QB/2018/0204 |
QUEEN'S BENCH DIVISION
On appeal from the County Court at Central London
HHJ Bailey
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
SAVI RABILIZIROV |
Claimant |
|
-and- |
||
(1) A2 DOMINION LONDON LTD |
Defendant/Additional Claimant/Respondent |
|
(2) A2 DOMINION HOMES LTD |
Defendant/Additional Claimant/Respondent |
|
(3) GROUND CONSTRUCTION LIMITED |
Defendant/Appellant |
|
(4) DURKAN LIMITED |
Third Party/Respondent |
____________________
Joseph Sullivan (instructed by Shoosmiths LLP) for the Third Party/Respondent
Adam Robb QC and Rebecca Drake (instructed by Clyde and Co LLP) for the First and Second Defendants/Respondents
The Claimant (who was not a party to the appeal) did not appear and was not represented
Hearing date: 9th November 2018
____________________
Crown Copyright ©
Mrs Justice Farbey :
The Facts
"We are as always prepared to meet and amicably discuss the… matter further. Our construction director, John Power who has been actively involved in the… matter from inception, is available to meet on site and discuss a solution. In light of the above, we would advise you not to undertake any remedial works in the interim prior to meeting with GCL".
"We must reiterate that GCL does not accept responsibility for the above problem experienced on site. As per our letter, we are prepared to meet and discuss the matter on site but advised Durkan not to undertake any remedial works in the interim…".
The County Court proceedings
The Judgment
The indemnity
"Works to be carried out in accordance with the terms and conditions of DOM2 except where superseded in this subcontractor order".
DOM2 is a reference to the Construction Confederation (CC) Domestic Sub-contract DOM/2 (1981 edition; reprinted 1998).
"indemnify and save harmless the Contractor against and from:
.1 any breach, non-observance or non-performance by the Sub-Contractor or his servants or agents of any of the provisions of the Main Contract insofar as they relate and apply to the Sub-Contract; and
.2 any act or omission of the Sub-Contractor or his servants or agents which involves the Contractor in any liability to the Employer under the provisions of the Main Contract insofar as they relate and apply to the Sub-Contract; and
.3 any claim, damage, loss or expense due to or resulting from any negligence or breach of duty on the part of the Sub-Contractor, his servants or agents…".
"Nothing contained in the Sub-Contract Documents shall be construed so as to impose any liability on the Sub-Contractor in respect of any act, omission or default on the part of the Employer, the Contractor, his other sub-contractors or their respective servants or agents nor create any privity of contract between the Sub-Contractor and the Employer or any other sub-contractor".
Foreseeability and remoteness of damage
"It was plainly foreseeable, and GCL assumed responsibility for damage arising from loss of use of the premises, that if a groundworks contractor so improperly carried out its contract that water penetrates into the premises, he cannot possibly say that he did not foresee that the owner of the premises might, indeed would, sustain a loss of use of the premises. That type of damage being foreseeable, it is not open to GCL to complain that because of Mr Rabilizirov's intention to substantially increase the size of the premises his claim is for a rather greater loss of use than GCL, had they put their minds to it, might have foreseen".
The question of delay as a novus actus interveniens
"Had GCL been dismissed from site and told that its input into the resolution of the problem [was] not required back in 2009/2010, the novus actus argument might have found favour given the extraordinarily long passage of time it has taken Durkan to deal with the water penetration. But the circumstances were otherwise. In effect, GCL dismissed themselves from site".
"I do not overlook the fact that at the end of their letter of 16 December 2010 there is a suggestion that they might get further involved if requested, but their attitude was plain".
Failure to mitigate
"GCL really do need to do more than they have to demonstrate that Durkan failed to act as a reasonable contractor in connection with the investigation and resolution of the water ingress".
Grounds of appeal
Scope of the appeal
"decisions of the Technology and Construction Court have special characteristics which affect the readiness of the Court of Appeal to reconsider them on appeal. First, the findings of fact often fall within an area of specialist expertise, where the evidence is of a technical nature and given by experienced experts, and which is evidence of a kind which judges of the Technology and Construction Court are particularly well placed to assess. Second, the conclusions of fact will frequently involve an assessment or evaluation of a number of different factors which have to be weighed against each other, which is often a matter of degree. Third, the decisions may deal with factual minutiae not easily susceptible of reconsideration on appeal. Fourth, the judgments will frequently be written on the basis of assumed knowledge of the detail by the parties and their advisors, and will not address a wider audience, with the consequence that the underlying reasoning may not always be readily apparent or fully articulated".
"The exigencies of daily court room life are such that reasons for judgment will always be capable of having been better expressed. This is particularly true of an unreserved judgment…but also of a reserved judgment based upon notes…These reasons should be read on the assumption that, unless he has demonstrated the contrary, the judge knew how he should perform his functions and which matters he should take into account….An appellate court should resist the temptation to subvert the principle that they should not substitute their own discretion for that of the judge by a narrow textual analysis which enables them to claim that he misdirected himself".
The Indemnity
Actions or omissions of other parties as novus actus interveniens
"when the conduct of the claimant exacerbates or adds to the injuries of which he complains, that conduct will generally result in a reduction of his damages on grounds of contributory negligence, or failure in his duty to mitigate damage. However it may be that the conduct of the claimant is so wholly unreasonable and/or of such overwhelming impact that that conduct equities the defendant's wrongdoing and constitutes a novus actus".
Events until 2011
Events from 2011 until trial
Failure to mitigate
Remoteness of damage
"It was plainly foreseeable that…if a groundworks contractor so improperly carried out its contract that water penetrates into the premises, he cannot possibly say that he did not foresee that the owner of the premises might, indeed would, sustain a loss of use of the premises".
That type of damage being foreseeable, it was not open to GCL to complain about its amount.
Other secondary submissions by the appellant
Durkan's respondent's notice
Conclusion