QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
MIRANT ASIA-PACIFIC CONSTRUCTION (HONG KONG) LIMITED |
Claimant |
|
- and - |
||
OVE ARUP AND PARTNERS INTERNATIONAL LIMITED OVE ARUP AND PARTNERS HONG KONG LIMITED |
Defendant |
____________________
Mr Roger Stewart QC, Mr Ian Wright and Mr Tim Chelmick (instructed by Beale & Co Solicitors) for the Defendants
Hearing dates: 5th October-23 November; 13th -14th December 2006
____________________
Crown Copyright ©
Para | |
Introduction and Previous History | 1 |
Previous steps in this Action and the Quantum Claim | 14 |
The Law - General principles | 24 |
The operative cause of delay | 32 |
The Burden of Proof | 39 |
Settlement of Claims | 40 |
The factual witnesses | 48 |
The Experts | 67 |
Disclosure and Related Issues | 73 |
The Critical Path and Critical Path Analysis | 119 |
The Facts up to the decision to dismantle the steelwork | 138 |
Summary of findings of fact to 26 June 1997 | 277 |
The decision to dismantle the steelwork | 290 |
From 26 June 1997 to the conclusion of the Boiler Unit remedial works in September 1997 | 313 |
Overall findings on delay as at September 1997 | 347 |
Framework of dates to the end of the Project | 358 |
The detailed history from September 1997 | 359 |
Delays to the Project other than the Boiler foundations | 461 |
The Coalyard and the Coal Jetty | 518 |
The Cooling Water System | 529 |
The Transmission Lines | 541 |
The Programming Experts and the Critical Path | 564 |
The Agreed Issues | 596 |
Issues 1 and 2 | 597 |
Is Mirant entitled to recover Arup's losses increased by SCC? (Issue 11) | 601 |
(a) Contentions of the Parties | 601 |
(b) The Law | 610 |
(c) Conclusions | 628 |
Issue 3 - the claim for $39,731,428 for delay and disruption | 632 |
Issue 4 - Mirant's claim for time related costs | 701 |
Issues 5 and 8 - Claims for additional preliminaries and disruption costs and acceleration payments pursuant to draft agreements in February 1998 | 707 |
Issue 6 – Mirant's claim for additional insurance cover | 736 |
Issue 7 – Mirant's claim for additional time related costs allegedly incurred by SCC | 744 |
Issue 9 – not pursued | 754 |
Issue 10 – rectification costs for the Unit 1 Boiler | 755 |
Issue 12 – Is Arup entitled to the benefit of the CAR Policy? | 771 |
Conclusion | 784 |
His Honour Judge Toulmin CMG,QC :
Introduction and Previous History
(a) An off-shore supply contract between Pangasinan Electric Corporation ("PEC") and the off-shore works supplied consortium including CEPAS and two Alstom companies, GEC Alstom Power Plants Limited and GEC Alstom Stein Industrie SA ("Stein"). Stein was amongst other things responsible for erecting the steelwork on the boiler. This consortium was responsible for the supply of all equipment procured outside the Philippines. The original contract is dated 9 January 1995.
(b) An on-shore contract, also dated 9 January 1995 to erect the plant and do all other work within the Philippines necessary to bring the plant into full commercial use. SCC was incorporated (as SSCC) on 21 December 1994 to be a member of this consortium. Other members of the consortium included two other Alstom companies.
(d) Under a deed of guarantee dated 12 July 1995 CEPAS agreed to guarantee the liabilities of SCC under the construction contract.
(e) Under an agreement also dated 12 July 1995 CEPAS agreed to guarantee SCC's liabilities under the Tripartite Agreement.
Previous Steps in this Action and the Quantum Claim
(a) Arup owed a duty to CEPAS in contract and tort not to cause economic loss to CEPAS
(b) Arup did not owe a duty to SCC in tort not to cause economic loss to SCC
(c) Arup failed to discharge that duty in relation to
(i) the design of the Unit 1 Boiler foundation
(ii) the verification of the assumptions on which the design was based.
Direct rectification costs | $ 1,552,889 |
Liquidated damages | $39,731,428 |
Additional preliminaries and disruption costs paid to Alstom Turbine/GEC Electro and their subsidiaries | $15,799,777 |
The cost of extended insurance | $621,607 |
Additional time related costs incurred by SCC | $5,727,000 |
Additional time related costs incurred by CEPAS | $1,467,180 |
Acceleration payments made to Alstom Turbine/GEC Electro | $10,273,060 |
Acceleration costs incurred by SCC | $3,724,428 |
$78,897,369 | |
(All figures are in US dollars) |
(a) The general principles of the award of damages
(b) The operative cause of delay.
(c) The settlement of claims.
(I will deal with other issues of law when dealing with the individual claims.)
(2) The witnesses
(a) Witnesses of fact.
(b) The experts.
(3) Disclosure and related issues
(4) A discussion of what is meant by "the critical path" and "Critical Path Analysis". These terms are used not only by the programming experts but also by witnesses of fact. An understanding of what the terms mean is essential to an understanding of the claims for delay.
(5) The facts relating to the progress of the contract.
(6) The specific issues which are raised in the litigation.
(7) Conclusions.
1. The Law
"Now I think a court of justice ought to be very slow in countenancing any attempt by a wrongdoer to make captious objection to the methods by which those whom he has injured have sought to repair the injury … Errors of judgment may be committed in this as in other affairs of life. It would be intolerable if persons so situated could be called to account by the wrongdoer in a minute scrutiny of the expense as though he were his agents, for any mistake or miscalculation provided they acted honestly or reasonably. In judging whether they have acted reasonably I think a court should be very indulgent and always bear in mind who is to blame. Accordingly if the case of the plaintiffs had been that they had acted on the advice of competent advisors in the work of reparation and had chosen the course they were advised was necessary it would go a very long way with me: it would go the whole way unless it became clear that some quite unreasonable course had been adopted."
"The first step in establishing causation is to eliminate irrelevant causes and this is the purpose of the "but for" test. The Courts are concerned, not to identify all of the possible causes of a particular incident but the effective cause of the resulting damage in order to assign responsibility for that damage. The "but for" test asks: would the damage of which the claimant complains have occurred "but for" the negligence (or other wrongdoing), or to put it more accurately, can the claimant adduce evidence to show that it is more likely than not, more than 50 per cent probable that but for "the defendant's wrongdoing the relevant damage would not have occurred. In other words, if the damage would have occurred in any event the defendant's conduct is not a "but for" cause."
"The logic of a global claim demands, however, that all the events which contribute to causing the global loss be events for which the Defender is liable. If the causal events include events for which the Defender bears no liability, the effect of upholding the global claim is to impose on the Defender a liability which in part is not legally his. That is unjustified. A global claim, as such, must therefore fail if any material contribution to the causation of the global loss is made by a factor for which the Defender bears no legal liability."
"1. it must be possible to identify a causal link between particular events and the individual items of loss and
2. "the question of causation must be treated by the application of common sense to the logical principles of causation."
2(a) The Factual Witnesses
2(b) The Experts
3. Disclosure and Related Issues
"I had instructed outside lawyers [Mallesons] to come to our offices and search through our files and begin looking to see what the records were with respect to these matters."
(a) Mr Kuester's 1997 reports. As I have already said, Mr Kuester became Managing Director of Mirant in June 1997 on the departure of Mr Elliott. Previous to this he had acted as Mr Elliott's deputy but unbeknown to Mr Elliott he had made confidential reports on Mr Elliott to Southern's head office in Atlanta, some of which must have been in writing.
(b) Documents concerning the resignation of Mr Elliott and the reasons for that resignation.
(c) Evidence surrounding Southern's geotechnical investigation and independent evaluation of the Boiler foundation settlement problems and remedies in about June 1997.
(d) Southern's internal audit files relating to Sual, including file notes on the internal auditing of the Project referred to in the presentation on 26 September 1997.
(e) Mr McManus's contemporaneous files. At a very late stage immediately before the trial began Mr McManus produced two files of documents.
(f) Documents surrounding the Hopewell Warranty Claim. This refers to a document disclosed again very late in the proceedings which indicates that in 1998 Southern drafted proceedings in the Commercial Court in London against Hopewell Holdings Limited using Linklaters & Paines, the well-known firm of international solicitors, claiming to recover payments made to Mr Elliott's company, Tileman, in respect of sub-contract works. The claim was that Tileman had received an advance payment from SCC of US$3.7 million without submitting invoices and had received a further US$7.35 million for work which they had not carried out.
(a) the settlement agreements were drafted by Mallesons in such a way as to maximise the prospects of obtaining recovery from Arup;
(b) the apportionment of liquidated damages between Alstom and SCC was governed by the net settlement payable to Alstom;
(c) the settlement was a global sum which included legal costs; and
(d) it was agreed informally or otherwise that Alstom would co-operate following the execution of the settlement agreement by providing access to its documents to Mirant.
(1) It is inevitable that in major and complex international litigation the parties will prefer to use the firm of solicitors with which they have a continuing relationship. It is reasonable that these firms will undertake much of the preparatory work even if a firm resident within the jurisdiction is used to conduct litigation.
"1. Where destruction of evidence was carried out deliberately so as to hinder the opposing parties' claim, that will reflect on the credibility of the destroyer. This would enable the Court to disbelieve the destroyer's evidence.2.. If the Court has difficulty in deciding which party's evidence to accept it would be legitimate to resolve that doubt by the application of the presumption.
3.. If the judge forms a clear view as to which side is telling the truth he is not required to apply the presumption to accept evidence in which he does not believe or to reject evidence which he believes to be true."
4. The Critical Path and Critical Path Analysis
"There may be more than one critical path depending on workflow logic of delay to the progress of any activity in the critical path which, without acceleration or resequencing, may cause the overall Project to be extended."[1]
"To reduce the number of disputes relating to delay, the contractor should prepare and the employer should accept a properly prepared programme showing the manner and sequence in which the contractor plans to carry out the works. The programme should be updated to record actual progress and any extensions of time granted. If this is done then the programme can be used as a tool for managing change and determining periods of time for which compensation may be due."[2]
5. The Facts
"Due to the above statement SSCC will accept no responsibility for any stoppage of the boiler erection works that might have occurred to date."
"The survey conducted on 18 April 1997 did reveal errors against design values which must put the results of previous surveys in doubt."
"Had the original pre-turnover results been readily available against a reliable site co-ordinate, it would have been relatively quick and simple to determine if the settlement had or had not occurred."
"(a) measured movements of the steel columns needed to be verified and reconciled with movements of the concrete foundations (currently undertaken by Alstom's staff);
(b) the depth of the decomposed materials should be verified."
"(d) If total measured movement relative to the datum established on 23 April 1997 exceeds 25 mm at any stage then all operations should cease and a detailed investigation of the foundation material should be undertaken. It is envisaged that this investigation would need to include rotary cored drill holes."
"Overall the Project is presently showing critical delay of 160 days in the area of the water treatment plant. The construction delay in the civils is the master delay which is masking a delay in the supply of materials of 43 days. The construction programme is currently being rescheduled to address this problem."
"The onshore construction contract continues to show the critical Project delays. Overall progress continues to be 4 weeks behind programme as per the April report."
The report notes that the common services have slipped to a 10 week delay, i.e. water treatment, coal jetty, coal yard and limestone unloading.
""Based on this we have concluded that any additional loading will result in settlement breaching further the above conditions. In consideration of this, the boiler erection is stopped completely from 7 May 1997 until SSCC correct the problem. Obviously any solution which allows continued boiler erection will be the most beneficial for the Project."
"The delay to present dates back to April 14 '97 when the problem was first identified to you. From April 14 '97 normal boiler erection has not been possible.
"As you are aware, the boiler erection lies on the Project critical path and therefore this delay is affecting the Project end date and your speedy resolution of this issue is required."
"remedial works and underpinning solutions as discussed in the meeting (piling, mini piles etc) to be developed for further consideration."
"The ground is behaving neither like sound rock nor as a fracture rock would. It is essential that the nature of the ground below the foundation is known before any decision on the ability of the ground to support the structure under static or combined static and dynamic load is made."
"…until it is clear that we can continue without causing damage to the boiler and we have insurers' approval to continue, all erection work on the boiler must remain suspended. In this regard we require that you issue a formal notice of suspension in accordance with clause 35.1 of the contract."
"9. We reiterate our opinion that there has been no necessity to suspend erection and that the structural integrity of the superstructure can be maintained with necessary jacking as has been effected to date and as recommended by our respective engineering consultants …"
"Despite requests, until the meeting on 18 May 1997, no information has been received as to the cause of the problem. Without your data, analysis and proposed solution it was clearly impossible to justify continued erection of the boiler in circumstances outside of its design criteria. Ample opportunity existed to avoid delay whilst boiler erection continued from 14 April 1997 when the problem became evident until 7 May 1997, when GECA (Alstom) found it necessary to stop erection."
"In our judgment excessive movement with as little as 1250 psf on a footing designed for 25+tons/ff² says this foundation has failed. We think it would be fruitless beyond this point to try to assess its further use as is, or adjust to the load. In our judgment time would be better invested in the core borings and plan to remediate the condition."
"Monitoring and documentation of the condition surrounding G2 and G5 as reported by Mr K F Hawkins of Soil Mechanics Limited appear to be complete, and very informative and to the mark concerning recommendations. We certainly agree with the concept of ceasing further loading of those foundations and moving into an investigative phase for remedial action."
"After working together for the last few months we have reluctantly concluded that your management style is not compatible with ours. On that basis we have requested your resignation from the company."
"Option 1: Piles used as temporary support to allow excavation for underpinning with mass concrete below the existing foundation.
Option 2: Piles used as temporary support initially but also forming part of the permanent works with a pile cap replacing the existing foundation."
Summary of Findings to 26 June 1997
Decision to Dismantle the Steelwork
(a) whether Arup should have specified a means of temporary support for the steel structure before piling commenced;
(b) whether the MOF support system would have provided the necessary support for the steel frame;
(c) the implications of further movement of the steel frame and the possibility that it might fail in the course of the progress of the remedial work; and
(d) the technical complexity of constructing the new foundations in situ.
From Dismantling Steelwork to Conclusion of the Boiler Unit 1 Remedial works in September 1997
Other Events on Site to September 1997
"They are currently reviewing site operations from top to bottom and making recommendations to further improve morale and production."
"1. Arup was not in control or acted unprofessionally.
2. Alstom is very concerned about its own position in relation to claims resulting from actions which they took before Mr Elliott's resignation.
3. There are those in GECA who fear that they will be blamed for the lack of timely resolution of the foundation problem. 'Scapegoats' are required."
Overall findings on delay as at September 1997
Key dates from September 1997 to the end of the Project
(1) On 1 December 1997 Arup completed its investigation into the causes of the problems of the Unit 1 Boiler foundation.
(2) On 9 December 1997 Alstom sent SCC what was described as the "Revision F Programme (Final)".
(3) On 4/5 February 1998 there was a meeting in Hong Kong between Alstom and SCC to discuss Alstom's claims for delay and disruption and for accelerating the works. Figures for compensation were agreed.
(4) On 25 February 1998 there were agreements between NEIE and GECA to settle NEIE's claims for delay and to agree a package of compensation for acceleration.
(5) The draft Incentive agreement was approved by CEPA on 11 March 1998. Under the draft agreement SCC agreed to pay Alstom for delay and disruption incurred by Alstom and its sub-contractors and to pay for accelerating the works. SCC paid Alstom $15,799,777 for additional preliminaries and disruption. $10,273,060 was also paid to Alstom for acceleration under the Acceleration Agreement.
(6) On 20 March 1998 Alstom circulated a draft Revision G strategy programme.
(7) On 18 August 1998 Alstom gave SCC formal notice of its various delay claims.
(8) On 3 October 1998 First Fire occurred for Unit 1. This was three months later than the date in Rev E.
(9) On 1 December 1998 the reliability trials were due to start for Unit 1 under plan Rev E and in accordance with the Contract. Rev E reliability trials were due to start for Unit 2 on 1 March 1999.
(10) On 22 December 1998 synchronisation of Unit 1 was achieved.
(11) On 6 January 1999 the failure of Unit 1 generator occurred. This is acknowledged to be an intervening cause of delay and was a consideration which was relevant to the financial settlement between Mirant and Alstom agreed in 2001.
(12) Early in September 1999 Alstom decided to proceed with Unit 2 as first in time.
(13) On 25 September 1999 reliability trials started for Unit 2.
(14) On 29 September 1999 reliability trials started for Unit 1.
(15) On 27 October 1999 reliability trials for Unit 2 were successfully completed.
(16) The monthly report for October 1999 confirmed that Unit 2 began commercial operations on 5 October 1999 and Unit 1 on 23 October 1999.
(17) In February 2001 Southern divested itself of its interest in the Mirant Companies.
(18) In November 2001 PEC, CEPAS, SCC and Alstom reached settlement agreements. The agreement recorded that reliability trials had been delayed by nine months. Although the agreements were global, the effect of the settlements was to apportion three months of the alleged delay to the boiler failure and six months to the generator.
(19) On 1 December 2004 SCC assigned its outstanding claims to Mirant.
From September 1997
"We do understand that the timely completion of the CW intake structure is critical to the overall completion of the Project and we are prepared to add additional resources to complete the works as quickly as possible."
"The Project cost does not vary very much from the original plan submitted in November 1996. CEPA does not feel that the five month delay discussed by the Independent Engineer (Brown & Root) will have a material effect on the Project cost as stated in the November 1996 Revised Base Case because in the Revised Base Case CEPA had already imposed a six month cushion Projecting completion in December 1999. The Independent Engineers' estimated five month delay is based on its original estimated Project completion in June 1999. One of the other potential problems areas, the transmission lines, was said to be expected to be completed by the end of January 1999."
"There is 'no official commercial operation date'. The boiler delay caused a five month schedule delay and we have developed a recovery plan called Revision G of the schedule which if we are able to recover it, will recover two months of the five months lost. Our agreement a couple (sic) ago was that we would pay for three months of schedule delays with an option of two months if we needed it.
Our boiler delay will not affect the installation date of the transmission line which is scheduled to be complete by the end of October 1998. However by losing three months of the schedule we will not require the transmission until some time in December 1998."
"The export of power from one unit can be accomplished through the 230-KV tie line and the new bay at the old Labrador substation. The new Labrador substation must be complete to be able to export power from both Unit 1 and Unit 2 simultaneously. Synchronisation of Unit 2 is presently scheduled for March 18 1999."
If the power station was to operate commercially it needed to be able to export power through both units.
"5. Finally, limited consideration of our possible counterclaims against Ove Arup & Partners ("OAP") arising from their involvement at Sual … We propose to use these counterclaims in our ongoing negotiations with OAP in relation to their outstanding payment claims … (reference to Mr Delkousis)
In my opinion you and your team can add real value to Sual. It is important however for us to strike a balance between your on-going role and the transfer of know-how from Shajiao [another Project]. I would therefore propose a monthly retainer for a period of nine months with a bonus to be awarded at the end of this period. This bonus would be at my discretion and in the order of 20% - 30% of the retainer. It would be payable should I determine that real value has been added by your firm. This is vague but I am certain your team is adding substantial value"
"Issue
Potential liability of Ove Arup in relation to the boiler foundation problems
Facts
A review of Ove Arup's role has discovered evidence to suggest a potential claim, particularly in relation to their possible role in monitoring the foundation/excavation works
- A number of evidentiary uncertainties may impact on any entitlement to recover from Ove Arup in particular the role of Stewart Elliott
- Draft contract issued."
"(i) Stewart Elliott's fear that the civil works could not be completed on time and delaying contract effectiveness gave the civil contractor time to progress its works, and
(ii) difficulties in obtaining confirmation that NPC would provide transmission access when required – there was no point to rushing through if transmission access was not in place."
"If the assignor receives any money arising out of or in connection with the claim or the appeal it must immediately notify the assignee and the assignor:
i. will hold such money on trust for the assignee, and
ii. will deliver such money to the assignee within seven days of receipt of such money."
There are also provisions in relation to indemnity, conduct of the claim, co- operation etc.
Delays to the Project other than to the Boiler Foundations
"The manufacture period of the precipitators has extended by three month (sic) but on a phased delivery means that the first item will be available four months before programme delivery complete, seven months before the erection phase so these activities do not threaten the programme."
"The six month delay of this design activity is at present affecting the end date of the Project."
"The civil design of the water treatment areas is showing five months' work to complete. This delay has utilised one month float in the programme … Impact on end date cannot be forecast at this time."
Plant Reliability Trials
FGD Plant | 5 March 1999 |
Waste Water Treatment | 14 April 1999 |
Coal Supply System | 24 December 1998 |
Cooling Water System | 27 November 1999 |
Electro-static Precipitator | 1 April 1999 |
Ash Systems | 11 January 1999 |
Unit 1 Boiler Steelwork | 25 November 1998 |
Plant Reliability Trials
FGD plant | 3 May 1999 |
Waste Water Treatment | 13 August 1999 |
Coal Supply System | 9 February 1999 |
Cooling Water System | 1 April 1999 |
Electro-static Precipitators | 4 October 1999 |
Ash Systems | 14 July 1999 |
Turbine Generator System | 26 February 1999 |
Unit 1 Boiler | 13 April 1999 |
Plant Reliability Trials
FGD plant | 10 May 1999 | (+ 1 week) |
Waste Water Treatment | 19 April 1999 | (- 4 months) |
Coal Supply System | 14 April 1999 | (+ 2 months) |
Cooling Water System | 26 February 1999 | (- 5 weeks) |
Electro-static Precipitators | 17 May 1999 | (- 5 months) |
Ash Systems | 7 April 1999 | (- 3 months) |
Turbine Generator System | 1 April 1999 | (+ 5 weeks) |
Unit 1 Boiler Steelwork | 12 April 1999 | (- 1 day) |
Plant Reliability Trials
FGD plant | 5 March 1999 | (- 2 months) |
Waste Water Treatment | 14 April 1999 | (- 5 days) |
Coal Supply System | 24 December 1998 | (- nearly 4 months) |
Cooling Water System | 27 November 1998 | (- 3 months) |
Electro-static Precipitators | 1 April 1999 | (- 6 weeks) |
Ash Systems | 11 January 1999 | (- 3 months) |
Turbine Generator System | 14 January 1999 | (- 2½ months) |
Unit 1 Boiler Steelwork | 25 November 1998 | (- 4½ months) |
Plant Reliability Trials
FGD plant | 2 March 1999 |
Waste Water System | 3 March 1999 |
Coal Supply System | 17 February 1999 |
Cooling Water System | 24 February 1999 |
Electro-static Precipitators | 27 January 1999 |
Ash Systems | 11 March 1999 |
Turbine Generator Systems | 3 February 1999 |
Boiler Unit 1 Steelwork | 24 February 1999 |
"There have been delays in the performance of the works. SCC accepts responsibility for a 153 day delay due to the failure of the Unit 1 boiler foundation between 1 April 1997 and 1 September 1997 as well as from an average approximate 3 month delay across the other civil construction works as reflected under the F2 strategy programme."
Plant Reliability Trials
FGD plant | 29 April 1999 |
Waste Water Treatment | 4 December 1998 |
Coal Supply System | 30 April 1999 |
Cooling Water System | 26 March 1999 |
Electro-static Precipitators | 5 April 1999 |
Ash Systems | 1 April 1999 |
Turbine Generator Systems | 6 May 1999 |
Boiler Unit 1 Steelwork | 26 March 1999 |
"The export of power from one unit can be accomplished through the 230 KV toe line and the new bay at the old Labrador substation. The new Labrador substation must be complete to be able to export power from both Unit 1 and Unit 2 simultaneously. Synchronisation of Unit 1 and export of power was targeted for 18 December 1998. Synchronisation of Unit 2 is presently scheduled for March 18, 1999."
"If by reason of delay, default …current event force majeure, the contract shall have been delayed or impeded in achieving commencement of a successful reliability run, then he is entitled to an extension of time."
The Programming Experts
"Whilst any delay caused by the Unit 1 boiler foundation settlement, together with any acceleration measures said to have been put into effect as a result, ought to be evident from my examination of Windows 1, 2 and 3, the principal purpose of Window 4 is to permit a continuing examination of the Project through to its completion. The reason for carrying out this exercise is to consider further whether, based on the actual progress of the work during Window 4, areas of work unrelated to the Unit 1 boiler foundations would themselves have had the potential to cause delay to the key Project milestones regardless of the settlement of those foundations."
"1. First, both experts agree that a "windows" approach is a valid method of delay analysis considering the Project facts and circumstances. Mr Lechner has adopted a more traditional form of Windows analysis, carrying out adjustments as necessary to the various strategy programmes used in the analysis. Mr Robinson has modified the Windows analysis methodology to identify a number of key work sequences, including but not restricted to the boiler sequence, and to independently project the likely start of dates for plant reliability trials based on the progress of each of those work sequences as reflected in the updated strategy programmes.
1. It was not a critical path analysis but a snapshot analysis of progress at the beginning/end of his chosen windows.
2. Mr Lechner therefore failed to investigate the causes of delay between April and October 1997 despite the important changes (including changes of management) which occurred in this period. Mr Lechner has not considered whether Arup is properly responsible for the whole of the 162 day delay which occurred and if not what lesser part of the delay.
3. Mr Lechner stopped his analysis in October 1998 soon after First Fire of the boiler although the benchmark under the contract was the commencement of the reliability trials.
4. Mr Lechner did not consider the effect of potential delays caused by events close to the critical path.
5. Mr Lechner did not consider the effect of problems relating to the transmission lines on the date for the commencement of the reliability trials.
6. Mr Lechner's first report allows a 42 day float for the Unit 1 boiler foundations at the start of his first period, i.e. Rev E, 20 March 1997. This allowance of 42 days was withdrawn subsequently and without any proper explanation.
7. Mr Lechner tends to rely on assertions in the witness statements of witnesses made many years later. This is despite the fact that, if his own analysis is correct, Mr Hall's assertion (and others) that the boiler is always on the critical path, appears to be mistaken.
8. Mr Lechner's grasp of the detail of the Project appeared from the answers which he gave in the witness box to be inadequate.
THE AGREED ISSUES
1. To what extent was there critical delay to the commencement of the Plant Reliability Trials for Boiler Unit 1 and Boiler Unit 2 and what activities or events caused or contributed to such delay (and who was responsible for the delay)?
2. What was the nature and effect of the acceleration measures (if any) undertaken by MAPC and/or SCC and/or GECA Construction and/or by others?
11. Is Mirant entitled to recover from Arup losses incurred by SCC either s (i) its own loss or damage, (ii) damages which by law Mirant must account to SCC? (The further questions relating to SCC are based on the premise that such sums are recoverable in law.)
3. In relation to delay and disruption costs, to what extent, if at all, is Mirant entitled to recover from Arup sums allegedly paid to PEC on behalf of SCC as liquidated damages?
4. To what extent if at all is Mirant entitled to recover time-related costs allegedly incurred by it from Arup ($1,467,180 based on an average of $489,060 per month)?
5. To what extent, if at all, is Mirant entitled to recover payments from Arup of $15,799,777 for additional preliminaries and disruption costs allegedly incurred by GECA Construction and allegedly paid by SCC?
6. Is Mirant entitled to recover $621,607 allegedly paid to Alstom and GEC Electro for additional insurance cover?
7. Is Mirant entitled to recover time-related costs in the sum of $5,727,000 allegedly incurred by SCC?
8. Did SCC pay GEC Alstom Turbine and GEC Electro the sum of $10,273,060 pursuant to the Acceleration Agreement and if so is Mirant entitled to recover payments made by SCC to GECA Construction under the Acceleration Agreement?
9. To what extent, if at all, is Mirant entitled to recover Acceleration costs consisting of additional fuel, labour and water incurred by SCC in the sum of $3,724,428 or any sum?
10. To what extent, if at all, is Mirant entitled to recover rectification costs to the Unit 1 Boiler in the sum of $1,522,889?
12. To what extent, if at all, is Arup entitled to cover and credit in respect of the CAR Policy?
I have already made detailed findings on this issue. In summary, critical delay is delay to the Project measured by reference to the reliability trials. I have concluded that the consequences of the boiler foundation failure were not the proximate or dominant cause and not therefore the operative cause (or one of the operative causes) of the delay. These findings dispose of the liquidated damages claim of $39,731,428, the additional Insurance costs claim, and the additional time costs claims of SCC and Mirant
2. What was the nature and effect of the acceleration measures (if any) undertaken by MAPC and/or SCC and/or GECA Construction and/or by others?
4. To what extent if at all is Mirant entitled to recover time related costs allegedly incurred by it from Arup ($1,467,180 based on an average of $489,060 per month)?
(1) What it describes as the narrow ground in Lord Diplock's speech in The Albazero [1977] AC 774, namely that where it is in the contemplation of the parties that proprietary interests may be transferred from one party (CEPAS) to another (SCC) after the contract has been entered into, the party entering into the contract is to be treated as entering into the contract on behalf of itself and the other party and is entitled to recover by way of damages the actual loss sustained by the other party (SCC). CEPAS would be under an obligation to account to SCC for the damages which it recovers.
The Law
"… in a commercial contract concerning goods, where it is in the contemplation of the parties that the proprietary interest in the goods may be transferred from one owner to another after the contract has been entered into and before the breach which causes loss or damage to the goods, an original party to the contract, if such be the intention of them both, is to be treated in law as having entered into the contract for the benefit of all persons who have or may acquire an interest in the goods before they are lost and damaged and is entitled to recover by way of damages for breach of contract, the actual loss sustained by those for whose benefit the contract is entered into."
"In my judgment the present case falls within the rationale of the exceptions to the general rule that a plaintiff can only recover damages for his own loss. The contract was for a large development of property which, to the knowledge of both Corporation and McAlpine was going to be occupied and jointly purchased by third parties and not by the Corporation itself. Therefore it could be foreseen that damage caused by a breach would cause loss to a later owner and not merely to the original contracting party, Corporation. As in contracts for the carriage of goods by land there would be no automatic vesting in the occupier or owner of the property for the time being who sustained the loss of any right of suit against McAlpine. On the contrary, McAlpine had specifically contracted that the right of action under the building contract could not, without McAlpine's consent, be transferred to third parties who became owners or occupiers and might suffer loss. In such a case it seems to me proper, as in the case of the carriage of goods by land, to treat the parties as having entered into the contract on the footing that Corporation would be enabled to enforce the contractual rights for the benefit of those who suffered from defective performance but who, under the terms of the contract, could not acquire any right to hold McAlpine liable for this breach. It is truly a case in which the rule provides 'a remedy where no other would be available to a person sustaining a loss under a rational legal system ought to be compensated by the person who has caused it. "
"On the one hand if they (the contracting parties) deliberately provided for a remedy for a third party it can readily be concluded that they have intended to exclude the operation of a solution which would otherwise have been imposed by law – The terms and provisions of the contract will then require to be studied to see if the parties have excluded the operation of the exception."
"It seems to me that a more realistic and practical solution is to permit the contracting party to recover damages for the loss which he and a third party has suffered being duly accountable to them in respect of their actual loss than to contract a theoretical loss in law on the part of the contracting party for which he may be under no duty to account to anyone since it is to be seen as his own loss. The solution is required where the law will not tolerate a loss caused by breach of contract to go uncompensated through an absence of privity between the party suffering the loss and the party causing it. In such a case, to avoid the legal black hole the law will deem the innocent party to be claiming on behalf of himself and any others who have suffered loss."
"… is one which is most likely to arise in the context of the domestic affairs of a family group or the commercial affairs of a group of companies. How the members of such a group choose to arrange their own affairs among themselves should not be a matter of necessary concern to a third party who has undertaken to one of their number to perform services in which they all have some interest. It should not be a ground of escaping liability that the party who instructed the work should not be the one who sustained the loss or all of the loss which in whole or in part has fallen on another member of the group"
"Where for its own purposes a group of companies decides which of its members is to be the contracting party in a project which is of concern and interest to the whole group I should be reluctant to refuse an entitlement to sue on the contract on the ground simply that the member who entered the contract was not the party who suffered the loss or a breach of the contract. But whether such an entitlement is to be admitted must depend on the arrangements which the group and its members have decided to make both among themselves and with the other party to the contract. In the present case there was a plain and deliberate course adopted whereby the company with the potential risk of loss was given a distinct entitlement directly to sue the contractor and the professional advisers. In the light of such a clear and deliberate course I do not consider that an exception can be admitted to the general rule that substantial damages can only be claimed by a party who has suffered substantial loss."
"Lord Griffiths' broader ground is not concerned with privity of contract as such. It is concerned with the damages recoverable by one party to a contract (the employer) against another (the contractor) for breach of contract and materials viz a building contract."
"I fully accept that the courts are not normally concerned with what a plaintiff does with his damages. But it does not follow that intention is not relevant to reasonableness at least if there are cases where the plaintiff does not intend to reinstate. Suppose in the present case Mr Forsyth had died, and the action had been continued by his executors. Is it to be supposed that they would be able to recover the cost of reinstatement even though they intended to put the property on the market without delay?"
"Damages are designed to compensate for an established loss and not provide a gratuitous benefit for an aggrieved party from which it follows that the reasonableness of an award of damages is to be limited to the loss sustained."
"I for my part cannot see that the tax reasons underlying the arrangements in the present case have any impact on the question whether Panatown is entitled to recover substantial damages from McAlpine."
"65. The authorities in this area demonstrate the courts' striving to ensure that wrongdoers do not escape from their liabilities by reference to the general principle that a person can only recover for his own loss because of the happenstance that a course of action lies in the hands of someone other than the person who has suffered the loss. The courts are concerned to see that justice is done between the parties."
3. In relation to the claim for delay and disruption costs amounting to $39,731,428 to what extent, if at all, is Mirant entitled to recover from Arup sums allegedly paid to PEC on behalf of SCC as liquidated damages?
(a) pursuant to the SCC indemnity or Tripartite Agreement indemnity and/or
(b) pursuant to Clause l.l.l of the Tripartite Agreement.
1. The Boiler Foundation claims did not delay the commencement of the Plant Reliability Trials (see above).
2. The amount was incurred by SCC and cannot be recovered by Mirant (see above).
3. No attempt was made by SCC in the negotiations with Alstom to assert that the delay payments were penal.
4. Damages over compensated PEC.
5. The Settlement was global with no attempt to identify damages for boiler and non boiler delays.
6. The claim fell outside the scope of Mirant's contract.
"1. The target dates for plant reliability trials were Unit 1 and the common parts, 1 December 1998, Unit 2, 1 March 1999.
2. On 24 September 1999 the contractors designated Unit 1 as Unit 2 and vice versa.
3. Significant delays were expressed as a result of the failure of the Unit 1 foundations and the generator with the result that the reliability trials were not completed until (Unit 2 first in time) and the common parts, 27 October 1999 and Unit 1, 24 November 1999.
4. The consortium had sought extensions of time for the dates for the reliability trials.
5. Delay payments in the sum of $101,243,049 had been received by PEC comprising $73,102,859 paid by Alstom on behalf of the supplier under the supply contract and $28,009,190 paid by CEPAS as agents for SCC on behalf of the contractors under the construction contract.
6. Other payments had been withheld by PEC in lieu of delay damages."
1. The contractor granted an extension of time of 13.5 days to the target date for the reliability trials for Unit 2 (first in time) and the common parts and 18 days for the target date for the reliability trials of Unit 1 (second in time).
2. The cumulative liability for delay damages to PEC under both the supply and construction contracts was $135,764,721 (including interest in the sum of $3,290,221) comprising $96,033,293 under the supply contract and $39,731,428 under the construction contract.
3. Clause 4 of the Agreement set out how the liability was to be discharged.
1. The monies to be paid to PEC pursuant to clause 4.2(a) of Settlement Agreement No.1 would be paid by Alstom Power Plant.
2. The monies to be paid to the supplier by PEC pursuant to clause 4.3(a) of Settlement Agreement No.1 would be $27,775,000 to Alstom Power Plant and $225,009.71 to CEPAS.
3. Sums that were to be paid to the supplier pursuant to clause 4.3(b) were also to be paid to Alstom Power Plant.
4. Delay payments of $11,641,238 payable to PEC would be payable by SCC.
5. Sums payable by PEC to the contractors in relation to retentions were to be paid by Alstom Power Plant and sums in relation to the cost of claims were to be paid by Alstom Power Services.
1. CEPAP was to design, construct and operate a 1000 MW power station comprising two units, each having a power output of 500 MW. The cost of construction was to be borne by CEPAP (Articles 2.3, 2.6 and 2.7).
"1.1.1. Although for the avoidance of doubt the Supplier and Contractor are separately liable for, respectively, the supplied works and the works, in order to ensure that the Plant is constructed and commissioned as specified in clause l.l.l of the construction contract and will meet the requirements both as to time, availability and performance, the supplier agrees that if there has been delay or failure in performance of any of
i. the supplied works including but not limited to indirect or consequential delay, damage or loss; and
(b) if the employer is or but for any dispute as to respective responsibilities between the supplier and the contractor would be entitled as a result of such delay or failure to claim or receive liquidated or other damages pursuant to either or both of the supply contract and the construction contract as the case may be (i) in and in respect of sub-clause (ii) above only the supplier is responsible for the whole or any part of such delay or failure."
1. CEPAS employed the Arup companies as consulting engineers for the design of the Unit 1 boiler foundations.
2. The agreement was made between CEPAS on about 29 May 1995 by the signing of the Letter of Intent and was contained in that letter (the Revision C offer) and the payment schedules (see paras 250, 251, 283, 285 and the declaration in relation to issue 2).
3. Arup knew that the designs were to be prepared for use by SCC as contractors on site (see para 289 of the judgment).
"A consortium comprising CEPA Slipform Engineering Limited (Slipform) and GEC Alstom (GECA) has been established to undertake the construction of a 2 x 600 MW capacity coal fired power station to be constructed at Sual in the Philippines. Slipform has requested Ove Arup & Partners (Arup) to submit technical proposals and a commercial bid for the design of the civil engineering works which will be fabricated and constructed by Slipform. This document constitutes Arup's offer."
"The issue is out of the apportionment – how much of that liquidated pool was to be borne by SCC and how much by Alstom and the advantage of acting for SCC was that it was an associated company with PEC, which was holding on to the money, so it took a year or so to try and maximise the commercial benefit and minimise SCC's contribution."
1. Mirant is not entitled to recover on behalf of SCC (see above).
2. The amounts in the various agreements were unreasonable amounts at which to settle.
3. The amounts allocated by Mirant to Alstom and its sub-contractors were not necessarily reasonable. Nor do they necessarily represent SCC's actual loss in relation to Alstom's sub-contractors. This would require proof that the sums claimed by Alstom's sub-contractors were reasonable sums to allow.
4. In order for the Court to be able to judge reasonableness it would need to be satisfied as to the amounts at which GECA settled its claims by sub-contractors.
1. I am satisfied that in principle Arup could be held liable for losses properly incurred by CEPAS as a result of delay claims.
2. For reasons which I have already set out, Arup was not responsible for any of the delay which resulted in SCC paying $39,731,428 to PEC (if the sums were indeed paid).
3. The Settlement Agreements dated 19 November 2001 were global settlements which may have paid some regard to perceived liabilities on the part of SCC and Alstom but did not represent a strict apportionment of liability for losses said to relate to the boiler and generator failures. As Mr Thomson said in evidence, the settlements were also concerned with maximising the financial benefit to the Mirant Group.
4. I have seen no evidence to satisfy me that the losses claimed under the tariff for liquidated damages under the offshore and onshore agreements represented a genuine pre-estimate of loss – see Mr Metcalfe's evidence. I must conclude that they were a penalty. In addition to this finding I note the Target Date for the commencement of the Reliability Trials. The loss to PEC could only start when it lost revenue. This was a later date than the commencement of the reliability trials. Losses could not occur until the plant was supplied with transmission lines which would enable the export of the electricity which it had generated on a communal basis. This was known at the time when the Supply and Construction Contracts were entered into.
5. Alstom would not be concerned in its negotiations whether SCC's liability arose by reason of delays caused by problems to the Boiler foundations or other causes (e.g. civils) for which SCC (or CEPAS) was responsible.
6. I am not satisfied that any proper allowance was made for extensions of time to which SCC (and Alstom) were entitled under the contract.
7. No attempt was made to consider delays to the transmission lines which would have entitled the consortium to an extension of time under the contract.
8. I am concerned that the settlement may have been arrived at to maximise Arup's potential liability.
9. I cannot therefore be satisfied on the evidence that the sums claimed against Arup as having been paid by Mirant in relation to the alleged delay caused by the failure of the boiler foundations represented a true estimate of any loss irrespective of who was liable to pay it.
10. For these reasons (and also because of my previous findings in relation to the boiler foundations) I conclude that CEPAS is not entitled to recover the sum of $39,731,428 from Arup.
4. To what extent if at all is Mirant entitled to recover time related costs allegedly incurred by it from Arup ($1,467,180 based on an average of $489,060 per month)?
"(a) Is the sum claimed reasonable; if not, what is a reasonable sum?
(b) to what extent, if at all, is there a causal nexus between any delay caused by the settlement to the boiler foundations and the time-related costs allegedly incurred by Mirant?
(c) which costs, if any, were incurred as a result of the failure of the boiler foundations?"
5. To what extent, if at all, is Mirant entitled to recover from Arup payment of $15,799,777 made by SCC under the draft Acceleration Agreement of 5 February 1998 in respect of additional preliminaries and disruption costs allegedly incurred by GECA Construction and allegedly paid by SCC under the terms of the Acceleration Agreement?
8. Did SCC pay GEC Alstom Turbines and GEC Electro the sum of $10,273,060 pursuant to the draft Acceleration Agreement of 5 February 1998 and, if so, is Mirant entitled to recover payments made by SCC to GECA Construction under the Acceleration Agreement?
1. He was unable to satisfy himself that individual sums were paid to sub-contractors NEIE, Ecco Asia, AG & P and EEI.
2. He was unable to satisfy himself as to the basis on which the sums paid to Alstom were calculated.
1. The amount was incurred by SCC and cannot be recovered by Mirant (see above)
2. The settlement does not differentiate between boiler and non boiler matters and is not recoverable.
3. The settlement is unreasonable in that no attempt has been made to verify or justify costs said to be incurred by Alstom or its sub-contractors.
4. The settlement was also global in the sense that it makes no attempt to link particular costs with matters for which Arup may be responsible.
6. Is Mirant entitled to recover $621,607 allegedly paid to Alstom and GEC Electro for the cover extension to the CAR and ALOP insurance policy?
7. Is Mirant entitled to recover time-related costs in the sum of $5,727,000 allegedly incurred by SCC?
(a) Did SCC incur the additional time-related costs of $5,727,000 taking into account the implementation of the acceleration measures?
(b) Is there a causal nexus between the settlement of the Boiler foundations and the alleged time-related costs?
(c) Were time-related costs in the sum of $5,727,000 or any lesser sum reasonably incurred and if so were they incurred as a result of the failure of the Unit 1 Boiler foundations?
(a) bonuses paid to expatriate staff as part of their salary packages
(b) overhead at SCC's Manila Office
(c) diesel used on site
(d) water used on site
(e) equipment hired.
1. Mr McManus said in oral evidence that the 'Actuals' figure was not reliable because the figures did not accurately reflect booked costs.
2. The 'Actuals' figures for July, August and September 1997 had changed in the spreadsheet for November 1997. Most of the figures had increased. In the case of the expatriate salaries they had increased significantly.
9. To what extent, if at all, is Mirant entitled to recover acceleration costs consisting of additional fuel, labour and water incurred by SCC in the sum of $3,724,428 or any sum?
10. To what extent is Mirant entitled to recover rectification costs to the Unit 1 Boiler in the sum of $1,522,888 or any sum?
1. The claim is substantially overstated.
2. The amount incurred by SCC cannot be recovered by Mirant (addressed as a separate issue).
3. The sum has been paid by insurers and cannot now be recovered from Arup.
4. The costs fall outside Mirant's contract.
1. A competitive tendering exercise should have been carried out in respect of purchase of the bolts and other components for the remedial scheme.
2. Mirant should have documentary evidence to support the claims to payment by Alstom and/or Stein.
3. There should be direct evidence that the bolts which were in fact purchased were used on the remedial works and not for some other purpose.
12. To what extent, if at all, is Arup entitled to cover and credit in respect of the CAR Policy?
"In my judgment the reason why an insurer cannot normally exercise a right of subrogation against a co-assured rests not on any fundamental principle relating to insurance but on ordinary rules about circuity."
"65. Although your Lordships do not need to resolve the issue in this case it seems to me that there is much force in the point that the rules about circuity of action do not provide the explanation. I would prefer to say that the time basis of the rule is to be found in the contract between the parties. In Hopewell Project Management Ltd v Ewbank Preece" [1994] 1 Lloyds Rep 448,458, Mr Recorder Jackson QC said that in his view it would be nonsensical if those parties who were jointly insured under a contractors' all risks policy could make claims against one another in respect of damage to the contract works, that such a result could not possibly have been intended by those parties and that had it been necessary for him to do so he would have held that there was an implied term to that effect. I would be content to accept that as a satisfactory basis for the rule on which, had it been necessary for them to do so, Wimpey & Hall would have been entitled to resist this claim (1437-1438).
(1) the party sued is one of those falling within the definition of 'insured' under the policy;
(2) the loss claimed is one of the losses within the cover provided under the policy.
(1) Arup is not a co-insured under the CAR Policy in respect of the loss caused by its negligent design of the boiler foundations.
CONCLUSION
Note 1 added by BAILII The text of the Delay and Disruption Protocol in fact reads as follows (see http://www.eotprotocol.com/) - "There may be more than one critical path depending on workflow logic. A delay to the progress on any activity in the critical path will, without acceleration or resequencing, cause the overall project duration to be extended." [Back] Note 2 added by BAILII The text of the Delay and Disruption Protocol in fact reads as follows (see http://www.eotprotocol.com/) - "To reduce the number of disputes relating to delay, the Contractor should prepare and the Contract Administrator should accept a properly prepared programme showing the manner and sequence in which the Contractor plans to carry out the works. The programme should be updated to record actual progress and any extensions of time (EOTs) granted. If this is done then the programme can be used as a tool for managing change and determining EOTs and periods of time for which compensation may be due." [Back]