QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Mueller Europe Limited |
Claimant |
|
- and - |
||
Central Roofing (South Wales) Limited |
Defendant |
____________________
Graham Eklund QC and Richard Liddell (instructed by Lyons Davidson Solicitors) for the Defendant
Hearing dates: 15, 16, 17, 21, 22, 23, 24, 28, 31 January 2013
____________________
Crown Copyright ©
Mr Justice Stuart-Smith:
Introduction
PART 1 – LIABILITY
Summary of Conclusions on Liability
i) The heaters had not been routinely isolated during the course of the works. This was because Mr Henwood of Central assumed, without checking, that Mueller would be isolating them and because Mr Jones of Mueller had not read Central's method statement and assumed that Mr Henwood would inform him if anything needed to be done. If Mr Jones had been asked to provide permits to work confirming isolation of the heaters he would have checked that they were isolated before issuing the permits; and if he had been informed of occasions where heaters were found burning in close proximity to the scaffolds, he would have taken steps to prevent it happening again;
ii) There had been prior incidents of heaters operating in close proximity to the birdcage scaffolds. They were known to Mr Henwood and to Mr Smith of Mueller, but were not reported either internally within Central or to Mr Jones, who was the Mueller employee responsible for the administration of the contract: see [13-68];
iii) Central acted in breach of its contractual obligations to carry out the works safely and to report prior incidents. Mueller acted in breach of its contractual obligation to isolate the heaters: see [69-106];
iv) No waiver or estoppel by convention is established: see [107-113 ];
v) Contributory negligence is inapplicable: see [114-119];
vi) Central's breaches of contract were an effective or dominant cause of the fire and Central is liable to Mueller for the consequences of the fire: see [120-129].
The Factual Background
The Parties
The Contract
"8.9 - Damages Or Destroyed Property – we confirm it is the responsibility of Mueller to protect their plant/equipment and isolating of mechanical and electrical services as required during the contract works. We request this be inserted here."
"I. DEFINITIONS
In addition to terms, which are defined elsewhere in these Master Terms and Conditions; the following terms have the meanings given them below:…
Construction Project means the particular Work to be performed by Contractor pursuant to a supplement.
Contract Documents means with respect to each Construction Project, these Master Terms and Conditions, the Supplement applicable to Construction Project, and any and all, Exhibits, Schedules, amendments, approved plans, drawings, specifications, addenda, standards, and modifications for such Construction Project…
Work means the work to be performed and/or materials to be supplied by Contractor as required by the Contract Documents.
II. COMMENCEMENT AND COMPLETION; PROGRESS REPORTS; FINAL ACCEPTANCE
2.1 Commencement and Completion.
(a) Contractor will begin the Work in accordance with the terms of the schedule of pre-construction document dated May 2007 issued at the tender stage and proceed diligently to complete the Work within the Contract Term…
…
IV. COMPANY'S OBLIGATIONS
4.1 Price.
Company will pay Contractor, and Contractor agrees to accept as full payment for satisfactory completion of the Work, the Contract Sum. The contract sum is £2,075,000.00…
VI. QUALIFICATION AND INDEPENDENCE OF CONTRACTOR
6.1 In performing and carrying out the Work.
Contractor agrees, and will cause each Subcontractor to agree, that Contractor and its Subcontractors are independent contractors, and not agents or employees of Company, except for the limited purposes provided in Section 5.2. Company will have no direction or control as to the method of performance of the Work. Contractor has represented itself as an expert with respect to the performance and completion of the Work, and Company is relying upon the expertise of Contractor in performing, completing and accomplishing the results intended by the Work even though Company may inspect the Work or provide materials or services in connection with the Work including, without limitation, specifications, drawings, or plans…
…
VIII. CONTRACTOR'S OBLIGATIONS
8.1 Compliance with Standards.
Contractor expressly assumes responsibility for ensuring that the Work meets the highest professional or trade standards, and is in accordance with the Contract Documents…
…
8.3 Adequate Staffing.
Contractor will provide competent and experienced supervisors, craftsmen and workers to perform the Work. The number of persons employed by Contractor will be adequate for job progress satisfactory to Company. Contractor will employ a competent and experienced superintendant and other key personnel satisfactory to Company…
…
8.5. Familiarity with Work and Project Site.
Contractor will acquaint itself thoroughly with the Work and will make all Work a complete, safe and finished job of its kind. Contractor represents that it has inspected the Project Site, is familiar with it and is satisfied as to its condition including, without limitation, hazards to life and property. Based upon its inspection, Contractor agrees that (i) the Contract Sum is just and reasonable compensation for all of the Work, including all foreseen and foreseeable risks, hazards and difficulties in connection with the Work excluding environmental and subsurface conditions;…
…
8.7 Inspections.
Contractor will give, and will cause all Subcontractors to agree to give, Company and its inspectors free access to all materials and equipment related to the Work and to the Project Site and any other of its work places. No inspection performed or failed to be performed by Company will be waiver of any of the Contractor's obligations under the Contract Documents or be construed as an approval or acceptance of all or any part of the Work…
…
8.9 Damaged or Destroyed Property.
Contractor will, at its own expense, repair, restore or replace any real or personal property, including tools and equipment, belonging to Company, which Contractor, its employees, agents or Subcontractors may damage, destroy or remove while performing, or in order to perform, the Work. Contractor will, at its sole cost and expense, promptly repair any damage or disturbance to walls, utilities, sidewalks, curbs and the property of third parties (including any Governmental Authority) resulting from the performance of the Work. It is the responsibility of Mueller Europe Ltd to protect and electrically/mechanically isolate all plant as required during the contract works.
…
8.12 Compliance with Applicable Laws
Contractor represents and warrants that the work will be performed and completed in a manner and with materials which comply with all applicable United Kingdom and local laws, regulations, ordinances and codes including, but not limited to, all those relating to
labour, employment and safety. Contractor will adhere to all generally accepted practices of safety and workmanship and to site safety standards or work rules to avoid … damage to equipment, materials and property.
8.13 Compliance with
United Kingdom Health and Safety at Work Act 1974
(a) Contractor acknowledges that it, its agents or Subcontractors are or may be subject to the provisions of the Health and Safety at Work Act 1974 (the "Act") as they may be amended, depending upon where the Work is to be performed. Contractor agrees that it will abide by, and will cause each Subcontractor to agree to abide by, all applicable rules and regulations promulgated by the "Act", or any other United Kingdom or local governmental agency having authority over Safety and Health. To the extent that training of its employees or Subcontractors is required under any United Kingdom or local rules or regulations existing now or at any time during the term of the Supplement, Contractor further agrees that its employees or Subcontractors will receive such training as is required. Company reserves the right to specify and require Contractor to perform additional job safety and health and safety training and activities and require Contractor to certify its compliance in writing.
(b) Contractor agrees to assume the entire responsibility and liability for any violations of the Acts, the regulations promulgated under the Acts, or other statutes and regulations relating to Safety and health caused by it or its agents or Subcontractors and to pay and, upon demand of Company, defend any citation, penalties, or assessments assessed against Company by the United Kingdom Health and Safety Executive or any Governmental Authority having authority over safety and health as a result of alleged violations of the Acts, the regulations promulgated under the Acts or other statutes and regulations relating to safety and health caused by Contractor or its agents or Subcontractors…
…
8.17 Project Site Rules and Employee Relation.
(a) The Company will Issue each Contractors and Sub Contractors personnel with the appropriate "PERMITS TO WORK". No Personnel of the Contractor or Sub Contractor will be allowed on site unless they have been issued with a current valid Permit to Work. All Contractors and Sub Contractors Personnel must abide by the Companies Health and Safety Rules stated on the Permit to Work. Contractor will supply a copy of the Company's Project Site rules regarding the Work to its Subcontractors and the Subcontractors will comply with such rules.
(b) Contractor will plan and conduct its operations so that its employees, agents, and Subcontractors work in harmonious relationship with other groups of workers at the Project Site, and so that they do not delay, endanger or avoidably interfere with the operations of others. Company shall have the right to reject or remove from the Work any of the subcontractors, or its or their employees or agents (or require Contractor to do them same) which Company determines to be incompetent, undesirable, whose productivity is below acceptable levels, whose workmanship is substandard, or whose conduct creates a danger to themselves or others. Company will give Contractor notice of such rejections or removals, and the time of persons so rejected or removed will not thereafter be charged to Company.
8.18 Accident Prevention: Security.
(a) Contractor will, and will cause each Subcontractor to take all precautions within their power necessary for the prevention of accidents, fires, theft, vandalism, injury or damage at the Project Site. …
(b) Contractor will conduct all operations under the Contract Documents in a manner to avoid, and will within its scope of Work promptly take all reasonable and necessary precautions against risk of loss, theft or damage by vandalism, sabotage or otherwise, to all or any part of the Work. Contractor will continuously inspect the Work, materials, equipment and the Project Site and will be solely responsible for the discovery, determination and correction of any such conditions and any potential accident-producing behaviours and/or conditions. Contractor will be liable for all loss or damage of any kind to materials, equipment and facilities contemplated by the Contract Documents or to any property of Contractor or any Subcontractor or for injury to employees of Contractor or any Subcontractor, caused by Contractor or by Contractor's failure to comply with this paragraph. … Contractor will cooperate with Company on all safety and security matters and comply with all Company safety and security requirements. However, such compliance will not relieve Contractor of its responsibility for maintaining proper safety and security, nor will it be construed as limiting Contractor's obligation to undertake reasonable action as required to establish and maintain safe and secure conditions at the Project Site. Contractor will prepare and maintain accurate reports of incidents of injury, loss, theft, damage or vandalism and shall furnish these reports to company within 24 hours of any incident.
…
XVII. MISCELLANEOUS
17.6 Headings and Captions.
Headings and captions in the Contract Documents are inserted for convenience of reference only and shall not expand, limit, modify or affect the text of any Contract Documents.
…
17.9 Waivers
No waiver of any provision of, or a default under, the Contract Documents nor any failure to insist on strict performance under the Contract Documents, may affect the right of Company or Contractor, as the case may be, thereafter to enforce said provision or to exercise any right or remedy in the event of any other default, whether or not similar."
The Pre-construction Period: October – December 2007
"Cranes must be isolated
Either – permit system
+ permit for asbestos release
+ handover
Inc lights + heat shut down Gas heating stopped"
"A Handover permit and work sequence will be written in to the revised Health & Safety documents"
By reference to this letter, Mr Parsons accepted that at the end of the 7 November meeting, Central were to go away and come up with a permit and work sequence for handover[16].
"BEFORE WORKS CAN COMMENCE…
1. ERECT TAPES AND BARRIERS AT GROUND LEVEL FOR SCAFFOLDERS TO ERECT ROOF VALLEY WALKWAYS.
2. HANDOVER IN WRITING OF WALKWAYS, ACCESS TOWER, LOADING BAYS AND PERIMETER EDGE PROTECTION, BY S.E.S. WEEKLY INSPECTIONS BY CRSW
3. INENDIFY AND AGREE WORK AREA WITH DAVE JONES, MUELLER, OBTAIN WRITIN CONFIRMATION BY PERMIT FOR ISOLATION OF ELECTRICS, HEATING AND CRANE SHUTDOWN TO WORK AREA .ERECT HERRIS TYPE FENCE AND WARNING SIGNS TO SHOPFLOOR TO ALLOW INTERNAL SCAFFOLDS TO COMMENCE.
4. ON COMPLETION OF SCAFFOLD AND PVC[18] ISOLATION A WRITTEN HANDOVER WILL BE ISSUED AND A COPY GIVEN TO DAVE JONES MUELLER, ON AGREEMENT THE FENCE CAN BE DISMANTLED AND OPERATIVES CAN THE WORK BELOW THE SCAFFOLDS.
5. DISMANTLING OF SCAFFOLD WILL FOLLOW AS ITEM 3. PLEASE NOTE THAT THE CRANE GAS AND ELECTRICS MUST REMAIN OFF UNTILL ALL WORKS ARE COMPLETE AND CENTRAL ROOFING ARE CLEAR OF THE AREA. CRSW WILL ISSUUE A SECTIONAL HANDOVER DOCUMENT TO CONFIRM THIS.
Health & Safety Plan Ref: - 11.1
All works are to be carried out in accordance with the Health and Safety Plan and Mueller Europe site rules.
CONSULT AND COOPERATE AT ALL TIMES
If you are in any doubt about your Method Statement or any Safety Matters in your working area you must consult management immediately."
The Performance of the Contract – pre-November 2008
November 2008 – The Fire
i) Had the factory's heaters been isolated during the course of the works and, if so, who had been isolating them?ii) Why were the heaters not isolated on 8/9 November 2008?
iii) Had the lights in the birdcage scaffolds been isolated during the course of the works and, if so, who had been isolating them?
i) Approximately 70 heaters in total would have been enclosed in the scaffolds as work progressed along the length of the factory. However, much of that work was done between May and October 2008, during which time an unspecified number of heaters, amounting to quite a large proportion, would have been isolated for reasons of economy unrelated to the works. The number of heaters that would have been enclosed in the scaffolds when they had not been isolated for reasons of economy is not known but is significantly fewer than 70[50];ii) Neither Mr Henwood nor anyone else made a request for the heaters to be turned off in advance of scaffold moves, either in pre-scaffold move meetings or when requesting permits to work;
iii) Mr Jones had not read the method statement and was not requested by Central to turn off the heating in advance of scaffold moves;
iv) Mr Henwood had read the method statement and was, as he accepted, responsible for implementing it on site. But he did not do so and did not implement any other procedure for ensuring that the heaters were off, relying instead upon an mistaken assumption that Mr Jones would have done so;
v) Although there were ample "visual reminders" of the presence of the heaters in close proximity to the scaffold that were available when Mr Jones was on the shop floor, they did not alert him to the danger posed by the heaters and he did not recognise it until the fire had happened;
vi) The evidence from the Mueller witnesses was, without exception, that they were not asked (either by Mr Jones or by Central or its subcontractors) to isolate heaters in advance of scaffolds being erected and that they were unaware of it being done;
vii) By contrast, the cranes were clearly in people's minds and were discussed at pre-scaffold movement meetings, with Mr Henwood sometimes making express requests for crane isolation and, typically, identifying the precise limits beyond which the cranes should not run[51]. Mueller's mechanical and electrical fitters would then be instructed to isolate the cranes mechanically and electrically before the scaffold was moved, and that was done;
viii) There was evidence from Mueller's witnesses that, if Mueller maintenance staff had isolated heaters, that would have been recorded in the maintenance log in the same way as the records of isolating and reinstating the cranes. There are no such records in the maintenance log;
ix) Mr Powell, an electrician employed by Estil, gave unchallenged evidence that when Estil followed on after the re-roofing he saw a number of heaters with the flying leads unplugged[52]. He did not know who had unplugged them. He said that, if any were still plugged in, Estil would have unplugged them. He had no memory of whether or not the local gas supply valves were open or closed;
x) After the fire, one heater that was beyond the area that the scaffolding and re-roofing had reached was found with the flying wire unplugged;
xi) The evidence relating to the heaters in and near the scaffold which caught fire shows that they had not been isolated, as discussed above.
"heaters and lights off during summer – occasionally scaffolders or asbestos removers would bring to EH's attention. Would then contact Dave Jones or Trevor Smith to get them turned off.
2 or 3 times heaters found on by scaffolders or asbestos sheeters then contacted Mueller (D[avid] J[ones]) or T[revor] S[mith]) to get them turned off."
After referring to the occasion 4-6 weeks before the fire, Mr Hotchkiss recorded Mr Henwood as saying "other 2 occasions, Xmas last year at warehouse end." Although by the time he came to give evidence Mr Henwood said that he could not remember these other occasions, I find that Mr Hotchkiss' record of this interview is essentially correct and that in November 2008 Mr Henwood could remember two other incidents when heaters were reported to be found on. Mr Hotchkiss' note "… then contacted Mueller (D[avid] J[ones]) or T[revor] S[mith]) to get them turned off" bears two possible interpretations. The first is that Mr Henwood had reported at least one occasion to Mr Jones and at least one occasion to Mr Smith so that, taking the three incidents overall, his reports had been either to Mr Smith or Mr Jones. The alternative is that he did not remember who he had reported them to but thought it would have been either Mr Jones or Mr Smith. Although Mr Smith gave evidence that he recalled only one such occasion, I prefer the second explanation because my assessment of Mr Jones is that, if he had been informed that heaters had been found on he would have remembered it and acknowledged it when he gave evidence. And, of equal importance, he would have discussed it with Mr Henwood to ensure that it could not happen again, which did not happen. I therefore find that there were two occasions early in the contract when heaters were found on in the vicinity of the scaffolders' work; that they were reported to Mr Henwood, who reported them to Mr Smith; that Mr Smith either isolated the heaters himself or caused them to be isolated; and that Mr Jones was not told of the incidents.
i) On 10 November 2008 Mr Hotchkiss noted "heaters unplugged" and to some heaters being isolated and then reconnected[54], but the significance of these entries was not explored or explained. In what appear to be notes relating to Mr Jones or Mr Urosevic (Mueller's electrical engineer), entries stating that the heaters in Bays 1 and 2 had been disconnected are crossed out[55]; there is a note that "isolations [are] done by Mueller requested at meetings prior to moves"[56]; and there are notes indicating that Mr Hotchkiss was told by a number of Mueller employees that no isolation of lights or heating had been carried out in the most recent Bay 1 and 2 positions for the scaffold[57];ii) On 12 November 2008 there is a contentious note of a conversation with Mr Jones as follows:
"- no permits issued for isolations. Meetings held, with Eddy [Henwood]. – Eddy would request isolations Dave would ask maintenance fitters to do it. But no formal notification given that work had been done.Mech[anical] fitters isolated heaters."That is followed by:"Trevor Smith – mechanical manager.Eddy – would ask for heaters to be isolated if any found on. …."Mr Jones said that the reference to heaters in the last line of the note of the conversation with him was a misunderstanding and that the discussion concerned cranes, which would be isolated by mechanical fitters. Central submits that the context provided by the following note shows that there was no misunderstanding and that the note relates to heaters.iii) On 19 November 2008 Mr Hardy is recorded as saying that he hadn't known heaters to be on and had only known lights to be on on one occasion;
iv) On 21 November 2008 there is a note of a conversation with Mr Jones in the course of which he is recorded as saying:
"When scaffolding is erected Eddy [Henwood] will go to maintenance office to request isolation of any lights or heating. – Never actually asked DJ for this – not discussed during meetings prior to scaffolding move. Both before + after fire Eddy has said that heaters and lights were off in 2 bay."[58]
Liability Discussion
Issue 1: The Allocation of Responsibility Under the Contract
Principles of contractual interpretation
The Contract Documents
Interpretation of the Contract: Express Terms
i) Central had responsibility for the safe carrying out of the works at all times. This was not affected by any rights to inspect or intervene that the contract gave Mueller;ii) Mueller's responsibility for the physical isolation of its plant arose when it was triggered by the provision of sufficient information to enable it to recognise that isolation was required.
i) Assumed responsibility for ensuring that the work to be performed and/or materials to be supplied by Central met the highest professional trade standards: Clause 8.1;ii) Was to provide competent and experienced supervisors, craftsmen and workers to perform the work that had been undertaken, and had full responsibility for all materials and equipment so as to permit the most rapid and economical completion of the work: Clauses 8.3 and 8.4;
iii) Represented and warranted that the work to be performed would be performed and completed in a manner which complied with all applicable laws, regulations and codes, including but not limited to those relating to safety: Clause 8.12 (and see Clauses 8.13(a) and (b));
iv) Was to take (and was to cause all its sub-contractors to take) all precautions within their power necessary for the prevention of fires at the site: Clause 8.18(a);
v) Was to conduct all operations under the Contract Documents in a manner to avoid, and would promptly take all reasonable and necessary precautions against risk of loss or damage to all parts of the work to be performed: Clause 8.18(b);
vi) Was to continuously inspect the work to be performed and the site and was to be solely responsible for the discovery, determination and correction of any conditions giving rise to risk of loss or damage and any potential accident-producing behaviours and/or conditions: Clause 8.18(b).
While it is arguable that Clause 8.1 imposed an obligation to achieve an end result rather than to achieve standards during the carrying out of the work, that argument is not applicable to the other obligations just listed. Singly and cumulatively, they applied throughout the course of Central's conduct of the works.
i) Clause 6.1, which provided that Mueller would have not direction or control as to the method of performance of the Work by Central;ii) Clause 8.7, which provided that no inspection performed or failed to be performed by Mueller would be a waiver of any of Central's obligations or be construed as an approval or acceptance of all or any part of the Work;
iii) Clause 8.13(a), which reserved to Mueller the right (but imposed no obligation upon Mueller) to specify and require Central to perform additional job safety and health training and activities;
iv) Clause 8.17(b), which reserved to Mueller the right (but imposed no obligation upon Mueller) to reject or remove (or to require Central to reject or remove) incompetent or dangerous subcontractors or their employees;
v) Clause 8.18(b) which required Central to cooperate with Mueller on all safety and security matters and to comply with all Mueller's safety and security requirements while stating expressly that such compliance would not relieve Central of its responsibly for maintaining proper safety and security and would not be construed as limiting Central's obligation to take reasonable action as required to establish and maintain safe and secure conditions at the site.
i) Central had represented itself as an expert with respect to the performance and completion of the Work;ii) Mueller was relying upon the expertise of Central in performing, completing and accomplishing the results intended by the Work, even though Mueller may inspect the Work;
iii) Central represented that it had inspected the site, was familiar with it and was satisfied as to its condition including hazards to life and property; and
iv) Mueller agreed that the Contract Sum was just and reasonable compensation for all of the Work, including all foreseen and foreseeable risks and hazards.
In the light of the events which happened, it is clear beyond argument that the heaters constituted a hazard to life and property; and the risk of fire caused by the heaters was a hazard that was not merely foreseeable but was foreseen by Central[70].
Interpretation of the Contract: Implied Terms
"(1) It must be reasonable and equitable; (2) it must be necessary to give business efficacy to the contract, so that no term will be implied if the contract is effective without it; (3) it must be so obvious that it "goes without saying"; (4) it must be capable of clear expression; (5) it must not contradict any express term of the contract."
Application of principles: breach of contract by Central
i) Failing to request the isolation of the heaters, which is alleged to be a failure to take all precautions within its power necessary for the prevention of fires, contrary to clause 8.18(a);ii) Failing to conduct all operations in a manner to avoid damage and failing to take all reasonable and necessary precautions against risk of damage, contrary to clause 8.18(b);
iii) Failing continuously to inspect the Work, contrary to clause 8.18(b);
iv) Failing to prepare and maintain reports of previous incidents where heaters were found to be on in the birdcages, contrary to Clause 18.8(b).
Application of principles: breach of contract by Mueller
Conclusions
Issue 2: Waiver
Applicable Principles
Discussion
Conclusions
Issue 3: Estoppel by Convention
Discussion and Conclusion
Issue 4: Contributory Negligence
Discussion of Principles
proximity to the heaters, were at fault in failing to operate either the system envisaged by the method statement or any other system for ensuring that the heaters posed no risk to life or property, even after it knew that the heaters were not being routinely isolated; and it was also at fault for failing to bring to Mueller's attention the fact that the heaters were not being isolated and posed a high risk of fire. Mr Henwood was at fault in failing to alert either Mr Thomas or Mr Jones to the incidents that had occurred or to the risk of further incidents, and in allowing the works to continue without taking any steps to guard against the risk of fire. Mr Thomas recognised (correctly) in his evidence that he was at fault in failing to carry out monitoring or supervision that would have identified the happening of the earlier incidents and the fact that his method statement was not being followed. On the other side of the contracting fence, Mueller's failure to appreciate that it was not routinely isolating the burners and that they posed a high risk of fire cannot possibly be justified. Primary responsibility must fall on the shoulders of Mr Jones, for his failure to read the method statement and his failure thereafter to appreciate the risk created by the proximity of the heaters to be scaffolds, which led to Mueller's continuing failures to isolate the heaters. Some responsibility must also lie with Mr Smith, who failed to alert Mr Jones when he knew of at least one "near miss" before the fire. The seriousness of the lapses is acknowledged by senior management on both sides who accepted that they would have justified the taking of disciplinary proceedings against the valued employees within their organisations who were directly responsible, though in the event none was taken.
Issue 5: Causation of Loss
The Applicable Principles
"In my judgment there does not have to be recklessness and nothing less than recklessness on the part of the buyer before a seller can disclaim liability for damage in respect of which the buyer claims an indemnity. It is, as Lawton L.J. said yesterday, always a question of degree at what point the damage claimed for ceases to flow naturally and directly from the breach." [Emphasis added]
"Where a Plaintiff does not know of a defendant's breach of contract and where he is entitled to rely upon the defendant having performed his contract, it will only be in the most exceptional circumstances that conduct of the Plaintiff suffices to break the causal relationship between the defendant's breach and the plaintiff's loss.
The plaintiffs' conduct was not voluntary in the sense of being undertaken with a knowledge of its significance. Conduct which is undertaken with a knowledge of its significance. Conduct which is undertaken without an appreciation of the existence of the earlier causal factor will normally only suffice to break the causal relationship if the conduct was reckless. It is the character of reckless conduct that it makes the actual state of knowledge of that party immaterial."
Discussion
PART 2 – QUANTUM
Summary of Conclusions on Quantum
Agreement and the Outstanding Issue on Quantum
___________________________________________________________________________
SCHEDULE OF AGREEMENT AND DISAGREMENT ON QUANTUM ISSUES
___________________________________________________________________________
Description | AGREEMENT/ DISAGREEMENT (Exclusive of interest) |
PROPERTY DAMAGE | |
Buildings | |
Total Phase 1 | 2,961,940 |
Total Phase 2 | 6,168,723 |
Machinery & Equipment | IN DISPUTE |
Loss of finished goods | 228,000 |
TIME ELEMENT | |
Loss of gross profit | |
UK loss of gross profit | 1,169,532 |
Export loss of gross profit | 1,200,000 |
Increased costs of working | |
Additional Rebates | 1,000,000 |
Purchase of Finished Goods | 1,401,181 |
Mueller US Related Costs | 0 |
Added Value on US Purchases | 0 |
Freight and Duty Costs | 122,000 |
Additional Customer Support | 60,000 |
Loss of margin on export contracts | 386,000 |
Total savings | (1,375,637) |
i) Mueller claims £8,036,150, which is the agreed cost of repair and replacement of the large diameter machinery and equipment damaged or destroyed in the fire on what Mueller contends is a like-for-like basis; whileii) Central contends that Mueller should recover £4,131,118, which is the agreed sum of money actually expended or in the process of being expended by Mueller (or its parent) in the UK and in the US in purchasing large diameter machinery.
The Factual Background – Quantum
i) One of the 30 tonne draw benches (no. 16) was reinstated at Bilston in June 2012 after being repaired and a replacement for the other (no. 17) will be installed at Bilston with completion in 2014;
ii) The 50 tonne draw bench no. 14 is going to be "replaced" by the installation of a 30 tonne draw bench at the group's plant in Fulton, USA, in the near future.
Discussion
The Relevant Principles
Application to the Facts of the Present Case
"Central contends that Mueller will have been restored to its pre-fire position when:
(i) Mueller was put in the position (by the repair or replacement of damaged machinery) that enable it to have the capacity to produce its product (large diameter tubing) and achieve profits from that production, as it had before the fire; and
(ii) Mueller has been compensated for any foreseeable loss of profit for its lack of capacity after the fire and before its pre-fire production capacity was restored; and
(iii) Mueller has been compensated for the cost of replacing or repairing the equipment required to restore the pre-fire production capacity and capability; and
(iv) Post-fire Mueller has equipment having a capital value which is at least equal to the pre-fire capital value of the machinery."
Conclusion
Note 3 Including F1/15, 67, 71 [Back] Note 5 In re-examination he suggested he may not have seen it until after the fire. That evidence is rejected. [Back] Note 8 Although Mr Parsons’ statement suggested that Mr Davies was there, that was not confirmed by other witnesses and the entries in Mr Henwood’s diary (L/196) and Mr Thomas’ notes (P/113A-C) do not record him being there. [Back] Note 12 See D24/[32]. The reference to “Gareth Jones” is an error. Although cross-examination established that he could not remember at which meeting Mr Thomas had said this, Central did not challenge his recollection of it being said. [Back] Note 13 T6/118.10-120.13 [Back] Note 14 T6/120.14-121.3 [Back] Note 16 T5/141.21-142.2 [Back] Note 18 Poly-vinyl-chloride sheeting was put up to as to enclose the asbestos removal works within the birdcage. [Back] Note 20 A/33. And see Section 3 “Setting Standards” – A/36 [Back] Note 22 A/37 – and see the method statement. [Back] Note 28 A/45 – but the risk assessment that was carried out was very general and did not identify the heaters as a potential hazard. Mr Thomas’ evidence was that this was covered instead by the method statement. [Back] Note 30 T6/152.15-153.25 [Back] Note 32 The contractual significance of the method statement is discussed later. What cannot be disputed is that Mr Jones knew the function of the method statements and that he would have the opportunity to object if he found anything in them unacceptable. [Back] Note 33 It appears that he was not a direct employee of Mueller, but this does not affect the nature of his responsibilities. [Back] Note 37 For example, an occasion when a scaffold was tampered with when it should not have been. [Back] Note 38 T2/130.6-137.14 [Back] Note 41 Mr Hardy was not aware that isolations could be entered on permits to work. [Back] Note 42 J10, 32. J32 was signed by Mr Henwood as accepter of the permit although the work was to be carried out by SCS personnel. [Back] Note 43 Other permits requiring or referring to isolation of the cranes were issued to Estil (J26, 44, 47) and Mueller’s own employees (J61, 64), the last of these being issued on 28 February 2008. [Back] Note 44 I reject the suggestion made by Mr Jones in his evidence that the fact of issuing monthly permits meant that isolations might not be needed during the currency of the permit. Most, if not all, monthly permits would have covered at least one move of a scaffold which required isolations that could (and should, if the method statement had been followed) have been provided for on a permit to work. [Back] Note 45 See Central’s closing submissions at [41], based on T3/85.8-9. See more generally, T3/84.9-85.9 and see also T3/89.4-10 and T7/37.25-40.1 [Back] Note 46 Central Opening at [28.5] [Back] Note 47 Central Opening at [29] [Back] Note 48 Central Opening at [29.6] [Back] Note 49 Central Closing at [52], [59] [Back] Note 50 See T4/35.13-36.13 and 66.23-67.22 [Back] Note 51 As happened at the meeting on 6 November 2008. Even if no specific requests for isolation was made in so many words by Mr Henwood on every occasion, it would be implicit in the discussion about the cranes which routinely occurred. [Back] Note 52 Mr Hotchkiss recorded him as saying on 12 November 2008 “heaters unplugged already”, without qualification. But on 18 December 2008 he recorded him as saying that he could not recall if all heaters were already unplugged or whether some were still plugged in. [Back] Note 53 In addition, he had given a similar account to the Fire Brigade’s Investigating Officer, Mr Bennett, on 11 November 2008, when he had said that the incident had been within Phase 6b: F2/379. [Back] Note 60 ICS Ltd v West Bromwich BS (HL) [1998] 1 WLR 896, 912H per Lord Hoffmann [Back] Note 61 Charter Re v Fagan [1997] AC 313, 348B-C per Lord Mustill [Back] Note 62 See ICS at 912H-913B, Chartbrook v Persimmon [2009] 1 AC 1101 at [38- 42] [Back] Note 63 GNER v Avon [2001] 2 Lloyds Rep 649 at [29] per Longmore LJ [Back] Note 64 Reardon Smith Line Ltd v Hansen-Tangen [1976] 1 WLR 989 at 995 per Lord Wilberforce [Back] Note 65 Gan Insruance Co Ltd v Tai Ping Insurance Co Ltd (No 2) [2001] 1 All ER (Comm) 299 at [16] [Back] Note 66 See BHP Petroleum Ltd v Briths Steel Plc [2000] 2 Lloyd’s Rep 277, 281 per Evans LJ [Back] Note 67 Mueller’s allegation that there was an implied term that Central would comply with the terms of the Health and Safety Plan and method statement gives rise to different and broader considerations, and is addressed at [87] below. [Back] Note 70 That is why Mr Thomas identified in the method statement a failsafe mechanism for them to be switched off: see T6/119.4-8, 126.9-13, 139.23-140.8, 142.25-143.17. Mr Henwood knew the heaters were an obvious fire risk: T7/28.3-14 [Back] Note 71 Clauses 3.1 “Upon receipt of a request from [Mueller] … [Central] shall furnish …”, 7.2(d) “Upon request, [Central] will provide …”, and 8.15(c). [Back] Note 72 Clauses 7.3(b) “Each subcontract must contain provisions that:… require that the subcontractor’s work be performed …”, 7.3(c) “Each subcontract must contain provisions that: … require submission to [Central] of applications for payment;”, 8.7 “If any of the Work is required to be inspected or approved by a Government authority, [Central] shall cause such inspection … to be performed.”, And “[Mueller] reserves he right to specify and require [Central] to perform additional job safety and health training … and require [Central] to certify its compliance in writing.”, 10.1 [Central] will procure and maintain … whatever other insurance [Mueller] may require …” [Back] Note 73 Clauses 8.9 “… as required during the contract works.”, 8.15(d) “… [Central] shall not be liable for or be required to incur any expense resulting from any environmental condition …”, 8.16 “If [Central] knows or should know that the Work required under the Contract Documents is at variance with ….”, 9.2 “if employment of separate counsel is required because of a conflict of interest…”, and 8.13(a) “To the extent that training of its employees … is required under any ... rules or regulations, Central further agrees that its employees … will receive such training as is required.” [Back] Note 76 The obligation to co-operate on safety matters was expressly imposed on the parties by Clause 8.18(b). [Back] Note 77 See [7], [20] and [21] above. [Back] Note 78 Subject to the argument that Mr Jones would have issued permits confirming that the heaters were off without ensuring that the permit was correct, which I have rejected as a matter of fact. [Back] Note 79 Not least because of his frank and patently genuine response that he was “horrified” when he found out after the fire that the system had not been operated properly: T6/166.24 [Back] Note 82 There is no inconsistency between (a) holding that the method statement was sufficient to trigger Mueller’s obligations as a “request” for the purposes of clause 8.9 and (b) holding that Central should have made further (and effective) requests in order to take all precautions in its power at a time when it knew or ought to have realised that the provision of the method statement had not been effective and that the procedure contemplated by the method statement was not being implemented. In that state of knowledge, the making of further requests was a precaution that was within Central’s power and was necessary for the prevention of fires. [Back] Note 83 “Contractor will conduct all operations under the Contract Documents in a manner to avoid, and will within its scope of Work promptly take all reasonable and necessary precautions against risk of loss, theft or damage by vandalism, sabotage or otherwise, to all or any part of the Work.” [Back] Note 84 Borealis at [45] [Back] Note 85 See by analogy in the law of tort, Reeves v Commissioner of Police [2000] AC 360 [Back] Note 86 T2/146.1-2, which is consistent with his evidence generally that he was relying upon Central to tell him what they wanted done. [Back] Note 87 See Parsons T5/8-12, Marsh D212.8b/[7] [Back] Note 88 Marsh T8/49.19-24, 56/7-19 [Back] Note 89 Parsons T5/16-20 [Back] Note 90 Parsons T5/120.1-7, 139.17-140.5 [Back] Note 92 The Kingsway [1918] P 344 [Back] Note 93 The London Corporation [1935] P 70; and see, more recently, Jones v Stroud DC [1986] 1 WLR 1141, The Maersk Colombo at [71(1) & (2)], Burdis v Livsey [2003] QB 36 CA at [84].
[Back]