KING'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT
Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
Technip Saudi Arabia Limited |
Claimant |
|
- and - |
||
The Mediterranean and Gulf Cooperative Insurance and Reinsurance Company |
Defendant |
____________________
James Brocklebank KC and Douglas Grant (instructed by Clyde & Co LLP) for the Defendant
Hearing dates: 15th – 18th and 23rd – 24th May 2023
____________________
Crown Copyright ©
Index
Section | Para. Number |
A: Introduction | 1 |
B: The chronology of events | 16 |
The parties and the contractual relationships | 16 |
The Allision | 26 |
Events subsequent to the Allision | 30 |
C: The Policy terms | 47 |
D: Did Technip have a legal liability to KJO | 50 |
D1: The relevant contractual terms | 50 |
D2: The parties' arguments | 54 |
Technip's argument | 54 |
Medgulf's argument | 63 |
D3: Discussion | 70 |
E: Absence of consent to settlement | 94 |
The issue | 94 |
The parties' arguments | 96 |
Discussion | 104 |
F: The Existing Property Endorsement and other exclusions | 119 |
F1: Introduction and the parties' arguments | 119 |
Introduction | 119 |
The Existing Property Endorsement: Medgulf's argument | 123 |
The Existing Property Endorsement: Technip's argument | 130 |
F2: Discussion | 144 |
Limb 1 | 147 |
Limb 3 | 184 |
F3: The Watercraft exclusion | 185 |
G: Quantum issues | 187 |
G1: Introduction to the issues | 188 |
G2: Legal principles | 198 |
G3: The expert evidence | 211 |
G4: Safeguarding costs | 213 |
G5: Repair costs: Agreed Scope or Reduced Scope | 226 |
G6: Reduced Scope – repair costs | 235 |
G7: Miscellaneous costs | 246 |
Conclusion | 253 |
MR JUSTICE JACOBS:
A: Introduction
(1) Section B provides some further detail as to the background facts, including the contractual arrangements between KJO and Technip. The latter are particularly important in the light of Medgulf's argument that Technip had no legal liability to KJO in respect of the consequences of the Allision.
(2) Section C sets out the relevant terms of the Policy.
(3) Section D addresses the question of whether Technip had any legal liability to KJO at all.
(4) Section E addresses Medgulf's argument based upon Technip's failure to obtain its consent to the settlement with KJO.
(5) Section F addresses the claim under Section II of the Policy, and in particular the Existing Property Endorsement and Watercraft exclusion relied upon by Medgulf.
(6) Section G addresses the issues concerning the reasonableness of the repair costs and other quantum issues.
B: The chronology of events
The parties and the contractual relationships
"WORK
The CONTRACTOR shall, in accordance with the terms and conditions set out in this CONTRACT, attached schedules and drawings, standards, specifications and other documents referred to in the schedules or in any of the referenced documents perform the WORK required for the Project entitled KHAFJI CRUDE RELATED OFFSHORE PROJECTS, which includes the following individual Projects:
i. INSTALLATION OF SECOND SUBMARINE POWER CABLE (SSPC)
ii. INSTALLATION OF POWER DISTRIBUTION PLATFORMS FOR ESP PHASE-II (PDP-4&5)
iii. CONSTRUCTION OF CONTROL AND LIVING PLATFORM (CLP)
iv. INSTALLATION OF INTEGRATED WELL JACKETS 6&7 (IWJ-6&7)"
The Allision
"No live subsea lines around the subject jacket since KJO operation is shutdown. All gas and oil lines are mothballed with minimum preservation pressure"
Accordingly, the Allision did not affect ongoing operations in any way.
Events subsequent to the Allision
(1) KJO owed Technip around US$ 20m in unpaid invoices;
(2) Technip held around US$ 24m of contractual performance bonds, such that (as Mr Cortas explained) Technip was exposed to a loss by reason of a drawdown under the bonds and was incurring costs for maintaining the bonds over an extended period of time;
(3) Retention monies of around US$20m would only be returned to Technip on final acceptance of the Project; and
(4) Technip and KJO were in dispute about various claims and change orders that Technip had submitted in respect of disruption, delays and additions to the Project, which together amounted to US$ 229m.
"General: safe access to wellheads and well suspension/closure and reactivation operations, including Preparation works such as flowlines, topside piping purging process, well suspension, Xmas tree protection, reinstating wells, in addition to the functionality of the J-tube internals (water injection flexible pipe)"
(1) Technip would pay KJO US$ 33m, which amount was allocated US$ 25m in respect of the Allision (clause 1) and US$ 8m in respect of punch and warranty items (clause 2); and KJO would pay Technip US$ 33m in respect of additional claims and change orders (clause 3). Those sums cancelled each other out and were set off against each other (clause 4);
(2) KJO would release all unpaid invoices (clause 5(a)). According to a presentation made by Technip in 2016, these amounted to around US$20m;
(3) KJO would pay Technip an additional US$ 4,751,342.81 for weather stand-by compensation (clause 5(b));
(4) Retention monies held by KJO would be released (clause 5(e)). According to the same presentation, these amounted to around US$ 19.2m;
(5) Contractual performance bonds would be released (clause 5(f)). These amounted to around US$ 24.7m;
(6) Technip would perform Home Office Detail Engineering for the Platform repairs at no additional cost (clause 5(c)(vii)).
C: The Policy terms
INSURANCE SCHEDULE
INSURED:
PRINCIPAL INSUREDS:
i. Technip Saudi Arabia and/or Aramco Gulf Operations Company (AGOC) and/or Kuwait Gulf Oil Company (KGOC) and/or associated and/or subsidiary companies and/or Joint Venturers and or co-venturers as they may now or subsequently exist.
ii. Parent and/or subsidiary and/or affiliated and/or associated and/or inter-related companies of the above as they are now or may hereafter be constituted and their directors, officers and employees while acting in their capacities as such.
Other Insureds:
iii. Project managers
iv. Any other company, firm, person or party (including contractors and/or sub-contractors and/or manufacturers and/or suppliers) with whom the Insured(s) named in i, ii, iii, and iv have entered into written contract(s) directly in connection with the Project.
INTEREST/POLICY LIMIT:
All works and operations connected with the Khafji Crude Related Offshore Projects (KCROP), including but not limited to: project studies, engineering, design, project management, procurement, fabrication, construction, load out, loading/unloading, transportation by land, sea or air (including call(s) at port(s) or place(s) as may be required), storage, towage, mating, installation, pipelaying, burying, trenching, hook-up, connection and/or tie-in operations, trials, testing and commissioning, existence, initial operations and maintenance all as more fully detailed in the Information Section contained herein.
…
Section II – Liability
Third Party Legal Liability and/or Contractual Liability as Welcar 2001, including Damage to Existing Property.
Section II – Liability
USD 125,000,000 any one occurrence combined single limit in respect of both third party liabilities and damage to existing property.
Deductibles / Excess (100%)
USD 250,000 for any one occurrence in respect of third party liabilities.
USD 500,000 any one occurrence in respect of damage to existing property.
OFFSHORE CONSTRUCTION PROJECT POLICY
Subject to the terms, conditions and exclusions herein, this Policy provides coverage for certain physical damage and liabilities incurred by the Insureds. Section I Physical Damage and Section II Liability are distinct sections, with the exception that the Scope of Insurance and General Terms and Conditions below shall apply to Section I and Section II.
SCOPE OF INSURANCE
(Applicable to…Section II)
Subject to the insuring agreements, applicable terms, conditions and exclusions, this insurance covers the following activities undertaken in the course of the project identified in Item 2 of the Declarations (hereinafter, the Project), provided such activities are within the insured values. Covered activities include but not limited to: design, engineering, management, procurement and supply of all materials, fabrication, construction, load-out, transit/tows, installation and existence during hook-up, testing and commissioning and all works associated with the Project, being platform modifications all as more fully described in the Project Information.
The Policy shall be deemed to be a separate insurance in respect of each Principal Insured hereunder without increasing Underwriters limits of liability.
1. INSUREDS
PRINCIPAL INSUREDS:
i. Technip Saudi Arabia and/or Aramco Gulf Operations Company (AGOC) and/or Kuwait Gulf Oil Company (KGOC) and/or associated and/or subsidiary companies and/or Joint Venturers and/or co-venturers as they may now or subsequently exist.
ii. Parent and/or subsidiary and/or affiliated and/or associated and/or inter-related companies of the above as they are now or may hereafter be constituted and their directors, officers and employees while acting in their capacities as such.
Other Insureds:
iii. Project managers.
iv. Any other company, firm, person or party (including contractors and/or sub-contractors and/or manufacturers and/or suppliers) with whom the Insured(s) named in i, ii, iii and iv have entered into written contract(s) directly in connection with the Project.
GENERAL TERMS AND CONDITIONS
(Applicable to…Section II)
15. CANCELLATION
The first named Principal Insured set out in Item 1 of the Declarations may cancel the Policy on behalf of all Insured(s) at any time prior to the first Occurrence that gives rise or may give rise to a covered loss.
SECTION II – LIABILITY
INSURING AGREEMENT
1. COVERAGE
Underwriters agree, subject to the limitations, terms, conditions and exclusions herein, to indemnify the Insured(s) for Ultimate Net Loss which the Insured(s) shall be obligated to pay by reason of
i. liability imposed upon the Insured(s) by law, and/or
ii. Express Contractual Liability,
for Bodily Injury or Property Damage caused by an Occurrence, provided always that the Occurrence takes place during the Project Period and arises out of the activities described in the Scope of Insurance section herein.
TERMS AND CONDITIONS
(Section II only)
1. NOTICE TO UNDERWRITERS
In the event of an Occurrence, the Insured(s) shall provide written notice to Underwriters as soon as in practicable stating the following:
(1) the specific Occurrence; and
(2) the damages which may result or has resulted from the Occurrence; and
(3) the circumstance by which the Insured(s) first became aware of the Occurrence.
In respect of Claims to which Exclusion 15 applies, the Insured(s) shall provide such notice within the timing requirements set forth in that exclusion.
4. CROSS LIABILITIES
In the event of one insured incurring liability to any other of the Insured(s), this Policy shall cover the Insured against whom the claim is or may be made in the same manner as if separate policies had been issued to each Insured. However, the inclusion of more than one Insured hereunder shall not operate to increase the Limit of Liability.
In no case shall this Policy provide coverage for any physical loss or physical damage to or defects discovered in the property insured
Coverage in respect of Other Insured(s) does not apply to actual or alleged liability to other contractors and/or vendors and/or suppliers for consequential loss, loss of profit or business interruption.
DEFINITIONS
(Section II only)
2. "CLAIMS EXPENSES" shall mean reasonable legal costs and other expenses incurred by or on behalf of the Insured(s) in the defence of any covered claim including attorney's fees and disbursements, investigation, adjustment, appraisal, appeal costs and expenses and pre- and post- judgement interest, excluding salaries, wages and benefits of the Insured's employees and the Insured's administrative expenses.
3. "DAMAGES" shall mean compensatory damages, monetary judgments, awards, and/or compromise settlements entered with Underwriters' consent, but shall not include fines or penalties, punitive damages, exemplary damages, equitable relief, injunctive relief or any additional damages resulting from the multiplication of compensatory damages.
4. "EXPRESS CONTRACTUAL LIABILITY" means liability that the Insured has expressly assumed prior to any Occurrence covered by this Policy in:
a. any written contract; or
b. any oral contract reduced to writing within 7 days after the contract is orally agreed
7. "ULTIMATE NET LOSS" shall mean the total sum the Insured is obligated to pay as Damages, and shall include Claims Expenses in respect of claims covered under this Policy.
EXCLUSIONS
(Section II only)
The insurance afforded by this policy does not apply to actual or alleged liability:
5. arising out of the use or operation of watercraft, whether owned, time chartered, bareboat chartered or operated by any Insured, or for which any Insured may be responsible other than as declared hereto:
11.for loss of or damage to any well or hole.
i. which is being drilled or worked over by or on behalf of the Insured, or
ii. which is in the care, custody or control of the Insured, or
iii. in connection with which the Insured has provided services, equipment or materials:
13. for loss of or damage to any drilling tool, pipe, collar, casing, bit, pump, drilling or well servicing machinery, or any other equipment while it is below the surface of the earth in any well or hole:
i. which is being drilled or worked over by or on behalf of the Insured, or
ii. which is in the care, custody or control of the Insured, or
iii. in connection with which the Insured has provided services, equipment or materials.
15. for Bodily Injury or Property Damage directly or indirectly caused by or arising out of seepage, pollution or contamination however caused whenever or wherever happening:
This exclusion shall not apply when the Insured has established all of the following conditions:
a. the seepage, pollution or contamination was caused by an event;
b. the event first commenced on an identified specific date during the Policy Period set out in Item 3 of the Declarations;
c. the event was first discovered by the Insured within 14 days of such commencement;
d. Underwriters received written notification of the event from the Insured within 60 days of the Insured's first discovery of the event; and
e. the event did not result from the Insured's intentional violation of any statute, rule, ordinance or regulation.
Even if the above conditions a) to e) are satisfied, this policy does not apply to any actual or alleged liability:
i. to evaluate, monitor, control, remove, nullify or clean up seeping, polluting or contaminating substances to the extent such liability arises solely from any obligations imposed by any statute, rule, ordinance, regulation or imposed by contract;
ii. to abate or investigate any threat of seepage onto or pollution or contamination of the property of a third party;
iii. for seepage, pollution or contamination of property which is or was, at any time, owned, leased, rented or occupied by any Insured, or which is or was at any time in the care, custody or control of any Insured (including the soil, minerals, water or any other substance on, in or under such owned, leased, rented or occupied property or property in such care, custody or control);
iv. arising directly out of the transportation by the Insured of oil (other than fuel or other substances used in furtherance of the Insured's operations) or other similar substances by watercraft; or
v. arising directly or indirectly from seepage, pollution or contamination which is intended from the standpoint of the Insured or any other person or organisation acting for or on behalf of the insured;
17. for loss of, damage to, or loss of use of property directly or indirectly resulting from subsidence caused by sub-surface operations of the Insured.
21. for damage to or loss of or loss of use of:
i. property owned or occupied by or rented or leased to the Insured;
ii. property used by the Insured; or
iii. property in the care, custody or control of the Insured or over which the Insured is for any purpose exercising physical control:
for the costs of removal, recovery, repair, alteration or replacement of any product (or any part thereof) which fails to perform the function for which it was manufactured, designed, sold, supplied, installed, repaired or altered by or on behalf of the Insured in the normal course of the Insured's operations.
ENDORSEMENTS
ENDORSEMENT 1
WATERCRAFT EXCLUSION Endorsement
Subject always to the terms and conditions of the Policy hereunder, Underwriters hereby agree that the Watercraft Exclusion 5 of Section II is deleted subject to watercraft associated with the Project maintaining Protection and Indemnity (P&I) cover up to a minimum of hull value.
All other insuring agreements, terms, conditions, definitions, exclusions, notice requirements, schedules and endorsements of the policy remain unchanged.
ENDORSEMENT 2
EXISTING PROPERTY Endorsement
Cover for damage to existing property is subject to the following Existing Property Contractual Exclusion and Buyback:
Existing Property Contractual Exclusion
The coverage provided under Section II of this policy shall not apply to any claim for damage to or loss of use of any property for which the Principal Assured:
1) owns that is not otherwise provided for in this policy;
2) has use of, custody, physical control, access, right of way or an easement to by operation of a contract or agreement, or
3) is liable or claimed to be liable by operation of any indemnification, hold harmless or similar provision contained within any contract or agreement.
All other insuring agreements, terms, conditions, definitions, exclusions, notice requirements, schedules and endorsements of the policy remain unchanged.
Existing Property Contractual Exclusion Buy-Back
Notwithstanding the Existing Property Contractual Exclusion above, it shall not apply to any claim for:
Physical loss of and/or physical damage to existing property as per Schedule of Existing Property below and extends to anything reasonably ancillary thereto.
All other insuring agreements, terms, conditions, definitions, exclusions, notice requirements, schedules and endorsements of the policy remain unchanged.
Schedule of Existing Property:
Offshore
Gas lift structure (GLS)
Riser platform (RP)
Production platform (PP)
Operational Control Platform (OCP)
Living quarter platform (LQP)
Utility platform (UTP)
Integrated Well Jackets (IWJ) (12 units)
Pipelines, flowlines and cables
Onshore
Main Oil Line (MOL)
Substations
D: Did Technip have a legal liability to KJO?
D1: The relevant contractual terms
1. DEFINITIONS
1.5 "FACILITIES" means the structures or items being designed, procured, fabricated, or constructed by CONTRACTOR pursuant to this CONTRACT.
1.6 "WORK" means all the FACILITIES, work, obligations and services to be performed by CONTRACTOR pursuant to this CONTRACT.
1.7 "WORK Site" means all locations at which CONTRACTOR performs any portion of the WORK.
1.37 "Subcontractor" means an organization contracted by and wholly responsible to CONTRACTOR for executing a specific part of the WORK.
5. CONTRACTOR's RESPONSIBILITY
5.2.1 The establishment or construction by CONTRACTOR of all WORK related storage areas and temporary structures on or adjacent to COMPANY premises must be authorized in advance by COMPANY and shall be confined to areas specified by COMPANY.
5.2.2 CONTRACTOR shall preserve and protect the environment at and adjacent to the WORK site
5.2.3 Except as may be otherwise provided in SCHEDULE "B", CONTRACTOR shall protect from damage all existing structures, improvements or utilities at or near the WORK Site, and shall repair and restore any damage thereto resulting from CONTRACTOR's failure to exercise reasonable care in protecting the same during CONTRACTOR's performance of the WORK. If CONTRACTOR fails or refuses to promptly repair any such damage, COMPANY may perform such repairs, or have them performed by others.
5.2.6 CONTRACTOR shall at all times keep the WORK Site neat, clean and free of waste material, any wreckage, debris of any kind and rubbish and dispose of same as instructed by COMPANY.
12. SUBCONTRACTS
12.1 Subcontracts for the performance of any portion of the WORK shall be procured only in accordance with the Subcontracting Plan contained in CONTRACTOR's bid, and only after CONTRACTOR has received written approval and authorization from COMPANY that CONTRACTOR may subcontract that portion of the WORK. In procuring subcontracts, CONTRACTOR shall select Subcontractors solely on the basis of financial and technical considerations, The submission of the Subcontracting Plan in the CONTRACTOR's Bid prior to Contract Award shall be considered as the minimum intention for compliance but shall not relieve the CONTRACTOR from its obligation to seek approval for the subcontractors after CONTRACT Award. The COMPANY reserves the right to reject a Subcontractor that is found unacceptable for the execution of the related part of the WORK, even if the Subcontractor is specified in the Subcontracting Plan at the Bidding Stage.
12.2 After receiving COMPANY's written authorization that a portion of the WORK may be subcontracted, CONTRACTOR shall, before procuring any subcontract for part or all of that portion of the WORK, submit a notification to COMPANY containing the following information:
12.2.1 If the proposed Subcontractor is a sole proprietorship or partnership, the name(s) and address(es) of the proprietor or all members of the partnership, as the case may be.
12..2.2 If the proposed Subcontractor is a corporation, the place of its incorporation or formation and its corporate headquarters.
12.2.3 The name and address of the proposed Subcontractor's principal bank and a copy of the Subcontractor's latest audited financial statement.
12.2.4 Evidence acceptable to COMPANY of the proposed Subcontractor's technical qualifications to perform the WORK to be subcontracted.
COMPANY shall review the information and, provided that the proposed Subcontractor is, in COMPANY'S opinion, both technically competent and financially able to perform the WORK to be subcontracted, COMPANY shall advise CONTRACTOR in writing of its non-objection to the proposed Subcontractor. If COMPANY objects to the proposed Subcontractor, CONTRACTOR shall either itself accomplish the WORK which would otherwise have been performed by the proposed Subcontractor or shall select another Subcontractor and submit a revised proposal for the approval of the COMPANY.
12.3 CONTRACTOR shall ensure that all Subcontractors selected by CONTRACTOR abide by and observe, to the same extent required of CONTRACTOR, all applicable COMPANY's regulations, and CONTRACTOR agrees to insert or cause to be inserted into all subcontracts provisions to that effect.
12.4 In the event of any substantial breach of this CONTRACT by CONTRACTOR and without regard to whether COMPANY terminates this CONTRACT or a portion of the WORK pursuant to Paragraph 22 of this SCHEDULE "A", CONTRACTOR shall, if COMPANY requests, assign to COMPANY all of its rights under all subcontracts entered into by CONTRACTOR and COMPANY may, to the extent permitted by applicable law and after prior written notice to CONTRACTOR, enforce directly against any such Subcontractor all rights of CONTRACTOR under such subcontract. All subcontracts entered into by CONTRACTOR shall contain a provision whereby the Subcontractor agrees and consents to such assignment by CONTRACTOR to COMPANY.
12.5 CONTRACTOR shall include in every subcontract under this CONTRACT, a provision prohibiting any further subcontracting of any portion of the WORK by the Subcontractor unless the Subcontractor first obtains the approval of CONTRACTOR. CONTRACTOR shall not give such approval without first obtaining approval of COMPANY.
12.6 CONTRACTOR shall be fully responsible to COMPANY for the acts, negligence, alteration, additions and omissions of all its Subcontractors at whatever tier, and their personnel, as if they were the CONTRACTOR's own personnel. CONTRACTOR shall manage, schedule and coordinate the work of all its Subcontractors so as to meet the Scheduled Completion Date and Critical Milestone Dates. Nothing in this CONTRACT shall create any contractual relationship between COMPANY and any Subcontractor unless COMPANY elects to exercise its rights under Paragraph 12.4. COMPANY's approval to subcontract any portion of the WORK and COMPANY's non-objection to CONTRACTOR's Subcontractor selection shall not relieve CONTRACTOR of any of its obligations under this CONTRACT.
14. DISTRIBUTION OF RISKS
The distribution of risks between COMPANY and CONTRACTOR set forth in Paragraphs 14.1 and 14.2 hereunder are subject to the specific exclusions set forth in Paragraph 14.3.
14.1 Persons and Properties
14.1.1 CONTRACTOR's Persons and Properties
The CONTRACTOR shall be liable to make payment for all CONTRACTOR's personnel, equipment, materials, services, tools, vehicles and other things required to be provided, secured and procured by the CONTRACTOR under this CONTRACT, and indemnify and hold the COMPANY harmless against and from any claims of whatsoever nature on account of the CONTRACTOR's failure to so pay.
The CONTRACTOR shall solely be responsible for and indemnify and hold the COMPANY harmless against and from any and all claims, demands, injunctions, judgments, suits, liabilities, costs and expenses of whatsoever nature arising or resulting on account of or in connection with damage to, destruction or loss of the CONTRACTOR's equipment and any other properties of the CONTRACTOR howsoever caused, any injury or sickness, fatal or otherwise, or disablement suffered by anyone of the CONTRACTOR's personnel or any other person employed directly or indirectly by the CONTRACTOR, howsoever caused.
14.1.2 COMPANY Persons and Property
The CONTRACTOR shall be responsible for and indemnify and hold the COMPANY harmless against and from any and all claims, demands, injunctions, judgments, suits, liabilities, costs and expenses of whatsoever nature arising or resulting on account of or in connection with injury or sickness, fatal or otherwise, or disablement suffered by any person employed by the COMPANY or for whom the COMPANY may otherwise be responsible, and damage to, destruction or loss of any properties of the COMPANY, when caused by misconduct, negligence or omission on the part of the CONTRACTOR.
14.2 Third Party
Each party shall be responsible and indemnify and hold the other party harmless against and from any and all claims, demands, injunctions, judgments, suits, liabilities, costs and expenses of whatsoever nature arising or resulting on account of or in connection with injury or sickness, fatal or otherwise, or disablement suffered by any third party person, and damage to, destruction or loss of any third party property, when caused by such each party's misconduct, negligence or omission.
In the event of the joint or concurrent negligence of the COMPANY and the CONTRACTOR, the responsibility shall be determined and damages shall be apportioned in accordance with the applicable laws or as agreed by the parties.
"Third party" in this Paragraph 14.2 means a person, whether natural or artificial, other than the parties, but does not include such contractors and subcontractors of any tier as being currently employed by each party whether in performance of this CONTRACT or not. These CONTRACTORS and Subcontractors of each party shall be deemed identical with such each party particularly for the intent of Paragraph 14.
15. INSURANCE
15.1 CONTRACTOR shall carry and maintain in force at all times during the term of this CONTRACT the following insurances:
15.1.5 Fabrication and Transit Insurance
Insurance to cover the full value of any loss, damage or destruction of any materials for the FACILITIES and which shall cover fabricated subassemblies incorporating those materials while they are located at fabrication yard(s), while in storage and during transit from these foregoing locations to the Installation Site.
15.1.7 CONTRACTOR'S All Risk Insurance
For the full value of the WORK covering the materials and WORK in progress up to successful completion of the Performance Acceptance Test required and issuance of the Performance Acceptance Certificate under the CONTRACT
15.3 The policies of those insurances shall contain a waiver of subrogation in favor of the COMPANY.
The COMPANY shall be named as the additional insured under those insurance policies in addition to the CONTRACTOR and others as their interests may appear, except for the insurances required under Paragraph 15.1.1 above.
The policies of those insurances shall also contain a cross liability clause such that the insurances shall apply to the CONTRACTOR and the COMPANY as separately insured, except for the insurances required under Paragraph 15.1.1 above.
3.1 Summary of Project FACILITIES
The purpose or FACILITIES encompassed within the related Projects hereby defined below, is to support maintaining the maximum sustainable capacity (MSC) of 300 thousand barrels per calendar day (MBCD) of Khafji crude and 50 thousand barrels per calendar day (MBCD) of Hout (KRL) crude:
i. INSTALLATION OF SECOND SUBMARINE POWER CABLE (SSPC)
ii. INSTALLATION OF POWER DISTRIBUTION PLATFORMS FOR ESP PHASE-II (PDP-4&5)
iii. CONSTRUCTION OF CONTROL AND LIVING PLATFORM (CLP)
iv. INSTALLATION OF INTEGRATED WELL JACKETS 6&7 (IWJ-6&7)
Pursuant to SCHEDULE "A", CONTRACTOR shall furnish, without limitation, all facilities, tools, labor, supervision, technical and professional services, material, equipment, supplies and consumables (except fuel which can be supplied by COMPANY on a back-charge basis at the market rates applicable at the time of delivery and water on a back-charge basis at the prevailing SWCC rate and those items specified in SCHEDULE "G") required to totally engineer /detailed design; procure, install, construct, test, pre-commission / mechanically complete, the FACILITIES in accordance with this SCHEDULE "B" – Job Specification.
Also CONTRACTOR shall assist COMPANY with start-up / commissioning and performance testing / acceptance activities as defined in Paragraph 9.7 of this SCHEDULE "B" and Scope of WORK documents.
3.2 Description of FACILITIES
CONTRACTOR shall refer to the documents outlined in Paragraph 4 of this SCHEDULE "B" for a detailed description of the FACILITIES' Scope of WORK, a summary description of which includes but is not limited to the following:
…
3.2.3 CONSTRUCTION OF NEW CONTROL & LIVING PLATFORM (CLP)
The objective of this Project is to accommodate the future expansion of offshore facilities and offshore manpower resources, by providing a new Control and Living Platform (CLP).
The existing Living Quarters Platform (LQP) and OCP will be refurbished to provide additional improved living and working facilities to personnel.
The Project Scope of Work will include but not be limited to:
New Offshore Facilities:
a) Installation of a Control and Living Quarters Platform for 69 people and Control Room to support 24 hours operation. The CLP will be provided with stand-alone utilities systems such as sea water, fresh water, hot water, fire water, instrument / plant air, sewage treatment, diesel etc.
b) Installation of Electrical, HVAC, Telecommunication & Process Control System (PCS).
c) Installation of an interconnecting bridge between CLP and existing UTP.
Modification to Existing Offshore Facilities:
a) Modifications to the UTP to allow Structural, Electrical and Piping Tie-ins to CLP
b) Refurbishment of three floor levels the OCP.
c) Refurbishment of two floor levels of the LQP.
3.2.4 INSTALLATION OF INTEGRATED WELL JACKETS IWJ-6&7
The objective of this project is to maintain crude oil production through the installation of two new integrated well jacket platforms to facilitate new producer and/or injection wells.
New Offshore WORK:
Installation of two (2) Integrated Well Jacket Platforms (IWJ-6&7). Each IWJ shall be provided twelve slots for drilling new producer and/or injection wells.
Installation of Electrical, Piping, Instrumentation and Fire and Gas system.
WORK
The CONTRACTOR shall, in accordance with the terms and conditions set out in this CONTRACT, attached schedules and drawings, standards, specifications and other documents referred to in the schedules or in any of the referenced documents perform the WORK required for the Project entitled KHAFJI CRUDE RELATED OFFSHORE PROJECTS, which includes the following individual Projects:
i. INSTALLATION OF SECOND SUBMARINE POWER CABLE (SSPC)
ii. INSTALLATION OF POWER DISTRIBUTION PLATFORMS FOR ESP PHASE-II (PDP-4&5)
iii. CONSTRUCTION OF CONTROL AND LIVING PLATFORM (CLP)
iv. INSTALLATION OF INTEGRATED WELL JACKETS 6&7 (IWJ-6&7)
D2: The parties' arguments
Technip's argument
Medgulf's argument
D3: Discussion
"The court's task is to ascertain the objective meaning of the language which the parties have chosen in which to express their agreement. The court must consider the language used and ascertain what a reasonable person, that is a person who has all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract, would have understood the parties to have meant. The court must consider the contract as a whole and, depending on the nature, formality and quality of drafting of the contract, give more or less weight to elements of the wider context in reaching its view as to the objective meaning of the language used. If there are two possible constructions, the court is entitled to prefer the construction which is consistent with business common sense and to reject the other. Interpretation is a unitary exercise; in striking a balance between the indications given by the language and the implications of the competing constructions, the court must consider the quality of drafting of the clause and it must also be alive to the possibility that one side may have agreed to something which with hindsight did not serve his interest; similarly, the court must not lose sight of the possibility that a provision may be a negotiated compromise or that the negotiators were not able to agree more precise terms. This unitary exercise involves an iterative process by which each suggested interpretation is checked against the provisions of the contract and its commercial consequences are investigated. It does not matter whether the more detailed analysis commences with the factual background and the implications of rival constructions or a close examination of the relevant language in the contract, so long as the court balances the indications given by each."
E: Absence of consent to settlement
The issue
"DAMAGES" shall mean compensatory damages, monetary judgments, awards, and/or compromise settlements entered with Underwriters' consent, but shall not include fines or penalties, punitive damages, exemplary damages, equitable relief, injunctive relief or any additional damages resulting from the multiplication of compensatory damages".
The parties' arguments
Discussion
""Damages" to an English lawyer imports this idea, that the sums payable by way of damages are sums which fall to be paid by reason of some breach of duty or obligation, whether that duty or obligation is imposed by contract, by the general law, or legislation".
"[70] It must be remembered that in this policy, like almost every other liability policy, there is a condition which provides that the insured shall not negotiate, admit liability or make any promise, payment or settlement without the insurer's written consent (General Condition 7b). Under general principles of English contract law I consider that where an insurer has notified the insured that it will not be granting indemnity in respect of a claim notified by the insured, the insurer cannot insist on compliance by the insured with his obligations under the policy in relation to that claim such as, for example, the obligation not to negotiate a settlement or admit liability, The insurer, having refused to perform his primary obligations under the contract in respect of that claim cannot at the same time insist on the insured complying with his primary obligations in respect of that claim. The conduct of the insurer means that the insured is effectively uninsured and must therefore take such steps as he reasonably can to protect his own interests. Such steps may well include attempting to negotiate a reasonable settlement of the claim against him."
F: The Existing Property Endorsement and other exclusions
F1: Introduction and the parties' arguments
Introduction
"Third Party Property
Details of any third party property - pipelines, platforms etc. - in vicinity of contract plus any indemnities provided under contract"
DAMAGES TO EXISTING PROPERTIES | |||
Existing properties | Value (USD) | Nature of the potential damage | Potential maximum risk (USD) |
OFFSHORE | |||
Gas lift structure (GLS) | 180,000,000.00 | Riser J-tube Structure |
5,000,000.00 |
Riser platform (RP) | 100,000,000.00 | Riser J-tube Structure |
5,000,000.00 |
Product platform (PP) | 140,000,000.00 | Riser J-tube Structure |
5,000,000.00 |
Operational Control Platform (OCP) | 120,000,000.00 | Riser J-tube Structure |
5,000,000.00 |
Living quarter platform (LQP) | 80,000,000.00 | Riser J-tube Structure |
5,000,000.00 |
Utility platform (UTP) | 120,000,000.00 | Riser J-tube Structure |
5,000,000.00 |
WHJ (12 units, each 50MUSD) | 600,000,000.00 | replacement | 50,000,000.00 |
Pipelines and frowlines [sic] (200km)* | 300,000,000.00 | puncture | 10,000,000.00 |
Cables and submarines (350km)* | 120,000,000.00 | cut | 15,000,000.00 |
Onshore | |||
MOL | 5,000,000.00 | damage equipment | 1,000,000.00 |
Substations | 15,000,000.00 | puncture | 1,000,000.00 |
TOTAL | 1,780,000,000.00 | Maximum risk to ensure per occurrence: | 50,000,000.00 |
*damages to these facilities can be simultaneous.
"Contractual requirements regarding third parties are in ATTACHMENT E.
For further information, see ATTACHMENTS previously given to MARSH"
The Existing Property Endorsement: Medgulf's argument
The Existing Property Endorsement: Technip's argument
a. Avoidance of the Policy by reason of a non-disclosure or misrepresentation by another insured will not prejudice the claimant insured.
b. The application of an exclusion based on wilful misconduct is limited to the guilty insured.
c. The application of other types of exclusion based on the conduct of an insured other than the claimant insured.
d. The application of a breach of warranty by one insured will not ordinarily affect another Insured.
e. The application of policy limits.
F2: Discussion
"[47] The core principle is that an insurance policy, like any other contract, must be interpreted objectively by asking what a reasonable person, with all the background knowledge which would reasonably have been available to the parties when they entered into the contract, would have understood the language of the contract to mean. Evidence about what the parties subjectively intended or understood the contract to mean is not relevant to the court's task".
In that regard, the Supreme Court referred (at paragraph [47]) to the summary of the relevant principles and case-law in paragraphs [62] – [66] of the judgment of the Divisional Court.
"[65] In my judgment, applying this approach, the Court must adopt an approach to the interpretation of insurance exclusions which is sensitive to their purpose and place in the insurance contract. The Court should not adopt principles of construction which are appropriate to exemption clauses - i.e. provisions which are designed to relieve a party otherwise liable for breach of contract or in tort of that liability - to the interpretation of insurance exclusions, because insurance exclusions are designed to define the scope of cover which the insurance policy is intended to afford. To this end, the Court should not automatically apply a contra proferentem approach to construction. That said, there may be occasions, where there is a genuine ambiguity in the meaning of the provision, and the effect of one of those constructions is to exclude all or most of the insurance cover which was intended to be provided. In that event, the Court would be entitled to opt for the narrower construction. This result may be achieved not only by the applicable of the contra proferentem approach, but also the approach adopted by Lord Clarke, JSC in Rainy Sky SA v Kookmin Bank [2011] UKSC 50; [2011] 1 WLR 2900, that in the case of ambiguity, the Court may opt for the more commercially sensible construction, at paragraph 21: "If there are two possible constructions, the court is entitled to prefer the construction which is consistent with business common sense and to reject the other". That said, as Lord Clarke, JSC also said, at paragraph 23 of his judgment: "Where the parties have used unambiguous language, the court must apply it". This would, however, be subject to considerations of absurdity or where something plainly has gone wrong with the language of the contract."
Limb 1
Limb 3
F3: The Watercraft exclusion
G: Quantum issues
G1: Introduction to the issues
""CLAIMS EXPENSES" shall mean reasonable legal costs and other expenses incurred by or on behalf of the Insured(s) in the defence of any covered claim including attorney's fees and disbursements, investigation, adjustment, appraisal, appeal costs and expenses and pre- and post- judgement interest, excluding salaries, wages and benefits of the Insured's employees and the Insured's administrative expenses."
G2: Legal principles
"… when loss was incurred by physical damage to a chattel and it could be economically repaired, then the diminution in value caused by the tort was measured by reference to the reasonable cost of repairs which, in practice, was "likely to be the lowest reasonably obtainable cost of repairs"."
"(1) Where a chattel is damaged by the negligence of another that loss (the "direct" loss) is suffered as soon as the chattel is damaged. (2) The proper measure of that loss is the diminution in value that the chattel has suffered as a result of the negligence of the defendant. This follows the general principle in awarding damages, i e that of restitution: see Livingstone v Rawyards Coal Co (1880) 5 App Cas 25, 39, per Lord Blackburn. In Lord Hobhouse's phrase, "this can be expressed as a capital account loss". (3) If the chattel can be economically repaired, the claimant is entitled to have it repaired at the cost of the wrongdoer, although the claimant is not obliged to repair the chattel to recover the direct loss suffered. (4) Events occurring after the infliction of the damage are irrelevant to calculating the diminution in value measure of damages: see Burdis v Livsey [2003] QB 36, para 95. Thus, subsequent destruction of the chattel, or a decision to delay repairs (The Kingsway [1918] P 344), or an ability to have the repairs done at less that cost (Jones v Stroud District Council [1986] 1 WLR 1141) or for nothing (The Endeavour (1890) 6 Asp MC 511; Burdis v Livsey [2003] QB 36, where no sum was payable because the repairs were carried out under an unenforceable credit agreement) will not prevent the claimant from recovering the diminution in value of the chattel that has been caused by the negligence of the tortfeasor. (5) Generally, the practical way that the courts have calculated this diminution in value is to ask how much would be the reasonable cost of repair so as to put the chattel back in the state it was in before it was damaged. In general this is a convenient practice which we think the courts should continue to follow. Only if the sum claimed appears to be clearly excessive will the court be justified in investigating whether that sum exceeds the cost that the claimant would have incurred in having the repairs carried out by a reputable repairer."
"[32] In summary, if a claimant, whose damaged chattel is capable of economic repair, chooses to repair it at a cost which is not reasonable, then the reason why he cannot recover that unreasonable cost as damages will be because that cost does not represent the diminution in value of the chattel. What is the diminution in value of a chattel or the "reasonable cost of repair" will always be a question of fact for the trial judge to determine if it is in dispute.
…
[44] The claim in respect of the physical damage to the vehicle is a claim in general damages and the measure of damages recoverable is the monetary amount of the diminution in value of the vehicle caused by the negligence of the defendant. That diminution in value figure is usually calculated, as a rule of thumb, by the reasonable cost of repairs (to the claimant) in a case where the vehicle is capable of economic repair. If, as is assumed by the form of the question in the third preliminary issue, it is the insurer that has arranged and paid for the repairs to the claimant's vehicle and the claimant then sues for the cost incurred by the insurer as the sum representing the diminution in value of the vehicle resulting from the negligence of the defendant, the court has only one question to consider. It is whether the actual sum claimed is equal to or less than the notional sum this claimant would have paid, by way of a reasonable cost of repair, if he had gone into the open market to have those repairs done. The court will examine the components of the notional overall figure which is said to represent what the claimant (not the insurer) would have had to pay if he had organised the repairs, to ensure that that sum represents the "reasonable cost" of repairs that the claimant would have had to pay. It will then compare that figure (stripped, if necessary, of any "unreasonable" elements) with the total sum representing the actual cost to the insurer, which will be the sum claimed by the claimant."
"Again, generally speaking, in order to claim under a liability policy where the insured has settled the claim of the third party the insured still has to demonstrate that it was or would have been liable to the third party. It cannot simply rely on the fact of the settlement to demonstrate either liability or that the amount of the settlement was reasonable. In order to show the settlement was reasonable, the insured must show that the amount of damage for which it would have been liable is at least as much as the amount paid under the settlement".
"The method of assessing the cost of repair has been elaborated in a number of cases. (1) The cost of repair must be reasonable, both in that the work must be necessary and the charges must not be extravagant".
In their opening submissions, Medgulf said that this was common ground.
"Where the court must fix the "proper" valuation of a property there is normally a range of valuations which might have been made by reasonably careful valuers: the court must choose the figure which it considers to be the most likely outcome of careful assessment: the defendant is not given the benefit of damages being assessed by reference to the highest figure which might have been given without negligence".
G3: The expert evidence
G4: Safeguarding costs
"The proposed Implementation Schedule for the chosen mitigation scheme is presented in Table 9-1, considering the criteria set in Section 5.1.
In order to implement the repair mitigation schemes effectively with minimum possible schedule, experienced Offshore Repairs Contractor(s) shall be assigned to carry out the repair works.
The major assumptions/considerations affecting the schedule are presented below.
1. As per KJO standard safety practice, temporary suspension of the two (2) Wells K-10 and K-213 is shall be performed prior to any repair/mitigation
2. Removal of piping, protection of Xmas trees and other topside facilities are expected to be carried before starting any repair works. (Atkins understand that NR-09 platform is currently in shutdown, hence hot work is permitted on the platform without further well intervention)".
"All gas and oil lines are mothballed with minimum preservation pressure. (gas line = 100 psig & oil line < 50 psig)".
"KJO …. have their certain procedures in place, what requirements they required … and those pipe supports did not require suspension of the wells otherwise they wouldn't have put it in their bid to have it done… So on offshore platforms, you can do work on them all the time, there is always hot works done … it just has to be done safely."
In my view, however, the rational explanation for the carrying out of work on the J-tube installation, which did require hot work, is that the wells had been safeguarded.
G5: Repair costs: Agreed Scope or Reduced Scope?
"… that you introduce more risk by disconnecting all the piping from the risers, which is connected to other platforms and the reservoir and also you introduce more risk by taking out and you need to disassemble a large portion of the structure, you don't know what the impact is of residual stress if you remove – a large cost construction on both the tripod deck, to take the tripod deck out and bring a new deck you need to remove that complete structure and that structure is in place to keep the top part of the legs together, it is part [of] the integrity but if you remove you have a high risk that residual stresses will give a lot of deviations in the structure.
But also removing the topside piping connected to the risers brings more risk and the transport of the complete tripod deck in a plane subject to wind load introduces more risk. So in the ranking of safety objectives and doing a risk assessment for the construction methodology, I would never change out the tripod deck and the piping and the structure involved. If it is not damaged, it is not needed, it brings more risk and is more expensive".
G6: Reduced Scope – repair costs
G7: Miscellaneous costs
CONCLUSION
Item | Description | Dr Lamport | Mr van Beek (Reduced Scope) | Mr van Beek (Agreed Scope) | Judge's Decision |
Scope definition | |||||
1 | DNV survey[2] | US$328,458 | US$328,458 | US$328,458 | US$ 328,458 |
2 | CCC offshore survey* | US$2,530,000 | US$1,371,347 | US$1,371,347 | US$ 2,530,000 |
3 | Insurance for offshore survey* | US$87,995 | US$87,995 | US$87,995 | US$ 87,995 |
4 | TPAD internal costs* | US$2,346,530 | US$1,187,171 | US$1,187,171 | 0 (No longer claimed) |
5 | TPAD survey costs* | US$88,126 | US$88,126 | US$88,126 | 0 (No longer claimed) |
6 | Atkins survey | US$503,928 | US$503,928 | US$503,928 | US$ 503,928 |
7 | KJO owner's cost | US$100,000 | US$100,000 | US$100,000 | US$ 100,000 |
8 | Salaries, travel cost of ESD and shareholders attended meetings by KJO | US$200,000 | US$100,000 | US$100,000 | US$ 100,000 |
9 | Scope definition subtotal | US$6,185,037 | US$3,767,025 | US$3,767,025 | US$ 3,650,381 |
Safeguarding (if required) | |||||
10 | Well safeguarding | US$7,140,000-US$14,280,000 | US$5,435,762 | US$5,435,762 | 0 |
11 | Safeguarding risers and pipelines | US$626,020-US$1,105,544 | US$88,320 | US$88,320 | 0 |
12 | Safeguarding topside piping | US$273,847-US$380,411 | Included in no. 11 above | Included in no. 11 above | 0 |
13 | Safeguarding subtotal | US$8,039,867-US$15,765,955 | US$5,524,082 | US$5,524,082 | 0 |
Platform Repairs | |||||
14 | Mobilisation/demobilisation | US$1,174,000 | US$361,600 | US$440,000 | |
15 | Project management and engineering | US$275,000-US$316,250 | US$212,160 | US$224,640 | |
16 | Offshore repairs | US$7,701,500-US$8,856,725 | US$4,221,686 | US$6,401,125 | |
17 | - Tripod deck removal | - Inc. | - Not required | - Inc. | |
18 | - Jacket repair works | - Inc. | - Not required | - Not required | |
18a. | - Divers | - Inc. | - Inc. US$17,189 | - Inc. US$60,161 | |
19 | - New tripod deck installation | - Inc. | - Not required | - Inc. | |
20 | - Topsides piping materials | - Inc. | - Not required | - Inc. | |
21 | - Topsides offshore hook-up/comm. | - Inc. | - Included to extent required | - Included to extent required | |
22 | Marine spread stand-by costs | Inc. | US$162,720 | US$264,080 | |
23 | Adjustment for repairs not attributable to Allision | (US$82,380) | (US$164,398), already included | (US$164,398), already included | |
24 | Platform repairs offshore subtotal | US$9,068,120-US$10,264,595 | US$4,958,166 | US$7,329,845 | US$ 4,958,166 |
25 | Technip Additional Engineering* | US$229,667 | US$229,667 | US$229,667 | US$ 229,667 |
26 | Engineering during construction phase | ||||
27 | - KJO | US$500,000 | Included in no. 29 below | Included in no. 29 below | |
28 | - Technip | US$425,000 | US$554,440 | US$665,328 | US$ 554,440 |
29 | Owner's management and supervision | US$1,329,000 | US$422,400 | US$422,400[3] | US$ 422,400 |
30 | Third-party inspection services | ||||
31 | - KJO | US$144,255-US$186,300 | Included in no. 29 above | Included in no. 29 above | |
32 | - Technip | US$29,700-US$44,550 | US$44,500 | US$44,500 | US$ 44,500 |
33 | EPC contractor's fee, overhead and profit | Included in other costs | Included in other costs | Included in other costs | |
34 | Dimensional survey | US$1,876,250-US$1,959,275 | Not required | Not required | |
35 | Adjustment for repairs not attributable to Allision | (US$78,214) | See no. 23 above. | See no. 23 above. | |
36 | Contingency | US$1,981,760-US$2,182,219 | US$54,939 (in addition to weather downtime per no. 22) | US$59,676 (in addition to weather downtime per no. 22) | US$ 310,458 |
37 | Cost to replace J-tube | Not required | Not required | Not required | |
38 | Platform Repair Subtotal | US$15,505,537-US$17,042,392 | US$6,264,112 | US$8,751,416 | US$ 6,519,631 |
Miscellaneous costs | |||||
39 | Geotechnical investigation | Not required | Not required | Not required | |
40 | Insurance | US$500,000 | US$190,385 | US$284,481 | US$ 190,385 |
41 | Withholding Tax and VAT | US$788,019—-S$906,222 | WHT: US$16,662 VAT: US$0 |
WHT: US$17,598 VAT: US$0 |
US$ 16,662 |
42 | Performance bond | Not attributable to Allision | Not attributable to Allision | Not attributable to Allision | 0 (not pursued) |
43 | Miscellaneous costs subtotal | US$1,288,019-US$1,406,222 | US$207,047 | US$302,079 | US$ 207,047 |
Note 1 In this section, I will fully capitalise terms where I am quoting a provision where they are so capitalised. However, where I am not quoting a provision, I will only capitalise the first letter of relevant defined terms such as “Work” or “Subcontract” or “Contractor” or “Subcontracting Plan”. [Back] Note 2 Costs marked with an asterisk are claimed as Additional Losses. [Back] Note 3 Mr van Beek estimated US$422,400 for the Reduced Scope; he did not produce a separate estimate for the Agreed Scope. [Back]