QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
INTERSERVE INDUSTRIAL SERVICES LIMITED |
Claimant |
|
- and - |
||
CLEVELAND BRIDGE UK LIMITEDDefendant |
____________________
183 Clarence Street Kingston-Upon-Thames Surrey KT1 1QT
Tel No: 020 8974 7300 Fax No: 020 8974 7301
Email Address: tape@wordwave.co.uk
____________________
Crown Copyright ©
Monday, 6 February 2006
MR JUSTICE JACKSON:
Part 1: Introduction
"(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section.
For this purpose "dispute" includes any difference.
(2) The contract shall--
(a) enable a party to give notice at any time of his intention to refer a dispute to adjudication(b) provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice(c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred(d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred(e) impose a duty on the adjudicator to act impartially and(f) enable the adjudicator to take the initiative in ascertaining the facts and the law.(3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement…"
"(1) Every construction contract shall--
(a) provide an adequate mechanism for determining what payments become due under the contract, and when, and(b) provide for a final date for payment in relation to any sum which becomes due.The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment.
(2) Every construction contract shall provide for the giving of notice by a party not later than five days after the date on which a payment becomes due from him under the contract, or would have become due if--
(a) the other party had carried out his obligations under the contract, and(b) no set-off or abatement was permitted by reference to any sum claimed to be due under one or more other contracts,specifying the amount (if any) of the payment made or proposed to be made, and the basis on which that amount was calculated.(3) If or to the extent that a contract does not contain such provision as is mentioned in subsection (1) or (2), the relevant provisions of the Scheme for Construction Contracts apply."
"(1) A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment.
The notice mentioned in section 110(2) may suffice as a notice of intention to withhold payment if it complies with the requirements of this section.
(2) To be effective such a notice must specify--
(a) the amount proposed to be withheld and the ground for withholding payment, or(b) if there is more than one ground, each ground and the amount attributable to it,and must be given not later than the prescribed period before the final date for payment.
(3) The parties are free to agree what that prescribed period is to be.
In the absence of such agreement, the period shall be that provided by the Scheme for Construction Contracts.
(4) Where an effective notice of intention to withhold payment is given, but on the matter being referred to adjudication it is decided that the whole or part of the amount should be paid, the decision shall be const rued as requiring payment not later than--
(a) seven days from the date of the decision, or(b) the date which apart from the notice would have been the final date for payment,whichever is the later."
"4. The Adjudicator's decision shall be binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement.
5. The Parties shall implement the Adjudicator's decision without delay whether or not the dispute is to be referred to legal proceedings or arbitration …
27. The Adjudicator may in any decision direct the payment of such simple or compound interest from such dates, at such rates and with such rests, as he considers appropriate.
28. The Adjudicator may, within 5 days of delivery of the decision to the Parties, correct his decision so as to remove any error arising from an accidental error or omission or to clarify or remove any ambiguity.
29. The Parties shall bear their own costs and expenses incurred in the adjudication.
30. The Parties shall be jointly and severally liable for the Adjudicator's fees and expenses, including those of any legal or technical adviser appointed under paragraph 19, but the Adjudicator may direct a Party to pay all or part of the fees and expenses. If he makes no such direction, the Parties shall pay them in equal shares. The Party requesting the adjudication shall be liable for the Adjudicator's fees and expenses if the adjudication does not proceed.
31. The Parties shall be entitled to the redress set out in the decision and to seek summary enforcement, whether or not the dispute is to be finally determined by legal proceedings or arbitration. No issue decided by the Adjudicator may subsequently be referred for decision by another adjudicator unless so agreed by the Parties."
Part 2: The Facts
"1(a) The Subcontractor shall provide all supervision, labour, materials, plant, equipment, tools, consumables and temporary works required for the execution of the Subcontract Works described in Part 3 of the Appendix in accordance with the subcontract and to the reasonable satisfaction of CBUK and the Client.
(b) The Subcontractor shall exercise all due skill, care and diligence in designing any part of the Subcontract Works for which design the Subcontractor is responsible, and in selecting any materials for which selection the Subcontractor is responsible.
(c) The Subcontractor shall execute, complete, maintain and remedy defects in the Subcontract Works in accordance with the Subcontract and to the reasonable satisfaction of CBUK and the Client.
…
2(a) The Subcontractor shall commence the Subcontract Works on site on the date instructed by CBUK in writing and shall thereafter proceed with the Subcontract Works with due diligence and without delay in such manner and sequence to avoid hindrance to the progress of others and to ensure timely completion of CBUK's Contract with the Client. The Subcontractor shall ensure that all necessary off-site works, designs, supply and manufacture, are carried out in good and sufficient time to enable the Subcontract Works to be commenced on site in accordance with this Clause 2(a), and subsequently completed in accordance with Clause 2(b).
…
8(f) Not later than 5 days after the due date for payment by CBUK, CBUK shall send written advice to the Subcontractor specifying the amount of the payment which is to be made and the basis on which that amount was calculated.
(g) Not later than 5 days before the final date for any payment by CBUK, CBUK may send written advice to the Subcontractor specifying the amount of the payment which is proposed to be deducted from the amount notified under Clause 8(f), together with the grounds for such deduction.
…
10(b) Either party may at any time serve written notice of its intention to refer any dispute under this Subcontract to adjudication. Unless otherwise mutually agreed, the procedure for appointment of an adjudicator and the deciding of the dispute shall be the same as that in CBUK's Contract with its Client. The adjudication provisions contained within CBUK's Contract with the Client shall be applicable under the Subcontract as between CBUK and the Subcontractor as if they were respectively the Client and CBUK except that CBUK and the Subcontractor shall each bear their own costs and expenses of any adjudication and shall share the cost and expenses of the adjudicator equally, whatever the result of the adjudication.
(c) If for any reason the adjudication provisions of the Scheme for Construction Contracts under the Housing Grants Construction and Regeneration Act 1996 should apply, then CBUK and the Subcontractor shall each bear their own costs and expenses of any adjudication and shall share the cost and expenses of the adjudicator equally, whatever the result of the adjudication.
…
18. In the event of conflict between the documents forming the Subcontract the order of precedence shall be the Appendix, the Standard Conditions of Subcontract, CBUK's Contract with the Client."
"Whereas …
C The Parties acknowledge that a delay has arisen to the progress of the Subcontract Works ("the Delay") and there is a dispute as to which party is responsible for the Delay ("the Dispute"),
D Pending resolution of the Dispute and in order to progress the Sub-Contract Works and to mitigate the effects arising from the Delay, CBUK and Interserve have agreed to the following terms.
NOW HEREBY IT IS AGREED AS FOLLOWS
GENERALLY:
1. CBUK undertakes to handover areas to Interserve in accordance with Appendix D.
2. Interserve undertakes to complete those elements of the Subcontract Works necessary to allow the complete removal of the traffic management to the M1 Motorway and A631 trunk roads no later than 31st October 2004 (refer to Appendix A) provided that it is not prevented from doing so by reason of an event referred to in Clauses 2(c)(i) and/or (ii) of the Subcontract.
3. Interserve undertake to complete the balance of the Subcontract Works no later than 31st January 2005 provided that it is not prevented from doing so by reason of an event referred to in Clauses 2(c)(i) and/or (ii) of the Subcontract.
For the avoidance of doubt this date is not to be taken as an acknowledgement on the part of CBUK of Interserve's entitlement to an extension of time under the Subcontract.
4. In consideration of the undertakings given by Interserve in paragraphs 1 & 2 above CBUK agree to provide additional funds to Interserve over and above the current forecast contract value, giving a total aggregate figure in the sum of £8,900,000 …
6. Payment of all additional funds under this Interim Funding Agreement are deemed to be interim and temporary funding payments made on account only pending resolution of the Dispute. Such interim temporary funding has been provided to progress the Works on an interim basis only and is not to be taken as an admission of culpability for delay by either party. Upon resolution of the Dispute, either CBUK will make immediate payment to Interserve of the balance of any amount agreed or awarded which exceeds the amounts previously paid or, conversely, Interserve will immediately repay to CBUK the overpaid balance if the sum agreed or awarded is less than the amounts previously paid to Interserve by CBUK plus the amount awarded to CBUK by way of losses as a result of any breach by Interserve. For the avoidance of doubt, this does not affect any other right or remedy which either party has under the Subcontract or otherwise."
1. The obligation to provide any necessary vertical longitudinal sheeting at or about the centre line of the viaduct rests with INTERSERVE.
2. The obligation to seal the Safespan access system against egress of substances arising from INTERSERVE's work rests with CLEVELAND.
3. The obligation to provide any necessary access system above the level of the Safespan Primary Access System rests with INTERSERVE.
Part 3: The present proceedings
Part 4: Should the sums awarded to Cleveland in adjudication three be set off against the sums awarded to Interserve in adjudication two?
"(2) Every such court shall give the same effect as hitherto--
(a) to all equitable estates, titles, rights, reliefs, defences and counterclaims, and to all equitable duties and liabilities; and
(b) subject thereto, to all legal claims and demands and all estates, titles, rights, duties, obligations and liabilities existing by the common law or by any custom or created by any statute,
and, subject to the provisions of this or any other Act, shall so exercise its jurisdiction in every cause or matter before it as to secure that, as far as possible, all matters in dispute between the parties are completely and finally determined, and all multiplicity of legal proceedings with respect to any of those matters is avoided."
"… section 111 now constitutes a comprehensive code governing the right to set off against payments contractually due. RBSTB has not complied with it. It would make a nonsense of the overall purpose of Part II of the Act, to which sections 108 and 111 are central and in which they are closely associated, not least by the terms of section 111(4), if payments required to comply with adjudication decisions were more vulnerable to attack in this way than those simply falling due under the ordinary contractual machinery. To return to the question left unanswered in paragraph 56 above, therefore, I find these compelling reasons for concluding that in clause 39A.7.2 and 39A.7.3, at least on the facts of this case, "comply " means "comply, without recourse to defences or cross-claims not raised in the adjudication"."
"But to my mind the answer to this appeal is the straightforward one provided by Judge Wilcox. The intended purpose of section 108 is plain. It is explained in those cases to which I have referred in an earlier part of this judgment. If Mr Collings and HHJ Thornton are right, that purpose would be defeated. The contract must be construed so as to give effect to the intention of Parliament rather than to defeat it. If that cannot be achieved by way of construction, then the offending clause must be struck down. I would suggest that it can be done without the need to strike out any particular clause and that is by the means adopted by Judge Wilcox. Clauses 29.8 and 29.9 must be read as not applying to monies due by reason of an adjudicator's decision."
Longmore LJ gave a judgment to the same effect.
"Now, in the present case, when one looks at clause 39A.7, although the language is not precisely the same, the contractual purpose, it seems to me, is clearly the same as that which was referred to by Longmore LJ [in Levolux]. The decision of the adjudicator is binding on the parties under clause 39A.7.1 until determined by arbitration or legal proceedings. The parties are to comply with the decision of the adjudicator and both parties shall ensure that the decision of the adjudicator is given effect to, and if either party does not comply then the other party shall be entitled to take legal proceedings to secure such compliance. That scheme, it seems to me, necessarily indicates that the decision of the adjudicator is to be given effect to and the idea that the decision of the adjudicator can be defeated by a withholding notice in respect of events which occurred subsequent to the commencement of the adjudication seems to me to be entirely inconsistent with the statutory purpose of providing a quick and effective remedy on an interim basis. An adjudicator's decision is meant to be enforced and complied with without, it seems to me, subtle arguments and detailed arguments as to other provisions of the contract."
"So what one has, is an adjudicator's decision ordering payment of monies, that is the 1.33 million. I will return in a moment to the claim in relation to the other two items: the two later certificates 22 and 23. So far as the adjudicator's decision is concerned, one has simply an adjudicator's award which, in my judgment, was clearly given within his jurisdiction. He may have been right or he may have been wrong in relation to the validity of the original section 24.1 notices but that is not a point which is for me to deal with today. That can be challenged in subsequent proceedings, if necessary. Having given the decision, the question then is: can the defendant refuse payment based on a cross-claim that it is going to be entitled to liquidated damages if it succeeds in the claim which it has put forward? In my view, the answer to this is no."
Judge Gilliland then referred to his own previous decision in Gleeson. Then at paragraph 30 he said this:
"Mr Singer submitted, correctly, that there is no express provision in clause 39.7 saying "there shall be no setoff" but that does not meet the point, which, it seems to me, is that if parties agree to comply with the adjudicator's award they are saying that they will do that, and that means they will not then refuse to do it on other grounds which may or may not turn out to be valid. That simply delays payment. The purpose of an adjudicator's decision ordering the payment of money is to assist cash flow. It is possible to challenge the matter subsequently if the parties wish to do so. That seems to me to be a clear policy and in my previous decision I did refer to the decision of the Court of Appeal in Levolux v Ferson which seems to me to support that principle."
Part 5: Should there be a stay of execution?
Part 6: The adjudicator's fees and interest
Part 7: Conclusion