QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
BOVIS LEND LEASE LIMITED |
Claimant |
|
- and - |
||
THE TRUSTEES OF THE LONDON CLINIC |
Defendant |
____________________
Miss O'Farrell QC (instructed by Linklaters LLP) for the Defendant
Hearing dates: 15 and 28 January 2009
____________________
Crown Copyright ©
The Hon Mr Justice Akenhead :
Introduction
The Detailed History
'1.2.2 This is a preliminary report. At this stage the costs in this report are mostly estimated but are based on Bovis' … cost data and records for the project and final accounts and costs claims submitted by the work package contractors employed by Bovis … The claim items and costs require further development and substantiation. Bovis … are currently investigating their costs and settling the work packages/final accounts and will be submitting their detailed claims for loss and/or expense in due course.
2.1.1 The following items are claimed in this report:
2.1.2 Loss and/or expense incurred as a result of extensions of time awarded under the Contract and further extensions now sought by [Bovis] in the Preliminary Report of Mr John Marshall …
2.1.3 Loss and/or expense incurred through the provision of additional site supervision and site establishment resources ("Preliminary Thickening") …
2.1.4 Non-productive overtime costs expended …
2.1.5 Design costs incurred by [Bovis] and the sub-contractors …
2.1.6 Head Office costs arising from greater than planned Head Office staff input.
2.1.7 Finance costs in respect of liquidated damages that [Bovis] consider have been wrongly imposed …
3.2.1 The estimated amount currently claimed for staff costs is £392,557 …
3.2.4 The staff resources currently claimed for the delay period and the planned tender staff, with utilisations assessed by [Bovis], have been priced at tender rates. These estimated costs will be replaced with actual costs in a later claim.
4.2.1 The estimated amount currently claimed [for preliminaries and the thickening] is £427,902. The build-up of this amount is in Appendix 2 of this report. This amount is an estimate for advice purposes that will be replaced by actual, substantiated costs supported by the narratives referred to earlier.
5.2.1 The estimated amount currently claimed is £102,708 which is for the claimed extended period of 42.4 weeks to 4 April 2006. The build-up of this amount is in Appendix 3 of this report. This amount is an estimate for advice purposes that will be replaced by actual, substantiated costs.'
[At paragraphs 6, 7 and 8 are similar statements with regard to non-productive overtime costs, design and sub-contractors.]
"9.2.1 This claim [for head office costs] is currently being prepared. However, for the purposes of this report head office costs are currently at 4% of the total of the claim amounts before the addition of finance costs plus the costs of employing Mr Preston. The 4% is an estimate by [Bovis] of the head office costs compared with turnover.
10.2.1 The amount claimed [in finance costs] is £30,729 … This is a provisional calculation using simple interest. A more detailed calculation will be prepared when the full assessment of the extensions of time has been completed."
"The amounts claimed for loss and/or expense are summarised below."
There then followed this:
"11.1.2 The above amounts are estimated and based on incomplete [Bovis] and sub-contractors' costs and other data and on the current preliminary report of Mr Marshall. They are therefore subject to amendment when further and better information is available."
"You will note that we have found no grounds to fix a later completion date than the date we gave notification of by cover of our letter … dated 23 March 2005."
Put another way, Mr Wade was sticking by the four week extension of time which had been granted relatively earlier during the project. The 51 page review looked only at the delay and programming considerations. It did not consider Mr Wort's quantum report.
"We give you and your client notice that should the differences between us proceed to adjudication, then we will seek a direction from the Adjudicator that, if we have not been provided with the report upon which you subsequently seek to rely, your client should be prevented from adducing the same."
Mr Wade replied on 9 November 2007 saying that they had considered Mr Marshall's report but they did not accept Mr Marshall's analysis or conclusions. On 13 November 2007, Bovis submitted their Valuation No. 35 which sought the same payment as before for loss or expense based on Mr Wort's report of 30 November 2006. Again, that application was not accepted by the Clinic's professional advisers.
"I refer to [the Architect's] letter dated 16th March 2007, by which they notified BLL of their decision that there are no grounds to fix a later completion date than that notified on 23rd March 2005, namely 22nd July 2005.
BLL have applied for an extension of time by letter dated 18th May 2006. BLL relied on the expert reports issued to you on 30th November 2006 and 4th December 2006.
There is clearly a dispute between … the … Clinic and us in respect of our application and extension of time.
BLL claims:
(1) an extension of time of 40.2 weeks (over and above the four weeks previously granted),
(2) reimbursement of the Liquidated and Assessed Damages paid during this period in the sum of £1,608,000,
(3) loss and expenses arising from this delay and disruption in the sum of £3,437,245.44 less £150,000 already paid by you on account for loss and expense, i.e. £3,287,245.44.
Please pay BLL the total sum of £4,895,245.44 by 12 noon on Monday 21st July 2008.
If the Trustees fail to do so, BLL will proceed to refer this dispute to adjudication forthwith … in accordance with Clause 41A of the JCT Standard Form …
Please find attached BLL's Draft Referral Notice together with supporting documentation for your consideration. BLL is ready to refer this dispute to adjudication and will do so if the Trustees fail to pay the sums claimed by 12 noon, as stated above. Please notify us as soon as possible if you do not intend to pay the sums claimed.
In the event that you do not intend to pay the sums claimed, it would be sensible for us to agree upon an adjudicator without delay. Please indicate whether you agree to proposal of one of the following three adjudicators …"
The draft Referral Notice had with it Mr Wort's latest report, with other new expert reports, together with the five witness statements. It referred to some 31 files of contemporaneous documentation which were not enclosed in the package sent to the Clinic under cover of Bovis' letter of 7 July 2008.
'We acknowledge receipt of your letter of 7 July 2008 and confirm that it did not enclose the documents referred to at paragraphs 4.3 and 5 in the draft Referral Notice. Please forward copies as soon as possible.
We are in the process of reviewing the documentation enclosed with your letter and our file for this project …
… our file indicates that your application for an extension was dated 21 October 2006, the "Interim Case" (your letter of 21 December 2006 refers, copy attached) to which was attached two reports issued to us on 30 November (from Mr Marshall, dated 27 November 2006 and from Mr Sworder, dated 30 November 2006) and a further report issued on 4 December 2006 (from Mr Wort, dated 30 November 2006).
On the basis of the material enclosed with your letter of 7 July 2008, it appears that you now rely on a different application for an extension of time as well as two further reports that we had not previously seen dated 2 April (Mr Marshall) and 10 June 2008 (Mr Wort) respectively.
We would be grateful if you could please clarify our understanding of your position and confirm the status of the "Interim Case".
As you will appreciate, there is a substantial amount of documentation to get through and we are doing our best to consider and digest their contents as soon as possible. We will similarly aim to review the documents referred to in paragraphs 4.3 and 5 of the Draft Referral Notice.
Accordingly, we would be grateful if you would allow us until 18 August to provide you with our considered response to your letter of 7 July. We consider this a reasonable request in the circumstances.
We propose to also, at that time, address the appointment of the Adjudicator.
We look forward to hearing from you.'
"… I accept that in the case of Mr Wort's report you have not seen this before. Mr Marshall's report you will have seen as it is essentially the same document delivered previously. It has, of course, been updated to address the report prepared by [the Architect] delivered by letter dated 16th March 2007 and their refusal to grant any additional extension of time and clearly you will have to consider what we say in response. Additionally, you now have the benefit of our witness statements.
The documents referred to within the draft Referral Notice at paragraphs 4.3 and 5.0 are apart from our list of case authorities documents that you will have seen before and which are within your care, custody and control. In those circumstances, I do not propose to furnish you with these documents, but they will, of course, be supplied in support of our referral when served.
Our letter of 7th July clearly sets out the areas where there is a dispute between the parties and is the basis upon which we propose to proceed.
Given the passage of time since completion of this project your request for yet another month in which to provide us with your considered response to the claim, the existence of which you were well aware, is surprising but given the nature of your request I am prepared to accede to this and allow you until close of business on Monday 18th August 2008."
Therefore, in the event, the Clinic was given six weeks from 7 July 2008 to respond.
'We write further to recent correspondence regarding the draft Referral Notice enclosed with your letter of 7 July.
We have devoted considerable time and resources to review and consider the matters raised in the Notice in a relatively short period of time. This difficult task could have been easier had you agreed to (a) provide us with a copy of the bundle of supporting documentation referred to in the Notice and which were clearly intended to be read in conjunction with the Notice, and (b) to clarify the position with respect to previous application(s).
Nevertheless, we have done our best in the circumstances – we have taken the Notice and the documents enclosed with your letter of 7 July at face value and given them due consideration.
With respect to the factual evidence upon which you rely, the first we saw of this was as set out in the five witness statements enclosed with your letter of 7 July. We have reviewed the matters raised in these statements with the relevant personnel involved with the project.
With respect to the expert evidence upon which you rely, you have provided copies of reports prepared by Messrs Marshall, Sworder and Wort respectively. We have likewise considered the contents of these reports with the relevant personnel and the project professional team.
You accept that Mr Wort's report, stated to be to quantify your claim for loss and expense, had not previously been provided. It appears to us that prior to receiving this report, any application for loss and expense had not been substantiated. Perhaps you could clarify the position in this regard. We understand that this could have implications for the matters to be considered to be "in dispute".
You also say that Mr Marshall's report is an updated version from that provided in support of a previous submission. We note that the "updates" to his earlier report include a completely new section. We would have thought it reasonable for Mr Marshall to have identified in the body of his revised report the changes to the original text.
In short, the Notice sets out a very significant claim for which you rely on new evidence in support and in order to substantiate. Notwithstanding the difficulties with reviewing the claim in its entirety as noted above, on our review of the material provided and following detailed consideration of the matters raised in the documents received with your letter of 7 July with our project team and our professional advisers on the project, we do not consider that there is sufficient evidence to support the claim that you set out.
In the event, it is appropriate to point out that, as a minimum, we consider that a valid application under clause 26 of the Contract requires the following additional categories of information to be provided (and which request is hereby made on behalf of Terry Farrell Partnership and/or Davis Langdon):
(1) Each of the documents referred to in Mr Wort's Report which enabled him to reach his conclusion and in particular [there then follow six categories of documents related to sub-contractors and suppliers].
(2) Copies of your diary records for the project and labour allocation sheets for resources employed.
(3) Where claims are made for overtime working, thickening and design, identify the work (or additional work) undertaken in each instance and the instruction in relation thereto. In the case of Inviron, please provide details of the work undertaken in the pre-construction period, both planned and actual.
(4) Correspondence exchanged with BLL regarding the acoustic/fire partition/ceiling issues.
Finally, as to adjudicators, we do not agree with either of your proposed alternatives. We would suggest instead the parties appoint Mr Paul Darling QC of Keating Chambers.
We would also confirm that our solicitors, Linklaters, are instructed to accept service of any proceedings on our behalf. (Reference: Digby Hebbard).'
"The dispute comprises the following inter-related issues:
(1) Whether and to what extent delay and/or disruption was caused by BLL's Contract works by reason of matters for which the Clinic was responsible;
(2) The period of any Extension of Time to which BLL is entitled;
(3) BLL's entitlement to reimbursement of Liquidated and Ascertained Damages deducted during the period of this Extension of Time in the sum of £40,000 per week;
(4) The losses and expenses incurred by BLL by reason of the delay and disruption to the Contract Works."
The letter also goes in some detail into the Factual Background and the basis for Bovis's Claim. There is a page's worth headed "Crystallisation of the Dispute" followed by a "Summary of Redress Sought". Extension of time of a total of 44.2 weeks was sought (including the four weeks already awarded), together with the recovery of £1,608,000 for liquidated damages deducted and £3,287,245.44 for loss and expense arising from delay and disruption. There were various other aspects of redress sought.
The Course of the Adjudication
'It is sensible to ignore the element of BLL's claim for loss and expense for the reasons that you say. However, more importantly, simply, BLL is not in any event entitled to loss and expense under the contract. Clause 30.1.1 (as amended) provides that "as a condition precedent to the issue of any such Interim Certificate, the Contractor shall have submitted to the Architect and to the Quantity Surveyor a claim for payment in respect of amounts eligible for inclusion in an Interim Certificate in accordance with the provisions of clause 30.2. Such claim should be supported by a detailed valuation".
A quick review of the history of BLL's "loss and expense position", demonstrates that BLL haven't complied with these relevant provisions and therefore have not satisfied the condition precedent. Their interim applications have singularly failed to substantiate claims for loss and expense items by way of detailed valuation …
The first that the Clinic knew of BLL's current claim for loss and expense and Mr Wort's 10 June 2008 report on which the claim is based was when the Clinic received a draft referral notice under cover of the letter dated 7 July containing a "loss and expense" section. The nature of this claim was materially different to that which was the subject of the 2006 report from Mr Wort. Indeed, the Mr Wort's (sic) subsequent report is significantly larger than the November 2006 document.
In short, the Clinic maintain that BLL has never submitted an application for payment pursuant to clause 30.1.1.1 for monies allegedly due as loss and expense and as set out in Mr Wort's 2008 report. Further, by letter dated 22 July, BLL confirmed to the Clinic that Mr Wort's report upon which they rely to support this element of the claim had not previously been submitted.
Accordingly, the Clinic would agree that the loss and expense elements of the referral be disregarded entirely by the Adjudicator and the Clinic.
Alternatively, if the loss and expense elements are not disregarded entirely, the Clinic submits that the dispute on loss and expense become the subject of a further adjudication in respect of which the contractual rules would of course apply …'
"TB [the Adjudicator] queried why we'd asked this point, was it to gain more time? I said that we did want more time. He said that up until two weeks ago, he may not have had any discretion to grant extensions, however, following recent guidance from Akenhead J, TB now has that discretion. He queried what sort of extension I was seeking and I said until Friday would be suitable, 5 September.
SB [Counsel for Bovis] said that although he cannot understand the grounds upon which are being relied to request an extension his view would be that no extension is warranted because the Clinic has had the claim for almost two months. I said that although we had the claim and the expert reports and witness statements, we'd not been provided with the documents relied upon and forming the bundle. SB said those were common to the parties. I said that regardless, it was a big job to try to get the documents together. I said that we needed time to get through the documents and to consult with the members of the professional team to consider the points in the Referral. I said we were doing our best to get a Response out. He [SB] then agreed to the extension until midnight, Thursday. This extension was then agreed and the procedure became regularised, in other words, there were no points that were going to be taken on the contents of the Referral Bundle and the Adjudicator's appointment.
TB raised the issue of a meeting with experts. He said that this was something he might like to do and felt could be very productive. He felt that lawyers need not attend. However, he was not going to exclude them. He said that the appropriate time for these meetings would be following the Response. On the material that he has read to date, he would like to definitely meet with Mr Marshall and possibly Mr Wort.
I said that the Clinic had not yet made a decision on expert evidence for the Response … I said that a decision had not yet been taken. However, that as stated we were discussing the points in the Referral with the professional team. I said that if there was not sufficient time to obtain expert reports, then expert evidence could be incorporated into a Response. If the Clinic was not going to include expert evidence with its Response, the nature of the case was going to be opening up the Award/Certificate and in that regard, TB would still want to meet with TFB and Marshall …" (emphasis added)
'2.1 BLL has not established in the Referral the entitlement to additional time and money that it seeks by this Adjudication.
2.2 The Clinic will demonstrate in this Response that the true causes of delay to completion were not as BLL allege; that their expert analysis is misconceived; and that a significant element of the claim for a declaration as to money should be disregarded as a consequence of it not being part of a dispute capable of adjudication. The Clinic will also explain (a) why BLL's claims for variation should not be entertained and (b) that [the Architect's] Post-Completion Review was correct and justified …
2.4 As to the claim for additional money (loss and expense), this cannot be part of the dispute because BLL has failed to submit its claim in accordance with the Contract. In any event, the expert evidence relied upon is fundamentally deficient …
4. The Dispute
4.1 BLL have referred a "Dispute" to Adjudication under clause 41A of the Contract. Clause 41A.1 provides that Clause 41A applies where "either party refers any dispute or difference arising under this Contract to Adjudication" [emphasis added].
4.2 BLL contend that the dispute referred to in this Adjudication includes BLL's claim for loss and expense in the sum of £3,287,245.44.
4.3 The Clinic's position is that this loss and expense claim cannot be included as part of the dispute before the Adjudicator, because, even if it could be said that the parties were in dispute about loss and expense, such dispute has not arisen under the Contract.
4.4 BLL's entitlement to additional money for loss and expense arises under the Contract and indeed, their claim is said to be based on a contractual entitlement. However, BLL have never made an application for payment for (or including) loss and expense in the sum of £3,287,245.44.
4.5 It must follow then that there is no dispute or difference under the contract in respect of this claim.
4.6 By failing to make an application for payment in accordance with the agreed contractual machinery for loss and expense in this amount, BLL is precluded from relying on the Contract to justify referral of a dispute or difference in respect of loss and machinery, to Adjudication, in accordance with Clause 41A.
4.7 Accordingly, the Clinic respectfully submits that the Adjudicator makes a declaration that he has no jurisdiction to decide the dispute on loss and expense as set out in the Referral.
5.1 It is self-evident that BLL's case is heavily reliant on expert reports of Mr Marshall, Mr Wort and Mr Sworder. The Clinic has carefully reviewed their reports with its own advisers and the project professional team and consider that BLL's experts have simply got it wrong. This Response will highlight the fundamental flaws in BLL's expert analysis
[There then follows over the next 32 pages a detailed analysis of the delay claim.]
12.1 For the reasons set out above at Section 1 of this Response, "the Dispute", the Clinic's case is that the loss and expense claim in the Referral is not part of the present dispute for the purposes of this Adjudication.
12.2 Without prejudice to that contention, the Clinic's submissions below are made entirely without prejudice.
[Paragraph 12.9 to 12.14 addresses the defence that because no application for the current claim was ever made in whole or in relation to any individual sum that there was any obligation to pay.]
12.18 Moreover, as the analysis in Appendix 6 shows, the Clinic can legitimately conclude that the Report does not evidence that any further sum is currently due to BLL, for amongst other reasons:
12.8.1 The report is in truth little more than an extensive figures as figures vouching process. It does not fully and properly consider the contract itself …
12.8.2 The Report is not an application for Payment, for which Clause 30 provides a condition precedent requirement, nor a Clause 26 ascertainment.
12.8.3 Further, it is in very many cases devoid of the very details that the Architect and the Quantity Surveyor require to arrive to an ascertainment …
12.8.4 This Report [Mr Wort's later report] does not provide the documents that are fundamental for a proper analysis and whilst Mr Wort acknowledges that the evidence does not always exist, he includes the sums nonetheless.
12.8.5 Events of BLL's culpable delay are ignored.'
"6.3 The Clinic has employed experienced and competent solicitors. It has obviously taken care with the drafting of its Response. Costs have clearly not been an issue. It has been given every opportunity to put its best foot forward in this Reference and it has taken it;
6.4 It is all the more revealing, then, that the Response is almost entirely unsupported by factual or expert evidence …"
This Reply addresses the Response in some detail but makes emphatically the points that the Response was unsupported by factual and expert evidence.
'5. "No dispute".
5.2 The correct characterisation of the dispute is of course fundamental to this, and any Adjudication. The Clinic's position is that the Adjudicator had no jurisdiction to consider this issue because a loss and expense dispute has not crystallised.
5.3 There is clear authority for the contention that a dispute does not arise unless and until it emerges that a claim is not admitted …
5.5 Whilst the Clinic admits it received the draft Referral Notice, it denies that the failure to admit the claim for loss and expenses crystallised the dispute. The Clinic also denies that BLL must comply with clause 26.
5.6 The draft Referral contained the report from Mr Wort dated 10 June 2008 which the Clinic had never seen. BLL rely on Mr Wort's report to quantify the claim for loss and expense. The documents provided to the Clinic along with the draft Referral did not contain the necessary information to support a claim for loss and expense …
5.9 The Clinic submits that this 18 August letter did not crystallise the dispute on loss and expense. It is self-evident that further information was required in order for the claim to be considered as an application under clause 26. Rather than "not admit the claim", the intention of the letter was to request further and necessary information. The Clinic's view is that the true meaning and effect of this letter will be apparent to the Adjudicator …
5.10 Notwithstanding that a dispute had not crystallised (and without providing further information requested) BLL proceeded to refer a dispute to Adjudication and this dispute includes the claim for loss and expense in the sum of £3,287,245.44.
5.11 On the basis that a dispute regarding this element of the claim has not crystallised, the Clinic submits that the Adjudicator has no jurisdiction.'
The Clinic attached a witness statement from a Mr Lovell.
The Decision
(a) that Bovis was entitled to the full extension of time (44.2 weeks) claimed;
(b) that the Clinic should reimburse Bovis for the liquidated damages: a sum of £1,608,000 was ordered to be reimbursed. In addition, interest thereon was allowed in the total sum of £301,088;
(c) against the sum of £3,287,245.44 in respect of loss and expense, he decided that the Clinic should pay the sum of £1,878,257.09; and
(d) he ordered the Clinic to pay the Adjudicator's fees and expenses.
It is a substantial document and there is some genuine analysis of the delay claim and an item by item assessment of the loss and expense.
"As stated in our email of 2 December, the Clinic has repeatedly made the point that the Adjudicator lacked jurisdiction to decide the loss and expense elements of the Referral. In addition, the Clinic will challenge your application on the basis that the timing and manner in which your claim was presented and subsequently prosecuted and dealt with (by way of adjudication) amounted to an abuse of process and a breach of natural justice."
This latter assertion was made for the first time in this letter.
The Clinic's Contentions in Summary
"(1) The claim for loss and expense made in the Adjudication was new and based on new expert evidence. Therefore, there was no crystallised dispute in respect of the claim and the Adjudicator had no jurisdiction to determine the claim.
(2) The nature and volume of new evidence served by Bovis for the purpose of the Adjudication and the timetable imposed on the Clinic in the Adjudication did not give the Clinic a fair or effective opportunity to respond to the new case. As such, the Decision was in breach of the rules of natural justice and invalid."
"(1) Bovis' application for prolongation and/or loss and expense contained in its applications for payment did not amount to claims for loss and expense in accordance with Clauses 26 and/or 30 of the Contract …
(2) Mr Wort's First Report dated 30th November 2006 did not contain a claim for loss and expense in accordance with Clauses 26 and/or 30 of the Contract and has not put forward as such a claim. The Report identified the loss and expense figures as estimated figures for advice purposes that will be replaced by claims for actual and substantiated figures …
(3) Although Bovis intended to included figures for loss and expense in its subsequent applications, they were based on Mr Wort's preliminary report. Bovis failed to serve any actual and substantiated figures for loss and expense prior to the service of its draft referral in July 2008.
(4) Mr Wort's Second Report was the first time that Bovis served on the Clinic its loss and expense claim the subject of the Adjudication:
(a) The figures for each element of the loss and expense claim are different to those estimated for the First Wort Report and were included as actual rather than estimated costs.
(b) The report contained much more detailed presentation of the nature of the claims and the figures …
(c) The report referred to 31 appendices of calculations and supporting documentation amounting to some 300 pages of relevant information not previously seen by the Clinic.
(5) Bovis held back service of Mr Wort's Second Report (completed on 10th June 2008) until it served its draft referral on 7th July 2008 …
(6) Bovis refused to provide the Clinic with much [of] the supporting documentation relied on in support of its new claim prior to service of the Referral Notice.
(7) The Clinic did not have sufficient time to consider the new claim, to obtain an audit of the costs information or to obtain a report in response to the same from its consultants. Such a review would take months (particularly in circumstances where its Project Quantity Surveyor was on maternity leave and its external consultants, Pontins, had been stood down).
(8) In its letter dated 18th August 2008, the Clinic neither accepted nor rejected the new claim for loss and expense. The Clinic reasonably requested additional details of the claim and the supporting documentation that had been deliberately withheld by Bovis …
(9) The Clinic challenged the jurisdiction of the Adjudicator to deal with the loss and expense claim as set out in the Adjudication documents … "
The Law
'68. From this review of the authorities, I derive the following seven propositions:
1. The word "dispute" which occurs in many arbitration clauses and also in section 108 of the Housing Grants Act should be given its normal meaning. It does not have some special or unusual meaning conferred upon it by lawyers.
2. Despite the simple meaning of the word "dispute", there has been much litigation over the years as to whether or not disputes existed in particular situations. This litigation has not generated any hard-edged legal rules as to what is or is not a dispute. However, the accumulating judicial decisions have produced helpful guidance.
3. The mere fact that one party (whom I shall call "the claimant") notifies the other party (whom I shall call "the respondent") of a claim does not automatically and immediately give rise to a dispute. It is clear, both as a matter of language and from judicial decisions, that a dispute does not arise unless and until it emerges that the claim is not admitted.
4. The circumstances from which it may emerge that a claim is not admitted are Protean. For example, there may be an express rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time, thus giving rise to the same inference.
5. The period of time for which a respondent may remain silent before a dispute is to be inferred depends heavily upon the facts of the case and the contractual structure. Where the gist of the claim is well known and it is obviously controversial, a very short period of silence may suffice to give rise to this inference. Where the claim is notified to some agent of the respondent who has a legal duty to consider the claim independently and then give a considered response, a longer period of time may be required before it can be inferred that mere silence gives rise to a dispute.
6. If the claimant imposes upon the respondent a deadline for responding to the claim, that deadline does not have the automatic effect of curtailing what would otherwise be a reasonable time for responding. On the other hand, a stated deadline and the reasons for its imposition may be relevant factors when the court comes to consider what is a reasonable time for responding.
7. If the claim as presented by the claimant is so nebulous and ill-defined that the respondent cannot sensibly respond to it, neither silence by the respondent nor even an express non-admission is likely to give rise to a dispute for the purposes of arbitration or adjudication.'
'31. Each of the parties has accepted in this court that the Judge's propositions correctly state the law. I am broadly content to do so also, but with certain further observations, as follows:
1. Clause 66 refers, not only to a "dispute", but also to a "difference". "Dispute or difference" seems to me to be less hard-edged than "dispute" alone …
2. In many instances, it will be quite clear that there is a dispute. In many of these, it may be sensible to suppose that the parties may not expect to challenge the Engineer's decision in subsequent arbitration proceedings. But major claims by either party are likely to be contested and arbitration may well be probable and necessary. Commercial good sense does not suggest that the clause should be construed with legalistic rigidity so as to impede the parties from starting timely arbitration proceedings. The whole clause should be read in this light. This leads me to lean in favour of an inclusive interpretation of what amounts to a dispute or difference …
5. I agree with the judge that, insofar as the existence of a dispute may involve affording a party a reasonable time to respond to a claim, what may constitute a reasonable time depends on the facts of the case and the relevant contractual structure. The facts of the case here included that:
(a) Major defects in very substantial works emerged relatively shortly before the perceived end of the limitation period. These required detailed investigation. In consequence, the formulation of a precisely detailed claim was impossible within a short period.
(b) Liability for the defects was bound to be highly contentious, but Amec were bound to be a first candidate for responsibility.
(c) Amec (and others) were inevitably going to resist liability well beyond the perceived end of the limitation period.'
'51. Now this present case is obviously different. DML did not just ignore Application 33, they asked for further information. That is an every day occurrence in the construction industry and if every request for information was regarded as a dispute leading to adjudication there would not be enough adjudicators to go round …
53. I entirely agree with Judge Gilliland's statement of principle [in Cruden Construction Ltd v Commission for the New Towns [1995] 2 Ll. Rep. 387 at 393] and with his application of principle to the facts of that case, but how should the principle be applied to the facts of this case? It would be most undesirable if a practice grew up of examining in minute detail the terms of letters between the parties to ascertain the precise details of any dispute there set out, and then compare those details with the details of what was put before the adjudicator.
I can see that some lawyers might be tempted to take that course. A broader approach is required. Application No. 33 was made and it was not paid. Is that enough to make a dispute? In one sense there was a dispute. The paying party was denying that payment was due at least until some verification was forthcoming. But DML were not denying the claim outright, nor were they ignoring it; they were asking for clarification. The best approach to clarification that they got was so close in time to the notice of adjudication that they had no opportunity to respond to it. The conduct of the adjudication indicates that, if given a reasonable opportunity to respond, there would have been a dispute, but that is not the point.
54. This is not as plain a case as the one before Judge Gilliland, but I take the view that, in the words of Judge Gilliland, this is a case where DML at the date of the adjudication notice:
"… has not in fact been told and is unaware in what respects it is alleged to have broken his obligations."
I therefore find that on this additional ground the adjudicator was lacking in jurisdiction …'
"The common law rules of natural justice or procedural fairness are two-fold. First, the person affected has the right to prior notice and an effective opportunity to make representations before a decision is made. Secondly, the person affected has the right to an unbiased tribunal. These two requirements are conceptually distinct. It is quite possible to have a decision from an unbiased tribunal which is unfair because the losing party was denied an effective opportunity of making representations. Conversely, it is possible for a tribunal to allow the losing party an effective opportunity to make representations, but be biased. In either event, the decision will be in breach of natural justice, and be liable to be quashed if susceptible to judicial review, or (in the world of private law) to be held to be invalid and unenforceable."
This current case is not concerned with issues of bias. The real complaint is that the Clinic had insufficient notice of the claim and did not have an effective opportunity of responding to Bovis' claims.
(a) The fact that a dispute is complex or involves consideration of large volumes of material does not necessarily mean that any decision reached within an adjudication is procedurally unfair (see CIB Properties. Ltd v Birse Construction [2005] BLR 173).
(b) The mere fact that there has been an "ambush" by the claiming party in an adjudication does not in itself amount to procedural unfairness (see London & Amsterdam Properties Ltd v Waterman Partnership Ltd [2003] EWHC 3059 (TCC) at paragraph 179).
"On the severability issue, I conclude, albeit obiter in the result, as follows:
(a) The first step must be to ascertain what dispute or disputes has or have been referred to adjudication. One needs to see whether in fact or in effect there is in substance only one dispute or two and what any such dispute comprises.
(b) It is open to a party to an adjudication agreement as here to seek to refer more than one dispute or difference to an adjudicator. If there is no objection to that by the other party or if the contract permits it, the adjudicator will have to resolve all referred disputes and differences. If there is objection, the adjudicator can only proceed with resolving more than one dispute or difference if the contract permits him to do so.
(c) If the decision properly addresses more than one dispute or difference, a successful jurisdictional challenge on that part of the decision which deals with one such dispute or difference will not undermine the validity and enforceability of that part of the decision which deals with the other(s).
(d) The same in logic must apply to the case where there is a non-compliance with the rules of natural justice which only affects the disposal of one dispute or difference.
(e) There is a proviso to (c) and (d) above which is that, if the decision as drafted is simply not severable in practice, for instance on the wording, or if the breach of the rules of natural justice is so severe or all pervading that the remainder of the decision is tainted, the decision will not be enforced.
(f) In all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially, in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the Court."
Discussion – Jurisdiction
(a) One needs to examine the Clinic's letter of 18 August 2008 in the context that the Clinic had indicated on 21 July 2008 that it was intending to revert with its "considered response" to Bovis' letter of 7 July 2008.
(b) It is clear on the face of the Clinic's letter of 18 August 2008 that the Clinic and its professional advisers had given "detailed consideration [to] the matters raised" in that letter.
(c) The Clinic had provided that "detailed consideration" within the time limit which they themselves had asked for: whilst the letter of 7 July 2008 called for a response within two weeks, the Clinic had asked for an additional four weeks. That request had been granted by Bovis.
(d) Upon any proper interpretation of its letter of 18 August 2008, the Clinic was rejecting the claims (both as to time and as to money) put forward in or by the letter of 7 July 2008. Its expression that "we do not consider that there is sufficient evidence to support the claim that you set out" is the clearest defence being put forward that the whole claim (extension, liquidated damages return and loss an expense) is being rejected because it is not substantiated, properly or at all. That might have been or might prove to be a good defence. It is in one sense a classic "non-admission" defence.
(e) However, a further defence and challenge to jurisdiction is put forward which is that no valid application has been made under Clause 26 of the Contract. That is why the Clinic makes a request in this letter on behalf of the Architect and DL for a number of documents. Again, and I make no finding about that, this might be or might have been a valid defence. The argument is based on Clause 26.1 of the building contract conditions, which materially says as follows:
"If the Contractor makes written application to the Architect stating that he has incurred … direct loss and/or expense (of which the Contractor may give his quantification) in the execution of this Contract for which he would not be reimbursed by a payment under any other provision in this Contract … or because the regular progress of the Works or of any part thereof has been … materially affected by any one or more of the matters referred to in Clause 26.2; and if and as soon as the Architect is of the opinion that the direct loss and/or expense has been incurred … or that the regular progress of the Works or any part thereof has been or is likely to be so materially affected as set out in the application of the Contractor then the Architect from time to time thereafter shall ascertain, or instruct the Quantity Surveyor to ascertain, the amount of such loss and/or expense which has been or is being incurred by the Contractor; provided always that:
26.1.1 The Contractor's application shall be made as soon as it has become, or should reasonably have become, apparent to him that the regular progress of the Works or of any part thereof has been or was likely to be affected as aforesaid; and
26.1.2 The Contractor shall in support of his application submit to the Architect upon request such information as should reasonably enable the Architect to form an opinion as aforesaid; and
26.1.3 The Contractor shall submit to the Architect or the Quantity Surveyor upon request such details of such loss and/or expense as are reasonably necessary for such ascertainment as aforesaid."
This was coupled to a specific amendment to Clause 30.1, which deals with interim certificates and interim payments, which sought to provide for a condition precedent to the issue of any Interim Certificate that
"the Contractor shall have submitted to the Architect and to the Quantity Surveyor, to assist them in making the appropriate valuation a claim for payment in respect of amounts eligible for inclusion in an Interim Certificate in accordance with the provisions of Clause 30.2 …"
Thus, it was the case that the letter of 18 August was arguing by way of defence that unless and until further information was provided there had not been a valid application under Clause 26. The clear inference from this was that no sum was due under Clause 26 because no "valid application" had been made.
Discussion – Natural Justice
(a) A most important factor is that not once during the course of the adjudication did the Clinic or its professional advisers complain or even raise the assertion that it had had insufficient time at any stage during the adjudication to prepare its Response or Rejoinder or do anything else which it wanted to do to put forward its position. It is difficult to criticise the Adjudicator on the grounds that he did not give the Clinic sufficient time to do whatever it wanted to do if the Clinic never asked for more time.
(b) Whenever (and it was only one occasion) the Clinic by its professional advisers asked for more time, the Adjudicator granted such additional time and, indeed, Bovis agreed to it.
(c) The contents of the Response and the Rejoinder do not begin to indicate that insufficient time had been allowed. To the contrary, the letter of 18 August 2008, the Response to the Referral and the Rejoinder demonstrate in candid and express terms that the Clinic had been able to give sufficient time to give a detailed consideration and carefully review Bovis' claim in the adjudication. Detailed consideration was given by the Clinic both as to time and loss and expense. A whole day was given over to examination and cross-examination of key witnesses (programming, experts and the Architect) to review the time issues. A relatively detailed analysis clearly was done as to the loss and expense which, indeed, found some substantial favour with the Adjudicator who reduced the claim by over 40%.
(d) It was argued that the Adjudicator should have been able to see, infer or deduce that the Clinic had insufficient time. The facts that no point was raised on this topic by the Clinic, that their written pleadings did not raise the issue and that the Clinic was represented by well known and highly experienced Solicitors and Counsel wholly undermine that argument.
(e) It is difficult to see how there can have been a material breach of the rules of natural justice where, if it was material, the Clinic or its professional advisers did not see fit to mention it as something which was materially affecting them during the course of the adjudication.
(f) For reasons given above, I do not consider that there was any "ambush". Even if there was, this is not a term of art and sufficient time was requested, given and taken by the Clinic to address the issues in the adjudication.
The Clinic has simply failed to establish any or any realistically arguable case that there has been a breach of the rules of natural justice.
Discussion - Severability
Decision