QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ALLIED P & L LIMITED |
Claimant |
|
- and - |
||
PARADIGM HOUSING GROUP LIMITED |
Defendant |
____________________
Christopher Camp (instructed by Owen White) for the Defendant
Hearing date: 5 November 2009
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
The factual background
"Without prejudice to any other rights or remedies which the Employer may possess if the Contractor shall default in any one or more of the following respects that is to say:
10.1.1 if without reasonable cause it wholly suspends the carrying out of the design or construction of the Dwellings before completion thereof
10.1.2 if it fails to proceed regularly and diligently with the performance of its obligations under this Agreement
10.1.3 it refuses or neglects to comply with a written notice from the Employer's Agent requiring it to remove defective works or improper materials or goods and by such refusal/neglect the works are materially affected
Then the Employer may give to the Contractor notice by Registered Post or Recorded Delivery specifying the default. If the Contractor shall continue such default for nine Working Days after receipt of such notice or shall at any time thereafter repeat such default (whether previously repeated or not) the Employer may within six Working Days after such continuance or repetition by notice served by Registered Post or Recorded Delivery forthwith determine the employment of the Contractor under this Contract PROVIDED that such notice shall not be unreasonably or vexatiously given or served. Upon determination of the Contractor shall vacate the Property and remove all plant and machinery from the same."
Clause 10.2 provided that Paradigm would thereafter be under no liability to make any further payments until it had practically completed the dwellings in question.
"16.1 If any dispute or difference arises under this Agreement either party may refer it to adjudication in accordance with the provisions of this Clause 16…
16.4.1 Where pursuant to this Clause 16 a party requires a dispute or a difference to be referred to Adjudication then that parties shall give notice ("the notice of adjudication") to the other party of his intention to refer the dispute or difference briefly identified in the notice of adjudication. Within 7 days from the date of the notice of adjudication…the party giving notice of intention shall refer the dispute or difference to the Adjudicator for his decision ("the referral") and shall include within that referral particulars of the dispute or difference together with a summary of the contentions on which he relies a statement of the relief or remedy which is sought and any material he wishes the Adjudicator to consider. The referral and its accompanying documentation shall be copied simultaneously to the other party."
"1. That Allied failed to complete the contract by the contractual completion date, and no extension of time has been sought or agreed.
2. That the failure to complete has been caused by Allied's suspension of the design and construction of the dwellings without reasonable cause.
3. That Allied have failed to proceed regularly and diligently with the performance of its obligations under the Agreement.
4. That Allied have failed to complete the site, the access road and the installation of the utilities.
5. That Allied have failed to resolve the wrong positioning of the sub-station and the loss of car parking spaces for Paradigm.
6. That Allied have failed to complete the necessary S278 works to secure access from the site, causing Paradigm potential losses in respect of the cost of completing traffic lights and bridge repairs required by the S. 278 Agreement.
7. That Allied have wrongly used the site as a base for their works on neighbouring sites.
8. That Allied have failed to provide evidence of the Power of Attorney under which the Bank of Scotland has executed a Deed of Variation of the Section 106 Agreement, as required by the Local Authority.
9. That the above breaches have or will cause Paradigm to suffer damages and costs in completing the contract considerably in excess of any monies due under the contract to Allied. The losses include…
Paradigm require Allied to remedy these omissions and faults within 10 working days from the date of service of this Notice, and if such remedies are complete, then the withholding of the stated account will end."
"This job can be completed diligently, but only once Paradigm honour the contract they have breached. We have not been paid anything since August 2008, some nine months ago."
"You have 9 working days from receipt of this Notice to rectify the breaches and if those are not rectified within this time limit the contract will terminate in accordance with Clause 10 thereof."
In an accompanying letter of the same date, they wrote to Allied's solicitors about the construction of hoarding around the site saying also:
"The contractual obligations your client has is [sic] to complete the development, which they have singularly failed to do, despite numerous warnings…
We agree that all outstanding issues should be either discussed around the table on a without prejudice basis, and in default that any current disputes be referred to either the court or arbitration. We can discuss details of this later this week…"
"We refer to your letter dated the 19th May 2009 in which you purport to give Notice alleging breach of the Agreement.
On behalf of Allied…we are replying.
The Notice is in identical terms of the Notice withholding payment and the issues raised have already been answered. A further copy of our letter dated 19th May is attached.
We would further assert that a number of the matters referred to in the Notice are matters that are not within the control of Allied…who are the Contractor. In particular we will address this point to numbers 4, 5 and 7 of your Notice. These are matters not in any way connected to our clients as the Contractor. It is denied that there has been any breach of the Agreement at all and your clients are not entitled to terminate the Agreement."
"…I note what you say about certain aspects of the Notice, but I do not accept that as being correct. In any event, there are many breaches which are set out in the Notice which relate specifically to work, or lack of it, undertaken by Allied on site.
You mention payment of monies due under the Contract, but I would remind you that in accordance with Clause 10.2 the employer is not under any duty to make any further payment of the contractor until the contractor has reached practical completion. Even then, an account as to losses and expenses would need to be drawn up to address your client's failure under the Contract. As the Contract may be terminated if the Notice is not complied with, the sensible way to deal with payments is in accordance with Clause 10 and have a final account which would give full credit to any certified invoices…"
"My clients have already implemented the arbitration process due to your client's failure to meet payments in accordance with the Contract…
To put it quite simply it is not accepted that there are any breaches on our clients part and and invited [sic] your clients to terminate the Contract which we would now suggest it is sensible to await the arbitration determination and see where we go from there."
The English seems to have gone awry but it seems clear that Allied was saying that there were no breaches which entitled Paradigm to terminate.
"We, Paradigm…give you Allied…Notice that you continue to be in default of the Agreement…despite our Notice to you dated 19th May 2009.
Details of the continued breaches are:
1. You have not recommenced construction work, nor have you agreed to a programme to reach practical completion that is acceptable to Paradigm. You have not even submitted a programme for consideration.
2. You have not recommenced construction work, and have only undertaken very minor decorating. You have not sought permission to delay or postpone the works.
3. You have continued to use the site as an office, store and operating base for works on a neighbouring site.
4. You have failed to comply with the requirements set out in the Notice of 19th May 2009 numbered 1 to 7 within the required period.
TAKE NOTICE that in accordance with Clause 10 of the Contract Paradigm consider to have been determined by Notice and they require you to immediately vacate the site."
Paradigm ejected Allied from site on that day.
"It is with extreme concern and with a measure of disbelief that I have received notification of determination via Owen White…
We must therefore advise that following your failure to release the said certified payment, and in addition, ignore our replies to the alleged charges of default, we disagree with your action of securing the site and ejecting us from the same. We have been advised by Counsel to advise Paradigm that we will be preparing an action to recover all sums outstanding and any associated losses via the adjudication process. This is likely to involve a very substantial sum, comprising firstly, but not exclusively, the unpaid certificate, costs of works since certificate 15, and most importantly the fact that Paradigm have incorrectly indetermined [sic] the contract. In addition, I am informed, there is also retention due and loss of profit…
Should you wish to revoke your action and work with us as promised, we will take no further action. If you do not however, we must put Paradigm on notice that we will seek adjudication to protect our position particularly in relation to the incorrect determination of the contract…"
It is disputed however that this was sent or sent to and received by Mr Main.
"NATURE OF DISPUTE
On the 05 June 2009, [Allied] was ejected from the site…at around nine o'clock in the morning. At about 11 o'clock…[Allied] received [the] letter from [Paradigm's solictors] dated the 03 June 2009, purporting to, in accordance with the terms of the Contract, determine the Contract. [Allied] avers that [Paradigm] has wrongfully determined the Contract and has therefore by ejecting [Allied] from the Site and, by wrongfully determining the Contract, repudiated the Contract. [Allied] therefore seeks recovery of monies for works and variations that were carried out and not paid for and for the payment of damages for losses arising as a direct consequence of [Paradigm's] repudiatory breach of the Contract.
DECISION SOUGHT
The redress and/or relief sought in this adjudication are set out below. The Adjudicator will be requested to determine and decide that:-
(i) [Paradigm] has wrongfully determined [Allied's] employment under the Contract and has therefore repudiated the Contract.
(ii) [Allied] is entitled to payment in the sum of £248,016.80 or such other sum as the Adjudicator shall deem proper; being the balance between the sum due under the Contract as at the date of the repudiatory breach and the monies that have been paid to [Allied];
(iii) [Allied] is entitled to payment of damages for losses, in the sum of £30,456.40…incurred as a direct consequence of the repudiatory breach of the Contract;
(iv) [Allied] is entitled to payment in the sum of £8,567.15…of its expectation interest in the Contract i.e. the profit it would have earned on the Contract, had the Contract had been performed…"
There then followed claims for interest and costs. Three suggested non-legal adjudicators' names were proffered.
"…We consider that an appropriate adjudicator in this matter would be a legal adjudicator, i.e. a barrister with construction experience, rather than a surveyor. The issues in dispute are not technical ones…
We would also bring to your attention the fact that we have not had a letter of claim from your client, and therefore issuing a Notice of Adjudication is premature.
We also reserve our position in respect of the jurisdiction of the adjudicator, bearing in mind that the contract is now at an end, and will properly be the subject of either legal proceedings or arbitration. We are quite happy for either to take place, but put you on notice that we reserve our position on challenging the adjudicator's jurisdiction…"
"4. In summary, for the reasons set out below, and subject and without prejudice to Paradigm's rights in respect of jurisdictional objections raised in [their solicitors'] letter dated 10th July 2009 to Always Associates, (Appendix D) Paradigm submits that :-
4.1 The Adjudicator has no jurisdiction to determine Allied's claim for the reasons set out in [the] letter dated 10th July 2009 and as set out herein, Paradigm fully reserves its rights in respect of those jurisdictional objections, and this Response is served subject to and without prejudice thereto.
4.2 The dispute concerns the determination of the build contract and the consequences that flow from it. These losses have not yet crystallised and with no ongoing contract, the dispute is not a matter which is best decided by adjudication due to the contested nature of some of the evidence. Paradigm believe that this dispute would be best dealt with either by a Court or by Arbitration when such evidence can be fully tested. Further, Paradigm have never received a Letter before Referral setting out the matters now raised by Allied."
Paragraphs 4.3 to 4.9 address the merits of Allied's claims.
"As regards [Paradigm's] assertion that the Adjudicator does not have jurisdiction because [Allied] did not send a letter, [Paradigm] has not stated as to why the failure to send such a letter would in any way affect the jurisdiction of the Adjudicator. Furthermore, [Paradigm], through its solicitors, and presumably after appropriate legal advice, decided to determine, albeit wrongly, [Allied's] employment under the Contract. It is to be presumed therefore that [Paradigm] was fully aware of the risks of the course of action which it took and so cannot now claim to be surprised when it finds itself having to account for its actions in this adjudication. For the avoidance of doubt, adjudication is not subject [to] the Civil Procedure Rules Construction Pre-Action Protocol."
"41. Paradigm has raised three jurisdictional points…
41.1 that Allied requested the RICS to nominate an adjudicator prior to the contractual 7 day time period…
41.2 that losses have not yet crystallised and because the Contract is not ongoing it is not a matter best decided by adjudicator…
41.3 that Paradigm has never received a letter from Allied prior to the Referral setting out the matters now raised.
42. Allied resists these challenges and I reject them principally for the reasons set out below:-
42.1…
42.2…
42.3 Paradigm received the Notice of Adjudication, to which I have already made reference in this Decision, prior to the Referral."
The issues
The law
(a) Disputes can arise in a plethora of ways and over different periods of time. There is no formula by which one can say that a dispute has or has not arisen.
(b) The types of dispute are "Protean" (as was said in one case) or infinite in extent or quality. Parties on a multi million contract can have a dispute about £1 or £100m; disputes do not even have to relate to money at all but can relate merely to contractual interpretation or a legal issue. Indeed, disputes can relate to future as well as to past events.
(c) One must analyse what if any dispute has been referred at the time that the procedure to refer, laid down in the contract or by statute, is initiated.
(a) To enable a dispute or difference to arise, there must be a claim, an assertion or adoption of a position by one party which is expressly or by implication rejected or at least not accepted by the other (see e.g. Balfour Beatty Engineering Services (HY) Ltd v Shepherd Construction Ltd [2009] EWHC 2218 (TCC). The claim, assertion, rejection or non-acceptance does not need to be in writing or to be in any form or necessarily be detailed.
(b) The claim, assertion or adoption of the position must be communicated to the other party. It can not be enough to create a dispute that one party simply believes in its own mind (without any communication to the other) that if it was to make a claim it would in all probability be rejected by the other party.
(c) One needs to look at the history and the context in which the dispute is said to have arisen but the law adopts an inclusive interpretation as to what amounts to a dispute (see Amec Civil Engineering Ltd v The Secretary of State for Transport [2005] BLR 227 and Bovis Lend Lease ltd v The Trustees of the London Clinic [2009] EWHC 64 (TCC). The Court should not adopt an over legalistic analysis of what the dispute between the parties are ; instead it will determine in broad terms what the disputed claim, assertion or position is. In Cantillon Ltd v Urvasco Ltd [2008] EWHC 282 (TCC), it was said at Paragraph 55:
"There has been substantial authority, both in arbitration and adjudication, about what the meaning of the expression "dispute" is and what disputes or differences may arise on the facts of any given case. Cases such as Amec Civil Engineering Ltd -v- Secretary of State for Transport [2005] BLR 227 and Collins (Contractors) Ltd -v- Baltic Quay Management (1994) Ltd [2004] EWCA (Civ) 1757 address how and when a dispute can arise. I draw from such cases as those the following propositions:
(a) Courts (and indeed adjudicators and arbitrators) should not adopt an over legalistic analysis of what the dispute between the parties is.
(b) One does need to determine in broad terms what the disputed claim or assertion (being referred to adjudication or arbitration as the case may be) is.
(c) One cannot say that the disputed claim or assertion is necessarily defined or limited by the evidence or arguments submitted by either party to each other before the referral to adjudication or arbitration.
(d) The ambit of the reference to arbitration or adjudication may unavoidably be widened by the nature of the defence or defences put forward by the defending party in adjudication or arbitration…
In my view, one should look at the essential claim which has been made and the fact that it has been challenged as opposed to the precise grounds upon which it has been rejected or not accepted. Thus, it is open to any defendant to raise any defence to the claim when it is referred to adjudication or arbitration. Similarly, the claiming party is not limited to the arguments, contentions and evidence put forward by it before the dispute crystallised. The adjudicator or arbitrator must then resolve the referred dispute, which is essentially the challenged claim or assertion but can consider any argument, evidence or other material for or against the disputed claim or assertion in resolving that dispute."
(d) It follows from the above that if a basic claim, assertion or position has been put forward by one party and the other disputes it, the dispute referred to adjudication will or may include claims for relief which are consequential upon and incidental to it and which enable the dispute effectively to be resolved. Thus, even if the claim did not as such seek a declaration or discretionary interest or costs, it is so connected with and ancillary to the referred dispute as properly to be considered as part of it. There must be limits to this which can be determined by analysing what the essential dispute referred is.
"…I agree that the word "difference" probably goes wider than the concept of a "dispute."
He went on at Paragraph 65 to say, correctly in my view:
"The words "dispute" and "difference" are ordinary words of the English language. They are not terms of art. It may be useful in many circumstances to determine the existence of the dispute by reference to a claim which has not been admitted within a reasonable time to respond; but it would be a mistake in my judgement to gloss the word "dispute" in such a way. I would be very cautious about accepting that either a "claim" or a "reasonable time to respond" was in either case a condition precedent to the establishment of the dispute."
Little turns on the verbal distinction between the two words in this case.
"On the severability issue, I conclude, albeit obiter in the result, as follows:
(a) The first step must be to ascertain what dispute or disputes has or have been referred to adjudication. One needs to see whether in fact or in effect there is in substance only one dispute or two and what any such dispute comprises.
(b) It is open to a party to an adjudication agreement as here to seek to refer more than one dispute or difference to an adjudicator. If there is no objection to that by the other party or if the contract permits it, the adjudicator will have to resolve all referred disputes and differences. If there is objection, the adjudicator can only proceed with resolving more than one dispute or difference if the contract permits him to do so.
(c) If the decision properly addresses more than one dispute or difference, a successful jurisdictional challenge on that part of the decision which deals with one such dispute or difference will not undermine the validity and enforceability of that part of the decision which deals with the other(s).
(d) The same in logic must apply to the case where there is a non-compliance with the rules of natural justice which only affects the disposal of one dispute or difference.
(e) There is a proviso to (c) and (d) above which is that, if the decision as drafted is simply not severable in practice, for instance on the wording, or if the breach of the rules of natural justice is so severe or all pervading that the remainder of the decision is tainted, the decision will not be enforced.
(f) In all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially, in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the Court."
Discussion
(a) Their solicitor's letter of 10 July 2009 does not reserve a jurisdictional objection in relation to quantum matters or indeed on the grounds of non-crystallisation of any dispute. The fact that Paradigm had "not had a letter of claim from" Allied is not a jurisdictional point at all; it is more a complaint or criticism that there has been no formal claim beforehand. There is of course no requirement under the adjudication clause or in the HGCRA for there to be such a formal claim beforehand. It follows that their complaint that the issue of a Notice of Adjudication was premature was also unfounded. The language of the letter suggests that the solicitors were aware of the need to reserve their position in relation to jurisdictional matters because they go on to reserve "their position in respect of jurisdiction of the adjudicator" on a specific ground, albeit one that was totally unjustified and is no longer pursued. The fact that they did not use the language of reservation in relation to the "letter of claim" point supports the view that there was no intention to make a jurisdictional reservation with regard to that point.
(b) Turning to the Response, the cross-reference to and incorporation of the "jurisdictional objection" in their solicitor's letter of 10 July 2009 is ineffective because that letter, for the reasons given above, did not reserve Paradigm's position on jurisdiction in relation to what, if any, dispute had crystallised. If one was construing Paragraph 4.2 of the Response as a contractual document or statutory instrument, it would in context not purport to be a jurisdictional objection at all. The jurisdictional objection, such as it is, is contained in Paragraph 4.1. Furthermore, the first three sentences of Paragraph 4.2 on their face do not raise jurisdictional objections. The fact that the losses have not yet crystallised or that the dispute might better be resolved other than by way of adjudication can not be or have been intended to have been a jurisdictional objection. Paragraph 4 as a whole is simply a summary of Paradigm's contentions in the adjudication, with the vast bulk of it addressing the merits. The "tacking on" of the point about the non-receipt of a "Letter before Referral" is not obviously a jurisdictional objection either. The use of capital letters suggests, if anything, a belief by the author that there was some formal requirement for such a letter. It would have been very easy in a short sentence to summarise the objection which is now advanced before the Court. The objection could have been framed as simply as this: "No dispute has crystallised". The wording and the fact that it was not so framed leads me to the conclusion that in any event no jurisdictional objection to that effect was intended.
(c) For the reasons given above, there is no jurisdictional requirement for a letter of claim, formal or otherwise, to be submitted by the referring party prior to the initiation of the adjudication process. Even if the reference to the "Letter before Referral" was intended as some type of jurisdictional objection, it was a bad point.
(d) The fact that in its Reply Allied believed that the "Letter before Referral" was put forward as a jurisdictional objection is immaterial. To the extent that it was a jurisdictional objection, the Reply at Paragraph 24 (see above) was wholly correct. When Allied said in that paragraph that Paradigm "has not stated as to why the failure to send such a letter would in any way affect the jurisdiction of the Adjudicator", it was factually correct. The fact that at no stage thereafter Paradigm sought to clarify its position in this context again suggests strongly that it was not making a jurisdictional objection at all.
Decision
Costs and Interest
(a) Solicitors costs: there is no effective challenge to the rates used. Some 40 hours is claimed for "attendance on documents". I do not consider that it is reasonable for Paradigm to have to pay more than £3000. There are other elements such as the attendance of more than one solicitor at the hearing and unattributed "other work not included above". In all the circumstances, £9000 is a reasonable allowance in the circumstances.
(b) Counsel's fees at £7900: again this seems somewhat high for Junior Counsel of five years call for Paradigm to have to pay for in full in circumstances in which the ultimate hearing was only two hours long. In my view, a sum of £5000, including the brief and prior advice and pleading work, is reasonable.
(c) Disbursements: the court fees, application fees, photocopying and courier charges are not effectively challengeable as anything other than reasonable. I find some difficulty in some of the other charges. For instance £5,056 is claimed for Mr Mullender who is a quantity surveyor originally retained by Allied on the project; he is said to have assisted in the Claim with locating documentation, preparing witness evidence, assisting Counsel and then assisting solicitors. Given the relatively high level of work done by Solicitors and Counsel, I can not see what particularly useful work was done by this gentleman. I am certainly not satisfied that the vast bulk of it is justified as reasonably payable by Paradigm. £1,690 is claimed for previous solicitors; again it is not clear what of added value they did which could reasonably be charged to the account of Paradigm. Finally there is the sum of £4325 for accountants who were retained to assist with the stay of execution argument which was abandoned by Paradigm. This seems to me broadly to be a reasonable charge. In all £6500 represents a reasonable amount to be paid by Paradigm for disbursements.