QUEEN'S BENCH DIVISION
TECHNOLOGY and CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
DSND SUBSEA LIMITED (formerly known as DSND OCEANTECH LIMITED) |
Claimant/Part 20 Defendant |
|
- v - |
||
PETROLEUM GEO SERVICES ASA |
First Defendant |
|
PGS OFFSHORE TECHNOLOGY AS |
Second Defendant/Part 20 Claimant |
____________________
Mr S. Furst QC, Mr P. Coulson and Mr J. Lee (instructed by Messrs Watson, Farley and Williams for the Defendants)
____________________
Crown Copyright ©
Paragraphs | |
The System | 5 - 16 |
The Agreements | 17 - 37 |
History of Events up to 17 July 1998 | 38 - 43 |
The meeting of 17 July 1998 | 44 - 50 |
History of events from 17 July to 24 September 1998 | 51 - 66 |
The meetings of 24 and 25 September 1998 | 67 - 85 |
From the MOU to the MOA | 86 - 90 |
The Misrepresentation issues | 91 - 94 |
What representation (if any) was made | 96 - 100 |
Repetitions | 101-103 |
Reliance | 104-113 |
Was the representation false? | 114-126 |
Rescission | 127-129 |
Why did PGS enter into the MOA? | 130 |
Was the MOU entered into under duress? | 131-142 |
Affirmation | 143-148 |
The Termination issue 149-150 | |
Article 16.3 | 151-154 |
Article 16.1 | 155 |
Was there a breach of contract? | 156-192 |
Which breach of contract? | 193-194 |
Reasonable opportunity to remedy | 195-199 |
Repudiation | 200 |
Summary | 201 |
The System
The FPSO
The Risers
The turret and the RTIAs
Installation of risers
The Fennica
The Agreements
The Contract
"9.1 CONTRACTOR shall commence performance of the WORK, continue and complete the WORK in an expeditious and timely manner and in accordance with the PROGRAMME cited in EXHIBIT C together with the specified Key Dates and Milestones. CONTRACTOR acknowledges that the timely performance of its obligations hereunder are vital, fundamental and essential for the exploitation of the FIELD. Consequently time is of the essence of this CONTRACT, as delays in the performance of the WORK would cause most substantial prejudice to OWNER. CONTRACTOR shall be entitled to schedule the performance of the WORK so as to maximise efficiency, providing always that the key dates and milestones are not delayed."
HOA
"In the event that riser pull-in (hook-up) takes place or work continues after 1st November then all weather downtime shall be to OWNER account. In the event that the work is delayed beyond 1st December then all costs shall be reimbursed by OWNER to CONTRACTOR at cost plus fifteen%".
"4.11 In the event that any offshore WORK is delayed beyond the 1st November 1998 due to causes attributable to OWNER, OWNER shall in those circumstances only be liable to pay for all "Waiting on Weather". For the avoidance of doubt all "waiting on weather" prior to 1st November 1998 shall be for the sole and exclusive account of CONTRACTOR.
4.12 In the event that the PSO has not arrived at the FIELD by 1st December 1998 Riser Installation, Pull-in, Connection to Turret and Commissioning shall be performed by SUBCONTRACTOR VESSEL MARINE SPREAD and shall be reimbursed to CONTRACTOR by OWNER at open book documented cost plus a fee of fifteen percent."
"6.1 Up to 45 days prior to the FPSO arrival in field "target date" of September 2nd 1998, OWNER can change the target date provided a minimum of 45 days remains from the new target date for CONTRACTOR to plan for the remaining work. The pricing for the work will not change other than as described in the foregoing sections or the following requirements/clarifications:
1) CONTRACTOR can plan, schedule and execute the workscope at any time throughout the year provided that the work is complete 15 days in advance of the "target date".
2) The pricing mentioned herein is subject to the currently notified PGS delivery dates which are contained in Appendix A and Appendix B.
3) The price mentioned herein for the FPSO hook-up will be held firm up and until 1st November 1998.
4) In the event the FPSO arrival in the field is later than 1st November 1998 or the work continues beyond this date then all weather downtime incurred during mooring hook-up activities shall be to PGS account."
Appendix B contained a number of Riser Installation Assumptions.
MOU
"PGS confirms that DSND has no responsibility or liability with respect to the design of the RTIAs. Any delays or consequence that may occur during performance of the workscope caused as a result of the RTIA design shall be borne by PGS."
MOA
The issues
MOU
(a) Did PGS enter into the MOU because of economic duress?
(b) Is PGS entitled to have the MOU avoided on the grounds of economic duress?
(c) Did PGS enter into the MOU in reliance on misrepresentations made by DSND?
(d) Is PGS entitled to have the MOU avoided, or damages, on the grounds of misrepresentation?
MOA
(e) Would PGS have been obliged to enter into the MOA but for DSND's misrepresentation?
(f) Did the economic duress which applied at the time of the signature of the MOU remain, such that PGS had no realistic alternative but to enter into the MOA?
(g) (i) Is PGS entitled to avoid the MOA?
(ii) Alternatively, is PGS entitled to damages for economic duress?
(iii) Is DSND obliged to indemnify PGS against sums due under the MOA?
(iv) Does DSND's claim under the MOA fail for circuitry?
TERMINATION
(h) Was PGS entitled to terminate the Contract pursuant to Article 16.1, or alternatively under Article 16.3?
(i) Did PGS repudiate the Contract on 19 November 1998?
History of events up to 17 July 1998
The meeting of 17 July 1998
Review of the evidence
History of events from 17 July to 24 September 1998
"...all of the obligations of PGS under the CONTRACT 97003 are in place, valid for all construction activities and also naming DSND as additional assured. PGS has and will continue to comply with the requirements of our BAR policy and accordingly you are instructed to commence forthwith the RTIAs assembly and thereafter the installation at the FIELD".
The meetings of 24 and 25 September
"....as long as PGS has endeavoured to ensure that the contractor complies with the terms and conditions of the All Risks Insurance Policy, whether that be recommendations of the warranty Surveyor, implied or expressed warranties, if any, or the specific or general conditions of the policy, then the All Risks Insurance Policy extends to the contractor subject to any exclusions or limitations contained in the aforesaid police."
From the MOU to the MOA
The Misrepresentation Issues
PGS' pleaded case
"...its vessel Fennica would be able to perform the work required of it in the installation of the risers in a 3 metre significant wave height. Such representation continued until after the signature of the MOU".
"...the Defendants aver, in respect of each of the documents identified above that it necessarily followed from the Claimant's statements that (i) the Fennica would be able to perform riser installation in sea states up to Hs=3, and (ii) that the risers themselves could be safely, and would be, installed in sea states of up to Hs=3 (save in respect of the section containing buoyancy modules which were limited to Hs=2)."
What representation (if any) was made?
"In particular, unless one knew the procedure and the assumed sea state applicable to the RAOs and the spectrum of the wave, it was impossible to reach any meaningful conclusion as to the vessel's suitability for the work."
Repetitions
Was there reliance on the alleged representation(s) in entering into the MOU?
"DSND now consider that single wire installation or risers is now possible and clump weight solution for installation is no longer required. This will reduce the weather window from 50 hours at under 2M Hs to 18 hours at under 2M Hs."
Was the representation false?
(a) the experience of installing the umbilical riser between 2 and 4 October demonstrated that the Fennica was not capable of operating in 3M Hs. The sea state did not exceed 2.5M, and even at that level, the installation had to be abandoned, in part, at least, because the vessel was unable to maintain station;
(b) the evidence of Mr Legerstee showed that there were three separate reasons why the Fennica was not capable of operating in 3M Hs. These were the effect of motions and accelerations on the comfort of the men, her inability to keep station, and the limitations of the crane.
Rescission for misrepresentation
Why did PGS enter into the MOA?
Was the MOU entered into under duress?
The Law
Discussion
Affirmation
"the cavalier attitude displayed by DSND with respect to its obligations under the terms of the Memorandum of Understanding entered into on 25 September 1998, and in particular to the Schedule attached to, and forming an integral part of that Agreement."
"A transaction entered into as the result of undue influence is voidable and not void. The right to rescind on the ground of undue influence may be lost either by express affirmation of the transaction by the victim, by estoppel or by delay amounting to proof of acquiescence. Although there can normally be no affirmation until the party knows he has the right to rescind, it has been doubted whether this is a hard and fast rule: "the whole of the circumstances must be looked at to see whether it is just that the complaining beneficiary should succeed." Estoppel requires a clear and unequivocal representation that the claimant would not seek to set the agreement aside, intended to be acted on and in fact acted on by the other party to his detriment or in such a way that it would be inequitable to allow the claimant to go back on his representation. In either case, to be of any value, the affirmation must take place after the influence has ceased. "The right to property acquired by such means cannot be confirmed in this court unless there be full knowledge of all the facts, full knowledge of the equitable rights arising out of those facts, and an absolute release from the undue influence by means of which the frauds were practised." Lapse of time in itself does not seem to constitute a bar to relief, but it will provide evidence of acquiescence if the victim fails to take any steps to set aside the transaction within a reasonable time after he is freed from the undue influence. And where he has himself failed to commence proceedings in this way during his lifetime, his personal representatives cannot do so after his death."
The Termination Issue
"Resulting from your breach of CONTRACT in not having a suitable Diving Support Vessel at the Banff Field from 10th November 1998 as contractually committed by DSND, and your failure to remedy this serious breach following our notice to you, we have no alternative but to terminate the CONTRACT with immediate effect. You are hereby required to make available to PGS all technical documents and assign all subcontracts to PGS".
"By a Memorandum of Understanding dated 25 September 1998 ("the MOU") you undertook to provide a DSV for the period 10 November to 5 December 1998.....In breach of the above obligation, and in spite of our numerous requests from early November onwards for urgent action on our part to supply a DSV on a continuous basis in accordance with your obligations you completely failed to provide an in-house DSV or a third party DSV for the agreed period......In any event, your failure to procure a DSV from 10 November and thereafter is itself an irremediable breach, which entitled us to terminate the contract."
Article 16.3
"(I) Contractor persistently fails to perform the Work diligently in an efficient, workmanlike, skilful and careful manner, or (ii) Contractor fails to comply with any term of this Contract...
then in any such event Owner having given Contractor reasonable opportunity to remedy the situation shall have the right to terminate this Contract by giving written notice thereof to Contractor."
Article 16.1
Was there a breach of contract?
"The CONTRACTOR shall commence performance of the WORK, continue and complete the WORK in an expeditious and timely manner and in accordance with the PROGRAMME cited in Exhibit C together with the Key Dates and Milestones. CONTRACTOR acknowledges that the timely performance of its obligations hereunder are vital, fundamental and essential for the exploitation of the Field. Consequently time is of the essence of this CONTRACT, as delays in the performance of the WORK would cause most substantial prejudice to OWNER. CONTRACTOR shall be entitled to schedule the performance of the WORK so as to maximise efficiency, providing always that the key dates and milestones are not delayed."
(a) the work operations would be carried out in the sequence identified in the schedule;
(b) the rates and durations were indicative only, and were not absolute; and
(c) if DSND did not have its own DSV available, it would use a third party DSV if available, and (pursuant to an implied term of the contract) DSND would take reasonable steps to procure such a vessel, whether in-house or from a third party, so as to achieve the indicative dates.
"As a result of variations to the contract workscope and methodology used to install their riser systems and contract schedule, PGS and DSND agree to the below mentioned mechanism for compensation and revised schedule attached hereto" (emphasis added).
"Because of the uncertainty in providing the DSV(s) created by the many versions of DSV availability, none of which have materialised, PGS has no confidence in the current proposal, being the 5th contradiction since 10th November 1998".
He repeated that PGS were taking all means available to them to mitigate the effects of the "serious breach, including but not limited to sourcing a suitable DSV for our own account".
Which breach of contract?
Reasonable opportunity to remedy
Repudiation
Summary
MOU
(a) PGS did not enter into the MOU under duress.
(b) PGS did not enter into the MOU in reliance on any misrepresentation by DSND.
(c) If PGS had entered into the MOU under duress or in reliance on any misrepresentation by DSND, it would not have been entitled to avoid the MOU on either account.
MOA
(d) The issues do not arise.
TERMINATION
(e) PGS was not entitled to terminate the Contract under Article 16.1, and did not terminate under Article 16.3.