amend its statements of cases because (amongst other things): "9.2 in recent correspondence, the Co-op's solicitors have intimated yet further, and financially very significant, new allegations:... (b) the Co-op now suggests that each of the warehouse internal floor slabs requires wholesale replacement, on the grounds that an inadequate density of reinforcing fibres prevents the slabs complying with their specified loading capacity: see DAC Beachcroft's letter dated 24 April 2012..." |
Order of HHJ Raynor QC (dated 19/06/2012, but relating to hearing on 15/06/2012) Trial listed to commence on 26 November 2012 vacated Co-op ordered to serve draft Amended Particulars of Claim by 6 July 2012 Co-op ordered to serve draft Amended Schedule of Loss by 20 July 2012 |
09/07/12 | Co-op serves draft Re-Amended Particulars of Claim against Birse (the "July 2012 RAPOC") |
26/07/12 | Co-op applies for permission to serve the draft Amended Schedule of Loss and Damage on 7 September 2012 (rather than on 20 July 2012) |
03/08/12 | Birse serves draft Amended Particulars of Additional Claim against Stuarts |
06/08/12 | Birse serves Amended Particulars of Additional Claim against Jubb |
24/08/12 | Clyde & Co (for Birse) requests clarification of Co-op's draft Re-Amended Particulars of Claim, including in respect of the interrelationship between (i) steel fibre content, and (ii) thinness of the slab (see p.619). |
24/08/12 | RPC (for Stuarts) write to Clydes (for Birse), objecting to the draft Amended Particulars of Additional Claim against it. |
29/08/12 | Clyde & Co write to DAC Beachroft passing on Stuarts' objections to Co-op. |
05/09/12 | Hearing before HHJ Stephen Davies of Co-op's application to re-amend Particulars of Claim |
25/10/12 | Telephone hearing before HHJ Stephen Davies in respect of handing down of judgment following hearing on 05/09/2012 |
Telephone hearing before HHJ Stephen Davies in respect of handing down of judgment following hearing on 05/09/2012 | Order of HHJ Stephen Davies Co-op granted permission to re-amend its Particulars of Claim to plead claim for cost of replacing slabs Permission to appeal given. |
Order of HHJ Stephen Davies Co-op granted permission to re-amend its Particulars of Claim to plead claim for cost of replacing slabs Permission to appeal given. |
Judgment of HHJ Stephen Davies New Trial date fixed – 29/04/13 |
31/10/12 | Co-op serves draft Re-Amended Particulars of Claim against Birse with Amended Schedule of Loss (the "October 2012 RAPOC") No application to re-amend was made in respect of this draft in the light of the Court of Appeal's judgment |
08/11/12 | Birse serves Amended Particulars of Additional Claim against Jubb |
08/11/12 | Stuarts' Appellant's Notice issued |
08/11/12 | Birse's Appellant's Notice issued |
26/03/13 | Hearing before Court of Appeal |
29/04/13 | Date for commencement of trial, per Order of HHJ Raynor QC of 19/06/2012 |
01/05/13 | Judgment of Court of Appeal handed down Judgment of HHJ Davies reversed Co-op refused permission to re-amend its Particulars of Claim to plead claim for cost of replacing slabs |
03/05/13 | Order of Court of Appeal Order of HHJ Davies of 25/10/2012 varied to reflect reversal of judgment. |
17/05/13 | Co-op serves draft Re-Amended Particulars of Claim against Birse with Amended Schedule of Loss (the "May 2013 RAPOC") |
11/06/13 | Order (by consent) of HHJ Raynor QC Proceedings transferred from TCC in Manchester to TCC in London |
13/06/13 | Birse serves draft Amended Particulars of Additional Claim against Stuarts |
17/06/13 | Jubb serves Amended Defence to Birse's Additional Claim |
20/06/13 | Hearing before Akenhead J in respect of the May 2013 RAPOC |
27/06/13 | Judgment of Mr Justice Akenhead Co-op granted permission to re-amend its Particulars of Claim to plead claim for cost of replacing slabs, subject to specified conditions |
15/07/13 | Co-op serves "The Decision to Replace the Warehouse Slabs" |
16/07/13 | Co-op serves further draft of Amended Schedule of Causation, Loss and Damage |
17/07/13 | Co-op serves draft Re-Amended Particulars of Claim (the "July 2013 RAPOC") |
02/08/13 |
Judgment of Akenhead J in respect of hearing on 2 August 2013 Co-op refused permission to amend its statements of case to include a claim for the replacement of the warehouse floor slabs. |
02/08/13 | Order of Mr Justice Akenhead |
30/08/13 | Co-op serves draft Re-Amended Particulars of Claim with Amended Schedule of Loss (the "August 2013 RAPOC") |
05/09/13 | Co-op serves draft Re-Amended Particulars of Claim against Birse with Amended Schedule of Loss and Decision to Replace document (the "September 2013 RAPOC") |
05/09/13 | Co-op issues application to re-amend in accordance with the September 2013 RAPOC. |
07/10/13 | Hearing of Co-op's application to re-amend |
01/12/13 | Experts to resume without prejudice discussions to identify areas of agreement and disagreement (per Order of 2 August 2013) |
10/01/14 | Disclosure reports (per Order of 2 August 2013) |
17/01/14 | Review CMC (per Order of 2 August 2013) |
02/05/14 | Witness statements (per Order of 2 August 2013) |
06/06/14 | Experts' joint statements (per Order of 2 August 2013) |
04/07/14 | Experts' final reports (per Order of 2 August 2013) |
25/07/14 | PTR (per Order of 2 August 2013) |
03/11/14 | 3 week trial commences (per Order of 2 August 2013) |
The final italicised dates represent further programme requirements for the trial fixed in August 2013..
The Current Application
(a) This Court on 27 June 2013 accepted (Paragraph 14 of the judgment) that in principle the new claim for replacement costs attributable to the existing complaints about thickness and joints did not offend the Court of Appeal judgment. It also accepted the argument that it was reasonably arguable that where the loss or damage was caused by one factor (alleged lack of adequate thickness in this case), which was arguably the responsibility of Birse, that was sufficient to establish an appropriate causative link even if another cause of equal potency (shortage of steel fibre) was also established (where the Court of Appeal's judgement bars Co-op from relying upon it).
(b) Co-op accepts that it did not properly or fully comply with the Court's order requiring it to spell out (i) how, why, when, in what terms, on what basis and by whom the decision was taken to replace the floor slabs and (ii) the relevance both to the description of the pleaded defects and to the pleaded breach of the 70kN and other Specification Clause 2.08 requirements. It apologises for this failure.
(c) Because the Court's decision on 2 August 2013 was not a decision on the merits of the application to re-amend, the new application should be dealt with afresh to be considered on its merits. Its latest draft pleading, Schedule of Causation, Loss and Damage and Decision to Replace the Warehouse Slabs document now satisfy what the Court called for in June as a condition for permission to amend.
(d) A small reduction in the fibre content (as here) would not be considered a cause for removal or repair except where accompanied by other major defects such as lack of thickness.
(e) There will be, and has been, no delay which can be laid at the door of Co-op. It had applied for permission to re-amend before HHJ Davies reasonably promptly, the Court of Appeal took some six months to address the re-amendment appeal, it brought matters on reasonably promptly in June 2013 before the TCC in London, it tried to comply with the conditions imposed on the amendment reasonably promptly and it has moved as soon as practicable since 2 August 2013 to bring this latest application on. In any event, even if permission is granted, the newly fixed trial date in November 2014 will not be affected.
(f) There will be no prejudice to the other parties, at least for which cost orders can not compensate.
(a) This is the fifth draft re-amended pleading put before the court and in effect the fourth application to re-amend.
(b) There is reliance on the amended overriding objective in the Procedural Rules and in particular the emphasis on "proportionate cost" and "enforcing compliance with the rules, practice directions and orders". The legal and related costs of dealing with the draft re-amendments and the related applications and appeal have run to many hundreds of thousand pounds for the defending parties and, for instance over £750,000 on the part of Birse since about June 2012, as set out in its solicitor's statement dated 4 October 2013.
(c) Regard should be had to the Court's decision on 2 August 2013 by which the last application to re-amend was refused.
(d) On analysis, the latest re-amendment does offend against the underlying decision of the Court of Appeal.
(e) There has been delay to the proceedings caused in effect by the repeated applications to re-amend and the appeal for which Co-op is responsible. It is also suggested that Co-op and its non-legal professional team can be criticised for failing to pick up the steel fibre complaint until about April 2012. The trial would otherwise have been in late 2012 or mid-2013.
(f) There is likely to be prejudice not only from cost elements which will not be ascertainable or recoverable in connection with the repeated amendment applications. In particular, Jubb, who were engineers retained by Birse and are the fourth party, raise particular prejudice relating to Mr Shipp the engineer specifically involved with the project with a "Sword of Damocles" hanging over his head and the fact that Jubb themselves will have spent considerable time in relation to the amendments which will never be compensated for in costs.
(g) There has been an unacceptable "ducking and weaving" (my expression) in relation to the various iterations of the draft re-amendments with very real contradictions between what has been put forward in the past and what is now put forward. There are also, at least, unacceptable contradictions within the latest draft.
The Law and Practice
"1.1 (1) These Rules are a new procedural code with the overriding objective of enabling the court to deal with cases justly and at proportionate cost.
(2) Dealing with a case and at proportionate cost includes, so far as is practicable –
…(b) saving expense;
(c) dealing with the case in ways which are proportionate –
(i) to the amount of money involved;
(ii) to the importance of the case;
(iii) to the complexity of the issues; and
(iv) to the financial position of each party;
(d) ensuring that it is dealt with expeditiously and fairly;
(e) allotting to it an appropriate share of the court's resources, while taking into account the need to allot resources to other cases, and
(f) enforcing compliance with the rules, practice directions and orders."
"The rule has therefore been revised to emphasise (i) the centrality of dealing with cases at proportionate cost and (ii) the fact that the overriding objective requires the court to place a greater weight than it might have done previously on enforcing compliance."
"As Mr Moss recognizes, and it has been said more than once in this court, it is vital for the Court of Appeal to uphold robust fair case management decisions made by first instance judges. It has also been said, not least by Jackson LJ, that the culture of toleration of delay and non-compliance with court orders must stop. I can find no fault with the judge's approach or with the exercise of his discretion."
"…courts at all levels have become too tolerant of delays and non-compliance with orders. In so doing they have lost sight of the damage which the culture of delay and non-compliance is inflicting on the civil justice system. The balance therefore needs to be redressed."
Lord Justice Jackson himself said in his judgment, referring at paragraph 3 to the proposed rule changes:
"2. Non-compliance with the Civil Procedure Rules and orders of the court on the scale that has occurred in this case cannot possibly be tolerated. Any further grant of indulgence to the defendants in this case would be a denial of justice to the claimants and a denial of justice to other litigants whose cases await resolution by the court…
4. It is currently anticipated that this revised rule will come into force on 1 April 2013. After that date litigants who substantially disregard court orders or the requirements of the Civil Procedure Rules will receive significantly less indulgence than hitherto. As I say, that rule amendment lies in the future. In the present case, on the rules as they stand, relief from sanction must be refused."
"The overriding objective (of the CPR) is that the court should deal with cases justly. That includes, so far as practicable, ensuring that each case is dealt with not only expeditiously but also fairly. Amendments in general ought to be allowed so that the real dispute between the parties can be adjudicated upon provided that any prejudice to the other party caused by the amendment can be compensated for in costs, and the public interest in the administration of justice is not significantly harmed".
(a) The additions to the overriding objective are not mere verbiage.
(b) Courts are required, broadly in all that they do but particularly in the case management and procedural aspects of the case, to have particular regard not only to saving cost where it is fair and practicable to do so but also to keeping the costs overall and the costs of each party within proportionate bounds.
(c) There is nothing inappropriate in the Court taking a robust approach, provided that it is fair and within the ambit of the overriding objective, as amended.
(d) The Court must now have regard, particularly in the case management and procedural aspects of any given case, to compliance with the rules and orders.
The Scope of the Amendment now Sought
"(a) Clause 2.08 called for a Loading Category 2, Classification "Heavy". This loading classification typically refers to a floor capable of routinely dealing with traffic carrying very substantial loads such as bulk paper, bulk liquids such as paint, or other heavy industrial materials. In order to deliver a slab meeting this requirement, the designer selected Grade 40 concrete, which was sensible, and a concrete thickness of 150 mm. 150 mm was an appropriate minimum thickness for this type of floor and is the minimum thickness normally used and is typically the starting point for a design, which is to say: the designer might use a thickness greater than 150 mm, but 150 mm would be a minimum and/or start-point for an adequate design.
(b) Clause 2.08 also called for the ground floor concrete slab to reliably deliver a pallet racking leg load of 70 kN/leg. As with overall loading classification, pallet racking leg load requirements would only be met on the basis that the floor met the design intent of 150 mm thickness (less tolerance).
(c) Alternatively, taking various requirements of Clause 2.08 together, and based upon standard practice in the industry, the ground floor concrete slab called for by the Specification would need to have a minimum thickness of 150 mm (less tolerance).
[(d) to (g) explain, relatively non-controversially why a tolerance of plus or minus was 15 mm was appropriate]
(h) Applying these considerations, the minimum thickness of the slab should be 135 mm at any point.
Applying the above to the floors in question, the thickness was seen to vary considerably over the slab; thin areas, less than 135 mm, were scattered over the area of the slab; and Co-op and its experts had no ability to estimate or predict where the areas of existing slab, left in place, would all be sufficiently thick to withstand the intended loading. The Court is referred to the thickness survey data at Appendix A2 of the Decision to Replace the Warehouse Slabs. For the avoidance of doubt, this degree of inadequate thickness meant that the slab's performance, consistent with the Specification, could not be assured in service. Moreover, no amount of increase in fibre would ever have addressed these problems."
"(i) The slab in Warehouses 1 and 2 did not comply with sections 2.06 and 2.08 of the Specification within the Employer's Requirements in that the slab was not a reinforced concrete slab designed to BS8110 or was not designed or built in accordance with industry standards such as Concrete Society Technical Report TR34 and/or insufficiently thick, as explained in paragraph 33 (v) above, to meet the loading requirements of Clause 2.08. Further, this was a breach of clauses 2.1, 2.5.1.1.1, 2.5.1.1.2, 2.5.1.1.3, 2.5.1.2, 2.5.2 of the Building Contract and also a breach of the further obligations set out in paragraph 15 above, together with a breach of clauses 4.1.1, 4.1.2 and/or 4.1.3 of Defendant's Warranty..."
(iii) The sub-base beneath Warehouses 1 and 2 did not comply with the requirements of TR34 such that, as a result, the slab was of insufficient thickness in any event as explained in paragraph 33 (v) above…
"Accordingly, the Claimant is entitled to claim, and claims in these proceedings, damages for breach of contract and/or breach of duty. The Claimant's claim for damages is set out in a Schedule of Loss and Damage dated 25 November 2011 and a Re-Amended Schedule of Loss dated 5 September 2013."
"83F The Claimant concluded, as the repairs scheme was being implemented and indeed extended to cope with further areas of discovered damage as the slabs were opened up, that all of the slab in both warehouses was at risk of failure and that the only reasonable engineering and commercial response was the replacement of the whole of the slab using the incumbent remedial works contractor.
83F-1 For the reasons set out in the Re-Amended Particulars of Claim, as supported by the Decision to Replace the Warehouse Floor Slabs document, it is the Claimant's case that the need and/or decision to replace the warehouse floor slabs was reasonable in order to remedy the defects caused by the breaches pleaded in paragraph 33 and 36 of the Re-Amended Particulars of Claim. In summary it is the Claimant's case on causation that the concerns over the thickness of the slab in particular was, at the minimum, an effective cause of the decision to replace the whole of the slab.
83F-2 Accordingly the Claimant claims in these proceedings:
(1) The cost incurred in remedying the defects up to the suspension of these works and the decision to replace the warehouse floor slabs in their entirety; and
(2) The total cost of the replacement works.
83G Prior to the decision to replace the warehouse floor slabs the total cost incurred in removed the defects caused by the breaches pleaded in paragraph 33 and 36 of the Amended Particulars of Claim dated 30 August 2013 [this may be wrong date] was £370,304.58. This sum is claimed in full from the Defendant…
83I [This sets out the latest estimate for the total replacement cost was £2,493,065.20] For the avoidance of doubt, this estimate is subject to change and will be more fully particularised when the final account is agreed.
83J In the alternative to the claim for the total cost of replacement particularised above, if the Court finds that the breaches pleaded in paragraph 33 and 36 of the Re-Amended Particulars of Claim are not an effective cause of the need and/or decision to replace the warehouse floor slabs in their entirety, the Claimant is entitled to claim such proportion of the total replacement cost as would have been necessary to complete the remedial works required as a consequence of the breaches pleaded in paragraph 33 and 36 of the Re-Amended Particulars of Claim. The Claimant's best current estimate of the cost that had to be incurred in remedying the defects caused by the breaches pleaded in paragraph 33 and 36 of the Amended Particulars of Claim dated 30 August 2013 is the estimated cost of partial replacement projected in Costs Report number eight in the sum of £822,899.07…"
"The [thickness/calibration testing] results, tabled to Co-op on 18 January, 2012 showed confirmation of random thinning areas of the floor based on impact echo, but with variable correlation with the core length results…
- It was expert advice that this figure [the 35kg/m³ Stuarts were using in its floors in 1998] was not reliable and that it needed to be verified. Fibre content had now become a critical factor that affected the area of concrete that needed to be removed (relating to the edge condition) as well as the actual capacity of the floor itself. This verification could be done by examining the actual fibre content in samples of concrete from the floor. If the fibre content was lower than 35kg/m³ then this would change the analysis above and more floor may be needed to be removed…(page 3)
- The [steel fibre] results [two sets verifying averages of 20kg/m³ and 25kg/m³] were presented to BSP [Co-op's engineers] in Derby on 14 March. BSP then re-analysed the floor using the new data to see whether the low fibre content would satisfy the floor loading requirement of 70kN racking leg load for the intended thickness of 150mm
- The results were reported on 15 & 16 March that the lower fibre content would not meet 70kN racking leg load and that the leg load would have to be downgraded to 55kN.
- Fibre content and thickness are critical parameters in a SFRC floor. To meet design loads, the designer will select a concrete strength, floor thickness and fibre dosage that will produce the least cost design. In this case, the floor was assumed to be designed to have 35kg/m³ and 150mm thickness.
- Reduction in the thickness of the floor, or the fibre content (or both), due to poor workmanship and control on-site, will reduce the structural capacity of the floor.
- At Swift Valley, Stuart has contrived to produce a floor that has a highly variable thickness, with some areas reduced to 70mm as a result of deleterious materials left beneath the polythene separation membrane.
- The floor has never seen...the intended racking leg load of 70kN…This type of loading was not used by Woolworths but could happen with a future tenant…
- There remains a high probability that the floor could fail in service due to undetected thin areas beneath or adjacent to racking legs, irrespective of the fibre content.
- The confirmation that the fibre content is also low and below what would be needed in a design of compliant 150mm thickness, is also reason to condemn the floor.
- In Swift Valley, we have both situations." (page 4)
"4. In relation to both fibre and thickness, then in a situation where the floor has a slightly lower steel fibre content than the designer intended (as to repeat the situation that occurred at Swift Valley, namely not a "gross lack of fibre" that lost the enhanced flexural strength, but an average reduction of 5 kg/m³ from 30 kg/m³ to 25 kg/m³), that reduction would not give me undue concern provided the total is greater than the 20 kg/m³ threshold mentioned above and the thickness was compliant…
6…To conclude;
Thickness as a cause
Thickness has a very significant effect on the performance of the floor, such as its racking leg load resistance. Inadequate thickness is often in itself sufficient reason to condemn a slab. No floor intended to be 150mm in thickness should at any point be below the 135mm that is permitted by TR34.
Fibre as a cause
Deficiencies in steel fibre content alone (provided that the deficiencies were not a "gross lack of fibre") would not give rise to particular concerns, as the effect of fibre dosage on load capacity is relatively small. I am not aware of any floor where a slight reductions in steel fibre content had led to repair or removal, unless accompanied by other significant deficiencies is especially inadequate thickness."
Discussion
(a) In simple terms, Co-op's failure (no later than mid-2012) to plead its real and current case by way of re-amendment) has led to a delay of some two years (or approaching it) in this matter coming on for trial. There is a real risk that its failure to produce an (arguably) properly particularised draft re-amendment until September 2013 would lead (if allowed) to yet further delay in this matter coming on for trial.
(b) That failure has led directly to the overriding objective not being followed in terms of expedition. Whilst there is a balance to be held between the different facets of the overriding objective, a failure which has or will have led to such a delay will not usually be acceptable. It is not acceptable here.
(c) There is likely to be some very real, although unquantifiable, prejudice at least to the defending parties. The first aspect of this relates to the irrecoverable costs, even if the defending parties are paid their consequential costs of the various applications and appeal. Assessment on a standard basis, which much of it will be, is well-known to produce something between 60% to 80% of the total costs; even assessment on an indemnity basis rarely produces 100% recovery. Birse has estimated its total costs of and occasioned by the four re-amendment applications and the appeal at about £750,000. Whilst I am somewhat surprised at this amount, I can see that collectively the three defending parties' costs in this regard will substantially exceed £1 million. Co-op's costs relating to these matters must run into a comfortable (or possibly uncomfortable) six figure sum. The defending parties' directly quantifiable costs of over £1 million could be reduced on assessment by £200,000 to £400,000 or more which will be irrecoverable. One can add indirect and difficult to quantify costs, such as those which are related to the delay, which may never be recoverable (depending on the outcome, and, even if the defending parties win, their costs will be subject to assessment again with consequential irrecoverability of part).
(d) I should emphasise that in many cases the irrecoverability of costs on assessment will not be a major element in refusing permission to amend but where the shortfalls are likely to be substantial it will and should be a significant element to be taken into account in refusing permission. This is not only because the shortfalls are substantial but also because the incurrence of substantial costs bills in relation to amendments (and particularly amendments and amendment applications which lead to significant delays in the litigation) will often produce cost bills for individual parties and collectively for the parties overall which will be disproportionate to what is in issue. If, as here, the repeated amendment applications and their consequences have led and will lead to enormous related bills which would simply not have been incurred at anything like the level which would have been incurred if the amending party had "got its act together", the costs, as here, will be disproportionate.
(e) The other element of irrecoverable cost relates to management and other personnel time which employees within the defending parties are likely to have given in relation to the repeated amendment outings to the Court. Instructions will have to have been given by and sought from such employees and their time and the management costs involved are irrecoverable. It is a reasonable inference that in relation to all three defending parties a not insignificant amount of employee time will have been expended since mid-2012 in this regard.
(f) There is also likely to be additional prejudice in this and similar cases along the lines put forward by Jubb's Counsel, albeit unsupported by formal evidence. Individuals, whose actions or omissions are being criticised in the litigation such as Mr Shipp of Jubb will have the proceedings uncomfortably hanging over them in this case for significantly longer than would have been the case but for the delays occasioned by the actions or inactions of Co-op. Mr Shipp will have had this case hanging over him and his professional and private life for up to 2 years or possibly longer than would have been the case if Co-op had produced the requisite amendment in mid-2012.
(g) Another factor which the overriding objective requires should be taken into account is the allocation of an appropriate amount of judicial or other resources. Speaking only as the judge involved in the case management of three of the re-amendment applications, I have (with this one) spent the best part of 7 full working days or more on them (pre-reading, hearings and judgment writing). HHJ Davies and the Court of Appeal will have spent substantial time also. There comes a time when the application of the overriding objective in this regard leads to a conclusion that too much of the Court's resources have been applied to dealing with re-amendment applications which need not have been made if Co-op had produced a proper draft re-amendment in the middle of last year. This is a factor which I take into account, albeit that on its own it would not have been determinative.
(h) It is difficult to say that there has been much non-compliance by Co-op "with the rules, practice directions and orders" (as referred to now in the overriding objective). It is not a breach of the rules, practice directions or orders to apply to amend; if the application is hopeless, it will be dismissed with costs. Clearly the original application to re-amend before HHJ Davies was not hopeless and, indeed, all sides' position in the Court of Appeal was not hopeless. There was however a breach of the conditions imposed by this Court on 27 June 2013 in that, as Co-op frankly accepted, it did not comply with the conditions in that it did not provide the requisite particularisation; there was no good reason for this failure. Again, that on its own is a factor which would not been determinative but which I do take into account along with all the other matters.
(i) Finally, there is something in the fact of these repeated applications to re-amend which, to use Peter Gibson LJ's expression in the Cobbold case, tends significantly to harm "the public interest in the administration of justice". Obviously, it is not for the Court at this stage at least to determine whether anyone in particular within Co-op or their professional team is to "blame" for the lamentable failure to produce in mid-2012 pleadings which adequately reflected what its true case on thickness and replacement actually was. The evidence which Co-op has proffered in its latest application has not been tested. It may be true (as now said) that the thickness complaints were always the determinative factor (or cause) of the need to replace the slabs; if so, there can be little or no excuse for that case not to have been pleaded clearly in the first re-amendment. If the evidence turned out to be untrue (or at least not established on the balance of probabilities), then the Court will have been misled at this stage. Either logical possibility would harm the administration of justice.
(j) This final point about the administration of justice arises partly out of the judgment given by this Court on 2 August 2013 where at Paragraph 31 (in an oblique Shakespearian reference) I said that "there comes a time, and I believe the time has come, when a full stop must be imprinted". Repeated applications to amend in relation to the same subject matter should not be encouraged, particularly where technically issue estoppel (or res judicata) are inapplicable. The proper administration of justice should generally require, in the absence of good excuse, parties broadly to get right their applications to amend. Co-op did not get them right on at least three occasions.
Decision