QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ORANGE PERSONAL COMMUNICATIONS SERVICES LIMITED |
Claimant |
|
- and - |
||
HOARE LEA (a firm) |
Defendant |
____________________
Rachel Ansell (instructed by Beale & Co) for the Defendant
Hearing dates: 1 February 2008
____________________
Crown Copyright ©
Mr. Justice AKENHEAD:
Introduction
Background
"18.2 It is admitted that water flooded from the bunded area beneath RACU4C because Orange and their design team and/or Haden Young failed to design a drain for that area.
38. Kier did not advise or warn Orange or the design team that the hole was unnecessary and should be made good so that it was watertight, and was under no obligation to do so. It was for Orange and their design team to notify the intended purpose of the bunds to all other parties involved; and it was for Orange and their design team and/or Haden Young to give any instructions or requests that the hole was unnecessary and to be made good so that it was water tight.
62. If and insofar as Orange did suffer any loss and damage as a result of the flood, it was caused entirely or alternatively contributed to by the negligence of Orange its servants or agents.
"Particulars of Negligence
62.3 Failing to require that the water leak detection system operated an alarm in the security area…"
"….. such loss and damage as the Claimant may prove was caused wholly or in part by its own negligence and/or that of its …. agents.
Particulars
(i) The Claimant and/or its design team knew or ought to have known that the Hoare Lea drawings provided to Haden Young did not show any means of draining the Bund;
(ii) The Claimant and/or its design team instructed the sealing of the hole in fact made by Pearce Construction Limited which they presumably made because it was shown on the architect's drawing;
(iii) The Claimant and/or its design team did not thereafter give any instructions for the creation of alternative drainage;
(iv) The Claimant and/or its design team were aware that the bunds were defective and inadequate to contain water in the event of a leak…"
"6(B)(i) The conceptual design of the alarm system was by Hoare Lea;
(ii) The detailed design was sub-contracted by Haden Young to specialists;
(iii) The detailed design was approved by Hoare Lea and the fact that the system did not operate an alarm in the security area must have been obvious to them…"
(a) Orange made it clear that their primary case is that Kier and Haden Young are responsible for causing the flood (Paragraph 4).
(b) Reference is made to what Kier and Haden Young allege in their respective Amended Defences alleging in effect that Hoare Lea's acts and/or omissions and/or negligence and/or breach of contract caused or contributed to the flood and Orange's loss and damage (see paragraph 6).
(c) The agreement between Orange and Hoare Lea is pleaded at paragraph 10 and at paragraphs 11 and 12 a contractual and tortious duty of care is pleaded against Hoare Lea.
(d) In paragraphs 15 and 16 rather more detail is pleaded as to what Haden Young plead in their pleadings is or might be attributable to the failures of Hoare Lea.
(e) The plea against Hoare Lea is ultimately relatively simple:
"To the extent that Kier and/or Haden Young succeed in proving the allegations against… Hoare Lea that Kier and/or Haden Young make against… Hoare Lea in HT-06-313 Orange adopt those allegations as allegations of (1) negligence by … Hoare Lea and/or (2) breach by … Hoare Lea [of contract…"
The Parties' Arguments
(a) The Protocol is there to be complied with and should generally be complied with.
(b) There are advantages in general and in this case in particular of the Protocol process to be followed.
(c) Orange were guilty of a number of failings; it could have served the proceedings earlier; it should have served the proceedings earlier so that the Court could make informed directions in early November 2007; finally Orange should have brought the matter before the Court to seek directions at the time it issued the Claim Form or at least well before Christmas 2007.
(d) Hoare Lea wants to avoid the additional costs which will inevitably be incurred if the Pre-Action process is not implemented, particularly with regard to the exchange of information. Issues are likely to be narrowed if the process takes place and Hoare Lea would like to see if the differences can be resolved before litigation is implemented in earnest against them.
(e) The Particulars of Claim against Hoare Lea are inadequate in defining what negligence is in reality asserted against them
(a) Orange's case is very much a contingent claim it does not represent Orange's primary claim, which is against Kier and Haden Young.
(b) A Protocol process would be substantially a waste of time by reason of that factor.
(c) There is little if any information which can be exchanged which will be of assistance other than the pleadings in the earlier claim (already served) and disclosure by all the other parties which can be made available to Hoare Lea now if they so wish.
(d) There is little chance of resolution given that Orange's claim against Hoare Lea is a claim over in what Orange see as a relatively unlikely scenario.
(e) Hoare Lea's involvement in the combined claims now can ensure that it can participate both in the coming ADR and, if necessary, in the trial in October 2008.
Practice and the Law
"1.3 The objectives of this Protocol are as set out in the Practice Direction relating to Civil Procedure Pre-Action Protocols, namely:-
(i) to encourage the exchange of early and full information about the prospective legal claim;
(ii) to enable the parties to avoid litigation by agreeing a settlement of the claim before commencement of proceedings;
(iii) to support the efficient management of proceedings where litigation cannot be avoided."
2. The general aim of this Protocol is to ensure that before court proceedings commence:
(i) the claimant and the defendant have provided sufficient information for each party to know the nature of the other's case;
(ii) each party has had an opportunity to consider the other's case, and to accept or reject all or any part of the case made against him at the earliest possible stage;
(iii) there is more pre-action contact between the parties;
(iv) better and earlier exchange of information occurs;
(v) there is better pre-action investigation by the parties;
(vi) the parties have met formally on at least one occasion with a view to
• defining and agreeing the issues defining and agreeing the issues between them; and
• exploring possible ways by which the claim may be resolved;
(vii) the parties are in a position where they may be able to settle cases early and fairly without recourse to litigation; and
(viii) proceedings will be conducted efficiently if litigation does become necessary."
1.4 If proceedings are commenced, the court will be able to treat the standards set in this Protocol as the normal reasonable approach to pre-action conduct. If the court has to consider the question of compliance after proceedings have begun, it will be concerned with substantial compliance and not minor departures, e.g. failure by a short period to provide relevant information. Minor departures will not exempt the 'innocent' party from following the Protocol. The court will look at the effect of non-compliance on the other party when deciding whether to impose sanctions. For sanctions generally, see paragraph 2 of the Practice Direction – Protocols 'Compliance with Protocols'.
1.5 The overriding objective (CPR rule 1.1) applies to the pre-action period. The Protocol must not be used as a tactical device to secure advantage or to generate unnecessary costs…In all cases the costs incurred at the protocol stage should be proportionate to the complexity of the case and the amount of money which is at stake. The protocol does not require to marshal and disclose all the supporting details and evidence that may ultimately be required if the case proceeds to litigation.
6. If by reason of complying with any part of this protocol a claimant's claim may be time barred under any provision of the Limitation Act 1980, or any other legislation which imposes a time limit for bringing an action, the claimant may commence proceedings without complying with this Protocol. In such circumstances, a claimant who commences proceedings without complying with all, or any part, of this Protocol must apply to the court on notice for directions as to the timetable and form of procedure to be adopted, at the same time as he requests the court to issue proceedings. The court will consider whether to order a stay of the whole or part of the proceedings pending compliance with this Protocol."
"2.1 The Civil Procedure Rules enable the court to take account of compliance or non-compliance with an applicable Protocol when giving directions for the management of proceedings (see CPR Rules 3.1(4) and (5) and 3.9(e) and when making orders for costs (see CPR rule 44.3(5)(a)).
2.2 The court will expect all parties to have complied in substance with the terms of an approved Protocol.
2.3 If, in the opinion of the court, non-compliance has led to the commencement of proceedings which might otherwise not have needed to be commenced, or has led to costs being incurred in the proceedings that might not otherwise have been incurred, the orders the court may make include:
(1) an order that the party at fault pay the costs of the proceedings, or part of those costs, of the other party or parties;
(2) an order that the party at fault pay those costs on an indemnity basis; ….
2.4 The court will exercise its powers under paragraphs 2.1 and 2.3 with the object of placing the innocent party in no worse position than he would have been in if the protocol had been complied with."
"There can often be a complaint that one or other party has not complied with the Protocol. The court will consider any such complaints once proceedings have been commenced. If the court finds that the claimant has not complied with one part of the Protocol, then the court may stay the proceedings until the steps set out in the Protocol have been taken."
"39. What is the position in relation to parties who are brought into an ongoing action without having been involved in the previous Protocol procedures? In this situation there are two conflicting considerations. On the one hand, the new parties should not be deprived of the benefits of the Protocol. On the other hand, it is undesirable that the existing trial timetable should be maintained.
40. I have come to the conclusion that there is no simple formula or universal answer to this problem. The following considerations are, however, relevant to the exercise of the court's case management powers:
(1) When was it known that the party was going to be joined in the action?
(2) What information about the action and the underlying dispute was given to that party before joinder and when?
(3) How large a part does the new party play in the action as a whole?
(4) What stay, if any, could be accommodated in the proceedings against the new party without jeopardising the overall timetable?
(5) Does justice require that the whole timetable should be put back and that a new trial date should be fixed?
(6) Could the new party be compensated in costs for any non-compliance with the Protocol? If, so, should the question of costs be addressed immediately or should that question be addressed at the end of the action?
(7) Is there any way (other than a stay) within the parameters of the existing timetable by which the new party could be put in the same position that it would occupy if the Protocol had been followed?
45. More importantly, however, I do not think that the Protocol process would have achieved anything during that period [the pre-Part 20 proceedings period]…"
Decision and Discussion
(a) The overriding objective (in CPR Part 1) is concerned with saving expense, proportionality, expedition and fairness; the Court's resources are a factor. This objective whilst concerned with justice justifies a pragmatic approach by the Court to achieve the objective. The overriding objective is recognised even within the Protocol as having a material application.
(b) The Court is given very wide powers to manage cases in CPR Part 3 and elsewhere so as to achieve or further the overriding objective.
(c) The Court should avoid the slavish application of individual rules, practice directions or Protocols if such application undermines the overriding objective.
(d) Anecdotal information about the effectiveness of the Pre-Action Protocol process in the TCC is mixed. It is recognised as being effective both in settling disputes before they even arrive in the Court and narrowing issues but also as being costly on occasion and enabling parties to delay matters without taking matters very much further forward.
(e) Whilst the norm must be that parties to litigation do comply with the Protocol requirements, the Court must ultimately look at non-compliances in a pragmatic and commercially realistic way. Non-compliances can always be compensated by way of costs orders.
(a) I do not consider that the Protocol process will, at this stage of the two sets of proceedings, be sufficiently productive to justify a stay or more productive than if no stay is granted.
(b) Hoare Lea already has in its possession Orange's Particulars of Claim and the pleadings in the earlier proceedings which equate to a letter of claim under the Protocol. Hoare Lea's defence will equate to Hoare Lea's Protocol response. The information available, such as the other parties' views in their pleadings and the extensive document disclosure already made in the earlier claim, is equivalent and probably greater than what would normally be expected in a Protocol process. I take into account, with regard to information, Hoare Lea's reluctance to take up Orange's solicitors' offer of information on 3 January 2008.
(c) It is unlikely that any bilateral discussions between Hoare Lea and Orange would narrow issues significantly because Orange's published primary case is not against Hoare Lea at all who would simply agree (if at all and rightly or wrongly) in all probability that Kier and/or Haden Young were to blame. Hoare Lea's involvement in these disputes is to some extent provisional and only arises if the drainage, waterproofing and leak alarm issues turn out to be evidentially relevant.
(d) A settlement is much more likely if all the parties participate in the ADR planned for the Spring. A timetable can be achieved which will enable this to happen. I will also order that a Pre-Action protocol meeting between the parties should take place if Hoare Lea wants one after service of its Defence.
(e) The earlier action is somewhat behind the usual disposal time in the TCC as trial will be some two years after issue. I would be reluctant to delay the trial still further to enable a Protocol process to take place. That would be undesirable in terms of cost, time and resource.
(f) The two claims are intimately connected. It would be unfortunate if they had to be tried separately, with the extra costs and risk of inconsistent factual findings. They should be tried together. To try them together but accommodate a stay in this action would inevitably delay the joint trial well beyond October 2008.
(g) A timetable can be achieved for this later claim which can secure trial of both claims in October 2008. The claims are not complicated by the standards of the TCC. The pleadings can be completed before mid-March 2008, disclosure by Hoare Lea shortly thereafter, and witness statements and expert reports drafted and served by mid-summer. I do not accept Miss Ansell's pessimistic submission, on (doubtless bona fide) instructions, that Hoare Lea could not be ready for an October 2008 trial date. I have regard to the Court's experience in this regard and to the noteworthy absence of any such suggestion in Mr Richards' statement to that effect.
(h) So far as costs are concerned, although my judgment at present is that little in terms of time or cost would be saved by embarking on the Protocol process, I will reserve and defer any application for additional costs occasioned to Hoare Lea by the non-compliance with the Protocol so that it will be protected against the consequences of such non-compliance.
(i) I do not consider that, although Orange has not complied with the requirements to effect the Protocol process, this has been contumelious or Machiavellian.
Costs