QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London, EC4A 1HD |
||
B e f o r e :
____________________
MARK TONKIN MARIE LOUISE TOUREAU |
Claimants |
|
- and - |
||
UK INSURANCE LIMITED |
Defendant |
____________________
Ms Rosemary Jackson & Mr Jonathan Selby (instructed by Travers Smith) for the Defendant
Hearing dates: 13, 14, 15, 16, 20, 21, 22, 23 and 24 February, 2 March 2006
____________________
Crown Copyright ©
His Honour Judge Peter Coulson QC:
CONTENTS
A. | INTRODUCTION |
B. | THE POLICY AND THE RELEVANT PRINCIPLES OF LAW |
B1. | Buildings |
B2. | The Correct Date of Assessment |
B3. | Contents |
B4. | Personal Possessions |
B5. | General Obligations |
B5. | 1 The Claimants |
B5. | 2 The Defendant |
B6. | Interest |
C. | THE RELEVANT EVENTS |
C1. | The Original Conversion Works |
C2. | The Inspection by Mr Francis |
C3. | Lay-out and Condition just before the Fire |
C3. | 1 The Property |
C3. | 2 The Gallery |
C4. | The Fire |
C5. | The Immediate Aftermath of the Fire |
C6. | The Gallery |
C7. | The Reinstatement Works |
C8. | The June 2003 Tenders |
C9. | The Timber Frame |
C10. | The Ground Works |
C11. | The Meeting on 14 August 2003 and its Aftermath |
C12. | The October 2003 tenders |
C13. | The FOS Investigation |
C14. | Repudiation and After |
C14. | 1 Repudiation |
C14. | 2 The Result of the FOS Adjudication |
C14. | 3 Expert Determination |
C14. | 4 Repairs |
C14. | 5 Proceedings |
D. | THE PROPER APPROACH TO REINSTATEMENT CLAIMS |
D1. | Option 1 |
D2. | Option 2 |
D3. | Option 3 |
D4. | What an Insured Must Not Do |
D5. | The Claimants' Approach in the Present Case |
E. | THE ALLEGATIONS OF FRAUD |
E1. | Background |
E2. | Are the Allegations of Fraud Open to the Defendant? |
E3. | Applicable Principles |
E4. | The Allegations |
E5. | Evidence |
E6. | Conclusions |
F. | ESTOPPEL |
F1. | History |
F2. | Estoppel/ Width of Small Barn |
F2.1 | How Did The Increase In Width Come About? |
F2.2 | The Alleged Estoppel |
F3. | Estoppel/ The Entirety of Delavals' Scheme |
F4. | Conclusions on Estoppel |
G. | THE CLAIMANTS' PROPOSED SCHEME |
G1. | What Scheme Do The Claimants Rely On? |
G2. | Is It A Reinstatement Scheme? |
G2.1 | Introduction |
G2.2 | The Small Barn |
(a) | Width |
(b) | Roof Pitch |
(c) | Staircase |
(d) | Void |
(e) | Internal Layout Generally |
(f) | Framing |
(g) | Summary |
G2.3 | Timber Frame |
(a) | General |
(b) | Additional Work To The Flint Walls |
(c) | Structural Stability |
G2. | 4 First and Second Floors In The Main Barn |
(a) | Original Position |
(b) | The Delavals Scheme |
G2. 5 | Roof |
G2.6 | Floor of Main Barn |
G2.7 | Doors and Windows |
G2.8 | The Kitchen |
G2.9 | Miscellaneous Items |
G2.10 | Summary |
G3. | Is It Adequately Documented? |
G3.1 | Introduction |
G3.2 | Significant Deficiencies In The Scheme |
(a) | Inclusions Within The Specification |
(b) | Omissions From The Specification |
(c) | Drawings |
G4. | Has The Delavals Scheme Generated Accurate Figures? |
G4.1 | Introduction |
G4.2 | Cheesmur Tender |
G4.3 | Delavals PC Sums |
G4.4 | Mr Ireland's New Figures |
(a) | Comparison Between Costs of Work and "Soft Costs" |
(b) | Preliminaries |
(c) | Profit |
(d) | Site Establishment |
(e) | Contract Period |
(f) | Contingency |
(g) | Plus/Minus 5% |
(h) | Miscellaneous |
G5. | Summary |
H. | THE DEFENDANT'S PROPOSED SCHEME |
H1. | What Scheme Does The Defendant Rely On? |
H2. | Is It A Reinstatement Scheme? |
H2.1 | Overview |
H2.2 | Detailed Elements of Mr Beale's Scheme |
H2.3 | Is It Adequately Documented? |
H3. | Has It Generated Accurate Figures? |
H4. | Summary |
I. | RESPONSIBILITY FOR DELAY |
I1. | Introduction |
I2. | What Should Have Happened |
I3. | Why That Timetable Was Not Achieved |
I4. | The Defendant's Default |
I5. | Summary |
J. | CLAIM A: CONSTRUCTION COSTS |
J1. | Which Scheme? |
J2. | Assessment of Costs |
J2.1 | Basic Reinstatement Costs |
J2.2 | Local Authority Requirements |
J2. 3 | Incomplete Works |
J2.4 | Summary |
K. | CLAIM B: FEES |
K1. | Delavals' Fees |
K2. | Fees Already Paid |
K3. | Summary |
L. | CLAIM C: ALTERNATIVE ACCOMMODATION, ETC |
L1. | Container Storage Charges |
L2. | Contents, Fittings and Furnishings To Render The Gallery Habitable As Temporary Accommodation |
L3. | Cost of Complying With Planning Permission |
L4. | Alternative Accommodation |
L5. | Summary |
M. | CLAIM D: PERSONAL POSSESSIONS |
N. | CLAIM E: INCREASED CONSTRUCTION COSTS |
O. | CLAIM F: DEGRADATION REINSTATEMENT COSTS |
P. | CLAIM FOR DAMAGES FOR INCONVENIENCE |
Q. | CLAIM FOR INTEREST |
R. | CONCLUSIONS |
A. INTRODUCTION
B. THE POLICY AND THE RELEVANT PRINCIPLES OF LAW
B1. Buildings
"STANDARD COVER
The SUM INSURED under this Section of the Policy is £504,000
A. LOSS OR DAMAGE
We will pay for loss of or damage to the buildings caused by fire.
WHAT IS COVERED
4. Fees and Clearance Costs
We will pay for:
(a) the costs of architects, surveyors, consultants and legal fees
(b) costs necessarily incurred with our consent to clear the site and make it and the Buildings safe in the repair or reinstatement of the Buildings following damage recoverable under this Section
but not
fees for preparing any claim under the policy
5. Local Authority Requirements
We will pay for the extra costs of reinstatement or repairs of the damaged part of the Buildings incurred solely to comply with any Government or local authority requirement following damage recoverable under this Section
but not
if you were notified of the requirement before the damage occurred.
6. Alternative Accommodation and Rent
We will pay in addition to any other amount recoverable under this Section
(a) if You occupy Your Home
the cost of reasonable alternative accommodation for You, Your Family and domestic pets Any claim payment will not be more than 20% of the sum insured by this Section."
"E. BASIS OF CLAIMS SETTLEMENT
1. We will pay for the cost incurred in reinstatement or repair of that part of the Buildings which is damaged by any of the causes insured by this Section without any reduction for wear and tear provided that at the time of such damage the Buildings are in a good state of repair.
But not for the cost of replacing or repair to any undamaged items solely because they form part of a set, suite, group or collection of items of a uniform design, nature or colour.
2. If the damage to the Buildings is not reinstated or repaired or the Buildings are not in a good state of repair then We will pay at our option:
(a) the cost of reinstating the damage less a deduction for any wear and tear of betterment, or
(b) the difference between the sale value of Your Home in the open market immediately prior to the damage and its residual value following such damage.
3. The most we will pay for any one claim will be the total sum insured shown in Your Schedule plus any amount payable under Items 5, 6 and 7 [above].
7. The insurance premium charged is based upon the sums insured shown on your policy schedule/confirmation. If in our opinion the sums insured do not accurately reflect the rebuild cost of the risk on cover, at our option, we reserve the right to reduce any claims payment by the amount of the percentage of underpayment of premium due to this under-estimation of value."
B2. The Correct Date of Assessment
"When the insurer performs his promise of indemnity, the amount of indemnity is normally calculated on values at the time of loss (point 1), even though the insurer may not be obliged to pay until later (point 2), when the claim has been investigated. The traditional rule of contract law is to assess damages at the time of breach (point 2). Recently, however, courts mindful of inflation have stressed the basic aim of contract damages to put the plaintiff in as good a position as if the contract had been performed, and have based damages on values at the date of the hearing (point 3), "unless it can be said that the plaintiff ought reasonably to have mitigated by seeking an alternative performance at an earlier date, in which event the appropriate measure would be the cost of the alternative performance at that date"."
"In principle, loss is assessed on the basis of values at the time loss occurred. It is irrelevant that the values have changed since the time the insurance was contracted, or since the time of loss, or that they are likely to change in the foreseeable future."
B3. Contents
B4. Personal Possessions
B5. General Obligations
B5.1 The Claimants
"For any loss or damage claim You must at Your expense provide Us with such information and evidence as We may request including written estimates and proof of ownership or value "
Accordingly, as both parties accepted, it was always for the Claimants to provide proper information in support of their claims. As previously noted, this dispute has come to trial because the Defendant maintains that the Claimants have failed to comply with this condition. Whether or not that submission is right is explored in some detail later in this Judgment.
B5.2 The Defendant
"Caring For You
We will always try to be fair and reasonable whenever you have need of the protection of this Policy. We will also act quickly to provide that protection."
Both parties agreed that, as a result of this provision, there was an express obligation on the part of the Defendant to be fair and reasonable and to act "quickly" when dealing with the claim. The existence of such a provision gives rise to the final point of principle between the parties on the terms of the Policy.
"As a matter of law, it seems to me that the decisions already referred to show that there cannot be a claim for damages of this sort where the breach of contract relied upon is the late payment or non-payment of a sum of money by way of damages. But on the other hand, if as a matter law the plaintiff is able to show that the defendants have committed some other and separate breach of contract, and if specifically he can show that the defendants were in breach by failing to accept liability or to approve of the reinstatement at an early stage, then the recovery of damages would not be restricted to the discretionary award of interest which exists in the other case. Since this line of argument requires identifying a legal obligation other than the payment of interest, and since the statement of claim in fact refers only to the non-payment of what was called the claim for indemnity, it does seem to follow that the defendants are entitled to object that no such claim is set out in the pleaded case, nor was it brought specifically to the attention of the learned Judge."
B6. Interest
"As a general rule the court will award interest from the date at which the insurer is in default for not paying the claim, because the basic function of an award of interest is to compensate the Claimant for being kept out of his money. In indemnity insurance this is, strictly speaking, the date on which the assured's cause of action arose, and in property insurance this will be the date of the casualty, at which according to the established but unrealistic analysis of a claim for an indemnity as one for damages for breach of contract, the insurer is deemed to be in breach of an obligation to hold his assured harmless against loss caused by an insured peril. In practice, the courts are sometimes prepared to postpone the running of interest not only to the date at which a claim is notified to the insurers but to that at which a reasonable investigation of the claim ought to have been completed. In cases where the claim is inadequately formulated or documented the time for a reasonable investigation may well be extended in consequence.
The court may abridge the period for the running of interest or reduce the rate of interest to mark its disapproval of the claimant's delay in bringing or pursuing his claim, although this has the effect of providing a windfall to the insurer who should not have had the use of the money. It can be explained on the basis that the assured's unreasonable delay becomes a cause of the money remaining unpaid."
C. THE RELEVANT EVENTS
C1. The Original Conversion Works
"Now, if somebody's trying to say that there was no upstairs or somebody is trying to infer that there was no upstairs and the local authority didn't know about it I'm not a great lover of authority. If they didn't know about it, I'm not sorry. You know, it doesn't worry me "
C2. The Inspection By Mr Francis
a) Mr Francis valued the property in its "current condition" at £300,000. He described the physical condition of the property as "average".
b) He did not consider that the Main Barn was really habitable at the time of his inspection.
c) He thought that there was a good deal of work still to be carried out at the property but that, once that work was completed, the value of the property would be £550,000 (which was £250,000 more than his estimate of its current value).
d) He described the property as being "currently in the throes of being completely refurbished".
e) The rider to his report identified some of the works still to be carried out. This included "some repair to the timber frame" and "a new roof covering". He agreed in cross-examination that that must have been a reference to the Main Barn. He also identified the need for "a complete internal refit".
C3. Lay-Out and Condition Just Before The Fire
C3.1 The Property
a) The Main Barn was, in Mr Francis' words "not really habitable". It housed a games room and a workshop with an office above. It was unheated.
b) The Small Barn had been rebuilt by Mr Tonkin during the 1990s. The 'old' element was the flint wall that ran the length of the western side of the Small Barn and had a short return along the northern side. Despite the absence of planning permission or building control approval, the Small Barn had two storeys. On the ground floor, going from north to south, there was a bedroom, a music room, a bathroom and wc, and a living room. Coming out of the living room there were stairs going up to a first floor. There would have been very narrow headroom for the stairs. On the first floor there was a void above part of the living room, meaning that it was effectively a double volume room. There were three further bedrooms on this floor, with roof lights. Two of them would have been very small. All of them would have had very confined headroom.
c) In the crook of the elbow formed by the Small Barn and the Main Barn there were three rooms in a stepped structure. There was a kitchen, a porch and a pantry: the last two were of modern construction. There was no first floor over these three rooms.
a) At the western end of the Main Barn, there were three flint walls. These walls comprised half the southern wall of the Main Barn; the whole of the western wall of the Main Barn; and a small return forming the first part of the northern wall of the Main Barn. The remainder of the Main Barn (principally the eastern end) had an oak frame and the infill panels between the timber members comprised thermalite blocks.
b) The roof of the Main Barn was made of concrete tiles. The floor was largely built straight out of the ground using bricks, and without insulation. The Main Barn was not heated.
c) There was a first floor at the western end of the Main Barn which extended not more than halfway along the Main Barn. There was a second floor above that which may not have extended the full length of the first floor.
d) The Small Barn, rebuilt in the 1990s, comprised timber stud walls and timber joists, with a natural slate roof. Only in that sense could it be described as timber framed: it did not have a traditional barn timber frame, unlike (for instance) the eastern end of the Main Barn.
e) There were roof lights in the first floor of the Small Barn, which were of course essential given that, contrary to the planning documents, the first floor of the Small Barn comprised the Claimants' principal bedroom accommodation.
f) It appears that the kitchen in the elbow was a conversion of the pre-existing room there. The porch and the larder were of modern construction. The cat-slide roof above, which had been required by the planners, did not extend all the way along the north elevation of the Main Barn.
C3.2 The Gallery
C4. The Fire
C5. The Immediate Aftermath Of The Fire
"With respect to our continuing role therefore, I believe that Mr Tonkin will be utilising other consultants to design the building to be reinstated.
Obviously we respect his decision, although I am somewhat disappointed with the prompt attention I personally provided him with that he has not advised one way or the other whether he would wish to utilise our services.
From your point of view I suspect that his architect will not be familiar with the reinstatement process of insurers, and there may well be a cost control issue in this regard."
C6. The Gallery
C7. The Reinstatement Works
"Item 3.01 Allow to construct the building annotated as the north-south wing and shown on the contract drawing. Provide all materials, labour and plants associated with same. All work to comply with the Building Regulations. All work to comply with the Specification herein.
Item 4.01 Allow to construct the building annotated as the east-west wing and shown on the contract drawing. Provide all materials, labour and plants associated with same. All work to comply with the Building Regulations. All work to comply with the Specification herein.
Item 5.01 Allow to construct the building annotated as kitchen - housing the proposed new kitchen shown on the contract drawing. Provide all materials, labour and plants associated with same. All work to comply with the Building Regulations. All work to comply with the Specification herein."
C8. The June 2003 Tenders
"I note your comments and am certainly somewhat alarmed that the projected cost of the reinstatement works is in excess of the sums insured particularly as this will undoubtedly result in a further financial cost to be borne by the client. As you will appreciate, I am unable to give approval to commencement of the works without sight of the detailed specification of the proposed works such that I may verify that the intended works are those purely required to reinstate the building and that there are no additional aspects which will obviously fall outside the scope of policy cover. I will also require a detailed breakdown of costs in order that I may undertake a cost analysis and complete my quantum enquires."
As I have already noted, Mr Jones was never provided with a detailed breakdown of the costs. In addition, his reference to the need for "a detailed specification of the proposed works" made plain something which Mr Jones in cross-examination said was extremely important to him, namely the provision by Delavals of a detailed specification, with quantities and prices.
"We feel that going back to all three contractors to re-price the project will merely delay a start date. Furthermore, it is unlikely, and quite understandable, that the already unsuccessful contractors will be reluctant to waste their time on a project that they already failed to secure. Without doubt it is our opinion that we should continue negotiations with Cornford only."
The letter makes plain that Delavals were not planning to revise the (wholly inadequate) schedule of work, despite the fact that they knew that the existing document contained major errors, such as the proposal to install a full first floor in the Main Barn.
" serious concerns regarding the suitability of the drawings and specification currently prepared as being adequate for the size and complexity of the project. We would therefore suggest these documents be augmented or re-written and additional drawings provided in this respect."
The report also indicated that the proposed scheme, when compared to the ordnance survey map of the original property, was on a larger footprint.
"My own particular concern is that the schedule of works presented is not sufficiently detailed for me to verify that the works proposed are those required to reinstate the property and that there won't be any future increases in cost. I would suggest that in the very least the schedule of works should be revisited and that you continue to chase Cornford for a breakdown of their costs."
In all the circumstances, I consider that Mr Jones' comments were really quite mild and that his proposals were entirely constructive. Again, they were ignored by Delavals.
"Our clients are most anxious that the frame "looks right " and they wish to have the main posts 250 x 250 even if that means they are over-designed. Furthermore they have not as yet decided on the arrangement of rooms at either ground or first floor but the positions of windows and doors on the external walls are fixed (due to planning conditions). We are therefore looking to have totally uninterrupted floor space on both the ground floor and the first floor."
The letter went on to identify further "improvements", including the use of a curved raised tie at second floor level in order to give maximum headroom in the loft. Again, it is impossible not to conclude that this proposal was expressly designed so as to allow the second floor of the main barn to become habitable accommodation.
C10. The Ground Works
C11. The Meeting on 14 August and its Aftermath
C12. The October 2003 Tenders
"Having reviewed the specification and drawings sent out to tender to the contractors I would also point out that the specification is still poorly written, and the drawings are completely inadequate for such a complex building being merely sketched 1:100 to drawings blown up to 1:50 scale.
If we were appointed to act as Contract Administrator with the current information available we would have to start again to produce the required tender documentation and would then produce detailed drawings at 1:50 scale together with a suitable specification of works based on NBS Standard Preliminary and Preamble Clauses including Materials and Workmanship Sections and a detailed Schedule of Works."
"We have now delivered everything that we contracted to provide and are beginning to feel frustrated by the lack of progress."
I understand their frustration, but it seems to me that they were the cause of the problems. They had not begun to provide "everything that we contracted to provide" and their statement to the contrary reveals an alarming failure on their part to understand just what it was they needed to do.
C13. The FOS Investigation
C14. Repudiation And After
C14.1 Repudiation
"The key problem with this case throughout has been your client and his agent's inability or unwillingness to submit a properly framed claim. We have made an offer on the best information available to us. It is not our duty to provide these figures to you; it is your client's duty to prove his claim. It is now clear he has no intention of doing so. Therefore the offer is withdrawn and the claim repudiated for breach of general condition 5B(i) after waiting 19 months for the proper particulars."
" to meet the costs of a consultant surveyor or structural engineer to review and advise you independently on the adequacy of the specification."
C14.2 The Result of the FOS Adjudication
"Having considered all the reports and other evidence submitted, it is my opinion that the complainant has not adequately discharged his responsibility to provide proof of the extent of his loss, whereas the firm has produced considerable evidence to demonstrate that the specification for the reinstatement of the property includes substantial betterment both in the size and specification from the original pre-fire situation.
Consequently, in view of the technical nature of this dispute, I consider that the most appropriate resolution to the dispute that has been brought to this service is for the complainant and the firm to jointly appoint an independent architect to review all the documents produced to date and to prepare a detailed specification for the build of the complainant's property based on his expert consideration of the pre-fire specification, and for both the firm and the complainant to fully accept the independent architect's conclusions in this matter."
C14.3 Expert Determination
" We consider that it would be best and most quickly resolved by involving an independent third party specialist, rather than through protracted legal correspondence. Therefore, we would propose that the parties jointly appoint an architect who specialises in barn conversions, with input from whatever other professionals he requires, to review the specifications, tenders, reports and other relevant documentation produced so far, with a view to providing an opinion as to the specifications of your client's property prior to the fire, and preparing a detailed independent specification for the rebuild based on the architect's conclusions as to the proper specification of your client's property prior to the fire."
C14.4 Repairs
C14.5 Proceedings
D. THE PROPER APPROACH TO REINSTATEMENT CLAIMS
D1. Option 1
D2. Option 2
D3. Option 3
D4. What An Insured Must Not Do
D5. The Claimants' Approach In The Present Case
"Q: So you did not get involved, and say, 'well, it is bigger, but it compensates for something else'?
A: I would not have had that discussion.
Q: Did you instruct Delavals to have that discussion?
A: I did not ask Delavals to get into a conversation about that."
It seems to me that this was a plain admission; that Mr Tonkin felt that it was perfectly proper for him to put forward a scheme which featured numerous changes and improvements and leave it to the Defendant to identify what those changes and improvements might be. For the avoidance of doubt, I find that such an approach was wrong in principle and contrary to the Claimants' obligations under the Policy.
"Q: He did not ask you to recreate what was there?
A: We would build something similar [to what was there] which was acceptable to the Local Authority.
Q: Did you discuss that with Mr Tonkin? Was he with you at all times?
A: Yes."
E. THE ALLEGATIONS OF FRAUD
E1. Background
E2. Are The Allegations Of Fraud Open To The Defendant?
E3. Applicable Principles
"Fraud is proved when it is shown that a false representation has been made (i) knowingly (ii) without belief in its truth or (iii) recklessly, careless of whether it be true or false."
"The balance of probability standard means that a court is satisfied an event occurred if the court considers that, on the evidence the occurrence of the event was more likely than not. When assessing the probabilities the court will have in mind as a factor, to whatever extent is appropriate in the particular case, that the more serious the allegation the less likely it is that the event occurred and hence the stronger should be the evidence before the court concludes that the allegation is established on the balance of probability. Fraud is usually less likely than negligence built into the preponderance of probability standard is a generous degree of flexibility in respect of the seriousness of the allegation.
Although the result is much the same, this does not mean that where a serious allegation is in issue the standard of proof required is higher. It means only that the inherent probability or improbability of an event is itself a matter to be taken into account when weighing the probabilities and deciding whether, on balance, the event occurred. The more improbable the event, the stronger must be the evidence that it did occur before, on the balance on probability, its occurrence would be established."
" would not generally in those circumstances be right to conclude readily that someone had behaved fraudulently merely because he put forward an amount greater than that which he reasonably believed he would recover".
In similar vein, in Orakpo v Barclays Insurance Services [1995] LRLR 443, Lord Hoffmann expressed the view that:
"In cases where nothing is misrepresented or concealed and the loss adjuster is in as good a position to form a view of the validity of the claims of the insured, there would be a legitimate reason that the insured was merely putting forward a starting figure for negotiation."
E4. The Allegations
E5. Evidence
"We paid for the kitchen. That was netted off against the under-floor heating I would expect that to be in the paperwork."
E6. Conclusions
F. ESTOPPEL
F1. History
" To reinstate the Main Barn, kitchen and Small Barn on the footprint represented by the ground works already in situ in accordance with the Delavals' revised spec/plan " (my emphasis)
F2. Estoppel/ Width of Small Barn
F2.1 How Did The Increase In Width Come About?
F2.2 The Alleged Estoppel
F3. Estoppel/The Entirety of the Delavals Scheme
F4. Conclusions On Estoppel
G. THE CLAIMANTS' PROPOSED SCHEME
G1. What Scheme Do The Claimants Rely On?
G2. Is It A Reinstatement Scheme?
G2.1 Introduction
G2.2 The Small Barn
(a) Width
(b) Roof Pitch
(c) Staircase
(d) Void
(e) Internal layout generally
(f) Framing
(g) Summary
G2.3 Timber Frame
(a) General
(b) Additional Work to the Flint Walls
(c) Structural stability
G2.4 First And Second Floors In The Main Barn
(a) Original Condition
(b) The Delavals Scheme
G2.5 Roof
G2.6 Floor Of Main Barn
G2.7 Doors And Windows
G2.8 The Kitchen
G2.9 Miscellaneous Items
G2.10 Summary
G3. Is It Adequately Documented?
G3.1 Introduction
G3.2 Significant Deficiencies In The Scheme
(a) Inclusions Within the Specification
(b) Omissions From the Specification
"But it needed a tightly worded specification. The tenderers would have to fill it in. It needed something that the tenderers could then fill in the figures. So that a quantity surveyor could then check it. A lot of people make basic errors."
A little later in his cross-examination he reiterated this point. He said:
"I wanted a specification with unit areas put in. I expected blanks in the specification for the tenderers to fill in."
(c) Drawings
G4. Has The Delavals' Scheme Generated Reliable Figures?
G4.1 Introduction
G4.2 Cheesmur Tender
"Q: So these figures were not set in stone?
A: I think he says that here. Yes, you've answered the question."
G4.3 Delavals' PC sums
"Q: So you agree that, if at the end of the trial, the Claimants seek to make the insurers pay the precise amounts of these PC sums, you would agree that that was a misuse of the specification?
A: Yes I would.
Q: So it would be unfair to turn these PC sums into sums representing actual costs?
A: Yes, it probably would."
There were other exchanges with both Mr Stillman and Mr Ward to the same effect.
G4.4 Mr Ireland's new figures
(a) Comparison between cost of work and "soft cost"
(b) Preliminaries
(c) Profit
(d) Site establishment
(e) Contract period
(f) Contingency
(g) Plus/Minus 5%
(h) Miscellaneous
G5. Summary
H. THE DEFENDANT'S PROPOSED SCHEME
H1. What Scheme Does The Defendant Rely On?
H2. Is It A Reinstatement Scheme?
H2.1 Overview
H2.2 Detailed Elements Of Mr Beale's Scheme
H2.3 Is It Adequately Documented?
H3. Has It Generated Accurate Figures?
H4. Summary
I. RESPONSIBILITY FOR DELAY
I1. Introduction
I2. What Should Have Happened
I3. Why That Timetable Was Not Achieved
I4. The Defendant's Default
I5. Summary
J. CLAIM A: CONSTRUCTION COSTS
J1. Which Scheme?
J2. Assessment Of Costs
J2.1 Basic Reinstatement Costs
J2.2 Local Authority Requirements
J2.3 Incomplete Works
i) Small Barn/Dry Lining And Insulation
ii) Small Barn/Roof
iii) Small Barn/Loft Replacement
iv) Main Barn/Dry-Lining and Insulation
v) Main Barn/Roof Insulation
vi) Main Barn/Repairs To Frame and Doors
vii) Main Barn/Roof
viii) Windows
Summary
J2.4 Summary
K. CLAIM B: FEES
K1. Delavals' Fees
Paragraph of judgment |
Amount |
364-365 | £27,577.62 |
367-369 | £587.50 |
370 | £2,335 |
371-372 | £176.25 |
375 | £1,700.50 |
Total | £32,376.87 |
K2. Fees Already Paid
K3. Summary
L. CLAIM C: ALTERNATIVE ACCOMMODATION, RENT, STORAGE
L1. Container Storage Charges
L2. Contents, Fittings And Furnishings To Render The Gallery Habitable As Temporary Accommodation
a) Item 4, in respect of the kitchen sink, was formally abandoned on day 4 of the trial.
b) The claim for £1,155.02 for an electric oven and hob (item 5) cannot be recoverable in these proceedings since the Defendant has already paid for a kitchen and this item was included in the scope of works prepared by DJA, approved by the Defendant and included within the DJA invoice.
c) Item 6, the fridge, is in respect of an item which can be used in the property when it is rebuilt. It cannot possibly be said to be a temporary item for which the Claimants will derive no benefit. No claim can therefore be made in respect of this item. The same is also true of item 7, the freezer.
d) Item 8 is a claim for the pottery shed in the sum of £1,450. I reject this item of claim. Again, there is no reason why this pottery shed cannot be utilised after the property has been rebuilt. It is a top-of-the-range mock Swiss chalet log cabin. There is no evidence that the shed would be sold or somehow destroyed after the property has been rebuilt. I therefore reject this item of claim.
e) Item 9 is in respect of duvets, item 11 is in respect of sofa and chairs, and item 13 is in respect of dining table chairs. Again it has simply not been established that these items are in some way temporary and could not be reused by the Claimants when they moved back into the property.
f) Item 12 is in respect of small filing cabinets and item 14 is in respect of the oak office desk. These are plainly items which can be reused when the property is rebuilt.
g) Item 15 is in respect of the small tv. It is extraordinary that this item is maintained given that Mr Tonkin accepted in cross-examination that the item was not properly recoverable and would be used by the family when they moved back into the property.
h) Items 16, 17 and 18 are all in respect of bedding, which can again be reused when the Claimants move back into the property. Again these items cannot be allowed.
i) There are a number of items, such as items 20 and 21 where no proof of quantification has been provided. It does not seem to me to be appropriate to allow anything in respect of these items where it is unclear what has been purchased or how and why the material purchased could not be re-utilised in the property. The same comment also applies to items 27, 28, 30 and 32.
L3. Cost Of Complying With Planning Permission
L4. Alternative Accommodation
L5. Summary
C1 | Container storage charges | £687.38 |
C2 | Contents, fittings, etc | £1,855.24 |
C3 | Complying with Planning Permission | £5,000 |
£7,542.62 |
M. CLAIM D: PERSONAL POSSESSIONS
N. CLAIM E: INCREASED CONSTRUCTION COSTS
"In my judgment it is impossible to say that any such breach, even if and to the extent that it was a breach of contract, would carry with it a right to substantial damages representing the claim which is now put forward. What has to be said, however hard it may seem to say it, is that in such circumstances the cause of any delay which the plaintiff suffered must be regarded as the consequence of his own decision not to proceed with repair or reinstatement, whether that decision was voluntary or not. In other words, if, unfortunately, through his own financial circumstances he is unable to do so without assistance from the defendants, he cannot allege that the defendants were in breach of contract by failing to accept liability at that stage."
Similarly here, the Claimants have not proceeded with the reinstatement scheme ("whether the decision was voluntary or not") and cannot therefore allege breach of contract.
O. CLAIM F: DEGRADATION REINSTATEMENT COSTS
P. CLAIM FOR DAMAGES FOR INCONVENIENCE
Q. CLAIM FOR INTEREST
R. CONCLUSIONS
Claim A (reinstatement costs) £275,776.18
Claim B (professional fees) £33,846.24
Claim C (alternative accommodation, etc) £7,542.62
Total £317,165.04