QUEEN'S BENCH DIVISION
MANCHESTER DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
Bridge Street West Manchester |
||
B e f o r e :
____________________
THERMAL ENERGY CONSTRUCTION LIMITED |
(Claimant) |
|
-v- |
||
AE & E LENTJES UK LIMITED |
(Defendant) |
____________________
J.L. Harpham Limited
Official Court Reporters and Tape Transcribers
55 Queen Street, Sheffield S1 2DX
____________________
Crown Copyright ©
JUDGE DAVIES:
"The parties agree that liquidated or unliquidated damages shall not be applicable to the contract in the event of delays to completion of the works, irrespective of the causes of such delays, and accordingly the purchaser shall not hold the contractor liable for late completion and/or any consequential costs arising therefrom".
"This decision would be taken bearing in mind that the Claimant's liability was capped and liquidated damages were not applicable on this contract".
"If the Defendant had confirmed they did not intend to pay for various costs that the Claimant were expending, then the Claimant would have been able to make a commercial decision upon whether they would incur this further expenditure when they were aware that they would be unable to recover that cost".
"My valuation of the issues in dispute, as indicated on the attached schedule, is as follows ..."
Figures were given against each of the four issues, including, as Mr. Furst has observed, "Nil" against Issue 3. There followed a section dealing with when payment should be made. The decision itself ended by dealing with the Adjudicator's fees and expenses, and there was attached a schedule which contained a detailed breakdown of the sums decided to be due, with no reference to any set-off or counter-claim.
"If an Adjudicator is requested to give reasons pursuant to Paragraph 22 of the Scheme, in my view a brief statement of those reasons will suffice. The reasons should be sufficient to show that the Adjudicator has dealt with the issues remitted to him and what his conclusions are on those issues. It will only be in extreme circumstances, such as those described by Lord Justice Clark in Gillies Ramsey and Others -v- PJW Enterprises, that the Court will decline to enforce an otherwise valid Adjudicator's decision because of the inadequacy of the reasons given. The complainant would need to show that the reasons were absent or unintelligible, and that as a result he had suffered substantial prejudice".
"The Adjudicator may, on his own initiative or on the application of a party, correct his decision so as to remove any clerical mistake or error arising from an accidental slip or omission";
Paragraph 32(ii) (2) provides that:
"Any application for the exercise of the Adjudicator's powers under paragraph (i) shall be made within 5 days of the date that the decision is delivered to the parties, or such shorter period as the Adjudicator may specify in his decision".
"Every decision of the Adjudicator shall be implemented without delay. The parties shall be entitled to such reliefs and remedies as are set out in the decision, and shall be entitled to summary enforcement thereof, regardless of whether such decision is or is to be the subject of any challenge or review".
___________________