HT-09-452 |
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133- 137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
FENICE INVESTMENTS INC |
Claimant |
|
- and - |
||
JERRAM FALKUS CONSTRUCTION LIMITED |
Defendant |
|
JERRAM FALKUS CONSTRUCTION LIMITED |
Claimant |
|
- and – |
||
FENICE INVESTMENTS INC |
Defendant |
____________________
Mr Robert Sliwinski (instructed by Davies and Davies Associates) for Jerram Falkus
____________________
Crown Copyright ©
Mr Justice Coulson:
INTRODUCTION
(a) What is the proper construction of the interim payment provisions in the contract?(b) Do those provisions comply with the Housing Grants (Construction & Regeneration) Act 1996 ("the Act")?
(c) What is the proper course to be adopted by a party who has been required to pay a sum of money by an adjudicator but who has a bona fide point of law to raise in connection with that decision?
Having set out the relevant terms of the contract and the material facts, I deal with those issues in turn below.
THE CONTRACT
"1.3 The Agreement in these Conditions are to be read as a whole but nothing contained in the Employer's Requirements, the Contractor's Proposals or the Contract Sum Analysis shall override or modify the Agreement or these Conditions.
……
4.9.2 Where Alternative B applies, Applications for Interim Payment shall be made on the dates provided for in Alternative B in the Contract Particulars up to the date named in the Employer's Practical Completion Statement or the date within one month thereafter. Applications for Interim Payment thereafter shall be made as and when further amounts are due to the Contractor and upon whichever is the later of the expiry of the Rectification Period or the Issue of the Notice of Completion of Making Good… provided always that the Employer shall not be required to make any Interim Payment within one calendar month of having made a previous Interim Payment.
4.9.3 Each Application for Interim Payment shall be accompanied by such details as may be stated in the Employer's Requirements.
Interim Payments
4.10.1 The final date for payment of an Interim Payment shall be 21 days from the date of receipt by the Employer of the Application for Interim Payment …
4.10.3 Not later than five days after the receipt of an Application for Interim Payment, the Employer shall give a written notice to the Contractor which shall, in respect of that Application for Interim Payment, specify the amount of the payment proposed to be made, to what the amount of the payment relates and the basis on which that amount was calculated.
4.10.4 Not later than five days before the final date for payment, the Employer may give a written notice to the Contractor which shall specify any amount proposed to be withheld and/or deducted from the amount due, the ground or grounds for such withholding and/or deduction and the amount of withholding and/or deduction attributable to each ground.
4.10.5 Subject to any notice given under 4.10.4, the Employer shall no later than the final date for payment pay the Contractor the amount specified in the notice given under clause 4.10.3 or, in the absence of a notice under clause 4.10.3, the amount due to the Contractor as determined in accordance with clause 4.8 …"
"The first date shall be one month after the commencement of the CDM Planning Period and thereafter the same date in each month or the nearest business day in that month".
The evidence is that JFC had taken possession of the site on 3rd March 2008 and that JFC's first application for an interim payment was made on 7th March 2008. This indicates that subsequent applications were going to be made on or around 7th of each month.
'Interim payments shall be made monthly by the Employer to the Contractor in accordance with section 4 and Alternative B of the contract conditions.
The evaluation procedure shall be as follows:
a) Contractor to submit to the quantity surveyor his valuation of the work properly executed, any design work carried out and materials and goods delivered to site three days prior to the agreed on site valuation meeting date.
b) The quantity surveyor shall review with the contractor and issue an interim valuation recommendation to the Employer's Agent and Contractor.
c) Employer's Agent to issue interim certificate to the Employer and Contractor within 5 days of the date of issue of interim valuation recommendation. For the purpose of the contract, "the date of receipt by the employer of the application for an interim payment" shall be the date of issue of the interim certificate.
d) The Contractor upon receipt of the Employer's Agent interim certificate shall issue a VAT invoice to the Employer.
e) The Employer upon receipt of the Employer's Agent interim certificate and Contractor's VAT invoice will pay the Contractor within 21 days of the date of issue following the interim certificate in accordance with clause 4.10.1.'
THE EVENTS SURROUNDING APPLICATION 19
"We refer to your Application for payment No. 19 dated 6th August 2009.
This letter is a notice of withholding and is served pursuant to clause 4.10.4 of the Building Contract dated 1st February 2008.
The notice reflects the Employer's entitlement to withhold the sum of £163,480 from the sum of £71,473, being the sum which has been notified to you as the sum due in the notice/valuation pursuant to clause 4.10.3. The Employer require you to pay the remainder of the sum due, i.e., £92,007, as under clause 2.29.2.1.
The sum which is withheld from you/required to pay is therefore £163,480. The ground for withholding this sum is as follows:
(1) Liquidated damages for extended duration of the work beyond non-completion date:
67 calendar days x 2,440 = £163,480."
THE RELATIONSHIP BETWEEN CLAUSES 4.9 AND 4.10 OF THE JCT TERMS AND SECTION 15 OF THE EMPLOYER'S REQUIREMENTS
(a) a monthly application for an interim payment by the contractor pursuant to clause 4.9.2;(b) consideration of that application by the employer and his agent, and a written notice from the employer (which, as it was here, will often be in the form of an interim certificate) specifying the amount to be paid to the contractor within five days of the application, pursuant to clause 4.10.3;
(c) consideration by the employer and his agent of whether and if so what grounds there may be for withholding sums otherwise due pursuant to the interim certificate, and a written notice specifying any amount to be withheld to be provided by the employer to the contractor not less than five days before the final date for payment, pursuant to clause 4.10.4; and
(d) payment of the amount certified, less any sum validly withheld, 21 days after the original application, pursuant to clause 4.10.1.
(a) Section 15a) envisages a monthly application by the contractor. There is, therefore, no conflict between section 15a) of the Employer's Requirements and clause 4.9.2 of the JCT conditions.(b) Section 15b) envisages a review by the employer's quantity surveyors. Although not expressly referred to in clause 4.10.3, it seems to me highly likely that, in considering the amount of any interim certificate, the employer's agent will have taken the advice of a quantity surveyor. Indeed, in this case, the employer's agent, Sawyer & Fisher, were themselves quantity surveyors. Again, therefore, it seems to me that there is no conflict between section 15b) of the Employer's Requirements and the mechanism referred to in clause 4.10.3 of the JCT conditions.
(c) Section 5c) of the Employer's Requirements provides that the interim certificate will be issued five days after the issue of the employer's quantity surveyor's interim valuation recommendation. Clause 4.10.3 says that the interim certificate (or the written notice of payment as it is there described) must be issued five days after the employer's receipt of the contractor's application. Since the quantity surveyor cannot begin his evaluation until after receipt of the contractor's application, so that any certificate or payment notice will always be later than the contractor's application on which it is based, these two provisions would seem, on the face of it, to be in conflict. This point is examined in more detail below.
(d) Sections 15d) and 15e) of the Employment's Requirements introduce a new requirement, not set out in clauses 4.9 and 4.10 of the JCT conditions, that suggests that no sum will be paid until the employer has received a VAT invoice from the contractor. That does not necessarily mean that there is a conflict between the two provisions, but it would appear to suggest that section 15 is, at the very least, providing some degree of modification to the contractual conditions.
PRECEDENCE OF CONTRACT DOCUMENTS AND CONTRACT TERMS
"I confess with diffidence that I cannot go all the way with the Master of Rolls on either question. To apply the general principle that type should prevail over print seems to me to contradict the express provision of clause 12 that the reverse is to be true of this particular contract … In so far as they introduce further contractual obligations, as they do at paragraph 9, they may add obligations which are consistent with the obligations imposed by the conditions, but they do not affect them by overriding or modifying them or in any other way whatsoever. It follows from a literal interpretation of clause 12 that the Court must disregard – or even reverse – the ordinary and sensible rules of construction and that the first of the documents comprising the works Wimpeys offered in their tender of December 17th 1968 to carry out expressly prevents the Court from looking at the second of those documents to see what the first of them means."
In my view, that analysis applies equally to clause 1.3 here. In fact, it applies a fortiori because here, as I have found, section 15 of the Employer's Requirements conflicts with the contract clauses.
'…I think that the whole phrase "quality and quantity of the work included in the contract sum" is wide enough for me to look at the bills and find that the relevant work, although formally included, is pragmatically excluded. Adopting this line of approach, I take the pragmatic view that the relevant work is work not forming part of the contract and accordingly does fall within paragraph (h).'
(a) There was a conflict between clauses 4.9 and 4.10 of the contract on the one hand, and section 15 of the Employer's Requirements on the other;(b) The conflict was fundamental and irreconcilable. The payment provisions must be provided by either one or other of these sets of provisions: they cannot be taken together;
(c) Clause 1.3 made plain that, in the event of just such a conflict, it had to be resolved in favour of the contract terms themselves (in this case clauses 4.9 and 4.10).
DOES SECTION 15 COMPLY WITH THE ACT?
ARTICLE 3
"Save to the extent that the employer may otherwise specify by written notice to the contractor, the employer's agent shall have full authority to receive and issue applications, consents, instructions, notices, requests or statements and otherwise to act for the employer under any of the conditions."
Mr Webb's final argument was to the effect that section 15 comprised a notice under Article 3 and that clause 4.10 did not apply on the facts of this case because Application 19 was sent by JFC to the quantity surveyor and not to the employer or his agent. In this way, he said that the section 15 regime must apply by default.
CONCLUSIONS AND ORDERS MADE
Note 1 This reference gives me an opportunity to pay tribute to Edgar Fay, who died last month aged 100. He was one of a group of judges in the 1970s and early 1980s, with Sir William Stabb QC and HHJ Lewis Hawser QC, who did so much to build up the reputation of the old Official Referees’ Court, the predecessor of the TCC. [Back]