QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
JERRAM FALKUS CONSTRUCTION LIMITED |
Claimant |
|
- and - |
||
FENICE INVESTMENTS INC |
Defendant |
|
[No.4] |
____________________
Mr William Webb (instructed by Field Fisher Waterhouse LLP) for the Defendant
____________________
Crown Copyright ©
Mr Justice Coulson:
1: INTRODUCTION
2: THE ISSUES
Conclusivity Issues
a) Is the decision of the adjudicator in the third adjudication, dated 28.10.10, conclusive, such that JFC's arguments as advanced before the court are simply not open to them?b) Are JFC's Final Account and Final Statement conclusive as to the matters contained therein, such that Fenice cannot challenge JFC's claim for loss and expense?
c) Conversely, in the events that occurred, is it JFC who are prevented now from raising their delay claims as a result of the conclusivity of their own Final Account and Final Statement?
Prevention Issues
d) What caused the delays to the works?
e) Did Fenice prevent JFC from completing the contract works?
f) If Fenice did prevent completion, but the delay so caused was concurrent with delays which were JFC's fault, was time set at large?
Liquidated Damages
g) Was there an agreement to vary liquidated damages and, if so, what was the effect of that agreement?
h) Are Fenice entitled to £209,840 (gross) or £122,102.36 (net) by way of liquidated damages?
JFC's Final Account Claim
i) Are JFC entitled to £311,393.78 by way of their Final Account or some other sum?
3: THE CONTRACT TERMS
"1.9 1 The Final Statement, when it becomes conclusive as to the balance due between the Parties in accordance with clause 4.12.4, or the Employer's Final Statement, when it becomes conclusive as to the balance due between the parties in accordance with clause 4.12.7, shall, except as provided in clauses 1.9.2, 1.9.3 and 1.9.4 (and save in respect of fraud), have effect in any proceedings under or arising out of or in connection with this Contract (whether by adjudication, arbitration or legal proceedings) as:
1 conclusive evidence that where and to the extent that any of the particular qualities of any materials or goods or any particular standard of an item of workmanship was described expressly in the Employer's Requirements, or in any instruction issued by the Employer under these Conditions, to be for the approval of the Employer, the particular quality or standard was to the reasonable satisfaction of the Employer, but the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement shall not be conclusive evidence that they or any other materials or goods or workmanship comply with any other requirement or term of this Contract;
2 conclusive evidence that all and only such extensions of time, if any, as are due under clause 2.25 have been given; and
3 conclusive evidence that the reimbursement of direct loss and/or expense, if any, to the Contractor pursuant to clause 4.19 is in final settlement of all and any claims which the Contractor has or may have arising out of the occurrence of any of the Relevant Matters, whether such claim be for breach of contract, duty of care, statutory duty or otherwise.
2 If any adjudication, arbitration or other proceedings have been commenced by either Party before the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement, as the case may be, the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement, as the case may be, shall have effect as provided in clause 1.9.1 upon and from the earlier of either:
1 the conclusion of such proceedings, in which case the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement, as the case may be, shall be subject to the terms of any decision, award or judgment in or settlement of such proceedings; or
2 the expiry of any period of 12 months from or after the submission of the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement, as the case may be, during which neither Party takes any further step in such proceedings, in which case the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement, as the case may be, shall be subject to any terms agreed in settlement of any of the matters previously in issue in such proceedings.
3 If any adjudication, arbitration or other proceedings are commenced by either Party within 28 days after the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement, as the case may be, would otherwise become conclusive by the operation of clause 4.12.4 or 4.12.7, the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement, as the case may be, shall have effect as conclusive evidence as provided in clause 1.9.1 save only in respect of the matters to which those proceedings relate.
4 In the case of a dispute or difference on which an Adjudicator gives his decision on a date which is after the date of submission of the Final Account and Final Statement or the Employer's Final Account and Employer's Final Statement, as the case may be, if either Party wishes to have that dispute or difference determined by arbitration or legal proceedings, that Party may commence arbitration or legal proceedings within 28 days of the date on which the Adjudicator gives his decision."
"2.26.5 Any impediment, prevention or default, whether by act or omission, by the Employer or any of the Employer's Persons, except to the extent caused or contributed to by any default, whether by act or omission, of the Contractor or of any of the Contractor's Persons.
2.26.6 The carrying out by a Statutory Undertaker of work in pursuance of its statutory obligations in relation to the Work, or the failure to carry out such work…"
"2.29.1 Provided:
1 the Employer has Issued a Non-Completion Notice for the Work or a Section; and
2 the Employer has Informed the Contractor in writing before the date when the Final Account and Final Statement (or, as the case may be, the Employer's Final Account and Employer's Final Statement) became conclusive as to the balance due between the Parties that he may require payment of, or may withhold or deduct, liquidated damages,
the Employer may, not later than 5 days before the final date for payment of the debt due under clause 4.12, give notice in writing to the Contractor in the terms set out in clause 2.29.2."
"4.12.1 Within 3 months of practical completion the Contractor shall submit the Final Account and the Final Statement referred to in clause 4.12.3 for agreement by the Employer, and the Contractor shall supply the Employer with such supporting documents as the Employer may reasonably require.
2 The Final Account shall set out the Contract Sum together with the adjustments referred to in clause 4.2.
3 The Final Statement shall state:
1 the Contract Sum adjusted as necessary in accordance with clause 4.2; and
2 the sum of the amounts already paid by the Employer to the Contractor;
and the difference (if any) between the two sums shall be expressed as a balance due to the Contractor from the Employer of to the Employer from the Contractor, as the case may be. The Final Statement shall state the basis on which that amount has been calculated.
4 The Final Account and the Final Statement as submitted by the Contractor in accordance with clause 4.12.1 shall on the expiry of one month from whichever of the following occurs last:
1 the end of the Rectification Period in respect of the Works or (where there are Sections) the last such period to expire;
2 the date named in the Notice of Completion of Making Good under clause 2.36 or (where there are Sections) in the last such notice to be issued; or
3 the date of submission of the Final Account and the Final Statement to the Employer by the Contractor,
be conclusive as to the balance due between the Parties in accordance with the Final Statement except to the extent that the Employer disputes anything in that Final Account or Final Statement before the date on which, but for the disputed matters, the balance would be conclusive…
8 Not later than 5 days after the Final Statement becomes conclusive as to the balance due between the Parties in accordance with clause 4.12.4 or after the Employer's Final Statement becomes conclusive as to the balance due between the Parties in accordance with clause 4.12.7 the Employer shall give a written notice to the Contractor which shall, in respect of any balance stated as due to the Contractor from the Employer in the Final Statement or in the Employer's Final Statement, specify the amount of the payment proposed to be made, to what the amount of the payment relates and the basis on which that amount was calculated.
9 The final date for payment of the balance by the Employer to the Contractor or by the Contractor to the Employer, as the case may be, shall be 28 days from the date the Final Statement becomes conclusive as to the balance due between the Parties in accordance with clause 4.12.4 or after the Employer's Final Statement becomes conclusive as to the balance due between the Parties in accordance with clause 4.12.7. Not later than 5 days before the final date for payment of the balance the Employer may give a written notice to the Contractor which shall specify any amount proposed to be withheld and/or deducted from any balance due to the Contractor, the ground or grounds for such withholding and/or deduction and the amount of withholding and/or deduction attributable to each ground."
4: OUTLINE CHRONOLOGY
"150 Loudoun Road
Employer Response to Final Account/Final Statement
I refer to your Final Account submission of 17th November 2009 and Final Statement dated 1st July 2010 in relation to the above project.
I have considered and reviewed your Final Account submission in full on the basis of all of the substantiation provided, the relevant adjudication decisions and my own knowledge of the project together with the discussions in our recent meetings.
Having completed this review, please find enclosed on behalf of Fenice Investments Inc its response to your final account identifying those adjustments to the Contract Sum identified in your Final Account submission which are agreed and those which were incorrect in your original submission and so for the purpose of the Contract are identified as disputed. Where an item is disputed, there is included in the enclosed response the correct valuation for that item.
You will note that some of the items shown as disputed have been agreed between us in the sum recorded in this response in discussions which took place after your original Final Account submission. Where this is the case the items are nevertheless identified as disputed (on grounds that the correct assessment differs from that which was included in your formal Final Account submissions) but have been annotated to record the agreement subsequently reached for the relevant item.
As you will see from the enclosed, when properly assessed the final Contract Sum as adjusted in accordance with Clause 4.2 of the Contract is £3,945,531.64.
Fenice has made payment to you to date of £4,067,634.00.
A balance of £122,102.36 is therefore due and payable to Fenice, relating to and calculated in accordance with the content if the enclosed response to your Final Account and is required to be paid in accordance with the timeframe set out in Clause 4.12.9."
5: CONCLUSIVITY
5.1 The Decision in the Third Adjudication (Issue a))
5.2 JFC's Conclusivity Case (Issue b))
5.3 Fenice's Second Conclusivity Case (Issue c))
6: OUTLINE OF DELAY ISSUES
7. THE PREVENTION PRINCIPLE
"i) actions by the employer which are perfectly legitimate under a construction contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date.
ii) Acts of prevention by an employer do not set time at large if the contract provides for extension of time in respect of those events."
"The conduct therefore has to render it "impossible or impracticable for the other party to do the work within the stipulated time" The act relied on must actually prevent the contractor from carrying out the works within the contract period or, in other words, must cause some actual delay".
8: ANALYSIS OF DELAY ISSUES (Issues d), e) and f)
8.1: Delays Generally
8.2 The Principal Cause of The Later Delay: The Problem With The Levels
"It has been drawn to my attention your design for the setting out of the ground floor slab of the houses to the above is lower than the adjacent highway pavement levels.
The works have therefore not been constructed in accordance with the design resulting in the main entrance doors being lower than the pavement level and the inevitable introduction of a combination of ramps and steps.
Under clause 2.12 sole responsibility and ownership of the design is with JFC and as such any additional costs to rectify the works will be your responsibility…
We urgently await your proposals to remedy these defects and deliver the project by the contractual completion date."
a) The levels problem was first drawn to JFC's attention by letter dated 11 June 2009.b) JFC's architect, (ATP Group) failed to supply any response until 23 June 2009, a delay of 12 days. That delay, and the reasons for it, is wholly unexplained, and on any view was JFC's responsibility.
c) The solution suggested by ATP on 23 June 2009 involved external ramps to the front door from the pavement. The only reason that external solutions were being considered was because it was thought that they would have significantly less impact on the works than internal changes to houses which were well on the way to completion. To the extent that JFC now criticise Fenice (and by extension their own architects ATP) for pursuing external options, I reject that criticism. It was plainly sensible for that option to be explored.
d) The 23 June option was rejected the very next day because the steepness of the gradients failed to comply with the Building Regulations. There can be no criticism of Fenice either as to the time of response or the reasons for rejection.
e) On 25 June, ATP had another attempt at an external solution which involved external steps, but that was also promptly rejected for what Mr Foskett fairly accepted were both aesthetic and drainage reasons. Again, there can be no criticism of Fenice as a consequence.
f) On 30 June 2009, ATP provided an internal step drawing, although it was not clear when that was provided to Fenice.
g) In any event, on 7 July 2009, Miss Stockhammer asked JFC to review the internal step detail issued by ATP and said, amongst other things, that "the internal steps should be located next to the existing stair to avoid stepping down and then up again, and also more in keeping with the detail as shown on ATP drawings for house 2 (but one step only)." Again, it does not appear that any criticism can be made of Fenice's actual response (which dealt with the detail of the solution), or the time it took for them to respond.
h) At a site meeting on 9 July, ATP agreed to produce further drawings as a result of Fenice's comments, and these were provided on 13 July 2009.
i) The following day, namely 14 July 2009, there was a site meeting. The relevant minutes read as follows:
"4.4 Architectural Matters
a. ATP tabled the latest contractor's proposals to overcome the defect to the main entrance levels to house 4 and 5. The proposals incorporate an internal step to house 4 and 5.
b. HDG confirmed the internal step arrangement had been approved and JF should proceed as ATP drawing with the exception of the step to the hall and last step from stairs should align in a single plane."
8.3 Delay By British Gas
8.4 Delay by EDF
8.5 Summary on Delay
8.6 Concurrency
9: OTHER ISSUES
9.1: Agreement for Liquidated Damages (Issue g))
"I have agreed with Jerrams that completion of house 4 will not be a formal handover, Jerrams will maintain security, insurances etc, but we can get access for marketing. I have said that if the house and the externals are complete we would discount this off any claim we might make for LAD's. Jerrams were going for a formal partial possession."
It is common ground that how this discount might work was never discussed, let alone agreed.
9.2: Breach of Condition Precedent
10 SUMMARY
Note 1 Lewison, The Interpretation of Contracts, 4th edition, section 7.03 [Back] Note 2 This is a point expressly made in the 12th edition of Hudson in the Note at the end of paragraph 6-029, where the learned editors say that the decision in SMK “does not mean that variations or other acts which cause no additional delay beyond that already incurred by the Contractor will invalidate the [completion] clause”. [Back] Note 3 This ‘evidence’ seemed to be based on a completely contrived argument that the email of 24 April (paragraph 80 above) referred to the 5 June date in a separate paragraph to the rest of the discount agreement. [Back]