QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
NATAS GROUP LIMITED (IN ADMINISTRATION) |
Claimant |
|
- and - |
||
STYLES & WOOD LIMITED |
Defendant |
____________________
Jonathan Selby (instructed by Weightmans LLP) for the Defendant
Hearing dates: 12 and 19 December 2011
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Background
"2.4.1 The Joint Administrators "assigned two Company debtors [sic] to Asbestos Contamination Services Limited ("ACSL"). Mr Lopacki, a Director of [the Claimant] is a Director and Shareholder of [ACSL]. Mr Lopacki sought independent legal advice prior to assignment.
2.4.2 ACSL are pursuing these debtors on the basis that a percentage of the realisations shall be paid to the [Claimant] for the benefit of creditors. The assignment was made in order to ensure that no cost order could be made against the [Claimant] whilst ensuring a successful action would be of benefit to the creditors of the company. The Joint Administrators undertook the assignment following advice from Naismiths Ltd, independent professional appraisers with specific knowledge of the construction litigation."
The report concludes with noting that the administrators should give full support and assistance to ACSL in its action against the Defendant.
The Security Application-The Law
"12…Thus, the threshold to the Court having jurisdiction where the claimant is a company is that there is reason to believe that it will be unable to pay the defendant's costs if ordered to do so. Once the threshold is established, the Court has a broad discretion as to whether to order security for costs and if so in what amount.
13. Although the case of Keary Developments Ltd v Tarmac Construction Ltd [1995] 3 All ER 534 occurred before the Civil Procedure Rules, the judgement of Peter Gibson LJ provides useful guidance as to the criteria to which a court can and should have regard when deciding as a matter of discretion whether to order security for costs in the case of a company:
"The relevant principles are, in my judgement, the following.
1. As was established by this Court in Sir Lindsay Parkinson and Co Ltd v Triplan Ltd … [1973] QB 609, the court has a complete discretion whether to order security, and accordingly it will act in the light of all the relevant circumstances.
2. The possibility or probability that the plaintiff company will be deterred from pursuing its claim by an order for security is not without more a sufficient reason for not ordering security…By making the exercise of discretion under s 726 (1) [ of the Companies Act] conditional on it being shown that the company is one likely to be unable to pay costs awarded against it, Parliament must have envisaged that the order might be made in respect of a plaintiff company that would find difficulty in providing security…
3. The court must carry out a balancing exercise. On the one hand it must weigh the injustice to the plaintiff if prevented from pursuing a proper claim by an order for security. Against that, it must weigh the injustice to the defendant if no security is ordered and at a trial the plaintiff's claim fails and the defendant finds himself unable to recover from the plaintiff the costs which had been incurred by him in his defence of the claim. The court will properly be concerned not to allow the power to order security to be used as an instrument of oppression, such as by stifling a genuine claim by an indigent company against a more prosperous company, particularly when the failure to meet that claim might in itself have been a material cause of the plaintiff's impecuniosity…but it will also be concerned not to be so reluctant to order security as it becomes a weapon whereby the impecunious company can use it inability to pay costs as a means of putting unfair pressure on the more prosperous company…
4. In considering all the circumstances, the court will have regard to the plaintiff company's prospects of success. But it should not go into the merits in detail unless it can clearly be demonstrated that there is a high degree of probability of success or failure…
5. The court in considering the amount of security that might be ordered will bear in mind that he can order any amount up to the full amount claimed by way of security, provided that it is more than simply a nominal amount; it is not bound to make an order of a substantial amount…
6. Before the court refuses to order security on the ground that it would unfairly stifle a valid claim, the court must be satisfied that, in all the circumstances, it is probable that the claim would be stifled. There maybe cases where this can be properly be inferred without direct evidence…
However, the court should consider not only whether the plaintiff company can provide security out of its own resources to continue the litigation, but also whether it can raise the amount needed from its directors, shareholders or other backers or interested persons. As this is likely to be peculiarly within the knowledge of the plaintiff company, it is for the plaintiff to satisfy the court that it will be prevented by an order of the security from continuing the litigation…
7. The lateness of the application for security is a circumstance which can properly be taken into account…"
14. HHJ Peter Coulson QC (as he then was) summarised various principles relating to the potential stifling of a genuine claim in William Newman v Wenden Properties Ltd [2007] EWHC 336 (TCC):
"It is often argued that the application for security for costs, if allowed, would stifle a genuine claim. In consequence, the courts have refined this element of the discretion under CPR Part 25. It seems to me that the following principles are relevant to the present application:
"9 (a) Where an order for security for costs against the claimant company might result in oppression, in that the claimant company would be forced to abandon a claim which has a reasonable prospect of success, the court is entitled to refuse to make that order, notwithstanding that the claimant company, if unsuccessful, would be unable to pay the Defendant's costs (see Aquilla Design (GRB) Products Ltd. -v- Cornhill Insurance plc [1988] BCLC, 134, Court of Appeal);
(b) Before the court refuses to order security on the ground that it would unfairly stifle a valid claim, the court must be satisfied that in all the circumstances it is probable that the claim would be stifled (see Keary Developments Ltd. -v- Tarmac Construction Ltd. [1995] 2 All E.R., 535, Court of Appeal);
(c) In all but the most unusual cases, the burden lies on the claimant company to show that, apart from the question of whether the company's own means are sufficient to meet an order for the security, there will be no prospect."
"These three cases are not absolutely determinative as to whether ATE insurance can provide adequate or effective security for the defending party's costs. That is not surprising because it will depend upon whether the insurance in question actually does provide some secure and effective means of protecting the defendant in circumstances where security for costs should be provided by the claimant. What one can take from these cases, and as a matter of commercial common sense, is as follows:
"(a) There is no reason in principle why an ATE insurance policy which covers the claimant's liability to pay the defendant's costs, subject to its terms, could not provide some or some element of security for the defendant's costs. It can provide sufficient protection.
(b) It will be a rare case where the ATE insurance policy can provide as good security as a payment into court or a bank bond or guarantee. That will be, amongst other reasons, because insurance policies are voidable by the insurers and subject to cancellation for many reasons, none of which are within the control or responsibility of the defendant, and because the promise to pay under the policy will be to the claimant.
(c) It is necessary where reliance is placed by a claimant on an ATE insurance policy to resist or limit a security for costs application for it to be demonstrated that it actually does provide some security. Put another way, there must not be terms pursuant to which or circumstances in which the insurers can readily but legitimately and contractually avoid liability to pay out for the defendant's costs.
(d) There is no reason in principle why the amount fixed by a security for costs order could not be somewhat reduced to take into account any realistic probability that the ATE insurance would cover the costs of the defendant."
The Security Application-Evidence and Argument
(a) Its claim will be stifled by a further security requirement.
(b) The Counterclaim should be taken into account and security should not be granted.
(c) The Claimant's impecuniosity has been caused or contributed to by the Defendant's failure to pay sums due to it.
(d) ATE insurance worth £250,000 has been obtained.
(e) The amount of security sought overall (c. £280,000) is in any event excessive.
The Defendant challenges all these points. It argues that the evidence about stifling was and remains "thin", that the Counterclaim is simply a consequential reflection of the Defence and that it has no independent "vitality", that the impecuniosity point is not established, that the ATE insurance does not provide any or any significant comfort and that something between two-thirds and three-quarters of the overall costs should be provided by way of security. It also asserts that part of the reason for the costs being increased above the earlier estimate relates to procedural incompetence and delay on the part of the Claimant.
(a) Mr Taylor in his first witness statement dated 9 December 2011 says on instructions that "a major cause of [the Claimant] having to go into Administration was the Defendant's failure to properly reimburse it for the works it undertook on the John Lewis Partnership project in question". He says that the £144,000 sum paid into court related to the period up to and including exchange of experts' reports. He explains that T&S is the "major creditor by far" and that it too has become insolvent as a result of significant underpayment to it. He says that the original application for security was very late in the day. He says that the Counterclaim arises out of the same facts and circumstances of the claim and "it is difficult to see what if any costs are being saved as the costs would be incurred in any event in relation to the Counterclaim." In this first statement, he simply refers to the existence of the ATE insurance with costs cover of £250,000 and accepts that "there are arguments that such cover is not 100% guaranteed" albeit he suggests "at the very least the Defendant's exposure is significantly reduced by such a policy." He points to the fact that an undisclosed payment certificate from John Lewis's quantity surveyor demonstrates that a sum of just under £29,000 was certified as due. He gives some evidence that the case is being funded by Mr Rees, a director of T&S and that this funding has come from family, friends and acquaintances; although he is responsible for all disbursements "and a small monthly retainer" to Mr Taylor's firm, he has been struggling to meet this commitment and is behind some months in payments. Mr Rees' first statement dated 12 December 2011 confirms that he is funding the claim, it having been initially funded partly by Mr Lopacki. He explains that he no longer has his business and is now in employment. He says that he will be unable to make any payments towards the provision of further security and explains that he and his wife separated and he is now funding two households. It is a short statement.
(b) Mr Taylor's second statement attaches the ATE insurance policy, albeit somewhat redacted. He confirms that his firm is instructed by the Administrators of the Claimant but he does not address the issue raised by Counsel for the Defendant at the first hearing relating to the assignment of the Claimant's claims against the Defendant to ACSL.
(c) Mr Rees goes into much more detail about his personal financial position. Thus he explains that T&S claims against the Claimant just over £2.2 million plus interest. Since its ceasing work, he has worked as a bricklaying contractor until August 2011 since when he has been employed by his son, being paid £1600 per month which after outgoings leaves him with about £200 per month. His wife lives in the matrimonial home and, although he jointly owns a one acre farm, there is little equity in it and his sons have taken over the payment of the mortgage in return for the property. He has £12 savings and is in debt on personal guarantees to the tune of some £48,000. He accepts that he owes the Claimant's solicitors, about £20,000. He says that he has borrowed money over the last year from various people but there is little or none left to be borrowed. He borrowed the £144,000 provided as security for costs from three named individuals. He attaches a number of corroborative documents.
(d) Mr Lopacki's witness statement explains that he has found it financially difficult to continue to fund the case due to debts, reduced income and living expenses and commitments. The potential return to him, he says, has diminished particularly in circumstances in which T&S is by far the largest creditor and there will be little or no equity left in the Claimant after any debts are paid off, to the extent that the claim succeeds. He believes that it is "unrealistic to expect Natas to recover its claim in full". He says that he simply does not have the available funds or income to fund the claim. He has "several business debts following the fact that Natas went into Administration and I am committed to grow my current company". His income has dropped and his outgoings continue to rise and he is "not willing or able to fund the case against" the Defendant. He does not address the assignment to his other company. He gives no detail of his financial position. There is another statement from another creditor, a Mr Robbins, who has provided quantity surveying services to the tune of some £60,000. He says he does not have savings or spare income, as his wife recently gave birth to twins.
(e) Mr Smailes, one of the administrators, provided a very late short statement. He says that he his report of July 2011 contains an error and states simply:
"4. There were 2 deeds of assignment entered into between Natas (executed by the Administrators) and Asbestos Contamination Services purporting to assign 2 debts owing by [the Defendant] to Natas. Both [the Defendant] and Mr Tomlinson are aware that the Birmingham County Court found that the assignment of the Lloyds Bank project debt was ineffective as an assignment. As both the assignments were identical, simply a different project, the purported assignments of the debt due on the John Lewis project Debt was also ineffective. Accordingly a new arrangement was entered into whereby Max Lopacki was appointed by the Administrators to recover the debt at his cost.
5. Subsequently Max Lopacki could no longer afford to fund the claim and a similar agreement was entered into with Anthony Rees whereby he would on behalf of the Administrators collect in the debt at his cost."
No details of these arrangements or agreements are provided.
"In relation to condition 5(a) of the policy wording, No claim would fall to be paid under the ATE policy unless the client(s) lost entirely on all heads of their claim and any counterclaim from the opponents and an order for costs was made against them save for the deficiency in damages".
"Deficiency of damages " is defined as arising where "any Opponent's Legal Costs, Funded Own Legal Costs, Funded Disbursements, Premium, and Loan/Funding interest and Fees that the Insured is liable to pay…exceed the total amount of Damages and costs awarded to the Insured against the Opponent in the event of a claim reaching a Successful Conclusion". "Successful Conclusion" is defined as being one "where the Insured is awarded an amount in respect of damages and or costs". The Limit of Indemnity is the "aggregate amount payable by the Insurer under this policy in respect of Opponent's Costs, Own Disbursements, Own Costs, interest, funding fee and VAT if applicable".
"The Insurer shall only be liable to make a payment under this Policy either:
(i) the Court orders the Insured to pay Opponent's Legal Costs and the Proceedings are not subject to any further legal action; or
(ii) the Legal Representative advises that the Insured has no reasonable prospects of success and the insurer has given its prior written consent to and agreed the terms of the compromise, discontinuance or withdrawal of Proceedings including the terms of such a settlement."
Clause 8 provides:
"In the event of misrepresentation, misdescription or nondisclosure of any material particular by the Insured in relation to either the formation of the contract of this insurance or the conduct of the Proceedings, the Insurer shall become entitled to avoid this Schedule forthwith upon giving notice of such avoidance to the Insured and the Premium paid to the Insurer shall be forfeited."
Clause 9 makes it clear that no person, not a party to the policy, has any right to enforce any terms of the policy.
"6. Proceedings which had been conducted in such a manner that, in the reasonable opinion of the Insurer, their position as insurers has been prejudiced as a result of the delay or other default by the Insured or the Legal Representative, save where such delay does not occasion material loss…
9. No claim shall fall to be paid under this policy unless the Insured has lost entirely on all sections or heads of the claim and any counterclaim from the opponents and a costs order has been made against the Insured unless specifically agreed otherwise in writing by the Insurer…"
"2. In cases where the Insurer is informed (or should have been informed) of any material development the Insurer may at its absolute discretion withdraw the benefit of this Policy and will have no liability to make any payment under this Policy from the date upon which the Insurer was notified or should have been notified of such material development. The Insurer shall provide the Insured with the written notification that the benefit under this Policy has been withdrawn."
Discussion
"2.19 Naismiths LLP advised that the Company's last application to payment, an unpaid balance of approximately £2 million, remained outstanding. However, Mr Robbins acknowledged that the claim is overstated in certain areas and considers that a recovery of up to £1,200,000 is more realistic."
The amount of £1,217,526 is identified as the amount claimed by non-preferential unsecured creditors in their Administrators' most recent report dated 26 July 2011. Mr Lopacki in his witness statement clearly believes that there is nothing in it for him to continue to fund the claim: he says that he would be "paying good money for no potential gain"; that suggests that the proceeds from the litigation will leave nothing to him, in his estimation. Debtors are said to be over £3m, which presumably includes sums said to be due from the Defendant
(a) It can not and should not be incumbent on the Court on a security for costs application to determine with any precision what the insurance policy, properly construed, actually is. What the Court can do is to identify risks and uncertainties and weigh them in the balance on the exercise of the discretion.
(b) Special Condition 1 could be read, in conjunction with Exclusion 9, as meaning that the insurer might not be liable if the Claimant succeeded on a section of its claim, say for instance, the claim identified in Schedule 1 to the Particulars of Claim, but lost overall because there were over-payments or excessive allowances on the other nine heads of claim. It could be read as meaning that, if the Defendant only succeeded on its Counterclaim to the tune of say 10%, there would be no liability on the insurer. I regard this as a not insignificant risk albeit that one would hope that any decent insurer would not take the point. There is no evidence before the Court about the pedigree of this Lichtenstein insurer. Additionally, if there has been or is to be a Part 36 offer made by the Defendant and if it was effective in that the Claimant "won" but did not "beat" the offer, there is an even greater chance that the insurer could argue that it had no liability at all to pay out anything.
(c) The termination Clause 2 is a worrying clause in the sense that there is no definition of what "material development" could lead the Insurer to withdraw the benefit of the Policy. It is highly arguable that a material development might be the discovery that a key witness can not support, any more, a significant part of the claim or that such a witness is not prepared to co-operate with the Claimant any more. If that is right, the insurers could pull out and the Defendant would be left with no security.
(d) Clause 8 has ramifications in respect of and over which neither the Court nor the Defendant can be aware or have any control. The Administrators will have procured this insurance, I presume, on the presentation of evidence and opinion supporting the Claimant's position. Whilst of course the Court does not expect these privileged documents to be put in front of it, it is at the very least reasonably arguable that any material misrepresentation or non-disclosure can lead to an avoidance of the policy, which would be retrospective in effect. It is of course not necessary that there should have been any fraud on the part of the Administrators.
(e) There is at least some confusion in the drafting of the policy as to how the premium is dealt with in circumstances in which there is an overall order for costs against the Claimant. The premium comes into the "deficiency of damages" calculations.
There is no certainty also that the disbursements of the Claimant will stay at the level suggested in their February 2011 estimate of costs or that breaches of the policy could not lead to the reduction in the cover available.
Decision