COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM BRISTOL COUNTY COURT
(Technology and Construction Court)
(JACOB J)
Strand London WC2 Thursday 25th April 2002 |
||
B e f o r e :
LORD JUSTICE CHADWICK
and
LORD JUSTICE CLARKE
____________________
SAUNDERS | Claimant | |
- v - | ||
WILLIAMS | Defendant |
____________________
Smith Bernal Reporting Limited
190 Fleet Street, London EC4A 2AG
Telephone No: 020-7421 4040 Fax No: 020-7831 8838
(Official Shorthand Writers to the Court)
MR ANDREW ARENTSEN (instructed by Palser Grossman Solicitors, Cardiff CF10 4HA) appeared on behalf of the Defendant
____________________
Crown Copyright ©
"With regard to the transfer of your claim to Bristol for hearing, on further investigation I understand that objection was raised to His Honour Judge Moseley QC taking the case resulting in another TCC judge needing to be sought. There was not another TCC judge available to sit in Cardiff on 11th July 2001, although it was still hoped that Judge Graham Jones sitting in Swansea might become available, allowing him to sit in Cardiff. By delaying the decision it was hoped that transfer of the case to Bristol could be avoided. Hence the delay in forwarding notification of the change of venue. The late decision to transfer the trial to Bristol for hearing by Jacob J was made by the listing officer at Cardiff Civil Justice Centre with authority given by His Honour Judge Graham Jones. However, as sated in my previous letter, the hearing notice does contain a warning that cases may be moved to another judge, possibly at a different court."
"TCC claims may be dealt with either in the High Court or, subject to paragraph 2.3 below, in a county court. Cases allocated to the TCC will, unless and until a judge of the TCC otherwise directs, be dealt with by a judge of the TCC."
"It is concluded that the total costs of taking the wall down, building another one and fortifying the roof are £24,572. That figure stands admitted. The real question before me is whether there should be any more, if so how much."
"... it is a wholly unforeseeable consequence that nobody would get the wall mended for eight years. What one would expect is the wall be mended within a reasonable period. Mrs Saunders said she did not have the money to get another builder. I know not whether that is true; it has not been fully investigated. Whether it was possible to borrow it, I do not know. She indicated at another point she would have been able to borrow money for other purposes but in the event I do not think that the consequence of Mr Williams' negligence foreseeably could include anything other than a reasonable period in which to get the wall mended or, if necessary, replaced.
It is difficult to put a time period on what that reasonable period is. Counsel for Mr Williams suggested six months. To my mind that is rather short. Bitter experience of anything to do with builders know that it takes longer than that to get anything done. So I am prepared to accept a period of one year."
"In the end, it is almost impossible to put a figure on what the loss of the rooms for a year would be worth. The figure which must be rough and ready to which I have arrived is £1,000. Accordingly, there is judgment for Mrs Saunders for the sum of £24,572 plus £1,000. The £1,000 may carry interest. I will have to hear argument about that."
"The fundamental basis is thus compensation for pecuniary loss naturally flowing from the breach, but this first principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach, and debars him from claiming any part of the damage which is due to his neglect to take such steps."
"The onus of proof on the issue of mitigation is on the defendant. If he fails to show that the plaintiff ought reasonably to have taken certain mitigating steps, then the normal measure will apply."
"I do not know whether that is true. It has not been fully investigated."