KINGS'S BENCH DIVISION
BIRMINGHAM DISTRICT REGISTRY
33 Bull Street, Birmingham B4 6DS |
||
B e f o r e :
____________________
(1) HIGH SPEED TWO (HS2) LIMITED (2) THE SECRETARY OF STATE FOR TRANSPORT |
Claimants |
|
- and |
||
FOUR CATEGORIES OF PERSONS UNKNOWN -and- ROSS MONAGHAN AND 58 OTHER NAMED DEFENDANTS |
Defendants |
____________________
Tim Moloney KC and Owen Greenhall (instructed by Robert Lizar Solicitors ) for the Sixth Named Defendant (James Knaggs)
A number of Defendants appeared in person and/or filed written submissions
Hearing dates: 26-27 May 2022
____________________
Crown Copyright ©
See also: [2022] EWHC 2364 (KB)
Mr Justice Julian Knowles:
Introduction
Democracy and opposition to HS2
"UPON the Claimants' application by an Application Notice dated 25 March 2022
AND UPON the Claimants confirming that this Order is not intended to prohibit lawful protest which does not involve trespass upon the HS2 Land and does not block, slow down, obstruct or otherwise interfere with the Claimants' access to or egress from the HS2 Land."
" the Bill which became the Act was a hybrid Bill and, as such, subject to a petitioning process following its deposit with Parliament. In total [the Claimants' witness] says 3,408 petitions were lodged against the Bill and its additional provisions, 2,586 in the Commons and 822 in the Lords and select committees were established in each House to consider these petitions.
17. She says the government was able to satisfy a significant number of petitioners without the need for a hearing before the committees. In some cases in the Commons this involved making changes to the project to reduce impacts or enhance local mitigation measures and many of these were included in one of the additional provisions to the Bill deposited during the Commons select committee stage.
18. Of the 822 petitions submitted to the House of Lords select committee, the locus of 278 petitions was successfully challenged. Of the remaining 544 petitions, the select committee heard 314 petitions in formal session with the remainder withdrawing, or choosing not to appear before the select committee, mainly as a result of successful prior negotiation with the Claimants."
" Those lawful activities in this case [viz, the building of HS2] had been authorised by Parliament through the 2017 Act after lengthy consideration of both the merits of the project and objections to it. The legislature has accepted that the HS2 project is in the national interest. One object of section 68 is to discourage disruption of the kind committed by the respondent, which, according to the will of Parliament, is against the public interest The Strasbourg Court has often observed that the Convention is concerned with the fair balance of competing rights. The rights enshrined in articles 10 and 11, long recognised by the Common Law, protect the expression of opinions, the right to persuade and protest and to convey strongly held views. They do not sanction a right to use guerrilla tactics endlessly to delay and increase the cost of an infrastructure project which has been subjected to the most detailed public scrutiny, including in Parliament."
"Our vision is for HS2 to be a catalyst for growth across Britain. HS2 will be the backbone of Britain's rail network. It will better connect the country's major cities and economic hubs. It will help deliver a stronger, more balanced economy better able to compete on the global stage. It will open up local and regional markets. It will attract investment and improve job opportunities for hundreds of thousands of people across the whole country."
See: https://www.gov.uk/government/organisations/high-speed-two limited/about
The Claimants' land rights
"(1) The nominated undertaker may enter upon and take possession of the land specified in the table in Part 4 of this Schedule -
(a) for the purpose specified in relation to the land in column (3) of the table in connection with the authorised works specified in column (4) of the table,
(b) for the purpose of constructing such works as are mentioned in column (5) of the table in relation to the land, or
(c) otherwise for Phase One purposes.
(2) The nominated undertaker may (subject to paragraph 2(1)) enter upon and take possession of any other land within the Act limits for Phase One purposes.
(3) The reference in sub-paragraph (1)(a) to the authorised works specified in column (4) of the table includes a reference to any works which are necessary or expedient for the purposes of or in connection with those works."
"(1) Not less than 28 days before entering upon and taking possession of land under paragraph 1(1) or (2), the nominated undertaker must give notice to the owners and occupiers of the land of its intention to do so.
(2) The nominated undertaker may not, without the agreement of the owners of the land, remain in possession of land under paragraph 1(1) or (2) after the end of the period of one year beginning with the date of completion of the work for which temporary possession of the land was taken."
"29. The First or the Second Claimant are the owner of the land coloured pink on the HS2 Land Plans, with either freehold or leasehold title (the "Pink Land"). The Claimants' ownership of much of the Pink Land is registered at HM Land Registry, but the registration of some acquisitions has yet to be completed. The basis of the Claimants' title is explained in the spreadsheets named "Table 1" and "Table 3" at JAD2. Table 1 reflects land that has been acquired by the GVD process and Table 3 reflects land that has been acquired by other means. A further table ("Table 2") has been included to assist with cross referencing GVD numbers with title numbers. Where the Claimants' acquisition has not yet been registered with the Land Registry, the most common basis of the Claimants' title is by way of executed GVDs under Section 4 of the HS2 Acts, with the vesting date having passed.
30. Some of the land included in the Pink Land comprises property that the Claimants have let or underlet to third parties. At the present time, the constraints of the First Claimant's GIS data do not allow for that land to be extracted from the overall landholding. The Claimants are of the view that this should not present an issue for the present application as the tenants of that land (and their invitees) are persons on the land with the consent of the Claimants.
31. The Claimants' interest in the Pink Land excludes any rights of the public that remain over public highways and other public rights of way and the proposed draft order deals with this point. The Claimant's interest in the Pink Land also excludes the rights of statutory undertakers over the land and the proposed draft order also deals with this point.
32. The First Claimant is the owner of leasehold title to the land coloured blue on the HS2 Land Plans (the "Blue Land"), which has been acquired by entering into leases voluntarily, mostly for land outside of the limits of the land over which compulsory powers of acquisition extend under the HS2 Acts. The details of the leases under which the Blue Land is held are in Table 3.
33. The First Claimant has served the requisite notices under the HS2 Acts and is entitled to temporary possession of that part of the HS2 Land coloured green on the HS2 Land Plans ("the Green Land") pursuant to section 15 and Schedule 16 of the Phase One Act and section 13 and Schedule 15 of the Phase 2a Act. A spreadsheet setting out the details of the notices served and the dates on which the First Claimant was entitled to take possession pursuant to those notices is at Table 4 of JAD2."
"31. As explained by Mr Justice Holland QC at paragraphs 30 to 32 of the 2019 Harvil Rd Judgment (SSfT and High Speed Two (HS2) Limited -v- Persons Unknown [2019] EWHC 1437 (Ch)), the First Claimant is entitled to possession of land under these provisions provided that it has followed the process set down in Schedules 15 and 16 respectively, which requires the First Claimant to serve not less than 28 days' notice to the owners and occupiers of the land. As was found in all of the above cases, this gives the First Claimant the right to bring possession proceedings and trespass proceedings in respect of the land and to seek an injunction protecting its right to possession against those who would trespass on the land.
32. For completeness and as it was raised for discussion at the hearing on 11.04.2022, the HS2 Acts import the provisions of section 13 of the Compulsory Purchase Act 1965 on confer the right on the First Claimant to issue a warrant to a High Court Enforcement Officer empowering the Officer to deliver possession of land the First Claimant in circumstances where, having served the requisite notice there is a refusal to give up possession of the land or such a refusal is apprehended. That procedure is limited to the point at which the First Claimant first goes to take possession of the land in question (it is not available in circumstances where possession has been secured by the First Claimant and trespassers subsequently enter onto the land). The process does not require the involvement of the Court. The availability of that process to the First Claimant does not preclude the First Claimant from seeking an order for possession from the Court, as has been found in all of the above mentioned cases.
33. Invoking the temporary possession procedure gives the First Claimant a better right to possession of the land than anyone else even the landowner. The First Claimant does not take ownership of the land under this process, nor does it step into the shoes of the landowner. It does not become bound by any contractual arrangements that the landowner may have entered into in respect of the land and is entitled to possession as against everyone. The HS2 Acts contain provisions for the payment of compensation by the First Claimant for the exercise of this power.
34. The power to take temporary possession is not unique to the HS2 Acts and is found across compulsory purchase - see for example the Crossrail Act 2008, Transport and Works Act Orders and Development Consent Orders. It is also set to be even more widely applicable when Chapter 1 of the Neighbourhood Planning Act 2017 is brought into force."
"35. the First Claimant is entitled to take possession of temporary possession land following the above procedure and in doing so to exclude the landowner from that land until such time as the First Claimant is ready to or obliged under the provisions of the HS2 Acts to hand it back. If a landowner were to enter onto land held by the First Claimant under temporary possession without the First Claimant's consent, that landowner would be trespassing."
The Claimants' case
The Defendants' cases
"(2) PERSONS UNKNOWN ENTERING OR REMAINING WITHOUT THE CONSENT OF THE CLAIMANTS ON, IN OR UNDER LAND ACQUIRED OR HELD BY THE CLAIMANTS IN CONNECTION WITH THE HIGH SPEED TWO RAILWAY SCHEME SHOWN COLOURED PINK, AND GREEN ON THE HS2 LAND PLANS AT https://www.gov.uk/government/publications/hs2-route-wide-injunction-
proceedings ("THE HS2 LAND") WITH THE EFFECT OF DAMAGING AND/OR DELAYING AND/OR HINDERING THE CLAIMANTS, THEIR AGENTS, SERVANTS, CONTRACTORS, SUB-CONTRACTORS, GROUP COMPANIES, LICENSEES, INVITEES AND/OR EMPLOYEES"
"It includes those present on HS2 land on public highways. A person who walks over HS2 land on a public footpath is covered by the definition (subject to the consent of the Claimants). A demonstration on a public footpath which had the effect (intended or not) of hindering those connected to the Claimants (for any degree) would be caught within the definition."
"AND UPON the Claimants confirming that they do not intend for any freeholder or leaseholder with a lawful interest in the HS2 Land to fall within the Defendants to this Order, and undertaking not to make any committal application in respect of a breach of this Order, where the breach is carried out by a freeholder or leaseholder with a lawful interest in the HS2 Land on the land upon which that person has
an interest.
AND UPON the Claimants confirming that this Order is not intended to act against any guests or invitees of any freeholder or leaseholder with a lawful interest in the HS2 Land unless that guest or invitee undertakes actions with the effect of damaging, delaying or otherwise hindering the HS2 Scheme on the land held by the freeholder or leaseholder with a lawful interest in the HS2 Land."
Discussion
Legal principles
(i) Trespass and nuisance
"7. There are subject to the order three different categories of land. First of all, there is land within the freehold ownership of the First Claimant that is coloured blue on both sets of plans, and is referred to as "the blue land". Secondly, there is land acquired by the First Claimant pursuant to its compulsory purchase powers in the High Speed Rail (London - West Midlands) Act 2017 (to which I shall refer as "the 2017 Act"). That land is coloured pink on the various plans and is referred to as "the pink land". Thirdly, there is land in the temporary possession of the Second Claimant by reason of the exercise of its powers pursuant to section 15 and Schedule 16 of the 2017 Act, that land is coloured green on the plans
.
30. The first cause of action is trespass. The Claimants are entitled, as a matter of law, to bring a claim in trespass in respect of all three categories of land and, as I have said, it was not seriously suggested that they could not. In particular, I was referred to section 15 and paragraphs 1, 3 and 4 of Schedule 16 to the 2017 Act
31. Thus, the procedure is simply this: if the Second Claimant wishes to take temporary possession of land within a defined geographical limit, it serves 28 days' notice pursuant to paragraph 4. Thereafter, it is entitled to enter on the land and 'take possession'. That, to my mind, and it was not seriously argued otherwise, gives it a right to bring possession proceedings and trespass proceedings in respect of that land.
32. In paragraph 40 of his judgment in Ineos at first instance [Ineos Upstream Ltd v Persons Unknown [2017] EWHC 2945 (Ch)], Mr. Justice Morgan says this:
"The cause of action for trespass on private land needs no further exposition in this case."
Exactly the same is the case here, it seems to me, and it is the First Defendant, the definition of which persons I have described above, who is, or are, subject to such a claim in trespass."
"9. The following general principles are well-settled, and uncontroversial on this appeal.
(1) Peaceful protest falls within the scope of the fundamental rights of free speech and freedom of assembly guaranteed by Articles 10(1) and 11(1) of the European Convention on Human Rights and Fundamental Freedoms. Interferences with those rights can only be justified if they are necessary in a democratic society and proportionate in pursuit of one of the legitimate aims specified in Articles 10(2) and 11(2). Authoritative statements on these topics can be found in Tabernacle v Secretary of State for Defence [2009] EWCA Civ 23 [43] (Laws LJ) and City of London v Samede [2012] EWCA Civ 160 [2012] 2 All ER 1039, reflecting the Strasbourg jurisprudence.
(2) But the right to property is also a Convention right, protected by Article 1 of the First Protocol ('A1P1'). In a democratic society, the protection of property rights is a legitimate aim, which may justify interference with the rights guaranteed by Article 10 and 11. Trespass is an interference with A1P1 rights, which in turn requires justification. In a democratic society, Articles 10 and 11 cannot normally justify a person in trespassing on land of which another has the right to possession, just because the defendant wishes to do so for the purposes of protest against government policy. Interference by trespass will rarely be a necessary and proportionate way of pursuing the right to make such a protest."
"45. We conclude that there is no basis in the Strasbourg jurisprudence to support the respondent's proposition that the freedom of expression linked to the freedom of assembly and association includes a right to protest on privately owned land or upon publicly owned land from which the public are generally excluded. The Strasbourg Court has not made any statement to that effect. Instead, it has consistently said that articles 10 and 11 do not "bestow any freedom of forum" in the specific context of interference with property rights (see Appleby at [47] and [52]). There is no right of entry to private property or to any publicly owned property. The furthest that the Strasbourg Court has been prepared to go is that where a bar on access to property has the effect of preventing any effective exercise of rights under articles 10 and 11, or of destroying the essence of those rights, then it would not exclude the possibility of a State being obliged to protect them by regulating property rights.
46. The approach taken by the Strasbourg Court should not come as any surprise. articles 10, 11 and A1P1 are all qualified rights. The Convention does not give priority to any one of those provisions. We would expect the Convention to be read as a whole and harmoniously. Articles 10 and 11 are subject to limitations or restrictions which are prescribed by law and necessary in a democratic society. Those limitations and restrictions include the law of trespass, the object of which is to protect property rights in accordance with A1P1. On the other hand, property rights might have to yield to articles 10 and 11 if, for example, a law governing the exercise of those rights and use of land were to destroy the essence of the freedom to protest. That would be an extreme situation. It has never been suggested that it arises in the circumstances of the present case, nor more generally in relation to section 68 of the 1994 Act. It would be fallacious to suggest that, unless a person is free to enter upon private land to stop or impede the carrying on of a lawful activity on that land by the landowner or occupier, the essence of the freedoms of expression and assembly would be destroyed. Legitimate protest can take many other forms.
47. We now return to Richardson [v Director of Public Prosecutions [2014] AC 635] and the important statement made by Lord Hughes JSC at [3]:
'By definition, trespass is unlawful independently of the 1994 Act. It is a tort and committing it exposes the trespasser to a civil action for an injunction and/or damages. The trespasser has no right to be where he is. Section 68 is not concerned with the rights of the trespasser, whether protester or otherwise. References in the course of argument to the rights of free expression conferred by article 10 of the European Convention on Human Rights were misplaced. Of course a person minded to protest about something has such rights. But the ordinary civil law of trespass constitutes a limitation on the exercise of this right which is according to law and unchallengeably proportionate. Put shortly, article 10 does not confer a licence to trespass on other people's property in order to give voice to one's views. Like adjoining sections in Part V of the 1994 Act, section 68 is concerned with a limited class of trespass where the additional sanction of the criminal law has been held by Parliament to be justified. The issue in this case concerns its reach. It must be construed in accordance with normal rules relating to statutes creating criminal offences.'
48. Richardson was a case concerned with the meaning of 'lawful activity', the second of the four ingredients of section 68 identified by Lord Hughes (see [12] above). Accordingly, it is common ground between the parties (and we accept) that the statement was obiter. Nonetheless, all members of the Supreme Court agreed with the judgment of Lord Hughes. The dictum should be accorded very great respect. In our judgment it is consistent with the law on articles 10 and 11 and A1P1 as summarised above.
48. The proposition which the respondent has urged this court to accept is an attempt to establish new principles of Convention law which go beyond the "clear and constant jurisprudence of the Strasbourg Court". It is clear from the line of authority which begins with R (Ullah) v. Special Adjudicator [2004] 2 AC 323 at [20] and has recently been summarised by Lord Reed PSC in R (AB) v. Secretary of State for Justice [2021] 3 WLR 494 at [54] to [59], that this is not the function of a domestic court.
49. For the reasons we gave in para. [8] above, we do not determine Ground 1 advanced by the prosecution in this appeal. It is sufficient to note that in light of the jurisprudence of the Strasbourg Court it is highly arguable that articles 10 and 11 are not engaged at all on the facts of this case.
73. The question becomes, is it necessary to read a proportionality test into section 68 of the 1994 Act to render it compatible with articles 10 and 11? In our judgment there are several considerations which, taken together, lead to the conclusion that proof of the ingredients set out in section 68 of the 1994 Act ensures that a conviction is proportionate to any article 10 and 11 rights that may be engaged.
74. First, section 68 has the legitimate aim of protecting property rights in accordance with A1P1. Indeed, interference by an individual with the right to peaceful enjoyment of possessions can give rise to a positive obligation on the part of the State to ensure sufficient protection for such rights in its legal system (Blumberga v. Latvia No.70930/01, 14 October 2008).
75. Secondly, section 68 goes beyond simply protecting a landowner's right to possession of land. It only applies where a defendant not merely trespasses on the land, but also carries out an additional act with the intention of intimidating someone performing, or about to perform, a lawful activity from carrying on with, or obstructing or disrupting, that activity. Section 68 protects the use of land by a landowner or occupier for lawful activities.
76. Thirdly, a protest which is carried out for the purposes of disrupting or obstructing the lawful activities of other parties, does not lie at the core of articles 10 and 11, even if carried out on a highway or other publicly accessible land. Furthermore, it is established that serious disruption may amount to reprehensible conduct, so that articles 10 and 11 are not violated. The intimidation, obstruction or disruption to which section 68 applies is not criminalised unless it also involves a trespass and interference with A1P1. On this ground alone, any reliance upon articles 10 and 11 (assuming they are engaged) must be towards the periphery of those freedoms.
77. Fourthly, articles 10 and 11 do not bestow any "freedom of forum" to justify trespass on private land or publicly owned land which is not accessible by the public. There is no basis for supposing that section 68 has had the effect of preventing the effective exercise of freedoms of expression and assembly."
"Not every interference with an easement, such as a right of way, is actionable. There must be a substantial interference with the enjoyment of it. There is no actionable interference with a right of way if it can be substantially and practically exercised as conveniently after as before the occurrence of the alleged obstruction. Thus, the grant of a right of way in law in respect of every part of a defined area does not involve the proposition that the grantee can in fact object to anything done on any part of the area which would obstruct passage over that part. He can only object to such activities, including obstruction, as substantially interfere with the exercise of the defined right as for the time being is reasonably required by him".
"13 The second type of wrong which the Injunction sought to prevent was unlawful interference with the claimants' freedom to come and go to and from their land. An owner of land adjoining a public highway has a right of access to the highway and a person who interferes with this right commits the tort of private nuisance. In addition, it is a public nuisance to obstruct or hinder free passage along a public highway and an owner of land specially a?ected by such a nuisance can sue in respect of it, if the obstruction of the highway causes them inconvenience, delay or other damage which is substantial and appreciably greater in degree than any su?ered by the general public: see Clerk & Lindsell on Torts, 22nd ed (2017), para 20181."
"The law relating to the user of highways is in truth the law of give and take. Those who use them must in doing so have reasonable regard to the convenience and comfort of others, and must not themselves expect a degree of convenience and comfort only obtainable by disregarding that of other people. They must expect to be obstructed occasionally. It is the price they pay for the privilege of obstructing others."
"44. The law of nuisance and of public nuisance can be traced back for centuries, but the answers to the questions confronting the House are not to be found in the details of that history. What may, perhaps, be worth noticing is that in 2 Institutes 406 Coke adopts a threefold classification of nuisance: public or general, common, private or special. Common nuisances are public nuisances which, for some reason, are not prosecutable. See Ibbetson, A Historical Introduction to the Law of Obligations, p 106 nn 62 and 65. So for Coke, while all public nuisances are common, not all common nuisances are public. Later writers tend to elide the distinction between common and public nuisances but, throughout, it has remained an essential characteristic of a public nuisance that it affects the community, members of the public as a whole, rather than merely individuals. For that reason, the appropriate remedy is prosecution in the public interest or, in more recent times, a relator action brought by the Attorney General. A private individual can sue only if he can show that the public nuisance has caused him special injury over and above that suffered by the public in general. These procedural specialties derive from the effect of the public nuisance on the community, rather than the other way round.
(ii) The test for the grant of an injunction
"I would accept that the prima facie position is that an injunction should be granted, so the legal burden is on the defendant to show why it should not."
"In cases where the defendant has already infringed the claimant's rights, it will normally be appropriate to infer that the infringement will continue unless restrained: a defendant will not avoid an injunction merely by denying any intention of repeating wrongful acts."
"I do not regard the use of the word 'imminent' in those passages as negativing a power to grant a mandatory injunction in the present case: I take the use of the word to indicate that the injunction must not be granted prematurely.
In different cases differing phrases have been used in describing circumstances in which mandatory injunctions and quia timet injunctions will be granted. In truth it seems to me that the degree of probability of future injury is not an absolute standard: what is to be aimed at is justice between the parties, having regard to all the relevant circumstances."
"(3) Interim injunctive relief may only be granted if there is a sufficiently real and imminent risk of a tort being committed to justify [precautionary] relief."
(iii) The Canada Goose requirements
"(1) The 'persons unknown' defendants in the claim form are, by definition, people who have not been identified at the time of the commencement of the proceedings. If they are known and have been identified, they must be joined as individual defendants to the proceedings. The 'persons unknown' defendants must be people who have not been identified but are capable of being identified and served with the proceedings, if necessary by alternative service such as can reasonably be expected to bring the proceedings to their attention. In principle, such persons include both anonymous defendants who are identifiable at the time the proceedings commence but whose names are unknown and also Newcomers, that is to say people who in the future will join the protest and fall within the description of the 'persons unknown'.
(2) The 'persons unknown' must be defined in the originating process by reference to their conduct which is alleged to be unlawful.
(3) Interim injunctive relief may only be granted if there is a sufficiently real and imminent risk of a tort being committed to justify [precautionary] relief.
(4) As in the case of the originating process itself, the defendants subject to the interim injunction must be individually named if known and identified or, if not and described as 'persons unknown', must be capable of being identified and served with the order, if necessary by alternative service, the method of which must be set out in the order.
(5) The prohibited acts must correspond to the threatened tort. They may include lawful conduct if, and only to the extent that, there is no other proportionate means of protecting the claimant's rights.
(6) The terms of the injunction must be sufficiently clear and precise as to enable persons potentially affected to know what they must not do. The prohibited acts must not, therefore, be described in terms of a legal cause of action, such as trespass or harassment or nuisance. They may be defined by reference to the defendant's intention if that is strictly necessary to correspond to the threatened tort and done in non-technical language which a defendant is capable of understanding and the intention is capable of proof without undue complexity. It is better practice, however, to formulate the injunction without reference to intention if the prohibited tortious act can be described in ordinary language without doing so.
(7) The interim injunction should have clear geographical and temporal limits. It must be time limited because it is an interim and not a final injunction. We shall elaborate this point when addressing Canada Goose's application for a final injunction on its summary judgment application."
"41. Injunctions against unidentified defendants were considered by the Court of Appeal in the cases of Ineos Upstream Ltd v Persons Unknown [2019] 4 WLR 100 ["Ineos"] and Canada Goose Retail Ltd v Persons Unknown [2020] 1 WLR 2802 ['Canada Goose']. I summarise their combined affect as being:
(1) The Courts need to be cautious before making orders that will render future protests by unknown people a contempt of court [Ineos].
(2) The terms must be sufficiently clear and precise to enable persons potentially effected to know what they must not do [Ineos and Canada Goose].
(3) The prohibited acts must correspond to the threatened tort. They may include lawful conduct if, and only to the extent that, there is no other proportionate means of protecting the claimant's rights [Canada Goose]."
"89. A final injunction cannot be granted in a protester case against 'persons unknown' who are not parties at the date of the final order, that is to say newcomers who have not by that time committed the prohibited acts and so do not fall within the description of the 'persons unknown' and who have not been served with the claim form. There are some very limited circumstances, such as in Venables v News Group Newspapers Ltd [2001] Fam 430, in which a final injunction may be granted against the whole world. Protester actions, like the present proceedings, do not fall within that exceptional category. The usual principle, which applies in the present case, is that a final injunction operates only between the parties to the proceedings: Attorney General v Times Newspapers Ltd [1992] 1 AC 191, 224. That is consistent with the fundamental principle in Cameron (at para 17) that a person cannot be made subject to the jurisdiction of the court without having such notice of the proceedings as will enable him to be heard."
91. That does not mean to say that there is no scope for making 'persons unknown' subject to a final injunction. That is perfectly legitimate provided the persons unknown are confined to those within Lord Sumption's category 1 in Cameron, namely those anonymous defendants who are identifiable (for example, from CCTV or body cameras or otherwise) as having committed the relevant unlawful acts prior to the date of the final order and have been served (probably pursuant to an order for alternative service) prior to the date. The proposed final injunction which Canada Goose sought by way of summary judgment was not so limited. Nicklin J was correct (at para 159) to dismiss the summary judgment on that further ground (in addition to non-service of the proceedings). Similarly, Warby J was correct to take the same line in Birmingham City Council v Afsar [2019] EWHC 3217 (QB) at [132].
92. In written submissions following the conclusion of the oral hearing of the appeal Mr Bhose submitted that, if there is no power to make a final order against 'persons unknown', it must follow that, contrary to Ineos, there is no power to make an interim order either. We do not agree. An interim injunction is temporary relief intended to hold the position until trial. In a case like the present, the time between the interim relief and trial will enable the claimant to identify wrongdoers, either by name or as anonymous persons within Lord Sumption's category 1. Subject to any appeal, the trial determines the outcome of the litigation between the parties. Those parties include not only persons who have been joined as named parties but also 'persons unknown' who have breached the interim injunction and are identifiable albeit anonymous. The trial is between the parties to the proceedings. Once the 969trial has taken place and the rights of the parties have been determined, the litigation is at an end. There is nothing anomalous about that."
a. the Court undoubtedly has the power under s 37 of the SCA 1981 to grant final injunctions that bind non-parties to the proceedings ([71]).
b. the remedy can be fairly described as 'exceptional', albeit that formulation should not be used to lay down limitations on the Court's broad discretion. The categories in which such injunctions can be granted are not closed and they may be appropriate in protest cases ([120]);
c. there is no real distinction between interim and final injunctions in the context of injunctions granted against persons unknown ([89] and [93]). While the guidance regarding identification of persons unknown in Canada Goose was given in the context of an application for an interim injunction, the same principles apply in relation to the grant of final injunctions ([89]; see also [102] and [117];
d. as to the position of a non-party who behaves so as satisfy the definition of persons unknown only after the injunction has been granted (ie, a 'newcomer'), such a person becomes a party on knowingly committing an act that brings them within the description of persons unknown set out in the injunction: South Cambridgeshire District Council v Gammell [2006] 1 WLR 658, [32]. There is no need for a claimant to apply to join newcomers as defendants. There is 'no conceptual or legal prohibition on suing persons unknown who are not currently in existence but will come into existence when they commit the prohibited tort': Boyd, [30];
e. procedural protections available to ensure a permanent injunction against persons unknown is just and proportionate include the provision of a mechanism for review by the Court: 'Orders need to be kept under review. 'For as long as the court is concerned with the enforcement of an order, the action is not at end' ([89]); ' all persons unknown injunctions ought normally to have a fixed end point for review as the injunctions granted to these local authorities actually had in some cases' ([91]); 'It is good practice to provide for a periodic review, even when a final order is made' ([108]);
f. in the unauthorised encampment cases, the Court of Appeal has suggested that borough-wide injunctions should be limited to one year at a time before a review: Bromley London Borough Council v Persons Unknown [2020] PTSR 1043, [106].
(iv) Geographical scope of the order sought
" the geographical extent is considerable, since it covers 4,300 miles of roads, but this is in response to the unpredictable and itinerant nature of the Insulate Britain protests".
"87. It was also immaterial in this case that the Land formed only a small part of the HS2 project, that the costs incurred by the project came to 'only' £195,000 and the delay was 2½ days, whereas the project as a whole will take 20 years and cost billions. That argument could be repeated endlessly along the route of a major project such as this. It has no regard to the damage to the project and the public interest that would be caused by encouraging protesters to believe that with impunity they can wage a campaign of attrition. Indeed, we would go so far as to suggest that such an interpretation of a Human Rights instrument would bring it into disrespect."
(v) European Convention on Human Rights
"Article 10 Freedom of expression
1. Everyone has the right to freedom of expression. This right shall include freedom to hold opinions and to receive and impart information and ideas without interference by public authority and regardless of frontiers. This Article shall not prevent States from requiring the licensing of broadcasting, television or cinema enterprises.
2. The exercise of these freedoms, since it carries with it duties and responsibilities, may be subject to such formalities, conditions, restrictions or penalties as are prescribed by law and are necessary in a democratic society, in the interests of national security, territorial integrity or public safety, for the prevention of disorder or crime, for the protection of health or morals, for the protection of the reputation or rights of others, for preventing the disclosure of information received in confidence, or for maintaining the authority and impartiality of the judiciary.
Article 11 Freedom of assembly and association
1. Everyone has the right to freedom of peaceful assembly and to freedom of association with others, including the right to form and to join trade unions for the protection of his interests.
2. No restrictions shall be placed on the exercise of these rights other than such as are prescribed by law and are necessary in a democratic society in the interests of national security or public safety, for the prevention of disorder or crime, for the protection of health or morals or for the protection of the rights and freedoms of others. This Article shall not prevent the imposition of lawful restrictions on the exercise of these rights by members of the armed forces, of the police or of the administration of the State."
"Article 1 Protection of property
Every natural or legal person is entitled to the peaceful enjoyment of his possessions. No one shall be deprived of his possessions except in the public interest and subject to the conditions provided for by law and by the general principles of international law.
The preceding provisions shall not, however, in any way impair the right of a State to enforce such laws as it deems necessary to control the use of property in accordance with the general interest or to secure the payment of taxes or other contributions or penalties."
"84. The judge was not given the assistance she might have been with the result that a few important factors were overlooked. She did not address A1P1 and its significance. Articles 10 and 11 were not the only Convention rights involved. A1P1 pulled in the opposite direction to articles 10 and 11. At the heart of A1P1 and section 68 is protection of the owner and occupier of the Land against interference with the right to possession and to make use of that land for lawful activities without disruption or obstruction. Those lawful activities in this case had been authorised by Parliament through the 2017 Act after lengthy consideration of both the merits of the project and objections to it. The legislature has accepted that the HS2 project is in the national interest. One object of section 68 is to discourage disruption of the kind committed by the respondent, which, according to the will of Parliament, is against the public interest. The respondent (and others who hold similar views) have other methods available to them for protesting against the HS2 project which do not involve committing any offence under section 68, or indeed any offence. The Strasbourg Court has often observed that the Convention is concerned with the fair balance of competing rights. The rights enshrined in articles 10 and 11, long recognised by the Common Law, protect the expression of opinions, the right to persuade and protest and to convey strongly held views. They do not sanction a right to use guerrilla tactics endlessly to delay and increase the cost of an infrastructure project which has been subjected to the most detailed public scrutiny, including in Parliament."
"12. - Freedom of expression.
(1) This section applies if a court is considering whether to grant any relief which, if granted, might affect the exercise of the Convention right to freedom of expression.
(2) If the person against whom the application for relief is made ('the respondent') is neither present nor represented, no such relief is to be granted unless the court is satisfied -
(a) that the applicant has taken all practicable steps to notify the respondent; or
(b) that there are compelling reasons why the respondent should not be notified.
(3) No such relief is to be granted so as to restrain publication before trial unless the
court is satisfied that the applicant is likely to establish that publication should not be allowed."
"28. As is so often the case, there are rights that pull in different directions. It has also been authoritatively decided that there is no hierarchy as between the various rights in play. On the one hand, then, there are Mr Cuciurean's rights to freedom of expression and freedom of peaceful assembly contained in articles 10 (1) and 11 (1) of the ECHR. On the other, there are the claimants' rights to the peaceful enjoyment of their property. There was some debate about whether these were themselves convention rights (given that the Secretary of State for Transport is himself a public authority and cannot therefore be a "victim" for the purposes of the Convention, and HS2 Ltd may not be regarded as a 'non-governmental' organisation for that purpose). But whether or not they are convention rights, they are clearly legal rights (either proprietary or possessory) recognised by national law "
"22. In those circumstances, it seems to me that the approach laid down by Lord Steyn where both Article 8 and Article 10 ECHR rights are involved in Re S [2004] UKHL 47, [2005] 1 AC 593 at [17] is applicable in the present case. Here we are concerned with a conflict between the ODA's rights under Article 1 of the First Protocol, and the protesters' rights under Articles 10 and 11. The correct approach, therefore, is as follows. First, neither the ODA's rights under Article 1 of the First Protocol, nor the protesters' rights under Articles 10 and 11 have precedence over each other. Secondly, where the values under the respective Articles are in conflict, an intense focus on the comparative importance of the specific rights being claimed in the individual case is necessary. Thirdly, the justifications for interfering with or restricting each right must be taken into account. Finally, the proportionality test, or ultimate balancing test, must be applied to each."
" an executive non-departmental public body and statutory corporation established by section 3 of the London Olympic Games and Paralympic Games Act 2006 to be responsible for the planning and delivery of the Olympic Games 2012, including the development and building of Games venues."
"23. The protestors who have addressed me have made the point that they have sought to engage with the planning process in the normal way, and they have considered the possibility of seeking judicial review. As is so often the case, they say that they are handicapped by the lack of professional legal representation and the lack of finances to instruct lawyers of the calibre instructed by the ODA. They have also sought to engage normal democratic processes in order to make their points. It is because those processes have failed, as the protestors see it, that they have engaged in their protests.
24. That is all very understandable, but it does not, in my judgment, detract from the basic position which confronts the court. The ODA has rights as exclusive licensee of the land in question under Article 1 of the First Protocol to the Convention. As I observed in my judgment on 4 April 2012, the protestors' rights under Articles 10 and 11 are not unqualified rights. They must give way, where it is necessary and proportionate to do so, to the Convention rights of others, and specifically in the present case, of the ODA. The form of injunction sought by the ODA and which I granted on the last occasion does not, in and of itself, prevent or inhibit lawful and peaceful protest. It does not prevent or inhibit the protestors who wish to protest about the matters I have described from doing so in ways which do not interfere with the ODA's enjoyment of its rights in respect of the land
"38. This argument raises the question which the Judge identified at the start of his judgment, namely 'the limits to the right of lawful assembly and protest on the highway', using the word 'protest' in its broad sense of meaning the expression and dissemination of opinions. In that connection, as the Judge observed at [2012] EWHC 34 (QB), para 100, it is clear that, unless the law is that 'assembly on the public highway may be lawful, the right contained in article 11(1) of the Convention is denied' quoting Lord Irvine LC in DPP v Jones [1999] 2 AC 240, 259E. However, as the Judge also went on to say at [2012] EWHC 34 (QB), para 145:
'To camp on the highway as a means of protest was not held lawful in DPP v Jones. Limitations on the public right of assembly on the highway were noticed, both at common law and under Article 11 of the Convention (see Lord Irvine at p 259A-G, Lord Slynn at p 265C-G, Lord Hope of Craighead at p 277D-p 278D, and Lord Clyde at p 280F). In a passage of his speech that I have quoted above Lord Clyde expressed his view that the public's right did not extend to camping.'
39. As the Judge recognised, the answer to the question which he identified at the start of his judgment is inevitably fact-sensitive, and will normally depend on a number of factors. In our view, those factors include (but are not limited to) the extent to which the continuation of the protest would breach domestic law, the importance of the precise location to the protesters, the duration of the protest, the degree to which the protesters occupy the land, and the extent of the actual interference the protest causes to the rights of others, including the property rights of the owners of the land, and the rights of any members of the public.
40. The defendants argue that the importance of the issues with which the Occupy Movement is concerned is also of considerable relevance. That raises a potentially controversial point, because, as the Judge said at [2012] EWHC 34 (QB), para 155:
'[I]t is not for the court to venture views of its own on the substance of the protest itself, or to gauge how effective it has been in bringing the protestors' views to the fore. The Convention rights in play are neither strengthened nor weakened by a subjective response to the aims of the protest itself or by the level of support it seems to command. [T]he court cannot indeed, must not attempt to adjudicate on the merits of the protest. To do that would go against the very spirit of Articles 10 and 11 of the Convention. [T]he right to protest is the right to protest right or wrong, misguidedly or obviously correctly, for morally dubious aims or for aims that are wholly virtuous.'
41. Having said that, we accept that it can be appropriate to take into account the general character of the views whose expression the Convention is being invoked to protect. For instance, political and economic views are at the top end of the scale, and pornography and vapid tittle-tattle is towards the bottom. In this case, the Judge accepted that the topics of concern to the Occupy Movement were 'of very great political importance' - [2012] EWHC 34 (QB), para 155. In our view, that was something which could fairly be taken into account. However, it cannot be a factor which trumps all others, and indeed it is unlikely to be a particularly weighty factor: otherwise judges would find themselves according greater protection to views which they think important, or with which they agree. As the Strasbourg court said in Kuznetsov [2008] ECHR 1170, para 45:
'Any measures interfering with the freedom of assembly and expression other than in cases of incitement to violence or rejection of democratic principles however shocking and unacceptable certain views or words used may appear to the authorities do a disservice to democracy and often even endanger it. In a democratic society based on the rule of law, the ideas which challenge the existing order must be afforded a proper opportunity of expression through the exercise of the right of assembly as well as by other lawful means'.
The Judge took into account the fact that the defendants were expressing views on very important issues, views which many would see as being of considerable breadth, depth and relevance, and that the defendants strongly believed in the views they were expressing. Any further analysis of those views and issues would have been unhelpful, indeed inappropriate."
"43. The Court recalls that the applicants wished to draw attention of fellow citizens to their opposition to the plans of their locally elected representatives to develop playing ?elds and to deprive their children of green areas to play in. This was a topic of public interest and contributed to debate about the exercise of local government powers. However, while freedom of expression is an important right, it is not unlimited. Nor is it the only Convention right at stake. Regard must also be had to the property rights of the owner of the shopping centre under Art.1 of Protocol No.1.
47. That provision, notwithstanding the acknowledged importance of freedom of expression, does not bestow any freedom of forum for the exercise of that right. While it is true that demographic, social, economic and technological developments are changing the ways in which people move around and come into contact with each other, the Court is not persuaded that this requires the automatic creation of rights of entry to private property, or even, necessarily, to all publicly owned property (Government of?ces and ministries, for instance). Where however the bar on access to property has the effect of preventing any effective exercise of freedom of expression or it can be said that the essence of the right has been destroyed, the Court would not exclude that a positive obligation could arise for the State to protect the enjoyment of Convention rights by regulating property rights. The corporate town, where the entire municipality was controlled by a private body, might be an example."
a. Is what the defendant did in exercise of one of the rights in Articles 10 or 11?
b. If so, is there an interference by a public authority with that right?
c. If there is an interference, is it 'prescribed by law'?
d. If so, is the interference in pursuit of a legitimate aim as set out in paragraph (2) of Articles 10 and 11, for example the protection of the rights of others?
e. If so, is the interference 'necessary in a democratic society' to achieve that legitimate aim?
a. Is the aim sufficiently important to justify interference with a fundamental right?
b. Is there a rational connection between the means chosen and the aim in view?
c. Are there less restrictive alternative means available to achieve that aim?
d. Is there a fair balance between the rights of the individual and the general interest of the community, including the rights of others?
"57. Article 11(2) states that 'No restrictions shall be placed' except 'such as are prescribed by law and are necessary in a democratic society'. In Kudrevicius v Lithuania (2015) 62 EHRR 34, para 100 the European Court of Human Rights ("ECtHR") stated that 'The term 'restrictions' in article 11(2) must be interpreted as including both measures taken before or during a gathering and those, such as punitive measures, taken afterwards' so that it accepted at para 101 'that the applicants' conviction for their participation in the demonstrations at issue amounted to an interference with their right to freedom of peaceful assembly. Arrest, prosecution, conviction, and sentence are all "restrictions" within both articles."
"28. As is so often the case, there are rights that pull in different directions. It has also been authoritatively decided that there is no hierarchy as between the various rights in play. On the one hand, then, there are Mr Cuciurean's rights to freedom of expression and freedom of peaceful assembly contained in articles 10 (1) and 11 (1) of the ECHR. On the other, there are the claimants' rights to the peaceful enjoyment of their property. There was some debate about whether these were themselves convention rights (given that the Secretary of State for Transport is himself a public authority and cannot therefore be a "victim" for the purposes of the Convention, and HS2 Ltd may not be regarded as a 'non-governmental' organisation for that purpose). But whether or not they are convention rights, they are clearly legal rights (either proprietary or possessory) recognised by national law. Articles 10 (2) and 11 (2) of the ECHR qualify the rights created by articles 10 (1) and 11 (1) respectively. Article 10 (2) relevantly provides that:
"The exercise of these freedoms, since it carries with it duties and responsibilities, may be subject to such formalities, conditions, restrictions or penalties as are prescribed by law and are necessary in a democratic society, for the protection of health or morals, for the protection of the reputation or rights of others or for maintaining the authority of the judiciary."
29. Article 11 (2) relevantly provides:
"No restrictions shall be placed on the exercise of these rights other than such as are prescribed by law and are necessary in a democratic society for the protection of the rights and freedoms of others."
30. There is no doubt that the right to freedom of expression and the right of peaceful assembly both extend to protesters. In Hashman v United Kingdom (2000) EHHR 241, for example, the European Court of Human Rights held that the activity of hunt saboteurs in disrupting a hunt by the blowing of hunting horns fell within the ambit of article 10 of the ECHR. In City of London Corporation v Samede [2012] EWCA Civ 160, [2012] PTSR 1624 protesters who were part of the 'Occupy London' movement set up a protest camp in the churchyard of St Paul's Cathedral. This court held that their activities fell within the ambit of both article 10 and also article 11.
31. On the other hand, articles 10 and 11 do not entitle a protester to protest on any land of his choice. They do not, for example, entitle a protester to protest on private land: Appleby v United Kingdom (2003) 37 EHHR 38; Samede at [26]. The Divisional Court so held in another HS2 protest case, involving Mr Cuciurean himself who at that time was living in a tunnel for the purpose of disrupting HS2: DPP v Cuciurean [2022] EWHC 736 (Admin). In that case the court (Lord Burnett CJ and Holgate J) said at [45]:
"We conclude that there is no basis in the Strasbourg jurisprudence to support the respondent's proposition that the freedom of expression linked to the freedom of assembly and association includes a right to protest on privately owned land or upon publicly owned land from which the public are generally excluded. The Strasbourg Court has not made any statement to that effect. Instead, it has consistently said that articles 10 and 11 do not "bestow any freedom of forum" in the specific context of interference with property rights (see Appleby at [47] and [52]). There is no right of entry to private property or to any publicly owned property. The furthest that the Strasbourg Court has been prepared to go is that where a bar on access to property has the effect of preventing any effective exercise of rights under articles 10 and 11, or of destroying the essence of those rights, then it would not exclude the possibility of a State being obliged to protect them by regulating property rights."
32. Even the right to protest on a public highway has its limits. In DPP v Ziegler protesters were charged with obstructing the highway without lawful excuse. The Supreme Court held that whether there was a 'lawful excuse' depended on the proportionality of any interference with the protesters' rights under articles 10 and 11. Lords Hamblen and Stephens said at [70]:
'It is clear from those authorities that intentional action by protesters to disrupt by obstructing others enjoys the guarantees of articles 10 and 11, but both disruption and whether it is intentional are relevant factors in relation to an evaluation of proportionality. Accordingly, intentional action even with an effect that is more than de minimis does not automatically lead to the conclusion that any interference with the protesters' articles 10 and 11 rights is proportionate. Rather, there must be an assessment of the facts in each individual case to determine whether the interference with article 10 or article 11 rights was 'necessary in a democratic society'.'
33. But that proportionality exercise does not apply in a case in which the protest takes place on private land. In DPP v Cuciurean the court said:
"66. Likewise, Ziegler was only concerned with protests obstructing a highway where it is well-established that articles 10 and 11 are engaged. The Supreme Court had no need to consider, and did not address in their judgments, the issue of whether articles 10 and 11 are engaged where a person trespasses on private land, or on publicly owned land to which the public has no access. Accordingly, no consideration was given to the statement in Richardson at [3] or to cases such as Appleby.
67. For these reasons, it is impossible to read the judgments in Ziegler as deciding that there is a general principle in our criminal law that where a person is being tried for an offence which does engage articles 10 and 11, the prosecution, in addition to satisfying the ingredients of the offence, must also prove that a conviction would be a proportionate interference with those rights."
34. Where a land owner, such as the claimants in the present case, seeks an injunction restraining action which is carried on in the exercise of the right of freedom of expression or the right of peaceful assembly (or both) on private land, the time for the proportionality assessment (to the extent that it arises at all) is at the stage when the injunction is granted. Any 'chilling effect' will also be taken into account at that stage: see for example the decision of Mr John Male QC in UK Oil and Gas Investments plc v Persons Unknown [2018] EWHC 2252 (Ch), especially at [104] to [121], [158] to [167] and [176] (another case of protest predominantly on the highway); and the decision of Lavender J in National Highways Ltd v Heyatawin [2021] EWHC 3081 (QB) (also a case of protest on the highway). Once the injunction has been granted then, absent any appeal or application to vary, the balance between the competing rights has been struck: see National Highways Ltd v Heyatawin [2021] EWHC 3078 (QB) at [44]; National Highways Ltd v Buse [2021] EWHC 3404 (QB) at [30]."
(vi) Service
"50. Furthermore, it would have been open to Canada Goose at any time since the commencement of the proceedings to obtain an order for alternative service which would have a greater likelihood of bringing notice of the proceedings to the attention of protestors at the shop premises, such as by posting the order, the claim form and the particulars of claim on social media coverage to reach a wide audience of potential protestors and by attaching or otherwise exhibiting copies of the order and of the claim form at or nearby those premises. There is no reason why the court's power to dispense with service of the claim in exceptional circumstances should be used to overcome that failure."
"84. In the first two sentences of para 91, Canada Goose seeks to limit persons unknown subject to final injunctions to those "within Lord Sumption's category 1 in Cameron, namely those anonymous defendants who are identifiable (for example, from CCTV or body cameras or otherwise) as having committed the relevant unlawful acts prior to the date of the final order and have been served (probably pursuant to an order for alternative service) prior to [that] date". This holding ignores the fact that Canada Goose had already held that Lord Sumption's categories did not deal with newcomers, which were, of course, not relevant to the facts in Cameron.
85. The point in Cameron was that the proceedings had to be served so that, before enforcement, the defendant had knowledge of the order and could contest it. As already explained, Gammell held that persons unknown were served and made parties by violating an order of which they had knowledge. Accordingly, the first two sentences of para 91 are wrong and inconsistent both with the court's own reasoning in Canada Goose and with a proper understanding of Gammell, Ineos and Cameron.
91. The reasoning in para 92 is all based upon the supposed objection (raised in written submissions following the conclusion of the oral hearing of the appeal) to making a final order against persons unknown, because interim relief is temporary and intended to "enable the claimant to identify wrongdoers, either by name or as anonymous persons within Lord Sumption's category 1". Again, this reasoning ignores the holding in Gammell, Ineos and Canada Goose itself that an unknown and unidentified person knowingly violating an injunction makes themselves parties to the action. Where an injunction is granted, whether on an interim or a final basis for a fixed period, the court retains the right to supervise and enforce it, including bringing before it parties violating it and thereby making themselves parties to the action. That is envisaged specifically by point 7 of the guidelines in Canada Goose, which said expressly that a persons unknown injunction should have "clear geographical and temporal limits". It was suggested that it must be time limited because it was an interim and not a final injunction, but in fact all persons unknown injunctions ought 976normally to have a fixed end point for review as the injunctions granted to these local authorities actually had in some cases."
"50. Service on the named Defendants poses no difficulty but warning persons unknown of the order is far harder. In the first instance judgment in Barking and Dagenham v People Unknown [2021] EWHC 1201 (QB) Nicklin J [at 45-48, passages that were not the subject of criticism in the later appeal] stated that the Court should not grant an injunction against people unknown unless and until there was a satisfactory method of ensuring those who might breach its terms would be made aware of the order's existence.
51. In other cases, it has been possible to create a viable alternative method of service by posting notices at regular intervals around the area that is the subject of the injunctions; this has been done, for example, in injunctions granted recently by the Court in protests against oil companies. That solution, however, is completely impracticable when dealing with a vast road network. Ms Stacey QC suggested an enhanced list of websites and email addresses associated with IB [Insulate Britain] and other groups with overlapping aims, and that the solution could also be that protestors accused of contempt of court for breaching the injunction could raise their ignorance of its terms as a defence. I do not find either solution adequate. There is no way of knowing that groups of people deciding to join a protest in many months' time would necessarily be familiar with any particular website. Nor would it be right to permit people completely unaware of an injunction to be caught up with the stress, cost and worry of being accused of contempt of court before they would get to the stage of proceedings where they could try to prove their innocence.
52. In the absence of any practical and effective method to warn future participants about the existence of the injunction, I adopt the formula used by Lavender J [in National Highways Limited v Persons Unknown and others [2021] EWHC 3081 (QB)], that those who had not been served would not be bound by the terms of the injunction and the fact the order had been sent to the IB website did not constitute service. The effect of this will be that anyone arrested can be served and, thus, will risk imprisonment if they thereafter breach the terms of the injunction."
Merits
"6. The purpose of the order, if granted, is simply to allow the First and Second Claimant to get on with building a large piece of linear infrastructure. Its purpose is not to inhibit normal activities generally, nor to inhibit the expression of whatever views may be held. The fundamental disagreement with those who appear to defend these proceedings is as to what constitutes lawful protest. The Claimants say that they are faced with deliberate interference with their land and work with a view to bringing the HS2 Scheme to a halt.
7. That is not lawful, and it is not lawful protest."
(i) Trespass and nuisance
"10. Those engaged in protest action opposed to the HS2 Scheme are made up of a broad cross-section of society, including concerned local residents, committed environmentalists, academics and also numerous multi-cause transient protestors whom have been resident at a number of protest camps associated with a number of different 'causes'. Groups such as Extinction Rebellion (often known as 'XR') often garner much of the mainstream media attention and widely publicise their actions. They often only travel into an area for a short period (specific 'days of action' or 'weeks of action'), however once present they are able to execute comprehensive and highly disruptive direct action campaigns, whipping up an almost religious fervour amongst those present. Their campaigns often include direct action training, logistical and welfare support and complimentary media submissions, guaranteeing national media exposure. Such incidents have a significant impact on the HS2 Scheme but make up only a proportion of overall direct action protest against the HS2 Scheme, which occurs on an almost daily basis.
11. By way of explanation of a term that will be found in the evidence exhibited to this statement, activists often seek to anonymise themselves during direct action by referring to themselves and each other as "Bradley". Activists also often go
by pseudonyms, in part to avoid revealing their real identities. A number of the Defendants' pseudonyms are provided in the schedule of Named Defendants and those working in security on the HS2 Scheme are very familiar with the individuals involved and the pseudonyms they use.
12. On a day to day basis direct action protest is orchestrated and conducted by both choate groups dedicated to disruption of the HS2 Scheme (such as HS2 Rebellion and Stop HS2) and inchoate groups of individuals who can comprise local activists and more seasoned 'core' activists with experience of conducting direct action campaigns against numerous "causes". The aims of this type of action are made very explicitly clear by those engaged in it, as can be seen in the exhibits to this statement. It is less about expressing the activists' views about the HS2 Scheme and more about causing direct and repeated harm to the HS2 Scheme in the form of delays to works, sabotage of works, damage to equipment, psychological and physical injury to those working on the HS2 Scheme and financial cost, with the overall aim of 'stopping' or 'cancelling' the HS2 Scheme.
13. In general, the Claimants and their contractors and sub-contractors have been subject to a near constant level of disruption to works on the HS2 Scheme, including trespass on and obstruction of access to the HS2 Land, since October 2017. The Defendants have clearly stated - both to contractors and via
mainstream and social media - their intention to significantly slow down or stop work on the HS2 Scheme because they are opposed to it. They have trespassed on HS2 Land on multiple occasions and have issued encouragement via social media to others to come and trespass on HS2 Land. Their activities have impeded the First Claimant's staff, contractors and sub-contractors going about their lawful business on the HS2 Land and hampered the work on the HS2 Scheme, causing delays and extremely significant costs to the taxpayer and creating an unreasonably difficult and stressful working environment for those who work on the HS2 Land."
"At page 1 [of Ex RJ1] is a graphic illustration of the number of incidents experienced by the Claimants on Phase One of the HS2 Scheme that have impacted on operational activity and the costs to the Claimant of dealing with those incidents. That shows a total of 1007 incidents that have had an impact on operational activity between the last quarter of 2017 and December 2021. Our incident reporting systems have improved over time and refined since we first began experiencing incidents of direct action protest in October 2017 and it is therefore considered that the total number of incidents shown within our overall reporting is likely fewer than the true total.
15. The illustration also shows the costs incurred in dealing with the incidents. These costs comprise the costs of the First Claimant's security; contractor security and other contractor costs such as damage and repairs; and prolongation costs (delays
to the programme) and show that a total of £121.62 million has been incurred in dealing with direct action protest up to the end of December 2021. The HS2 Scheme is a publicly funded project and accordingly the costs incurred are a cost to the tax-payer and come from the public purse. The illustration at page 2 shows the amount of the total costs that are attributable to security provision."
"Put simply, activists enter onto HS2 Land without consent. The objective of such action is to delay and disrupt works on the HS2 Scheme. All forms of trespass cause disruption to the HS2 Scheme and have financial implications for the Claimants. Some of the more extreme forms of trespass, such as tunnelling (described in detail in the sections on Euston Square Gardens and Small Dean below) cause significant damage and health and safety risks and the losses suffered by the Claimants via the costs of removal and programme delay run into the millions of pounds. In entering onto work sites, the activists create a significant health and safety hazard, thus staff are compelled to stop work in order to ensure the safety of staff and those trespassing (see, for example, the social media posts at pages 38 to 39 about trespassers at the HS2 Scheme Capper's Lane compound in Lichfield where there have been repeated incursions onto an active site where heavy plant and machinery and large vehicles are in operation, forcing works to cease for safety and security reasons. A video taken by a trespasser during an incursion on 16 March 2022 and uploaded to social media is at Video (7). Worryingly, such actions are often committed by activists in ignorance of the site operations and or equipment functionality, which could potentially result in severe unintended consequences. For example, heavy plant being operated upon the worksite may not afford the operator clear sight of trespassers at ground level. Safety is at the heart of the Claimants' activities on the HS2 Scheme and staff, contractors and sub-contractors working on the HS2 Land are provided with intensive training and inductions and appropriate personal protective equipment. The First Claimant's staff, contractors and sub-contractors will always prioritise safety thus compounding the trespassers' objective of causing disruption and delay. Much of the HS2 Land is or will be construction sites and even in the early phases of survey and clearance works there are multiple hazards that present a risk to those entering onto the land without permission. The Claimants have very serious concerns that if incidents of trespass and obstruction of access continue, there is a high likelihood that activists will be seriously injured."
"21.2 Interviews with the BBC on 19.05.2020 and posted on the Wendover Active Resistance Camp Facebook page. D5 (Report Map at page 32) was interviewed and said: 'The longevity is that we will defend this woodland as long as we can. If they cut this woodland down, there will still be activists and community members and protectors on the ground. We're not just going to let HS2 build here free will. As long as HS2 are here and they continue in the vein they have been doing, I think you'll find there will be legal resistance, there'll be on the ground resistance and there will be community resistance.' In the same interview, another individual said: 'We are holding it to account as they go along which is causing delays, but also those delays mean that more and more people can come into action. In a way, the more we can get our protectors to help us to stall it, to hold it back now, the more we can try and use that leverage with how out of control it is, how much it is costing the economy, to try to bring it to account and get it halted.' A copy of the video is at Video 1."
(ii) Whether there is a real and imminent risk of continued unlawfulness so as to justify an anticipatory injunction
"20. There are a number of reasons for the Claimants' belief that unlawful action against the HS2 Scheme will continue if unchecked by the Court. A large number of threats have been made by a number of the Defendants and general threats by groups opposed to the HS2 Scheme to continue direct action against the HS2 Scheme until the HS2 Scheme is "stopped". These threats have been made on a near daily basis - often numerous times a day - since 2017 and have been made in person (at activist meetings and to staff and contractors); to mainstream media; and across social media. They are so numerous that it has only been possible to put a small selection of examples into evidence in this application to illustrate the position to the Court. I have also included maps for some individuals who have made threats against the HS2 Scheme and who have repeatedly engaged in unlawful activity that show where those individuals have been reported by security teams along the HS2 Scheme route ("Report Map"). These maps clearly demonstrate that a number of the Defendants have engaged in unlawful activity at multiple locations along the route and the Claimants reasonably fear that they will continue to target the length of the route unless restrained by the Court."
"79. 'Two arrested. Still need people here. Need to hold them up at every opportunity.'
'No, Lainey, these trees are alongside the road so they needed a road closure to do so. They can't have another road closure for 20 days. Meanwhile they have to worry BIG time about being targeted by extinction rebellion and, what's more, they're going to see more from us at other places on the route VERY soon. Tremble HS2, tremble.
"We have no route open to us but to protest. And however much we have sat in camp waving flags, and waving at passersby tooting their support, that was never and will never be the protest that gets our voices heard. We are ordinary people fighting with absolute integrity for truth that is simple and stark. We are ordinary people fighting an overwhelming vast government project. But we will be heard. We must be heard."
81. I fully accept that this expresses the passion with which the Fourth Defendant opposes the HS2 scheme and while they may not indicate that the Fourth Defendant will personally breach any order or be guilty of any future trespass, I think there is, I frankly find, a faintly sinister ring to these comments which in light of all that has gone before causes me to agree with Mr. Roscoe and the Claimants that there is a distinct risk of further objectionable activity should an injunction not be granted."
a. Interview with The Guardian on 13 February 2021 given by D27 after he was removed from the tunnels dug and occupied by activists under HS2 Land at Euston Square Gardens, in which he said: 'As you can see from the recent Highbury Corner eviction, this tunnel is just a start. There are countless people I know who will do what it takes to stop HS2.' In the same article he also said: 'I can't divulge any of my future plans for tactical reasons, but I'm nowhere near finished with protesting.'
b. In March 2021 D32 obstructed the First Claimant's works at Wormwood Scrubs and put a call out on Twitter on 24 March 2021 asking for support to prevent HS2 route-wide. He also suggested targeting the First Claimant's supply chain.
c. On 23 February 2022 D6 stated that if an injunction was granted over one of the gates providing entrance to Balfour Beatty land, they, 'will just hit all the other gates' and 'if they do get this injunction then we can carry on this game and we can hit every HS2, every Balfour Beatty gate' ([21.12]).
d. D6 on 24 February 2022 stated if the Cash's Pit camp is evicted, 'we'll just move on. And we'll just do it again and again and again' ([21.13]).
e. As set out in [21.14] on 10 March 2022 D17, D18, D19, D31, D63 and a number of persons unknown spent the morning trespassing on HS2 Land adjacent to Cash's Pit Land, where works were being carried out for a gas diversion by Cadent Gas and land on which archaeological works for the HS2 Scheme were taking place. This incident is described in detail at [78] of Jordan 1. In a video posted on Facebook after the morning's incidents, D17 said:
"Hey everyone! So, just bringing you a final update from down in Swynnerton. Today has been a really or this morning today - has been a really successful one. We've blocked the gates for several hours. We had the team block the gates down at the main compound that we usually block and we had yeah, we've had people running around a field over here and grabbing stuff and getting on grabbers and diggers (or attempting to), but in the meantime, completely slowing down all the works. There are still people blocking the gates down here as you can see and we've still got loads of security about. You can see there's two juicy diggers over there, just waiting to be surfed and there's plenty of opportunities disrupt and another one over there as well. It's a huge, huge area so it takes a lot of them to, kind of, keep us all under control, particularly when we spread out. So yeah. If you wanna get involved with direct action in the very near future, then please get in touch with us at Bluebell or send me a message and we'll let you know where we are, where we're gonna be, what we're gonna be doing and how you can get involved and stuff like that. Loads of different roles, you've not just, people don't have to run around fields and get arrested or be jumping on top of stuff or anything like that, there's lots of gate blocking to do and stuff as well, yeah so you don't necessarily have to be arrested to cause a lot of disruption down here and we all work together to cause maximum disruption. So yeah, that's that. Keep checking in to Bluebell's page, go on the events and you'll see that we've got loads of stuff going on, and as I say pretty much most days we're doing direct action now down in Swynnerton, there's loads going on at the camp, so come and get involved and get in touch with us and we'll let you know what's happening the next day. Ok, lots of love. Share this video, let's get it out there and let's keep fucking up HS2's day and causing as much disruption and cost as possible. Coming to land near you."
Hence, comments Mr Jordan, D17 was here making explicit threats to continue to trespass on HS2 Land and to try to climb onto vehicles and machinery and encourages others to engage in similar unlawful activity.
f. Further detail is given of recent and future likely activities around Cash's Pit and other HS2 Land in the Swynnerton area at Jordan 1, [72]-[79] and Dilcock 4, [33], et seq.
"The Claimant must establish that there is a risk of actual damage occurring on the HS2 Land subject to the injunction that is imminent and real. This is not borne out on the evidence. In relation to land where there is no currently scheduled HS2 works to be carried out imminently there is no risk of disruptive activity on the land and therefore no basis for a precautionary injunction."
"87. The interim injunctions which are sought are mostly, but not exclusively, claimed on a quia timet basis. There are respects in which the Claimants can argue that there have already been interferences with their rights and so the injunctions are to prevent repetitions of those interferences and are not therefore claimed on a quia timet basis. Examples of interferences in the past are said to be acts on trespass on Site 1, theft of, and criminal damage to, seismic testing equipment and various acts of harassment. However, the greater part of the relief is claimed on the basis that the Claimants reasonably apprehend the commission of unlawful acts in the future and they wish to have the protection of orders from the court at this stage to prevent those acts being committed. Accordingly, I will approach the present applications as if they are made solely on the quia timet basis.
88. The general test to be applied by a court faced with an application for a quia timet injunction at trial is quite clear. The court must be satisfied that the risk of an infringement of the claimant's rights causing loss and damage is both imminent and real. The position was described in London Borough of Islington v Elliott [2012] EWCA Civ 56, per Patten LJ at 29, as follows:
'29 The court has an undoubted jurisdiction to grant injunctive relief on a quia timet basis when that is necessary in order to prevent a threatened or apprehended act of nuisance. But because this kind of relief ordinarily involves an interference with the rights and property of the defendant and may (as in this case) take a mandatory form requiring positive action and expenditure, the practice of the court has necessarily been to proceed with caution and to require to be satisfied that the risk of actual damage occurring is both imminent and real. That is particularly so when, as in this case, the injunction sought is a permanent injunction at trial rather than an interlocutory order granted on American Cyanamid principles having regard to the balance of convenience. A permanent injunction can only be granted if the claimant has proved at the trial that there will be an actual infringement of his rights unless the injunction is granted."
89. In London Borough of Islington v Elliott, the court considered a number of earlier authorities. The authorities concerned claims to quia timet injunctions at the trial of the action. In such cases, particularly where the injunction claimed is a mandatory injunction, the court acts with caution in view of the possibility that the contemplated unlawful act, or the contemplated damage from it, might not occur and a mandatory order, or the full extent of the mandatory order, might not be necessary. Even where the injunction claimed is a prohibitory injunction, it is not enough for the claimant to say that the injunction only restrains the defendant from doing something which he is not entitled to do and causes him no harm: see Paul (KS) (Printing Machinery) v Southern Instruments (Communications) [1964] RPC 118 at 122; there must still be a real risk of the unlawful act being committed. As to whether the contemplated harm is 'imminent', this word is used in the sense that the circumstances must be such that the remedy sought is not premature: see Hooper v Rogers [1975] Ch 43 at 49-50. Further, there is the general consideration that 'Preventing justice excelleth punishing justice': see Graigola Merthyr Co Ltd v Swansea Corporation [1928] Ch 235 at 242, quoting the Second Institute of Sir Edward Coke at page 299.
90. In the present case, the Claimants are applying for quia timet injunctions on an interim basis, rather than at trial. The passage quoted above from London Borough of Islington v Elliott indicated that different considerations might arise on an interim application. The passage might be read as suggesting that it might be easier to obtain a quia timet injunction on an interim basis. That might be so in a case where the court applies the test in American Cyanamid where all that has to be shown is a serious issue to be tried and then the court considers the adequacy of damages and the balance of justice. Conversely, on an interim application, the court is concerned to deal with the position prior to a trial and at a time when it does not know who will be held to be ultimately right as to the underlying dispute. That might lead the court to be less ready to grant quia timet relief particularly of a mandatory character on an interim basis.
91. I consider that the correct approach to a claim to a quia timet injunction on an interim basis is, normally, to apply the test in American Cyanamid. The parts of the test dealing with the adequacy of damages and the balance of justice, applied to the relevant time period, will deal with most if not all cases where there is argument about whether a claimant needs the protection of the court. However, in the present case, I do have to apply section 12(3) of the Human Rights Act 1998 and ask what order the court is likely to make at a trial of the claim.
92. I have dealt with the question of quia timet relief in a little detail because it was the subject of extensive argument. However, that should not obscure the fact that the decision in this case as to the grant of quia timet relief on an interim basis is not an unduly difficult one.
93. What is the situation here? On the assumption that the evidence does not yet show that protestors have sought to subject Ineos to their direct action protests, I consider that the evidence makes it plain that (in the absence of injunctions) the protestors will seek to do so. The protestors have taken direct action against other fracking operators and there is no reason why they would not include Ineos in the future. The only reason that other operators have been the subject of protests in the past and Ineos has not been (if it has not been) is that Ineos is a more recent entrant into the industry. There is no reason to think that (absent injunctions) Ineos will be treated any differently in the future from the way in which the other fracking operators have been treated in the past. I therefore consider that the risk of the infringement of Ineos' rights is real.
94. The next question is whether the risk of infringement of Ineos' rights is imminent. I have described earlier the sites where Ineos wish to carry out seismic testing and drilling. It seems likely that drilling will not commence in a matter of weeks or even months. However, there have been acts of trespass in other cases on land intended to be used for fracking even before planning permission for fracking had been granted and fracking had begun. I consider that the risk of trespass on Ineos' land by protestors is sufficiently imminent to justify appropriate intervention by the court. Further, there have already been extensive protests outside the depots of third party contractors providing services to fracking operators. One of those contractors is P R Marriott. Ineos uses and intends to use the services of P R Marriott. Accordingly, absent injunctions, there is a continuing risk of obstruction of the highway outside P R Marriott's depot and when that contractor is engaged to provide services to Ineos, those obstructions will harm Ineos.
95. To hold that the risk of an infringement of the rights of Ineos is not imminent with the result that the court did not intervene with injunctions at this stage would leave Ineos in a position where the time at which the protestors might take action against it would be left to the free choice of the protestors without Ineos having any protection from an order of the court. I do not consider that Ineos should be told to wait until it suffers harm from unlawful actions and then react at that time. This particularly applies to the injunctions to restrain trespass on land. If protestors were to set up a protest camp on Ineos land, the evidence shows that it will take a considerable amount of time before Ineos will be able to recover possession of such land. In addition, Ineos has stated in its evidence on its application that it wishes to have clarity as to what is permitted by way of protest and what is not. That seems to me to be a reasonable request and if the court is able to give that clarity that would seem to be helpful to the Claimants and it ought to have been considered to be helpful by the Defendants. A clear injunction would allow the protestors to know what is permitted and what is not."
(iii) Whether an injunction should be granted against the named Defendants
"42. The Claimants have named as Defendants to this application individuals known to the Claimants (sometimes only by pseudonyms) the following categories of individuals:
42.1 Individuals identified as believed to be in occupation of the Cash's Pit Land whether permanently or from time to time (D5 to D20, D22, D31 and D63);
42.2 the named defendants in the Harvil Road Injunction (D28; D32 to D34; and D36 to D59);
42.3 The named defendants in the Cubbington and Crackley Injunction (D32 to D35); and
42.4 Individuals whose participation in incidents is described in the evidence in support of this claim and the injunction application and not otherwise named in one of the above categories.
43. It is, of course open to other individuals who wish to defend the proceedings and/or the application for an injunction to seek to be joined as named defendants. Further, if any of the individuals identified wish to be removed as defendants, the Claimants will agree to their removal upon the giving of an undertaking to the Court in the terms of the injunction sought. Specifically, in the case of D32, who (as described in Jordan 1) has already given a wide-ranging undertaking not to interfere with the HS2 Scheme, the Claimants have only named him because he is a named defendant to the proceedings for both pre-existing injunctions. If D32 wishes to provide his consent to the application made in these proceedings, in view of the undertaking he has already given, the Claimants will consent to him being removed as a named defendant.
44. This statement is also given in support of the First Claimant's possession claim in respect of the Cash's Pit Land and which the Cash's Pit Defendants have dubbed: "Bluebell Wood". The unauthorised encampment and trespass on the Cash's Pit Land is the latest in a series of unauthorised encampments established and occupied by various of the Defendants on HS2 Land (more details of which are set out in Jordan 1).
45. The possession proceedings concern a wooded area of land and a section of roadside verge, which is shown coloured orange on the plan at Annex A of the Particulars of Claim ("Plan A"). The HS2 Scheme railway line will pass through the Cash's Pit Land, which is required for Phase 2a purposes and is within the Phase 2a Act limits.
46. The First Claimant is entitled to possession of the Cash's Pit Land having exercised its powers pursuant to section 13 and Schedule 15 of the Phase 2a Act. Copies of the notices served pursuant to paragraph 4(1) of Schedule 15 of the Phase 2a Act are at pages 30 to 97 of JAD3. For the avoidance of doubt, these notices were also served on the Cash's Pit Land addressed to "the unknown occupiers". Notices requiring the Defendants to vacate the Cash's Pit Land and warning that Court proceedings may be commenced in the event that they did not vacate were also served on the Cash's Pit Land. A statement from the process server that effected service of the notices addressed to "the unknown occupiers" and the Notice to Vacate is at pages 98 to 112 of JAD3 and copies of the temporary possession notice addressed to the occupiers of the Cash's Pit Land and the notice to Vacate are exhibited to that statement."
a. The actions complained of are justifiable because the HS2 Scheme causes environmental damage. That is not a matter for me. Parliament approved HS2.
b. The order would interfere with protesters' rights under Articles 10 and 11. I deal with the Convention later.
c. Lawful protest would be prevented. As I have made clear, it would not and the draft order so provides.
d. The order would restrict rights to use the public highway and public rights of way. These are specifically carved out in the order (paragraph 4).
e. Concern about those who occupy or use HS2 Land pursuant to a lease or licence with the First Claimant. That has now been addressed in the Revised Land Plans.
f. Complaints about HS2's security guards. I have dealt with that.
(iv) Whether there are reasons to grant the order against persons unknown
(v) Scope
"3. With immediate effect until 23:59hrs on 31 May 2023 unless varied, discharged or extended by further order, the Defendants and each of them are forbidden from doing the following:
a. entering or remaining upon the HS2 Land;
b. obstructing or otherwise interfering with the free movement of vehicles, equipment or persons accessing or egressing the HS2 Land; or
c. interfering with any fence or gate on or at the perimeter of the HS2 Land.
4. Nothing in paragraph 3 of this Order:
a. Shall prevent any person from exercising their rights over any open public right of way over the HS2 Land.
b. Shall affect any private rights of access over the HS2 Land.
c. Shall prevent any person from exercising their lawful rights over any public highway.
d. Shall extend to any person holding a lawful freehold or leasehold interest in land over which the Claimants have taken temporary possession.
e. Shall extend to any interest in land held by statutory undertakers.
5. For the purposes of paragraph 3(b) prohibited acts of obstruction and interference shall include (but not be limited to):
a. standing, kneeling, sitting or lying or otherwise remaining present on the carriageway when any vehicle is attempting to turn into the HS2 Land or attempting to turn out of the HS2 Land in a manner which impedes the free passage of the vehicle;
b. digging, erecting any structure or otherwise placing or leaving any object or thing on the carriageway which may slow or impede the safe and uninterrupted passage of vehicles or persons onto or from the HS2 Land;
c. affixing or attaching their person to the surface of the carriageway where it may slow or impede the safe and uninterrupted passage of vehicles onto or from the HS2 Land;
d. affixing any other object to the HS2 Land which may delay or impede the free passage of any vehicle or person to or from the HS2 Land;
e. climbing on to or affixing any object or person to any vehicle in the vicinity of the HS2 Land; and
f. slow walking in front of vehicles in the vicinity of the HS2 Land.
6. For the purposes of paragraph 3(c) prohibited acts of interference shall include (but not be limited to):
a. cutting, damaging, moving, climbing on or over, digging beneath, or removing any items affixed to, any temporary or permanent fencing or gate on or on the perimeter of the HS2 Land;
b. the prohibition includes carrying out the aforementioned acts in respect of the fences and gates; and
c. interference with a gate includes drilling the lock, gluing the lock or any other activities which may prevent the use of the gate."
"3. With immediate effect until 23:59hrs on 31 May 2023 unless varied, discharged or extended by further order, the Defendants and each of them are forbidden from doing the following:
b. deliberately obstructing or otherwise interfering with the free movement of vehicles, equipment or persons accessing or egressing the HS2 Land; or
(vi) Convention rights
Would what the defendants are proposing to do be exercise of one of the rights in Articles 10 or 11?
If so, would there be an interference by a public authority with those rights?
If there is an interference, is it 'prescribed by law'?
If so, would the interference be in pursuit of a legitimate aim as set out in paragraph (2) of Articles 10 and 11, for example the protection of the rights of others?
If so, is the interference 'necessary in a democratic society' to achieve that legitimate aim? This involves considering the following: Is the aim sufficiently important to justify interference with a fundamental right? Is there a rational connection between the means chosen and the aim in view? Are there less restrictive alternative means available to achieve that aim? Is there a fair balance between the rights of the individual and the general interest of the community, including the rights of others ?
"Determination of the proportionality of an interference with ECHR rights is a fact-specific enquiry which requires the evaluation of the circumstances in the individual case."
"39. As the judge recognised, the answer to the question which he identified at the start of his judgment [the limits to the right of lawful assembly and protest on the highway] is inevitably fact sensitive, and will normally depend on a number of factors. In our view, those factors include (but are not limited to) the extent to which the continuation of the protest would breach domestic law, the importance of the precise location to the protesters, the duration of the protest, the degree to which the protesters occupy the land, and the extent of the actual interference the protest causes to the rights of others, including the property rights of the owners of the land, and the rights of any members of the public.
40. The defendants argue that the importance of the issues with which the Occupy Movement is concerned is also of considerable relevance. That raises a potentially controversial point, because as the judge said, at para 155: 'it is not for the court to venture views of its own on the substance of the protest itself, or to gauge how effective it has been in bringing the protestors' views to the fore. The Convention rights in play are neither strengthened nor weakened by a subjective response to the aims of the protest itself or by the level of support it seems to command the court cannotindeed, must notattempt to adjudicate on the merits of the protest. To do that would go against the very spirit of articles 10 and 11 of the Convention the right to protest is the right to protest right or wrong, misguidedly or obviously correctly, for morally dubious aims or for aims that are wholly virtuous.'
41. Having said that, we accept that it can be appropriate to take into account the general character of the views whose expression the Convention is being invoked to protect. For instance, political and economic views are at the top end of the scale, and pornography and vapid tittle-tattle is towards the bottom. In this case the judge accepted that the topics of concern to the Occupy Movement were 'of very great political importance': para 155. In our view, that was something which could fairly be taken into account. However, it cannot be a factor which trumps all others, and indeed it is unlikely to be a particularly weighty factor: otherwise judges would find themselves according greater protection to views which they think important, or with which they agree. As the Strasbourg court said in Kuznetsov v Russia, para 45: 'any measures interfering with the freedom of assembly and expression other than in cases of incitement to violence or rejection of democratic principles - however shocking and unacceptable certain views or words used may appear to the authoritiesdo a disservice to democracy and often even endanger it. In a democratic society based on the rule of law, the ideas which challenge the existing order must be afforded a proper opportunity of expression through the exercise of the right of assembly as well as by other lawful means ' The judge took into account the fact that the defendants were expressing views on very important issues, views which many would see as being of considerable breadth, depth and relevance, and that the defendants strongly believed in the views they were expressing. Any further analysis of those views and issues would have been unhelpful, indeed inappropriate."
a. I am satisfied that it is more likely than not that the Claimants would establish at trial that the Defendants' actions constitute trespass and nuisance and that they will continue to commit them unless restrained. There is an abundance of evidence that leads to the conclusion that there is a real and imminent risk of the tortious behaviour continuing in the way it has done in recent years across the HS2 Land. I am satisfied the Claimants would obtain a final injunction.
b. Damages would not be an adequate remedy for the Claimants. They have given the usual undertakings as to damages.
c. The balance of convenience strongly favours the making of the injunction.
(vii) Service
"Pursuant to CPR r. 6.27 and r. 81.4 as regards service of the Claimants' Application dated 25 March 2022:
a. The Court is satisfied that at the date of the certificates of service, good and sufficient service of the Application has been effected on the named defendants and each of them and personal service is dispensed with subject to the Claimants' carrying out the following additional methods within 14 days of the date of this order:
i. advertising the existence of these proceedings in the Times and Guardian newspapers, and in particular advertising the web address of the HS2 Proceedings website.
ii. where permission is granted by the relevant authority, by placing an advertisement and/or a hard copy of the papers in the proceedings within 14 libraries approximately every 10 miles along the route of the HS2 Scheme. In the alternative, if permission is not granted, the Claimants shall use reasonable
endeavours to place advertisements on local parish notice boards in the same approximate location.
iii. making social media posts on the HS2 twitter and Facebook pages advertising the existence of these proceedings and the web address of the HS2 Proceedings
website.
b. Compliance with 2 (a)(i), (ii) and (iii) above will be good and sufficient service on "persons unknown"'
"7. The Court will provide sealed copies of this Order to the Claimant's solicitors for service (whose details are set out below).
8. Pursuant to CPR r.6.27 and r.81.4:
a. The Claimant shall serve this Order upon the Cash's Pit Defendants by affixing 6 copies of this Order in prominent positions on the perimeter of the Cash's Pit Land.
b. Further, the Claimant shall serve this Order upon the Second, Third and Fourth Defendants by:
i. Affixing 6 copies in prominent positions on the perimeter each of the Cash's Pit Land (which may be the same copies identified in paragraph 8(a) above), the Harvil Road Land and the Cubbington and Crackley Land.
ii. Advertising the existence of this Order in the Times and Guardian newspapers, and in particular advertising the web address of the HS2 Proceedings website, and direct link to this Order.
iii. Where permission is granted by the relevant authority, by placing an advertisement and/or a hard copy of the Order within 14 libraries approximately every 10 miles along the route of the HS2 Scheme. In the alternative, if permission is not granted, the Claimants shall use reasonable endeavours to place advertisements on local parish council notice boards in the same approximate locations.
iv. Publishing social media posts on the HS2 twitter and Facebook platforms advertising the existence of this Order and providing a link to the HS2 Proceedings website.
c. Service of this Order on Named Defendants may be effected by personal service where practicable and/or posting a copy of this Order through the letterbox of each Named Defendant (or leaving in a separate mailbox), with a notice drawing the recipient's attention to the fact the package contains a court order. If the premises do not have a letterbox, or mailbox, a package containing this Order may be affixed to or left at the front door or other prominent feature marked with a notice drawing the recipient's attention to the fact that the package contains a court order and should be read urgently. The notices shall be given in prominent lettering in the form set out in Annex B. It is open to any Defendant to contact the Claimants to identify an alternative place for service and, if they do so, it is not necessary for a notice or packages to be affixed to or left at the front door or other prominent feature.
d. The Claimants shall further advertise the existence of this Order in a prominent location on the HS2 Proceedings website, together with a link to download an electronic copy of this Order.
e. The Claimants shall email a copy of this Order to solicitors for D6 and any other party who has as at the date hereof provided an email address to the Claimants to the email address: HS2Injunction@governmentlegal.gov.uk
9. Service in accordance with paragraph 8 above shall:
a. be verified by certificates of service to be filed with Court;
b. be deemed effective as at the date of the certificates of service; and
c. be good and sufficient service of this Order on the Defendants and each of them and the need for personal service be dispensed with.
10. Although not expressed as a mandatory obligation due to the transient nature of the task, the Claimants will seek to maintain copies of this Order on areas of HS2 Land in proximity to potential Defendants, such as on the gates of construction compounds or areas of the HS2 Land known to be targeted by objectors to the HS2 Scheme.
11. Further, without prejudice to paragraph 9, while this Order is in force, the Claimants shall take all reasonably practicable steps to effect personal service of the Order upon any Defendant of whom they become aware is, or has been on, the HS2 Land without consent and shall verify any such service with further certificates of service (where possible if persons unknown can be identified) to be filed with Court."
Final points
Conclusion
(1) PERSONS UNKNOWN ENTERING OR REMAINING WITHOUT THE CONSENT OF THE CLAIMANTS ON, IN OR UNDER LAND KNOWN AS LAND AT CASH'S PIT, STAFFORDSHIRE SHOWN COLOURED ORANGE ON PLAN A ANNEXED TO THE ORDER DATED 11 APRIL 2022 ("THE CASH'S PIT LAND")
(2) PERSONS UNKNOWN ENTERING OR REMAINING WITHOUT THE CONSENT OF THE CLAIMANTS ON, IN OR UNDER LAND ACQUIRED OR HELD BY THE CLAIMANTS IN CONNECTION WITH THE HIGH SPEED TWO RAILWAY SCHEME SHOWN COLOURED PINK, AND GREEN ON THE HS2 LAND PLANS AT https://www.gov.uk/government/publications/hs2-route-wide-injunction-
proceedings ("THE HS2 LAND") WITH THE EFFECT OF DAMAGING AND/OR DELAYING AND/OR HINDERING THE CLAIMANTS, THEIR AGENTS, SERVANTS, CONTRACTORS, SUB-CONTRACTORS, GROUP COMPANIES, LICENSEES, INVITEES AND/OR EMPLOYEES
(3) PERSONS UNKNOWN OBSTRUCTING AND/OR INTERFERING WITH ACCESS TO AND/OR EGRESS FROM THE HS2 LAND IN CONNECTION WITH THE HS2 SCHEME WITH OR WITHOUT VEHICLES, MATERIALS AND EQUIPMENT, WITH THE EFFECT OF DAMAGING AND/OR DELAYING AND/OR HINDERING THE CLAIMANTS, THEIR AGENTS, SERVANTS, CONTRACTORS, SUB-CONTRACTORS, GROUP COMPANIES, LICENSEES, INVITEES AND/OR EMPLOYEES WITHOUT THE CONSENT OF THE CLAIMANTS
(4) PERSONS UNKNOWN CUTTING, DAMAGING, MOVING, CLIMBING ON OR OVER, DIGGING BENEATH OR REMOVING ANY ITEMS AFFIXED TO ANY TEMPORARY OR PERMANENT FENCING OR GATES ON OR AT THE PERIMETER OF THE HS2 LAND, OR DAMAGING, APPLYING ANY SUBSTANCE TO OR INTERFERING WITH ANY LOCK OR ANY GATE AT THE PERIMETER OF THE HS2 LAND WITHOUT THE CONSENT OF THE CLAIMANTS
Name |
Received and reference in the papers |
Summary | |
D6 - James Knaggs |
SkA for initial hearing (05.04.22) |
Definition of persons unknown is overly broad, contrary to Canada Goose. Service provisions inadequate. No foundation for relief based on trespass because not demonstrated immediate right to possession, and seeking to restrain lawful protest on highway. No imminent threat. Scope of order is large. Terms impose blanket disproportionate prohibitions on demonstrations on the highway. Chilling effect of the order. | |
Defence (17.05.22) |
C required to establish cause of action in trespass & nuisance across all of HS2 Land and existence of the power to take action to prevent such. No admission of legal rights of the C represented in maps. Denied that Cash's Pit land is illustrative of wider issues re entirety of HS2 Land. Denied there is a real and imminent risk of trespass & nuisance re HS2 Land to justify injunction. Impact and effect of injunction extends beyond the limited remit sought by HS2. Proportionality. Denial that D6 conduct re Cash's Pit has constituted trespass or public/private nuisance. | ||
D7 - Leah Oldfield |
Defence (16.05.22) [D/3] |
D7s actions do not step beyond legal rights to protest, evidence does not show unlawful activity. Right to protest. Complaints about HS2 Scheme, complaints about conduct of HS2 security contractors. Asks to be removed from injunction on basis of lack of evidence | |
D8 - Tepcat Greycat |
Email (16.05.22) [D/4] |
Complaint that D8 was not identified properly in injunction application papers and that she would like name removed from schedule of Ds. | |
D9 - Hazel Ball |
Email (13.05.22) [D/7] |
Asks for name to be removed. Queries why she has been named in injunction application papers. Has only visited Cash's Pit twice, with no intention to return. Never visited Harvil Road. | |
D10 - IC Turner |
Response (16.05.22) [D/8] |
Inappropriateness of D10's inclusion as a named D (peaceful protester, no involvement with campaign this year, given proximity to route the injunction would restrict freedom of movement within vicinity). Inappropriateness of proceedings (abuse of process because of right to protest). Complaints about HS2 Scheme. | |
D11 - Tony Carne |
Submission (13.05.22) [D/10] |
Denies having ever been an occupier of Cash's Pit Land. Asks to be removed as named D. | |
D24 - Daniel Hooper |
Email (16.05.22) [D/12] |
Asks for name to be removed because already subject to wide ranging undertaking. Asks for assurance of the same by 20th May. | |
D29 - Jessica Maddison |
Defence (16.05.22) [D/14] |
Injunction would restrict ability to access Euston station and prevent access to GP surgery and hospital. Restriction on use of footpaths, would result from being named in injunction. Would lead to her being street homeless. Lack of evidence for naming within injunction. Criminal matters re lock on protests were discontinued before trial. Complaints about HS2 contractor conduct. | |
D35 - Terry Sandison |
Email (07.04.22) [D/15] |
Complaint about lack of time to prepare for initial hearing. | |
Application for more time - N244 (04.04.22) |
Says he wishes to challenge HS2 on various points of working practices, queries why he is on paperwork for court but feels he hasn't received proof of claims they have to use his conduct to secure injunction. Asks for a month to consider evidence and challenge the injunction and claims against himself. | ||
D36 - Mark Kier |
Large volume of material submitted (c.3k pages) [D/36/179-D/37/2916] |
Mr Kier sets out four grounds: (1) the area of land subject to the Claim is incorrect in a number of respects; (2) the protest activity is proportionate and valid and necessary to stop crimes being committed by HS2; (3) the allegations of violence and intimidation are false. The violence and intimidation emanates from HS2; (4) the project is harmful and should not have been consented. | |
D39 - Iain Oliver |
Response to application (16.05.22) [D/16] |
Complaints about alleged water pollution, wildlife crimes and theft and intimidation on HS2's behalf. Considers that injunction is wrong and a gagging order. | |
D46 - Wiktoria Zieniuk |
Not included in bundle |
Brief email provided querying why she was included. | |
D47 - Tom Dalton |
Email (05.04.22) [D/17] |
Complaint about damage caused to door from gaffatape of papers to front door. Says he is happy to promise not to violate or contest injunction as is not involved in anti HS2 campaign and hasn't been for years. (Undertaking now signed) | |
D54 - Hayley Pitwell |
Email (04.04.22) [D/19] |
Request for adjournment and extension of time to submit arguments, for a hearing and for name to be removed as D. Queries whether injunction will require her to take massive diversions when driving to Wales. Complaint about incident of action at Harvil Road that led to D56 being named in this application - dispute over factual matters (esp Jordan 1 para 29.1.10). Complaint that HS2 security contractor broke coronavirus act and D54 is suing for damages. N.b. no subsequent representations received. | |
D55 - Jacob Harwood |
17.05.22 [D/20] |
Complaint about injunction restricting ability to use Euston station, public rights of way, canals etc. Complaint that there is lack of evidence against D55 so he should be removed as named D. | |
D56 - Elizbeth Farbrother |
11.05.22 [D/23] |
Correspondence and undertaking subsequently signed. | |
D62 - Leanne Swateridge |
Email (14.05.22) [D/23] |
Complaint about reliance on crane incident at Euston. Complaints about conduct of HS2 contractors and merits of HS2 Scheme. | |
Joe Rukin |
First witness statement (04.04.22) [D/24] |
Says Stop HS2 organisation is no longer operative in practice, so emailing their address does not constitute service, and the organisation is not coordinating or organising illegal activities. Failure of service of injunction application. Scope of injunction is disproportionately wide, and D2 definition would cover hundreds of thousands of people on a daily basis. Complaints about GDPR re service of papers for this application. Concerns about injunction restricting normal use of highways, PRoW, and private rights over land where it is held by HS2 temporarily but the original landowner has been permitted to continue to access and use it. Would criminalise people walking into their back garden. | |
Second witness statement (26.04.22) [D/25] |
Complains there is no active protest at Cubbington and Crackley now since clearance of natural habitats. Complains Dilcock 2 [8.11] is wrong about service of proceedings at Cubbington & Crackley Land. | ||
Maren Strandevold |
Email (04.04.22) [D/26] |
Complaints about notice given for temporary possession land. Concern about temporary possession land and that there needs to be clear and unequivocal permission for those permitted to use their land subject to temporary possession to be able to continue to do so. Concerns the scope of the draft order is disproportionate. | |
Sally Brooks |
Statement (04.04.22) [D/27] |
Complaints about merits of HS2 Scheme, alleged wildlife crimes, and the need for members of the public to monitor the same | |
Caroline Thompson-Smith |
Email (04.04.22) [D/28] |
Objects to evidence of her, and that the injunction would prevent rights to freedom of expression, arts 10-11. Worry about adverse costs means she fears to engage with process. | |
Deborah Mallender |
Statement (04.04.22) [D/29] |
Complaints about merits of HS2 Scheme and conduct of HS2 Ltd and security contractors. Complaint that content of injunction has not been provided to all relevant persons. | |
Haydn Chick |
Email (05.04.22) [D/30] |
Email attachment of statement which will not open, plus article by Lord Berkeley, plus news story | |
Swynnerton Estates |
Email (05.05.22) [D/31] |
Email re whether Cash's Pit objectors had licence to occupy. | |
Steve and Ros Colclough |
Letter (04.05.22) [D/32] |
Consider themselves "persons unknown" by living nearby and using nearby PRoW. Complaint that HS2 should have written to everyone on the route informing them. | |
Timothy Chantler |
Letter (14.05.22) [D/33] |
Complaints about conduct of HS2 security contractors (NET re treatment of other protesters). Objection to the injunction on the basis of right to protest etc. | |
Chiltern Society |
Letter (16.05.22) [D/34] |
Concerns about public access to PRoW re HS2 Land. Concern of no adequate method to ensure a person using a footpath across HS2 Land would be aware of potential infringement. Concern that maintenance work on footpaths often requires accessing adjacent land which may constitute infringement. | |
Nicola Woodhouse |
Email (16.05.22) [D/35] |
Not lawful or practical to stop anyone accessing all land acquired by HS2. Maps provided are impossible to decipher, with land ownership not well defined. Excessive geographical scope. Notification of all relevant landowners is impossible. Residents of houses purchased by HS2 cannot move freely around their own homes, and members of the public cannot visit them. | |
The below statements are contained within the submission of D36 (Mark Keir) | |||
Val Saunders "statement in support of the defence against the Claim QB-2022-BHM-00044" |
Undated [D/37/2493] (bundle D, vol F) |
Merits of Scheme. Complaints about HS2 contractor conduct and alleged wildlife crimes. Protest important to hold HS2 to account. | |
Leo Smith "Witness statement" "statement in support of the defence..." |
14.05.22 [D/37/2509-2520] (bundle D, vol F) |
Merits of scheme/process of consultation. Necessity of protest to hold Scheme to account. HS2 use of NDAs re CPO. Photographs of rubbish left behind by protestors is misleading since they have been forcibly evicted. Protest mostly peaceful. Complaints about HS2 security contractor conduct. Alleged wildlife crimes. Negative impact on communities. | |
Misc statement - "statement in support of the defence..." |
Undated [D/37/2674-2691] (bundle D, vol G) |
Complaints about merits of scheme and conduct of HS2 security contractors against protesters. | |
Misc statement - "Seven arguments against HS2" |
Undated 2692-2697 |
Merits of scheme. Argues for scrapping. | |
Brenda Bateman - "statement in support of the defence..." |
Undated 2698-2699 |
Confusion caused by what HS2 previously said about which footpaths would be closed. Complaints about ecological impacts of Scheme, and other impacts. Complaints about use of CPO process. Right to peaceful protest should be upheld: injunction would curtail this. | |
Cllr Carolyne Culver - "statement in support of the Defence..." |
Undated 2700-2701 |
Complaints about conduct of Jones Hill Wood eviction. Issues over perceived delayed compensation for CPO. Need for nature protectors and right to protest. | |
Denise Baker - "Defence against the claim..." |
Undated 2702-2703 |
Photojournalist - concerns that injunction would limit abilities to report fairly on issues related to environment impact of HS2. Risk of arrest of journalists. Detrimental to accountability of project and govt. Concerns over conduct of HS2 security contractors. | |
Gary Welch - "Statement in support of the Defence..." |
Undated 2704 |
Criticism of merits of Scheme, and environmental impacts. Concern over closure of public foot paths recently. | |
Sally Brooks - "Statement in support of the Defence..." |
Undated 2705-2710 |
Alleged wildlife crimes. Need for members of public to monitor HS2 activities. Injunction would prevent this. | |
Lord Tony Berkeley - "Witness Statement"; "Statement in support of the Defence..." |
12.05.22 2711-2714 |
Doubts HS2 has sufficient land to complete the project without further Parliamentary authorisation. Doubts HS2's land ownership position generally given alteration to maps included with injunction application. Injunction is an abuse of rights, and an abuse of the laws of the country and HS2 Bill which brought it into being. | |
Jessica Upton - "statement in support of the Defence..." |
Undated 2715-2716 |
Criticism of merits of scheme, ecological impact etc. Concern that public need to be able to hold HS2 to account without being criminalised for it. | |
Kevin Hand - "statement in support of the Defence..." |
9.05.22 2717-2718 |
Ecologist who provides environmental training courses to activists and protesters against HS2. Emphasises importance of public/protesters being able to monitor works taking place to prevent alleged wildlife crimes. | |
Mark Browning - "Statement in support of the Defence..." |
Undated 2719 |
Partners brother is renting a property HS2 has compulsorily purchased near Hopwas in Tamworth area. Concern that the management of the pasture will be criminalised if injunction granted. Therefore requests exemption from the injunction. | |
Talia Woodin - "statement in support of the Defence..." |
Undated 2724-2731 |
Photographer and filmmaker. Concerns about alleged wildlife crimes and assaults on activists. Injunction would disable right to protest. | |
Victoria Tindall - "statement in support of the Defence..." |
Undated 2735 |
Complaint about Buckinghamshire HS2 security van monitoring ramblers near HS2 site. Concerns about privacy. | |
Mr & Mrs Phil Wall - "Statement" |
Undated 2737-2740 |
Complaints about conduct of HS2 contractors regarding works in Buckinghamshire. Complaints about CPO/blight compensation issues for their property. | |
Susan Arnott - "In support of the Defence..." |
15.5.22 2742 |
Merits of scheme. Protests are therefore valid. | |
Ann Hayward - Letter regarding RWI |
6.05.22 2743-2744 |
Resident of Wendover. Difficulty of reading HS2 maps, so difficult to know whether trespassing or not. Complaints about HS2 contractor conduct. RWI too broad, and service would be difficult and may be insufficient meaning everyone in vicinity of HS2 works could be at risk of arrest - risk of criminalising communities. People need to know whether injunction exists and where it is, but HS2 maps are not well defined. Would be difficult to apply the order, abide by it and police it. Important for independent ecologists to monitor HS2 works. | |
Annie Thurgarland - "statement in support of the Defence" |
15.05.22 2745-2746 |
Criticism of merits of scheme, especially re environmental impact. Need for public to monitor works re ecology and alleged wildlife crimes. People have a right to peaceful direct action. | |
Anonymous |
16.05.22 2747-2751 |
Anonymity because concerned about intimidation. RWI would have direct impact on tenancy contractual agreement for home, as it lies within the Act Boundary and is owned by HS2. Would be entirely at the mercy of HS2 and subcontractors to interpret the contractual agreement as they chose. Concerned that they were not notified of the RWI given the enormity of impact on residents who are lessees of HS2. Vague term un-named defendants could extend to anyone deemed as trespassing on land part of homes and gardens. Concern therefore that all land within boundary could become subject to constant surveillance, undermining right to privacy. No clarity on terms of injunction regarding tenants and when they would and would not be trespassing. Complaints about ecological impact of Scheme. Complaints about conduct of HS2 security contractors. | |
Anonymous (near Cash's Pit occupant) |
Undated 2752-2753 |
Complaints about impact of scheme on ability to use local area for recreation. Concerns that injunction would curtail protest right. Complaints about HS2 security contractors. Complaint that HS2 did not provide local residents with details of the injunction or proceedings. | |
Anonymous - "statement in support of the Defence..." |
Undated 2754-2755 |
Criticism of merits of Scheme, argument re right to protest. | |