If you found BAILII useful today, could you please make a contribution?
Your donation will help us maintain and extend our databases of legal information. No contribution is too small. If every visitor this month donates, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand London England WC2A 2LL |
||
B e f o r e :
____________________
TJ BRENT LTD and another |
||
v |
||
BLACK & VEATCH CONSULTING LTD |
____________________
Official Court Reporters
Cliffords Inn, Fetter Lane, London, EC4A 1LD
Telephone: 0207 269 0396
MELANIE WILLEMS and ROBERT BLACKETT of Howrey LLP appeared on behalf of the Defendant.
____________________
Crown Copyright ©
MR JUSTICE AKENHEAD:
Introduction
The practice
"1.3 The objectives of this Protocol are as set out in the Practice Direction relating to Civil
Procedure Pre-Action Protocols, namely:-
(i) to encourage the exchange of early and full information about the prospective legal claim;
(ii) to enable the parties to avoid litigation by agreeing a settlement of the claim before commencement of proceedings; and
(iii) to support the efficient management of proceedings where litigation cannot be avoided.
1.4 If proceedings are commenced, the court will be able to treat the standards set in this Protocol as the normal reasonable approach to pre-action conduct. If the court has to consider the question of compliance after proceedings have begun, it will be concerned with substantial compliance and not minor departures, e.g. failure by a short period to provide relevant information. Minor departures will not exempt the 'innocent' party from following the Protocol. The court will look at the effect of non-compliance on the other party when deciding whether to impose sanctions. For sanctions generally, see paragraph 2 of the Practice Direction – Protocols 'Compliance with Protocols'.
1.5 The overriding objective (CPR rule 1.1) applies to the pre-action period. The Protocol must not be used as a tactical device to secure advantage or to generate unnecessary costs…In all cases the costs incurred at the protocol stage should be proportionate to the complexity of the case and the amount of money which is at stake. The protocol does not impose a requirement on the parties to marshal and disclose all the supporting details and evidence that may ultimately be required if the case proceeds to litigation.
2. The general aim of this Protocol is to ensure that before court proceedings commence:
(i) the claimant and the defendant have provided sufficient information for each party to know the nature of the other's case;
(ii) each party has had an opportunity to consider the other's case, and to accept or reject all or any part of the case made against him at the earliest possible stage;
(iii) there is more pre-action contact between the parties;
(iv) better and earlier exchange of information occurs;
(v) there is better pre-action investigation by the parties;
(vi) the parties have met formally on at least one occasion with a view to
• defining and agreeing the issues defining and agreeing the issues between them; and
• exploring possible ways by which the claim may be resolved;
(vii) the parties are in a position where they may be able to settle cases early and fairly without recourse to litigation; and
(viii) proceedings will be conducted efficiently if litigation does become necessary."
3. Prior to commencing proceedings, the claimant or his solicitor shall send to each proposed defendant…a copy of his letter of claim which shall contain the following information:
(i) the claimant's full name and address;
(ii) the full name and address of each proposed defendant;
(iii) a clear summary of the facts on which each claim is based;
(iv) the basis on which each claim is made, identifying the principal contractual terms and statutory provisions relied on;(v) the nature of the relief claimed: if damages are claimed, a breakdown showing how the damages have been quantified; if a sum is claimed pursuant to a contract, how it has been calculated; if an extension of time is claimed, the period claimed;(vi) where a claim has been made previously and rejected by a defendant, and the claimant is able to identify the reason(s) for such rejection, the claimant's grounds of belief as to why the claim was wrongly rejected;(vii) the names of any experts already instructed by the claimant on whose evidence he intends to rely, identifying the issues to which that evidence will be directed.4.3.1 Within 28 days from the date of receipt of the letter of claim…the defendant shall send a letter of response to the claimant which shall contain the following information:
(i) the facts set out in the letter of claim which are agreed or not agreed, and if not agreed, the basis of the disagreement;(ii) which claims are accepted and which are rejected, and, if rejected, the basis of the rejection…5.1 Within 28 days after receipt by the claimant of the defendant's letter of response…the parties should normally meet.
5.2 The aim of the meeting is for the parties to agree what are the main issues in the case, to identify the root cause of disagreement in respect of each issue, and to consider (i) whether, and if so how, the issues might be resolved without recourse to litigation…
6. If by reason of complying with any part of this protocol a claimant's claim may be time- barred under any provision of the Limitation Act 1980, or any other legislation which imposes a time limit for bringing an action, the claimant may commence proceedings without complying with this Protocol. In such circumstances, a claimant who commences proceedings without complying with all, or any part, of this Protocol must apply to the court on notice for directions as to the timetable and form of procedure to be adopted, at the same time as he requests the court to issue proceedings. The court will consider whether to order a stay of the whole or part of the proceedings pending compliance with this Protocol."
"2.1 The Civil Procedure Rules enable the court to take account of compliance or non-compliance with an applicable Protocol when giving directions for the management of proceedings (see CPR Rules 3.1(4) and (5) and 3.9(e) and when making orders for costs (see CPR rule 44.3(a)).
2.2 The court will expect all parties to have complied in substance with the terms of an approved Protocol.
2.3 If, in the opinion of the court, non-compliance has led to the commencement of proceedings which might otherwise not have needed to be commenced, or has led to costs being incurred in the proceedings that might not otherwise have been incurred, the orders the court may make include:
(1) an order that the party at fault pay the costs of the proceedings, or part of those costs, of the other party or parties;
(2) an order that the party at fault pay those costs on an indemnity basis; ….
2.4 The court will exercise its powers under paragraphs 2.1 and 2.3 with the object of placing the innocent party in no worse position than he would have been in if the protocol had been complied with."
"There can often be a complaint that one or other party has not complied with the Protocol. The court will consider any such complaints once proceedings have been commenced. If the court finds that the claimant has not complied with one part of the Protocol, then the court may stay the proceedings until the steps set out in the Protocol have been taken."
The facts and whether there was compliance
"Our Clients: TJ Brent Limited
Claim by Southern Water
Fuel oil leak at Andover
Introduction
Clausen Miller LLP has been retained to represent [Brent] and its liability insurers in connection with the above incident.
Mayer Brown Rowe and Maw have been retained to represent [Loveland] and its liability insurers in connection with the above incident.
This letter is written on behalf of both Brent and Loveland and explains the basis of the claim that Brent and Loveland make against you ("BV").
Relevant events
Southern Water employed Brent as main contractor to execute works to facilitate improvements to the disinfection process at four water supply works … including Andover…
Brent employed Loveland to carry out the civil and building works…
BV … was the consulting engineer responsible for the design of the works employed by Southern Water.
The terms of Brent's employment are recorded in a written contract…dated 12 March 2001.
[There then follows 1½ pages of explanation about the escape of oil]
The total costs that will be incurred by Southern Water as a result of the incident are likely to be substantial.
The claim
[Details are given of Southern Water's claims with references to letters]
BV's duties as water treatment engineers
Brent and Loveland's case is that responsibility for the incident lies with BV.
We do not know upon what terms BV was employed by Southern Water…but the purpose of BV's employment was to audit and revise the facilities at…Andover..
We also note that BV was on site at the time of the relevant works, supervising their execution.
Accordingly we believe that BV assumed a contractual duty, and probably a common law duty also, to design and supervise the works at Andover to the standard of care expected of consulting engineers professing your specialism in water treatment design and construction.
It is clear that BV failed to discharge those duties at two stages in the project.
The first stage was in the audit and revision of the Andover facilities…[explanation is provided]
The second stage was when the line was damaged and exposed for repair… [explanation given]
In summary, BV was aware of the presence of the shallow buried fuel line at the original design stage and should have critically reviewed whether the line could safely be retained…
BV's failure to remove the gas oil pipeline resulted in the very damage, the contamination of the aquifer, that BV had been employed by Southern Water to prevent.
BV's legal liability
We consider that BV will be liable to Southern Water for breach of its duties both in audit, design and supervision in relation to the fuel line and its repair.
Consequently, if Brent and Loveland are found liable for the damage, they will have claims for contribution against BV under the Civil Liability (Contribution) Act 1978 since the damage is the same as that sustained by Southern Water as a result of BV's breaches of duty.
Conclusion
…If, however, Southern Water were to succeed in its claim against Brent, then Brent has a claim for, at the least, a very significant contribution, if not equivalent damages, against BV.
… we have no alternative but to now turn to BV
We think that it will be helpful for representatives of BV to meet with Clausen Miller LLP and Mayer Brown Rowe & Maw to discuss how best this matter may be taken forward in advance of any adjudication or litigation.
Such a meeting would clearly benefit if the parties meet on level terms. The best way to achieve this would be for each party to give disclosure in advance of the meeting,
On BV's part this disclosure would include, but not be limited to:
(i) the contract between Southern Water and BV..
We look forward to your prompt response."
"It seems to us that the direct cause of this damage was a defective repair by your client's subcontractor. In the circumstances, it would seem likely that Southern Water would have grounds for pursuing their claim solely against your client as the design build contractor."
"The potential liability of your clients to Sothern Water is clear...
The potential for there to be a duty in tort upon Black & Veitch towards your clients, as a design and build contractor, in these circumstances is not apparent to us…
Furthermore negligence by Black & Veatch is not apparent…
In any event the facts set out in your letter seem to us to demonstrate that your clients' breaches of contract and/or duty are intervening acts…
It would seem to us that there is no real prospect of your clients establishing that a duty was owed towards your client…or that…Black & Veatch were negligent or that in the event of negligence there is a causal connection to the damage.
With regard to the Civil Liability (Contribution) Act 1978… Black & Veatch are not liable to Southern Water…we do not accept your statement that any such liability (if established) would be in respect of the "same damage" for the purposes of section 1(1)…
If there was any room for argument under the 1978 Act, we consider that its is extinguished by the existence in our appointment of the following provision:
"[The Client shall indemnify and keep indemnified the Consulting Engineer against demands proceedings damages costs charges and expenses arising out of or in connection with pollution or contamination".]"
Hence Black & Veatch is not liable to Southern Water and the Act is not applicable.
In conclusion we do not see that there is any cause of action available to your clients in tort or for a contribution under the Act. For these reasons we are not inclined to accept your proposals for voluntary disclosure and a meeting…"
"We assume that Brent would be willing to attend such a without prejudice meeting. Indeed, there would be little point in holding a meeting if it was not present. We also consider it appropriate that Black & Veatch is present at this meeting, although we are aware of the fact that in previous correspondence it has rejected any claim advanced by Brent. We consider Black & Veatch as potentially liable to Brent and/or Loveland pursuant to the Civil Liability Contribution Act 1978 for the reasons previously canvassed in correspondence. No doubt this can be discussed on a without prejudice basis at the meeting. By a copy of this letter we request that Black & Veatch also confirms it is prepared to take part in a without prejudice discussion. We look forward to hearing from you and Black & Veatch in due course."
"In the absence of a reasoned response to Mr Tuffin's letter to Clausen Miller dated 23 September 2005 from either Clausen Miller or yourselves, we could not contemplate participating in the without prejudice meeting that you propose."
"We and Clausen Miller and our respective clients were very disappointed to note that you elected not to attend the without prejudice meeting with Southern Water on 23 June, despite our and their prior emails, telephone calls and letters. Whilst the meeting proved constructive in that the parties were able to discuss various aspects of Southern Water's claim, in your absence we were unable properly to debate your role and culpability…
In the circumstances, our clients and Brent intend to continue to pursue their claims against you robustly. Accordingly, we look forward to receiving as soon as possible the contractual documentation requested by Clausen Miller in their letter dated 26 July 2005, together with a detailed response as to why you do not consider that you are liable in the respects previously highlighted…"
"As explained during the discussion of 30 May 2007, we and Clausen Miller consider that there are potential claims in tort against your clients arising from the circumstances in which the repair to the pipe was carried out. The repair took place on 11 June 2001 and there is a possible imminent deadline in this respect. If, as you state, limitation is not an issue, then we do not understand why your client is reluctant to enter into a stand still agreement. To refuse to do so will simply increase costs and possibly attract publicity as we and Clausen Miller will have little option but to issue a protective Claim Form.
In the circumstances, we invite you to agree by close of business today that your client will enter into a stand still agreement with effect from 6 June 2007."
"In a situation where there is no cause of action in respect of which a limitation issue arises, it is wasteful of time and cost to enter into a stand still agreement. Issuing a claim in such circumstances exposes your client to costs and that is of course a decision for you."
"9. The Pre-action Protocol for Construction and Engineering Disputes requires that you should, prior to commencing proceedings, have sent a letter of claim to the proposed defendant setting out, amongst other things, the full name of that Defendant. This would have enabled Black and Veatch to alert you to your error in good time before proceedings were issued. Black and Veatch Limited received no letter of claim. The Claimants have not, therefore, complied with the Protocol and we reserve our position on costs in this regard."
"A considerable amount of letters and emails were subsequently sent by your client, Black and Veatch Limited, which dealt with substantive issues in the defence of the claims as well as our client's request for pre-action disclosure."
"The Claimants failed to comply with the Pre-action Protocol for Construction and Engineering Disputes. The court has a power to make such an order pursuant to 2.1 of Practice Direction: Protocols and CPR r 44.3(v)(a)."
"35. I confirm that, had the Claimants followed the normal procedure after their claim crystallised in August 2007, B&V (for whom Howrey by then had conduct of the matter) would have provided a Defendant's Response and attended a pre-action meeting in the usual way.
36. Howrey would have also advised B&V to accept any offer of mediation made at that stage, and I believe B&V would have followed that advice.
"37. A failure to follow the pre-action protocol, or a refusal to mediate, can have serious cost consequences. Had these issues arisen, I consider that it would have been the professional duty of Howrey LLP to warn B&V of these risks and to advise that the relevant positive steps should be taken. I have no reason to believe that B&V would not have followed that advice."
"The court should avoid the slavish application of individual rules, practice directions or protocols if such application undermines the overriding objective."
Decision