QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
JONATHAN PAUL HUNT and others |
Claimants |
|
- and - |
||
OPTIMA (CAMBRIDGE) LIMITED |
First Defendant |
|
-and- |
||
STRUTT & PARKER (a firm) |
Second Defendant |
|
-and- |
||
STEPHEN EGFORD |
Third Defendant |
|
-and- |
||
STRUTT & PARKER LLP |
Fourth Defendant |
____________________
Seb Oram (instructed by Howard Kennedy Fsi LLP) for the First Defendant
Katie Powell (instructed by Simmons & Simmons LLP) for the Second to Fourth Defendants
Hearing dates: 29 April 2013
____________________
Crown Copyright ©
Introduction
Interest
(a) She argues that the rate should reflect the fact that the diminution as found gives the Claimant more than they would have recovered if damages had been assessed on a cost of repairs basis. This is not a good point because(i) in relative terms, the large part of the capital diminution relating as it does to the acoustic and floor deflection problems does not reflect the true cost of repairs at all, and (ii) the fact of the matter is that the Claimants each spent more purchasing their properties than they were worth and their loss (however it was calculated) accrued when they purchased the properties.
(b) She says that the general damages awarded to the Claimants against Optima in some way would provide an element of double recovery. This is a "de minimis" point given the very modest amount of general damages awarded. It is in any event a bad point because the general damages are compensating the Claimants for the inconvenience and aggravation largely caused by Optima and not for having paid too much for their properties in the first place.
(c) Next, it is said that, if the Claimants spend their damages (payable by S&P) in repairing their properties, the flats will be in a better condition than they would have been had the works been carried out in the first place. This is to confuse the basis upon which the damages have been awarded against the two sets of defendants. It is undoubtedly the position in any event that the capital diminution reflecting the problems with the acoustics and the floors does not compensate them directly or adequately for the whole cost of putting right those problems. Again the argument runs into the brick wall that the Claimants overpaid for their properties from the start.
(d) Finally, she argues that it is artificial to characterise the Claimants as having suffered loss from the date of purchase. That is also an unsustainable point because the capital diminution, which was the basis of damages assessment accepted as appropriate by all parties in this litigation in relation to S&P, reflects the fact that each of the Claimants paid more for their properties than they should or would have done if the defects for which S&P is liable were not present.
"(1) Where a claimant has delayed unreasonably in commencing or prosecuting proceedings, the court may exercise its discretion either to disallow interest for a period or to reduce the rate of interest.
(2) In exercising that discretion the court must take a realistic view of delay. In the case of business disputes, litigation is for all parties an unwelcome distraction from their proper business. It is not reasonable to expect any party to take every litigious step at the first possible moment, or to concentrate on litigation to the exclusion of all else. Delay should only be characterised as unreasonable for present purposes when, after making due allowance for the circumstances, it can be seen that the claimant has neglected or declined to pursue his claim for a significant period.
(3) When determining what disallowance or reduction of interest should be made to mark a period of unreasonable delay, the court should bear in mind that the defendant has had the use of the money during that period of delay."
Costs
i. On 8 August 2012, the Claimants' solicitors made a "without prejudice save as to costs" offer to Optima which involved Optima purchasing the flats back at the prices paid by the Claimants, £4,000 each for legal costs on sale and purchase, £9,000 paid for moving costs, £26,000 for stamp duty and costs of £180,000. The offer called for exchange of contracts by 23 August 2012, completion by 12 October 2012 and for the provision of security pending completion.ii. Optima replied the following day saying that settlement by reference to the purchase price of the properties was incorrect in law.
iii. On 10 August 2012, Optima made what it called a Part 36 offer ("Optima's Offer") by which it would purchase the six flats at the open market value as at that date plus £5,000 to each of the Claimants in addition to the agreed purchase price. The open market value was to be determined as the average of three valuations, with the Claimants appointing two valuers and Optima one. In addition it would pay £3,000 per flat for legal costs of sale and purchase, £1,500 per flat for moving costs and £26,000 for stamp duty; exchange was proposed by 10 September 2012 with completion by 10 December 2012. In effect costs were offered also to be assessed if not agreed.
iv. That was responded to on the same day by the Claimants' solicitors. The Claimants were not willing to accept a valuation as at August 2012 but did accept the sums offered for legal costs on sale and purchase, moving expenses and stamp duty; they wished to have a fixed sum for costs. They required completion by 12 October 2012 and exchange by 10 September 2012; on this basis no security was required.
v. There was an exchange of e-mails about the possible provision of security by Optima in late August prior to a meeting between all three parties on 30 August 2012 On 31 August 2012, S&P's then solicitors wrote "without prejudice save as to costs" not actually offering anything on behalf of S&P but encouraging the Claimants to accept settlement on the basis of re-purchase by Optima because it was their view that this would "put your clients in the position that they would have been in but for any poor construction and the offer to compensate incorporate your clients' costs". This confused the Claimants' solicitors who inquired on the same day whether Optima's offer was a joint offer; the reply was that the offer was made by Optima "in full and final settlement of all of your clients' causes of action against the defendants". On 5 September 2012, the Claimants' solicitors replied asking what would happen about S&P's costs and if Optima defaulted. S&P's solicitors replied by e-mail on 6 September 2012 that their clients would pay their own costs but would not contribute to a settlement "which pays to the claimants anything other than the current market value of the flats" and that Optima should provide security.
vi. On 12 September 2012, the Claimants' solicitors wrote to the other parties saying that Optima's Offer was not on analysis a Part 36 offer. They offered to settle on the basis of re-purchase by Optima at 10% less than the original purchase prices, exchange by 5 October 2012, completion by 10 December 2012 and with £53,000 to be paid for moving expenses, legal costs for sale and purchase and stamp duty. In addition £162,000 including VAT was to be paid for costs.
vii. On 19 September 2013, Optima withdrew its offer.
viii. Nothing material happened in relation to offers (at least in relation to such offers as can be considered by the Court) until 4 February 2013 when S&P's solicitors wrote with the concurrence of Optima's solicitors offering to settle on the basis of re-purchase by Optima at purchase prices of 12.5% less than the original purchase prices, with the payment of £5,000 for each flat for compensation and £53,000 for removal costs, legal costs of sale and purchase and stamp duty. Additionally S&P would pay £250,000 for costs to the Claimant. The offer purported to be a Calderbank offer. I will call this the "4 February Offer".
ix. On Wednesday, 13 February 2013, S&P made five separate offers purportedly pursuant to Part 36 to each of the First, Second, Third, Fourth, Sixth, Seventh and Eight Claimants. A further offer was made to the Fifth Claimant on Thursday, 14 February 2013. By those offers, S&P offered £81,700 to Mr Hunt, £45,600 to Mr Bedwell, £60,500 to Mr and Mrs Sahi, £49,500 to Ms Ransome, £15,000 to Ms Wyatt and £58,500 to Mr and Mrs Peace. These offers ("The 13 February 2013 Offers") were inclusive of interest and by implication at least offered to pay the Claimants' costs.
x. The trial started on the following Monday and the 4 and 13 February Offers were not accepted.
Name | Offer | Judgment Value + interest |
Ms Ransome | £49,500 | £76,714 (+£24,000) |
Ms Wyatt | £15,000 | £41,547 (+£26,000) |
Mr and Mrs Sahi | £60,500 | £58,630.38 (- £1,869.62) |
Mr Hunt | £81,700 | £76,326 (-£5,373) |
Mr Bedwell | £45,600 | £43,056 (-£2,543) |
Mr and Mrs Peace | £58,500 | £56,458 (-£2,041) |
(a) She argues that Ms Ransome only beat the offer because she won on the conservatory issue and that new evidence only emerged during the trial. However, as Counsel accepts, even without the conservatory findings, Ms Ransome would have beaten the offer by more than £2,000. The point is a bad one in any event because the pleaded case against the Defendants was predicated clearly and obviously on the conservatory being defective and part of the obligation undertaken by Optima as well as being part of the responsibility of S&P to inspect; the Scott Schedule makes that clear. I do not consider that the relatively limited additional evidence which emerged added very much; a key piece of evidence was the e-mail dated 5 September 2003 referred to in Paragraph 191 of the judgement which was not new evidence. There was existing evidence that Mr Egford had applied his mind to the conservatory at the time.
(b) Finally, Counsel argues that Ms Wyatt would not have succeeded if the late amendment made on the first day of the trial had not been allowed; thus she argues that the offer when made was one which should have been accepted. This again is a bad point. It is undermined by the fact that, even after the amendments were made, there was no new offer to reflect the amendments. In any event, the amendments were substantially clarificatory with the collateral warranty clearly alluded to in Paragraph 26 of the Amended Particulars of Claims and the duty of care relating to the inspections being alluded to in Paragraphs 26 and 27.
Interim Payment on account of Costs
Miscellaneous Matters
(a) The costs of and occasioned by the Claimants' amendment application during the trial should be borne by the Claimants and the Defendants' consequential costs should be paid by the Claimants.
(b) The costs of and occasioned by the Claimants' applications referred to in Paragraphs 96 to 101 of the first judgment should be borne by the Claimants and the Defendants' costs relating thereto should be paid by the Claimants. The costs of and occasioned by Optima's application referred to in Paragraph 96 and 100 should be borne by Optima and the Claimants' costs relating thereto should be paid by Optima.
(c) There has been no order made in relation to the Amended Particulars of Claim served in November 2012. Apart from the production of the Scott Schedule which should be considered as costs in the case, the Claimants should pay their own costs of the amendment and pay for the Defendants' consequential costs of pleading to the Amended Particulars of Claim.
"I. This case, transferred to this Court from the Cambridge County Court, was the subject of directions given by Mr Justice Ramsey on 17 July 2012. The trial was listed for 18 February 2013. However the trial timetable required the Claimants to serve draft Amended Particulars of Claim and a draft Scott Schedule by 28 September 2012, it being clear that the existing Particulars of Claim were inadequate to set out the basis of the claims relating to defects pursued by the Claimants. There is nothing on the record to suggest that the Claimants at that stage considered that the Defence of the Second to Fourth Defendants, which was a reasonably full document, was inadequate or inadequately pleaded or particularised.
II. The Claimants' Request for Information of the Defence was served on 21 August 2012 and on its face called for a reply by 31 August 2012, which was optimistic in any event. The Request itself asks for particulars in effect relating to what was expressly certified (allegedly) by the Third Defendants. Thus, these Defendants have quoted from these certificates in Paragraph 23 and the Claimants seek to know what was meant in various quoted parts of those certificates. I doubt, without finally deciding the point, that the Request is justified because Paragraph 23 of the Defence is simply quoting from documents issued. Paragraph 23 does not involve an assertion that the contents of the certificates were true or carefully made.
III. I do not consider that it was appropriate to seek an "unless" order a few days after the arbitrarily fixed compliance date had passed. In my view there is much in what the Defendants say that it would be inappropriate to make any "unless" order either within such a short time frame, or without a hearing, or in circumstances in which the Claimants are expressly required to produce substantial and significant further pleadings.
IV. If the Claimants wish to pursue the obtaining of Further Information as requested, they may do so but they would need to issue another application and fix a 30 minute appointment. I have reserved the question of costs...."
These reasons themselves justify the award of costs. These costs should be assessed on a standard basis by the Costs Judge.
Claimant | Against Optima | Against S&P |
Mr Hunt (1st) | £84,822.83 £1,100 £2,000 |
£53,460 |
Mr Bedwell (2nd) | £60,023.14 £427 £1,850 |
£30,800 |
Mr and Mrs Sahi (3rd/4th) | £213 | £51,650 |
Ms Ransome (5th) |
£80,137.08. £550 £1,850 |
£52,390 |
Ms Wyatt (6th) | £108,141.51 £375 £1,850 |
£28,450 |
Mr and |Mrs Peace (7th/ 8th) | £573 | £43,300 |
Bar the two married couple Claimants, the sums awarded against Optima substantially exceeds what has been awarded against S&P. Also there are some losses awarded against Optima in respect of items which are not awarded against S&P; for instance the general damages and various defects (the mansard roofs and the soffit board). Furthermore, Optima should not get the "benefit" of the percentage mark-up proposed by Mr Swinley and accepted by me (+50%) because that relates to the capital diminution purely and simply.
Permission to Appeal
(i) It is not reasonably arguable that there was no collateral contract between the first six Claimants and S&P. The wording was reasonably clear and authorities in relation to the effectiveness of consideration passing in this case to Optima are well-established.
(ii) It is not reasonably arguable that no duty of care was owed to the Claimants in relation to the performance of the professional services referred to on the face of the Certificates. This is a matter of logic and is in any event broadly covered for instance by the victor of Lord Templeman in Smith v Bush.
(iii) It is not reasonably arguable that there was no reliance. This was largely a matter of fact.
(iv) It is not reasonably arguable that Section 14A of the Limitation Act not apply on the facts to Ms Wyatt's claim. It is unrealistic to proceed on the basis that merely because a small percentage of the defects were known about earlier by her that Section 14A can not be deployed in relation to the more serious defects which she could not reasonably be expected to have known about as justifying any cause of action against S&P.