QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
(1) ANATOLIE STATI (2) GABRIEL STATI (3) ASCOM GROUP S.A. (4) TERRA RAF TRANS TRAIDING LTD |
Claimants |
|
- and – |
||
THE REPUBLIC OF KAZAKHSTAN |
Defendant |
____________________
Ali Malek QC, Christopher Harris and Paul Choon Kiat Wee (instructed by Herbert Smith Freehills) for the Defendant
Hearing dates: 6-7 February 2017
____________________
Crown Copyright ©
Knowles J:
Introduction
Approach
(1) "Recognition or enforcement of a New York Convention award shall not be refused except in the following cases …if it would be contrary to public policy to recognise or enforce the award": section 103(1) and (3) Arbitration Act 1996.(2) "[T]he public policy exception in section 103(3) is confined to the public policy of England (as the country in which enforcement is sought) in maintaining the fair and orderly administration of justice: Mustill & Boyd, at pp. 91-92."; IPCO (Nigeria), Ltd v Nigerian National Petroleum Corporation [2005] EWHC 726 (Comm); [2005] 2 Lloyd's Rep 326 at [13] per Gross J.
(3) When addressing the question whether an award has been obtained by fraud or the award or the way in which it was procured is contrary to public policy the Court will normally look to see whether "some form of reprehensible or unconscionable conduct has contributed in a substantial way to the obtaining of the award": see Double K Oil Products 1996 Limited v Neste Oil OYJ [2009] EWHC 3380 (Comm); [2010] 1 Lloyd's Rep 141 at [33] per Blair J; and see Gater Assets Ltd v Nak Naftogaz Ukrainiy [2008] 1 CLC 141 at [41] per Tomlinson J ("That means conduct which we would be comfortable in describing as fraud, conduct dishonestly intended to mislead").
(4) It may be sufficient to show that a party "had deliberately and dishonestly failed to disclose [material] in the arbitration and made submissions or called evidence which deliberately and dishonestly continued that concealment and misled the tribunal" and that the material would have had "an important influence on or would probably have affected the result of the arbitration": Chantiers de l'Atlantique SA v Gaztransport & Technigaz SAS [2011] EWHC 3383 (Comm) at [58] and [311] per Flaux J.
(5) "[C]onsiderations of public policy, if relied upon to resist enforcement of an award, should be approached with extreme caution": IPCO (Nigeria), above, at [13].
(6) "[T]here can be no realistic doubt that s. 103 of the [Arbitration] Act embodies a pre-disposition to favour enforcement of New York Convention Awards, reflecting the underlying purpose of the New York Convention itself": IPCO (Nigeria), above, at [11].
(7) For the English Court to permit a party to pursue to a trial of the issues an allegation that a New York Convention award was obtained by fraud, normally two conditions will require to be fulfilled: Westacre Investments Inc v Jugoimport-SPDR Holding Co Ltd [2000] QB 288 (CA) at 309F per Waller LJ (dissenting in the result).
(8) The first condition is "that the evidence to establish the fraud was not available to the party alleging the fraud at the time of the hearing before the arbitrators": Westacre, above, at 309F, but noting the qualification at G-H.
(9) The second condition is that "there is a prima facie case of fraud which is sufficient to overcome the extreme caution of the court when invited to set aside an award on the grounds of public policy": IPCO (Nigeria) Limited v Nigerian National Petroleum Corporation [2015] EWCA Civ 1144; [2016] 1 Lloyd's Rep 5 at [191] per Christopher Clarke LJ.
(10) And "where perjury is the fraud alleged, i.e., where the very issue before the arbitrators was whether the witness or witnesses were lying, the evidence must be so strong that it would reasonably be expected to be decisive at a hearing, and if unanswered must have that result.": Westacre, above, at 309G.
The LPG Plant
The Award
"1743. First, in addition to an application of the Tribunal's considerations in the chapter on causation above in this Award, the Tribunal has no doubt that [the State's] actions found above to be in breach of the ECT, in particular were a cause for the delay and then discontinuance of Claimants' completion of the LPG Plant.
…
1745. The Tribunal is not persuaded by [the State's] and their experts' conclusion that the LPG is a failed project and must be considered to have a negative value and no damages at all can be claimed by Claimants. If that were so, [the State] would not have been ready to invest further expenses in the completion of the Plant, after [the State] had taken control of the Plant. However, there were obviously plans to complete it. Publicly available information indicates that [the State] was in fact preparing to open the LPG Plant in 2012. In a document entitled "List of Investment projects of the Mangistauskoi Region, which are being supervised in 2011", there is a specific reference to the LPG Plant under "Regional Projects". The project is identified as having a cost of USD 315 million (47 billion Tenge) and it was expected to start up in the first half of 2012 with a capacity of 7 mcm of gas per day (2nd FTI Report para 7.7 and fns. 138 and 139). [The State's] argument that it cannot be identified with this document is not persuasive. The LPG Plant was also listed on website of [the State's] Embassy in Israel under the caption "Large Investment Projects in Kazakhstan through 2012" with the same project costs (FTI 2nd Report para 7.7 and fn 140).
1746. Regarding the value of damages caused by [the State's] action, the Tribunal has taken note of the various extensive arguments submitted by the Parties relying on their respective experts' reports. However, the Tribunal considers that it does not have to evaluate these reports and the very different results they reach. In the view of the Tribunal, the relatively best source for the valuation in the period of the valuation date accepted by the Tribunal are the contemporaneous bids that were made for the LPG Plant by third parties after Claimants' efforts to sell the LPG Plant, both before and after October 14, 2008. Prospective purchasers bid on the Plant, not as scrap but obviously as prospectively operational. This is reflected in the undisputed indicative offers made by interested buyers in 2008, which valued the LPG Plant at USD 150 million on average. In this context, the Tribunal is not persuaded by [the State's] argument that these offers did not reflect the anticipated price bidders were ready to pay, but were only strategic offers to gain access to the data room. In this context, the Tribunal attributes a limited evidentiary value to the testimony of [the State's] witnesses from KNOC and Total E&P, since these foreign companies remain active investors in [the State] and, thus, for understandable reasons, have an interest to maintain a good relationship with the government of that country.
1747. On the other hand, the Tribunal considers it to be of particular relevance that an offer was made for the LPG Plant by state-owned KMG at that time for USD 199 million. The Tribunal considers that to be the relatively best source of information for the valuation of the LPG Plant among the various sources of information submitted by the Parties regarding the valuation for the LPG Plant during the relevant period of the valuation date accepted by the Tribunal …
1748. Therefore, this is the amount of damages the Tribunal accepts in this context."
The Alleged Fraud
a. The Claimants sought to justify the price charged under the Perkwood Contract in part on the basis of transportation costs but did not submit any evidence in support of the alleged transportation cost.b. The Claimants initially contended that the further US$ 31 million charged under the Perkwood Contract referred not to the same equipment but to spare parts. On the final day of the hearing the Claimants changed their position and submitted that new equipment that would be used to increase the capacity of the LPG Plant was involved, but did not submit any evidence in support of this.
c. The Claimants did not submit any corroborating evidence to support the proposition that management services were actually performed by or on behalf of Perkwood.
d. The Claimants did not offer any explanation for what equipment had been purchased for US$ 72 million, where it was stored or how it related to the state of completion of the LPG Plant
Effect of the alleged fraud
"The primary rationale behind our interest … is the strategy to continue increasing our reserves of hydrocarbon resources and building oil production through acquisitions of oil and gas producing assets in accordance with our Corporate Development Strategy.
…
The Indicative Offer herein relates to the proposed acquisition of 100% of the share capital of [Kazpolmunay LLP ("KPM") and TNG, collectively, "the Company")].
…
On the basis of the information contained in the Information Memorandum and publicly available information, subject to the conditions and assumptions set out elsewhere in this Indicative Offer and contingent upon further due diligence at Phase II of the sale process, we value the Company at US$754 million on a debt free and cash free basis (the "Enterprise Value") for expected completion of the Proposed Transaction in January 2009.
…
We estimate the value of the Borankol field at US$100 million, the value of the Tolkyn field at US$455 million, and the value of the LPG plant at US$199 million.
…
In formulating our Indicative Offer, we have relied upon the information contained in the Information Memorandum and certain other publicly available information. Our valuation depends upon this information and assumptions being substantiated in the next round through due diligence materials and meetings.
Due to lack of sensitive input data, we used comparative (transaction and trading multiples) method for valuation of Borankol and Tolkyn fields, whereas the LPG [P]lant was valued using the combination of comparative and cost methods.
…
The value of the LPG [P]lant was calculated as an arithmetical average between the matrix of comparative method value and cost method value. EV/EBITDA multiple of 5.5x was used as a base for comparative method valuation. Historical costs of US$193 million were used as a base for cost method valuation.
Inter alia, our estimates of the Company's value and the present Indicative Offer are based on the following key assumptions:
…
Historical production, revenues, costs and CAPEX were as reported in the Information Memorandum;
…
[KMG's subsidiary] and its advisors are prepared to begin reviewing the electronic data room and the vendor due diligence reports immediately, and would anticipate, at the very least, performing the following additional due diligence …"
(1) The KMG Indicative Bid was based on the information contained in the Information Memorandum and publicly available information.(2) It was contingent upon further due diligence to be carried out at Phase II of the sale process. The value of the LPG Plant at US$199 million depended (as did other values) upon this information, and assumptions, being substantiated in the next round through due diligence materials and meetings.
(3) The LPG Plant was valued using a combination of comparative and cost methods. The value of the LPG Plant was calculated as an arithmetical average, one part of which was the cost method.
(4) Historical costs of US$193 million were used as a base for cost method valuation.
"Indeed the offer made for the LPG plant by [KMG] at that time was US$199 million. While Claimants did not accept these offers because at the time they deemed them too low and did not feel that they would lead to a sale, the Tribunal should note that State-owned [KMG] itself offered almost US$200 million for the Plant, more than six times the highest value assigned to the LPG Plant by Deloitte of US$32 million. Little more is needed to demonstrate that Deloitte's salvage value assumptions and calculations are worthless."
I draw particular attention to the Claimants' phrase, addressed to and recorded by the Tribunal, that "little more is needed".
The decision of the US Court
"[I]t would not be in interest of justice to broaden the scope of this proceeding to consider whether [the Claimants] did or did not mislead the foreign arbitration panel when it presented evidence related to the value of the plant in question. The Court has not come to any conclusions about the legitimacy of the evidence presented to the arbitrators on this issue. But it has reviewed [the Award], and it is clear that the arbitrators did not rely upon the allegedly fraudulent evidence in reaching their decision, so [the State's] proposed submissions would not be germane to the petition to confirm [the Award] … Under those circumstances, and given the fact that the issue has already been presented to the Swedish authorities, it will not be in the interest of justice to conduct a mini-trial on the issue of fraud here when the arbitrators themselves expressly disavowed any reliance on the allegedly fraudulent material."
The decision of the Swedish Court
"5.3 The issue of the invalidity or setting aside of [the Award]
5.3.1 Invalidity based on the fraudulent scheme, false evidence, misleading information etc.
A. [The State] has argued that [the Award], and the manner in which it arose, violates public policy, and invoked the detailed circumstances set forth in section 3.1.2.1.
The Court of Appeal makes the following assessment.
B. In the arbitration at hand [the Claimants] claimed that [the State] had breached its obligations under the ECT by violating the investor protection provisions in the ECT and that [the State] was thus liable to pay damages to [the Claimants], inter alia with respect to what was referred to as the LPG [P]lant. It is undisputed in the case that the plant exists and, based on the evidence presented here, it is also clear that investments were made in it. [The Award] states that [the State] contested [the Claimants'] claim, and consequently [the Tribunal] made a substantive assessment of the claim. In light of the aforesaid, there is no reason to call into question the existence of an underlying real legal relationship between the parties …
C. In the arbitration [the Claimants] invoked evidence in the form of witness testimony, witness affidavits and expert reports to prove that the investment costs in the LPG [P]lant had amounted to the alleged sum. However, [the Award] states that [the Tribunal] based its assessment of the damages with respect to the LPG [P]lant on the so-called indicative bid which had been submitted by KMG, see paragraphs 1746-1748 in [the Award].
D. As the Court of Appeal has described above, the scope of application of the public policy provision is very narrow and the legislature has also clearly decided not to introduce into the [Swedish] Arbitration Act any provision corresponding to the concept of new trial. Accordingly, in the Court of Appeal's opinion there can be no question of declaring an arbitral award invalid solely on the ground that false evidence or untrue testimony has occurred, when it is not clear that such have been directly decisive for the outcome …. However, situations are conceivable in which the invocation of false evidence may have an indirect impact on the arbitral tribunal in its assessment of the dispute. In light of the narrow scope of application and the restrictive approach that should pertain as regards opening up a new substantive assessment of the arbitrated dispute within the scope of challenge proceedings, in the Court of Appeal's opinion there should be no question of allowing such an indirect impact on the arbitral tribunal to result in the arbitral award being deemed invalid, except when it appears to be obvious that such indirect influence has been of decisive significance for the outcome in the case.
E. Since [the Tribunal] based its assessment on the indicative bid, the evidence invoked by [the Claimants] in the form of witness testimony, witness affidavits and expert reports regarding the size of the investment cost – which evidence [the State] has claimed was false – has not been of immediate importance for the outcome. In the Court of Appeal's opinion, already in these circumstances, such evidence per se, even if it were proven to be false – does not constitute sufficient reason to consider [the Award] invalid. In the Court of Appeal's opinion, it is also not obvious that this evidence, through indirect influence of [the Tribunal], was decisive for the outcome of the case.
F. Moving on to the question of whether the indicative bid per se constituted false evidence, it is undisputed that, prior to the initiation of the arbitration, [KMG] had submitted the relevant offer of USD 199 million for the LPG Plant. Thus, the indicative bid per se is not to be regarded as false evidence, even if - through the annual reports for Tristan Oil, KPM and TNG – possibly incorrect information regarding the amount invested in the LPG [P]lant was among the factors that KMG took into account when calculating the size of the offer. Accordingly, the allegedly false information in the annual reports did not directly constitute any basis for [the Tribunal's] assessment of the value of the LPG [P]lant. Against this background, the invocation of the indicative bid by [the Claimants] did not constitute an invocation of false evidence.
G. Finally, with respect to [the State's] allegation that, in the arbitration proceedings, [the Claimants] withheld from [the Tribunal] and [the State] certain information which might have influenced the outcome in the case, the Court of Appeal notes that, in a procedure amenable to out-of-court settlement such as arbitration, it cannot be demanded that a party provide the opposing party with information which speaks against the party's own case. There is no room to regard [the Award] as invalid on this ground, particularly not in light of the very narrow scope of application of the public policy rule.
H. To summarise, the Court of Appeal finds that none of the circumstances argued by [the State] in this respect - neither separately nor together - are such that [the Award], or the manner in which it arose are manifestly incompatible with fundamental principles of Swedish law."
Availability of evidence of the alleged fraud
"Reasonable diligence would have plainly led to [the State] instructing its quantum expert to investigate and assess the costs of the LPG Plant …. [The State] made a series of allegations in the arbitration that the Claimants had perpetrated a fraud or something akin to it. As noted above, [the State] alleged that the Claimants had siphoned moneys from [the State] including via Perkwood, that the Claimants had sought to mislead potential investors in the LPG Plant as to its true value, and more generally to the effect that the Claimants' witnesses had lied in their testimony. … It naturally follows from these allegations that anything relating to the true costs of the LPG [P]lant would be tainted. … [The State] left no stone unturned in all other respects."
Estoppel
"[i]n a case where a remedy for an alleged defect is applied for from the supervisory court, but is refused, leaving a final award undisturbed , it will therefore normally be a very strong policy consideration before the English courts that it has been conclusively determined by the courts of the agreed supervisory jurisdiction that the award should stand. Just as great weight must be attached to the policy of sustaining the finality of international awards so also must great weight be attached to the policy of sustaining the finality of the determination of properly referred procedural issues by the courts of the supervisory jurisdiction. I use the word 'normally' because there may be exceptional cases where the powers of the supervisory court are so limited that they cannot intervene even where there has been an obvious and serious disregard for basic principles of justice by the arbitrators or where for unjust reasons, such as corruption, they decline to do so. However, outside such exceptional cases, any suggestion that under the guise of allegations of substantial injustice procedural defects in the conduct of an arbitration which have already been considered by the supervisory court should be reinvestigated by the English courts on an enforcement application is to be most strongly deprecated."
Abuse of process
Conclusion