QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
YCMS LIMITED (trading as Young Construction Management Services) |
Claimant |
|
- and - |
||
(1) STEPHEN GRABINER (2) MIRIAM GRABINER |
Defendants |
____________________
Riaz Hussain (instructed by Greenwoods) for the Defendants
Hearing dates: 16 and 31 January 2009
____________________
Crown Copyright ©
MR JUSTICE AKENHEAD:
Introduction
The history
The Adjudication
"We note that our Notice and Referral does not deal with the final account but only to specific items.
That said if there is the possibility that parties can mutually agree to extend your jurisdiction and if you have such suggestions then it will be appropriate that we be made aware of these and have time to consider these."
"I refer to YCMS faxed letter to me this evening together with Valuation No. 14 which, for the present, I will designate the draft Final Account.
As YCMS have appreciated I realised on re-reading the Notice and Referral that the direction to be issued with the draft Final Account, contained within my letter to the Parties of 25 September 2007, exceeded my jurisdiction.
I therefore now invite both Parties to mutually agree to extend my jurisdiction to consider and decide on the Final Account which, given the current circumstances, I suggest excludes any additional works which are yet to be instructed.
I note that I received the Referral on the19th September 2007 and therefore without YCMS granting an extension of time I am required, at present, to publish my Decision by no later than the 17th October 2007. However, time has been lost in the proceedings, with beneficial results, and as a consequence I now propose that YCMS agree to the date being extended to the 29th October 2007."
He called for an early response.
"Further to your/Abacus suggestion of extending the jurisdiction of the Adjudicator to deal with the Valuation No. 14 we note that the Adjudicator is prepared to accept such a suggestion.
We request that you put forward a draft of agreement dealing with the extension to jurisdiction and the new timetable that needs to be agreed as a result of this.
Finally, I think it is best that this is agreed between the Parties and then put forward to the Adjudicator."
Abacus was a claims consultant retained by the Defendants in relation to the adjudication.
"We have now received instructions from Mr and Mrs Grabiner with regards to the proposition contained within your facsimile transmission of 2 October 2007 that the Parties mutually agree to extend your jurisdiction to consider and decide upon the Final Accounts. Mr and Mrs Grabiner do not agree to such an extension of your jurisdiction."
" We have discussed, with our Clients, the Adjudicator's proposal to extend their jurisdiction to take into account the valuation of the Final Account and/or Valuation 14. Mr and Mrs Grabiner were not particularly happy with this idea and therefore instructed us to reject the proposal, which was done. A few minutes after our fax was sent to the Adjudicator the writer was made aware of your facsimile transmission. Your fax implies that you think there is some merit in such an extension of the Adjudicator's jurisdiction "
"I note and accept from Abacus's letter that the Respondent does not wish to extend my jurisdiction to appraise and decide on the Final Account "
"The Certificate preceding this one is Certificate No. 12."
"As a general summary of our position and based on an assessment of the information available to us it is [the Defendants'] case that YCMS are not entitled to any further payments over and above those that have been made (postal strike excepted) at the time of this Response. The Adjudication notice refer[s] to Certificates 12 and 13 but these have been superseded by Certificate 14 which has been honoured by the Employer (subject only to the postal strike). Matters relating to Defects and the issue a Practical Completion Certificate have been fully dealt with by Architect, exercising his authority under the Contract by issuing correspondence dealing with the date of practical completion and the schedule of defects."
"18. The table of payments issued by YCMS [in the Referral] is incorrect and does not deal with payments up to and including Valuation 14.
19. The Architect has received Certificate 13 as draft and seeks the express request of the Referring Party. The Referring Party cannot state that any document marked as 'draft' is not 'draft' by their wish and their wish alone
23. Certificate 14 was issued in response to an extensive bundle of documents that was deposited at the Architect's offices on Saturday 15 September 2007. These documents substantially clarified the issues raised in Application 13 and the issue of the draft Certificate. For avoidance of doubt and to ensure there was no confusion the revised Certificate has been referred to as 'Certificate 14' and not Certificate 13 (formal release) as was intended
28. The Responding Party requests that the Adjudicator accepts that Certificate 14 supersedes Certificate 13 (whether draft or otherwise) and that payment by [the Defendants] of the sums contained in Certificate 14 and in accordance with the provisions of the Contract resolves and deals with the matter of payment "
" the issue of what constitutes a dispute relies upon events leading up to that dispute. Once a dispute crystallises, its foundations are the events leading up to that dispute. The actions of parties after the issue of the Referral, for example, the making of payments does not remove the dispute. The Adjudicator still has to decide the dispute. The Adjudicator has jurisdiction (and indeed a contract) to decide the dispute referred to and decide the sums to be paid. If the Respondents make payment during the dispute and let us say for example the sums are found not to be due then I am sure you will agree with us that an adjustment would be proper. Hence it is our view that we must proceed to an award. Indeed without an award the parties would be at a loss as to how your costs are to be apportioned. Further events such as the Architect's issue of Certificate No. 14 and the interesting suggestion that this now becomes part of the dispute would suggest that the Respondents have singularly extended your jurisdiction, something I am sure that the Respondents would like to be able to do however I think you will concur you are unable to.
The point argued by the Respondents that certificate No. 14 is part of the dispute is therefore no longer relevant. Further if consideration must be given for certificate No. 14 (which our argument is that it should be ignored) we fail to see how the Respondents can maintain that position given that they have, as demonstrated in our Referral, proposed to pay certificate. 12 and 13 in instalments."
The First Adjudication Decision
"The balance of the sum due, certified up to and including Interim Certificate No. 14, of £25,942.74 plus the VAT which may be due on the sum certified under Interim Certificate No. 14." (Para 7.1)
"(d) A further payment, on account, of £100,000 was then made which reduced the shortfall of the sum due to £132,578.70 (adopting the sum actually claimed).
(e) Since the commencement of the adjudication
Interim Certificate no 14 has been issued certifying a further sum of £15,615.45 (excl VAT).
The following further payments have been made
24th September £72,672.36
8th October £18,348.15
Total £91,020.51
(f) These further payments reduced the shortfall up to and including the total sum certified on I.C. no 14 £25,942.74 (£132,578.70 minus £106,635.96).
(g) There is no provision within the Contract for the issue of a 'Draft' Interim Certificate therefore the qualification attached to I.C. no 13 is invalid.
COMMENT AND OPINION
(i) If a CA [Architect] is not in possession of all the information required to support the sum to be certified he should reduce the sum accordingly. A 'Draft' interim certificate cannot be issued.
(ii) If it is found the sum certified is incorrect then the proper procedure is to make the necessary adjustment in the next certificate.
(iii) Once an interim certificate is issued it triggers a number of other contractual provisions which cannot be ignored and therefore a certificate cannot be withdrawn.
(iv) It is therefore my opinion YCMS are entitled to be paid the further sum of £25,942.74."
"7.1 [The Defendants] pay within 7 days of the date of this decision [YCMS] the balance of the sum due, certified up to and including Interim Certificate no 14, of £25,942.74 plus the VAT which may be due on the sum certified under Interim Certificate no 14."
"We would like to draw your attention to page 7 items (e) and (f) specifically. We concur that the sums calculated in item (e) show £91,020.51. This figure is taken from copies of cheques received. These cheques include VAT.
In paragraph (f) you deduct the sum of £106,635.96. You have added VAT to £91,020.51. The figure of £91,020.51 includes VAT so there is no reason to add VAT again.
The correct calculation is £132,578.70 less £91,020.51 leaving the amount payable as £41,558.19 and not £25,942.74. Please could you revise your Award.
We note you refer to I.C. No. 14. We are of the opinion that this should read I.C. 13 as 14 was not part of this Adjudication and you awarded on the basis that I.C. 13 was in fact a valid certificate.
Finally we thank you for your Award and look forward to the correction of these slips."
This letter was copied to the Defendants and Abacus.
"I acknowledge receipt of YCMS' letter to me of the 29th October 2007 in which they drew my attention [sic] a 'slip' made in my calculations with respect to the outstanding sum to be paid from that certified up to and including Interim Certificate no 14.
I have now rechecked my calculations and found that the sum YCMS claim and my calculations are both incorrect. Our joint confusion has arisen because payments made, on account, do not relate to either of the sums certified or the amounts which are outstanding at any point together with the issue of I.C. 14 during the proceedings.
I therefore enclose pages nos 6, 7 and 12 of my Decision which have been amended to reflect the corrections required which will be substituted into the Decision.
I apologise in this matter "
"5(c) I note from the Schedule that payments were made in full up to and including Interim Certificate No. 9. The position was then, and subsequently
Int. Cert. | Sum Invoiced | Amount Paid | Payment Date |
9 | £97,718.44 | £83,164.33 | 04.01.07 |
£14,553.81 | 23.01.07 | ||
10 | £199,963.03 | £199,693.33 | 07.02.07 |
11 | £104,663.71 | £40,000.00 | 21.03.07 |
£64.663.71 | 30.04.07 | ||
12 | £172,672.36 | £100,000.00 | 09.07.07 |
£72,672.36 | 24.09.07 (In Adjudicaton Period) | ||
13 | £59,905.36 | ||
14 | £18,348.15 | 08.10.07 (In Adjudication Period) | |
Totals | £653,002.05 | £593,095.69 |
(d) The sum outstanding from Interim Certificates up to and including no 14 is therefore £59,906.36 (£653,002.05 total amount certified minus £593,095.69 total amount paid to date).
(e) There is no provision within the Contract for the issue of a 'draft' Interim Certificate therefore the qualification attached to I.C. no 13 is invalid.
COMMENT AND OPINION
(i) [as before]
(ii) [as before]
(iii) [as before]
(iv) It is therefore my opinion YCMS are entitled to be paid the further sum of £59,906.36
7.1 Mr and Mrs Grabiner pay, within seven days of the date of this Decision, [YCMS] the balance of the sum due, certified up to an including Interim Certificate no 14, £59,906.36 (which sum includes the VAT due) "
"In our calculations and based on the principles laid down in your Adjudication Decision we do not believe that there was any money owed by [the Defendants] to YCMS up to and including the proper issue of Certificate 14 and we invite you to correct your decision accordingly.
A schedule is attached that deals with the properly certified gross value (Certificate 14) and other values relating to payment."
That schedule took the gross value of work as certified in Certificate No 14, deducted retention, added VAT and deducted the amount paid by the Defendants to YCMS leaving a balance of "NIL".
"There is precedent supported by case law, which permits an Adjudicator to correct 'slips' within a Decision. I took advantage of this accepted practice to adjust the incorrect calculation in my Decision."
The Second Adjudication
"4.5 The first part of the Adjudication is about a dispute over the value of the preliminaries given that both the Contract Duration and Contract Sum have increased substantially. This part of the Adjudication shall be referred to as 'Additional Preliminaries'.
4.6 The second part of the Adjudication is about items of work that have been completed on site and valued in earlier Interim Certificates then omitted in subsequent Certificates. This part shall be referred to as 'Undervalued Works'."
£159,062.85 was claimed for the Additional Preliminaries whilst £111,732.97 was claimed with regard to the Undervalued Works.
"However, in view of:
1. The duplication between the two Adjudications (as to which, we refer you to our letter of 13 May 2008 and paragraphs F and G of the Rejoinder in the Second Adjudication), the sums awarded in the latter Adjudication quite clearly embrace the sum awarded in the former Adjudication, both being clearly expressed to be payments in excess of the gross sums certified and paid under Certification 14 your client cannot purport to adjudicate and recover the same sum twice, and
2. The fact that your clients have issued two sets of Enforcement Proceedings.
Such payment would be in full and final settlement of the sums awarded in both Adjudications and on the basis that the Enforcement Proceedings are brought to an end by withdrawal, discontinuance, stay or other appropriate procedural mechanism
The principal reason that the offer is expressed in this way is that your clients cannot adjudicate the same matters twice and for that reason your clients cannot seek enforcement of both Awards. Indeed, in the event that the offer is not accepted, our clients reserve their position to argue that because of that fact neither Adjudication Award is properly enforceable to oppose enforcement of both sets of proceedings on that basis "
The Third Adjudication
" the essence of [the dispute] was the value to be included in the Final Certificate as the adjusted Contract Sum."
In this Adjudication the Defendants were the Referring Party. Essentially the argument was that the Final Certificate valuation was such that there had been an over-payment.
"My decisions on redress are tailored to that requested in the Referral I order, direct and declare as follows:-
.1 The Final Account in total of the adjusted Contract Sum is £1,144,562.36 This sum excludes VAT.
.2 The Responding Party shall pay to the Referring Party under IFC 98 clause 4.6.1.3 the sum of £17,890.74, being the balance due to the Referring Party This Sum excludes VAT. The payment is to be made within 28 days of the date of my Decision reflecting the payment period prescribed by clause 4.6.1.3.
.3 The Court has not, at the date of my Decision, ordered enforcement of the First Award (in Adjudication 1), and there is therefore no requirement for me to consider the effects of those proceedings on my Decision
.5 I apportion my entire fee to the Responding Party. I direct the Responding Party to reimburse the Referring Party for the payment that the Referring Party is making against my interim/final invoice. The payment to be made is £8,238.75 plus VAT. The payment shall be made by the Responding Party within seven days of me confirming that I have received payment for my fee from the Referring Party "
These Proceedings
The Issues
(a) It is said that the First Award was made outside the Adjudicator's jurisdiction because the Adjudicator purported to award the sum due under Interim Certificates up to and including Certificate 14 (which had been issued after the Adjudication Notice and after the Parties expressly declined to extend the Adjudicator's jurisdiction to include an award of sums due under Certificate14).
(b) It is argued that the purported revision of the First Award was not valid.
(c) If the First Award (in its revised or unrevised state) is enforceable it is said that it is duplicated by the Second Award and because the Second Award was paid, in effect YCMS will be paid twice if anything is allowed to them pursuant to the First Award.
(d) The Defendants should be permitted to set off the sums awarded to them under the Third Decision.
The Law
(a) It is necessary to analyse with some care what has been referred to adjudication; put another way analysis needs to be done as to what the dispute is that has crystallised and has been referred to adjudication.
(b) It is open to the defending party in adjudication to put forward a defence which has not been raised before. There is nothing in the Housing Grants Construction and Regeneration Act 1996 ("HGCRA") which prevents a defendant from raising any defence. It may of course be that the defence raised is decided by the Adjudicator to be unarguable either in law or on the facts but that does not mean that the defendant should or can be barred from raising any such defence.
"It is clear that the error in this case falls into the category of the slip. [The Adjudicator] was giving effect to his first thoughts and intentions in his amended ruling. In my view, in the absence of any specific agreement to the contrary, a term can and should be implied into the contract referring the dispute to adjudication, that the adjudicator may, on his own initiative or on the application of a party, correct an error arising from an accidental error or omission. The purpose of the adjudication is to enable broad justice to be done between the parties. Parties acting in good faith will be bound to agree at the start of the adjudication that the adjudicator could correct an obvious mistake of the sort which he made in this case.
Clearly, there must be a time limit within which such an amendment can be made, but in this case the amendment was made within three hours of the communication of the original decision. This must in the circumstances of this case be within any acceptable time limit. I bear in mind that both parties agree that the revised decision corrected a manifest error and that there is no suggestion that Bloor was prejudiced by the amendment.
I note that the time limits under section 57(3) of the Arbitration Act 1996 stipulate a period of 28 days within which any application for the correction of an arbitrator's award must be made. I am not prepared to say that such a long time limit is necessarily appropriate for an adjudication.
An additional reason for holding that the slip rule applies is the lack of ability of the High Court to correct obvious errors in adjudication except in very restricted circumstances, even where such errors cause manifest injustice."
The Judge went on to say:
"The primary reason for my decision is that, in the absence of a specific agreement by the parties to the contrary, there is to be implied into the agreement for adjudication the power of the adjudicator to correct an error arising from an accidental error or omission or to clarify or remove any ambiguity in the decision which he has reached, provided this is done within a reasonable time and without prejudicing the other party "
"33. I conclude, therefore, that the law before this case is that in relation to a slip or alleged slip there are two questions: (1) is the Adjudicator prepared to acknowledge that he has made a mistake and correct it? (2) is the mistake a genuine slip which failed to give effect to his first thoughts? If the answer to both questions is 'Yes' then, subject to the important question of the time within which the correction is made and questions of prejudice, the court if the justice of the case so requires give effect to the amendment to rectify the slip.
34. Having considered the matter again, I adhere to my decision in Bloor. It found some limited support from Dyson J in Ed McNuttall v Sevenoaks District Council [decided 14 April 2000] a few days after Bloor when he concluded in relation to the decision in Bloor:
'In my view, putting the matter at its lowest, it is at least arguable that it is right.'
35. The decision in Bloor is, however, of very limited and narrow application "
"It is a distinction between having second thoughts and intentions and correcting an award to give effect to first thoughts or intentions which creates the problem. Neither an arbitrator nor a judge can make any claim to infallibility. If he assesses the evidence wrongly or misappreciates the law the resulting award or judgment will be erroneous but it cannot be corrected under section 17 (of the Arbitration Act 1950) or under the old Order 20 Rule 11. It cannot normally be corrected under section 22 (where the arbitrator has made a mistake). The remedy is to appeal if the right of appeal exists. The skilled arbitrator or judge may be tempted to describe this as an accidental slip but this is a natural form of self-exculpation."
The learned judge also quoted with approval the commentary in Mustill & Boyd on Commercial Arbitration at page 406:
"This [the Arbitration Act 1996] enables the arbitrator to make an award on a claim which he has inadvertently overlooked such as an award of interest or to correct errors of accounting or arithmetic such as attributing a credit item to the wrong party but the section does not give the arbitrator licence to give effect to second thoughts on a matter on which he has made a conscious judgment.'
(a) An adjudicator can only revise a decision if it is an implied term of the contract by which adjudication is permitted to take place that permits it. It does not follow that, if it is purely a statutory arbitration under the HGCRA (if there is no contractual adjudication clause), such implication can be said to arise statutorily.
(b) If there is such an implied term, it can and will only relate to "patent errors". A patent error can certainly include the wrong transposition of names or the failing to give credit for sums found to have been paid or simple arithmetical errors.
(c) The slip rule cannot be used to enable an adjudicator who has had second thoughts and intentions to correct an award. Thus for example, if an adjudicator decides that the law is that there is no equitable right of set off but then changes his mind having read some cases feeling that he has got that wrong, such a change would not be permitted because that would be having second thoughts.
(d) The time for revising a decision by way of the slip rule will be what is reasonable in all the circumstances. In the Bloor case, the Adjudicator revised his decision within several hours and before the time for issuing a decision had been given. It will be an exceptional and rare case in which the revision can be made more than a few days after the decision. The reason for this is that, unlike a court judgment or an arbitration award, a principal purpose of the 1996 Act is to facilitate cash flow. If an adjudicator was able to revise his decision, say, 21 or 28 days later that would necessarily slow down and interfere with the speedy enforcement of adjudicators' decisions. That would in broad terms be contrary to the policy of the Act.
" Where the parties to a construction contract engage in successive adjudications, each focused upon the parties' current rights and remedies, in my view the correct approach is as follows. At the end of each adjudication, absent special circumstances, the losing party must comply with the adjudicator's decision. He cannot withhold payment on the ground of his anticipated recovery in a future adjudication based upon different issues. I reach this conclusion both from the express terms of the Act, and also from the line of authority referred to earlier in this judgment."
Discussion
(a) It is clear that in the First Decision (Unrevised) the Adjudicator made an inexplicable arithmetical error. Having decided at Paragraph 5.1(d) that the sum due was £132,578.70 and at Paragraph 5.1(e) that £91,020.51 had been paid, he then deducted £106,635.96 (for some unaccountable reason) from the sum due to leave a balance of £25,942.74. Applying his logic, the sum which he should have found due was £132,578.70 less £91,020.51, namely a balance of £41,558.19 (which is exactly the figure which YCMS said in its letter of 29 October 2007 to the Adjudicator was the correct figure).
(b) If the Adjudicator had revised his Decision to produce this figure £41,558.19, the correction (subject to time) would have fallen within the ambit of the adjudication slip rule and its legitimate application.
(c) However, what the Adjudicator seems to have done in his revision was to decide that the net sum certified in Certificate No. 14 should be taken into account both in terms of a gross sum due as well as a sum paid. This was in effect another and a serious error for the Adjudicator to make because he overlooked the fact that Certificates 13 and 14 effectively and necessarily duplicated themselves because Certificate No. 14 was for a lesser sum than that certified in Certificate No. 13. Put another way, by allowing £18,348.15 in the sum invoiced and due column for Certificate No. 14, he was necessarily duplicating what was in the same column for Certificate No.13, because Certificate No 13 was overall for a greater sum than Certificate No.14. Thus, arithmetically if one takes the sum certified in Certificate No. 14 both in the sum invoiced and sum paid column whilst also allowing the gross sum certified as due in Certificate No. 13, the sum due on those figures is bound to be overstated by the amount certified as due in Certificate No. 14.
(d) I must conclude that the Adjudicator thought carefully about the changes which he introduced arithmetically. He had been pointed clearly by YCMS to the arithmetical error. He decided (and it was clearly in my judgment second thoughts) that he needed to bring in the sum due and sum paid on Certificate No. 14. He thus rejected any correction of a simple arithmetical error (which would have produced a total due to YCMS of some £41,000) in favour of a further calculation, the logic of which must be known only to the Adjudicator.
(e) In the ordinary course of events the operation of the slip rule does not result in any prejudice to either party because the Tribunal is simply putting right a mistake which it has made which it would not otherwise have made. Here, the Defendants are materially prejudiced by the amendment because the Adjudicator simply got it wrong the second time round.
The VAT Issue